Project Managers Handbook PDF
Project Managers Handbook PDF
GHB 7150.1 A
APRIL 1972
/--.',',5 35/
uncl a s
oo/tjl 0255352
PROJE.CT MANAGER'S
HANDBOOK
FOREWORD
Donald P . Hearth
Deputy Director
iii
C 0NT E AUTS
.
Part Page
.
Part Page
.
4.3 Documentation .......................................... 4-3
4.4 Simulations and Tests ................................... 4-8
vi
CONTENTS (continued)
Page
.
Part .
* 9 FINANCIAL MANAGEMEANT................................... 9-1
vii.
_-
CONTENTS (continued)
APPENDIXES
Appendix -
Page
viii
’ ILLUSTRATIONS
Figure Page
2-1 Documentation Inventory Report ............................. 2-25
.
PART 1
INTRODUCTION
, 1.1 SCOPE AND APPLICABILITY
7. Procurement (Part 8)
1-1
Directorate. Revisions must have the approval of the Deputy Director of
GSFC .
1.3 AUTHORIZATION
The Director, GSFC, has authorized publication of this handbook. After initial
release, the Office of the Director will approve additional o r revised procedures.
1.4 DISTRIBUTION
1-2
PART 2
PROJECT MANAGEME8T
2 . 1 INTRODUCTION
At GSFC, the Project Manager is the highest line official solely concerned with
a particular project. After a project is formally approved, he is the final au-
thority for saying "yesfrto a critical proposition. For example, in launch op-
eration, many officials can properly say "no" to the firing, but the Project
Manager. must be completely satisfied before the button is pushed. Goddard in-
vests full responsibility for mission success in the Project Manager. Within
the confines of established policies and procedures, full authority and accounta-
bility go with this.responsibility. However, because each Project Manager is
concerned primarily with his own project, the equitable distribution of available
resources is a function of Center general management. GSFC policy is to house
basic project personnel together, where practical.
2 . 2 PROJECT P U N N I N G
It is the policy of NASA that the implementation of major research and develop-
ment projects will b e done on the basis of plans and analyses that define the
effort to be accomplished. This policy is set forth in NiMI' 7121.1 (presently
being updated) and GHB-7121.3, GSFC Project Planning Handbook. (See also:
Management Study of HA% Acquisition Process dated June 1971, Letter to Dis-
tribution from Deputy Administrator dated June 9 , 1971, Subj : NASA Acquisition
Study Report). It should be remembered that the concept of Phased Project
Planning requires that a Project o r Study Manager take the time to plan the
effort such that the mission objectives can be accomplished for the minimum
expenditure of Government resources. This requires then that a Project Plan
(PP) (see para. 2.2.3) be formulated and approved prior to the initiation of
significant project effgrt. This plan then becomes a control document and is
in essence the "contract'! between GSFC and Headquarters:for the scope of
effort outlined.
GHB 7121.3 prescirbes detail format for Project Plans, and the following de-
scribes briefly how this effort is implemented at GSFC.
The GSFC effort w i l l usually be accomplished in DNo -phases, rather than the
four phases in superseded NHB 7 1 2 1 . 2 . The phases now are: (1)Feasibility
and Systems Definition, (2) Execution. The output of Feasibility and Systems
Definition will, in many instances, be used to justify Congressional approval of
development funds. Thus, it is essential that this redefined first phase activity
be expanded somewhat so that various programmatic options a r e developed in
depth. This will permit a more reliable estimate of scope, cost, and schedule
for new projects. It is important also that this effort be in concert with the
Congressional and Office of Management and Budget approval cycles in order to
eliminate "dead time" while awaiting for approvals.
In those cases where the Feasibility and Systems Definition activity has provided
a firm understanding of project objectives and requirements, but has identified
many system options and thus too great a n effort for in-house support, a compe-
tition should be initiated for multiple contractors to perform the Systems Design.
Subsequently a single contractor w i l l be selected for the Execution from the Sys-
tems Design effort contractors.
GHB 7121.3 describes the documentation and procedures required when a new
activity -
which might become a full project -
is started at GSFC.
2-2
In general, the Study Manager will conduct the Feasibility Study, produce an
Analytical Report at the completion of the Feasibility activity. Where there is
an affirmative decision for continuation of the effort, the Study Manager will
continue with Systems Definition and prepare a Project Plan in accord with the
timing and guidelines sanctioned by the Deputy Center Director.
2.2.2.3 Project Plan for the Next Phase. With an affirmative decision by
Center and Headquarters elements to proceed into System Definition, the Study
Manager will initiate these activities. A s early as feasible during the System
Definition activities the Projects Directorate, o r other responsible Directorate
w i l l recommend to the Management Council a Project Manager for the Execution
effort.
2-3
Implementation of the concept at GSFC involves the following steps:
A. New Project Ideas - Candidate Study Effort that surfaces ideas and
concepts within the Center that could culminate in development of a
spaceflight system (described in GHB 7121.3)
This section does not prescribe detailed project organizational structures ; but
Appendix B does indicate, in general, a project organization that is used on
most GSFC projects in Code 400. The smaller, in-house projects located in the
E.xplorer Project Office and International Projects Office (Code 700) a r e usually
structured on a similar basis. Although the following sections a r e outlined by
titles, emphasis is on responsibilities that must be assigned as applicable. The
scope and size of a particular project may require, o r make it desirable, to
assign more than one specific responsibility outlined here to a single individual.
The PP should illustrate individual project organizational structures showing.
responsibilities and line authority. Official a p p r o v i of such organizations de-
rives from approval of the P P .
2 -4
2.4.1 Overall Management Responsibility
-
The appropriate Oirector of nominates a i d the Center Director's office ap-
proves the Project Manager. If the project has "Division" status, Headquarters
must concur in the appointment. The Project Manager is responsible for as-
suring the performance of alI functions necessary for management of the project.
In particular, he is responsible f o r projectwide planning and evaluation, systems
engineering and design, systems integration, test, reliability and quality assur-
ance, scheduling, budgetary and financial planning, techrucal monitoring of con-
t r a c t s , and project reporting. He has full authority to c a r r y out these functions,
subject to limitations established by the Director's Office, GSFC. He also coor-
dinates project requirements with other activities of the Center as well as keep-
ing the Headquarters Program Manager apprised of project status (see Appendix
A). The Project Manager discharges his responsibilities with the assistance and
support of individuals and organizations assigned either administratively o r func-
tionally to the project management organization.
The appropriate Director of -, usually Space and Earth Sciences o r Space Appli-
cations and Technology Directorates, nominates and the GSFC Director approves
the selection of the Project Scientist. The Project Scientist is responsible for
assuring coordination between and satisfactory accomplishment of the scientific
objectives of the mission and its individual experiments. He participates in the
formation of the specific mission objectives; reviews the implementation of in-
dividual experiments to ensure that their objectives a r e consistent with the pro-
posal upon which the selection w a s based; reviews the spacecraft weight, power,
space, the telemetry assignments among e.xperiments , operating plans, data
acquisition and processing requirements all to ensure that the total system plan
is consistent with the overall mission objectives. He provides leadership in
assuring that the e-xperiment data a r e effectively used and the scientific results
of the mission are e-xpeditiously produced. The project scientist evaluates all
impacts on the scientific productivity of the project and provides scientific
guidance to the Project Nanager and others involved in the program.
2.4.4 Principal Investigator
The Project Plan will list the experiments to be performed on each spacecraft.
Experiments may be primarily scientifically, technologically, o r applications
oriented. The appropriate Associate Administrator selects all scientific ex-
periments and their associated principal investigators.
The Principal Investigator (PI)is responsible for assuring that the objectives
of the e.xperiment are met, managing the e.xperiment, publishing the results of
the experiment, and submitting the e-qeriment data to the National Space Science
Data Center (NSSDC) in a form usable by other e.qerienced investigators in the
field.
The Deputy Project Manager, when the position is required, is selected by the
Project Manager and his Director of -.
Approval by the Center Director's
office is required. The Deputy Project Manager is the alter-ego of the Project
Manager and as such may act for the Project Manager with respect to all the
Project Manager's responsibilities.
The Project Nanager selects with the concurrence of his Director of -, and the'
Center Director approves the Assistant Project Manager. The Assistant Proj-
ect Manager represents the Project Manager on all matters with the Project
Manager's cognizance to the e4xtentauthorized and assigned by the Project Man-
ager. As directed by the Project Manager, he may from time to time devote
full time to critical problems, assist in negotiating major contracts, etc. The
position of Assistant Project Manager is optional with the Project Manager.
2 . 4 . 8 Systems 3f;LIanagers
.
2.4.8.3 iMission Operations System Manager (MOSM) The MOSM is respon-
sible to and normally administratively assigned to the Project Manager for all
flight mission support and operations. This includes validating, and generating
project requirements, assuring adequate resources a r e committed and over-
viewing the implementation by the OTDA elements. He must have a complete,
detailed knowledge of the spacecraft including experiments and its operations,
capabilities, and limitations. The MOSM is responsible for preparing the op-
erations plan, beginning with the first elements of that plan as soon as the Proj-
ect Manager approves i t , and for refining and detailing the plan throughout the
life of the project. With the assistance of the Mission Support Manager and the
Network Support Manager the MOSivI will supervise, instruct, train, conduct
simulations with, and exercise the operations team to establish and assure a
performance capability consistent with the mission requirements. The MOSM
ensures that all equipment supplied by the project o r e.xperimenters for instal-
lation at any network station conforms to the.General Specifications for Network
Equipment Design and Construction, and is provided with the necessary spare
parts, manuals, and training.
2.4.8.4 Mission Support Xanager (3ISM). The M S M (Code 500) is the primary
contact for the Xission & Data Operations Directorate (ZYI&DOD)activities in
2-7
support of the project. He is responsible to the NOS31 for accepting and as-
sisting in the generation of project requirements, committing M&DOD re-
sources, and imp1ementh.g I\/Z&DOD support. He is responsible for preparing
the 42 &DOD inputs to the NASA support plan and the publication of the coordi-
nated plan. He is the prime contact for the Network Support Manager concern-
ing M&DOD National Directorate (ND)operational interfaces in support of the
mission.
2.4.8.5 Network Support Xanager. The Network Support Manager (Code 800)
is responsible to the Mission Operations Systems 3lanager for all network sup-
port to the project. He is responsible for accepting and assisting in the genera-
tion of project requirements and obtaining the commitment of network resources.
He is responsible for the committed network resources, preparation of the Net-
work Support Plan, including the launch vehicle tracking and data systems re-
quirements, implementing network operational support plans, and readiness
testing. He is the prime contact for the Mission Support Manager concerning
ND/M&DOD operational interfaces in support of the mission.
2.4.8.7 Test and Evaluation Support Xanager. For each project, the T&E
Division will assign an individual to support the Project Manager on all test
matters. The Support Manager advises the Project Manager on test require-
ments, prepares o r reviews the spacecraft test specification for approval of the
Project Manager, coordinates. the test program, and reviews test results. The
Support Manager's duties also include liaison with the T&E Division on techni-
cal, manpower. and fiscal matters.
.
2.4.8.9 Quality Assurance Support Nanager For each project, a Quality
Assurance Support 4fanager from the Quality Assurance Division, Systems Re-
liability Directorate, shall be assigned responsibility for assisting the Project
3Ianager in the project reliability and quality assurance effort. He also provides
liaison with the Quality Assurance Division on manpower and fiscal matters.
2-8
Specific responsibilities of the Quality Assurance Support Ganager on the proj-
ect staff a r e identified in Py-t 6, para. 6.2
The scope and size of the technical staff will depend on the size, type, and
management approach of each particular project. Personnel, such as subsys-
tem engineers, will in general be assigned from the Space Applications & Tech-
nology Directorate (Code 700). There must be an engineer responsible for each
spacecraft subsystem.
Each Project Manager shall name by direct and specific assignment to a par-
ticular individual (perhaps himself) the responsibilities of systems engineering.
2-9
This includes not only system design but the assurance that all interfaces a r e
adequately specified and reviewed. These interfaces shall include not only those
between the spacecraft and e.xperiment systems but also those between the com-
plete observatory o r satellite and the launch vehicle, ground complexes, and
operational requirements. Specific responsibilities and authorities of this posi-
tion depend upon the individual project organizational structure. This position
is a staff function to the Project Manager.
An Integration and Test Engineer may be assigned for each flight mission. The
scope of this position will depend on the method of project implementation; i.e.,
in-house integration and test, or contractor integration and test. This function
may be assigned to the Spacecraft Manager. The Integration and Test Engineer
shall be responsible for the preparation of plans and procedures for the final
assembly, integration, and flight acceptance test of the spacecraft system plus
experiments, and for the execution of those plans and procedures.
The Project Manager shall designate a Systems Safety Officer (perhaps himself)
to implement a Systems Safety Plan (see 2.12.20 and Appendix C ) .
~
--
I
2-10
evaluation of facilities and tests necessary for project requirements. The
environmental committee will evaluate results and will certify thar; results
'
meet the specifications and that the test program is adequate to meet the
mission objectives.
The Work Breakdown Structure (CVBS) is a basic management tool which is used
to systematically subdivide discrete blocks of work. A WBS, when properly
structured, can provide for: relating the specifications to the end item; identi-
fying controllable work packages for estimating resources ; budgeting and pricing;
work assignment and authorization and reporting.
2-11
*
It is a product-oriented family tree composed of hardware, software, services,
and other work tasks, which result from systems engineering and management
planning processes, and which completely defines the program/project. A W B S
displays and defines the products to be developed and relates the tasks to be
accomplished to each other and to the end product.
The structure represents how the work will be managed by the Project Office
and the contractor and is made up of work blocks arranged by level.. Blocks of
related and consistent work effort form a branch of the structure. Each block
is sub-divided into smaller elements down' to a control point which represents
the lowest level of controlled effort. by the project. .A WBS handbook has been
written at GSFC (GHB 7120.1; dated August 1971, Subject: Handbook for Prep-
aration and Implementation of Work Breakdown Structures).
A. hitial planning
The size and complexity of project activities dictate whether the scheduling
activity can be covered by "bar charts" o r whether machine processing and the
p r o g r a m e d logic of PERT will be required. Where appropriate, consideration
should be given to the relationship of the schedulirg matrix with the W B S a s
there should be a continuity between all reporting requirements.
2-12
2 S.4 Contractor Financial Management Report (533)
a. The contractor must develop a time-phased cost plan and must report
against that plan.
d. The WBS subdivides the contract into manageable units which en-
hances resource plannjng and control and permits detail work flow
analysis.
e. The data serve a warning system for detecting potential cost overruns.
XASA Handbook 9501.2A, October 1971, provides additional details on the use of
contractor financial reports. The Program Support Division, will assist Project
Managers in making financial reports and in analyzing data received.
Again there should be a correlation with the WBS for consistency and
continuity.
Xany techniques can be used to interrelate and correlate schedule and cost data
received, ranging from PERT cost (a'technique used by the Department of De-
fense @OD). in costing out all activities included in.a PERT netu;ork) to a simple
comparison that total technical effort is percent complete and total
costs a r e percent expended.
NASA has selected PERT-Compznion Cost for developing a system that provides
a common framework for both cost and schedule reportiing. The total PERT
network is structured into "fragnets ' I (fragments of a network) which clearly
2-13
. identify a unit of work that also becomes a basis for collection of costs. On a
meaningful segment of the project activity schedule; therefore, cost can be re-
viewed on a common and meaningful basis.
The project must review its funding requirements by fiscal year and for project
completion, as well as for the type of procurement envisioned and the estimated
date of availability of the procurement request. These data must be reafistic,
because compliance with the submitted POP becomes the measurement of the
effectiveness of the project's management of its resources.
....
2-14
obligations, and disbursement status is also available, a s a r e detailed'project
manpower application data. A machine-reporting register prepared by the
Business Data Branch constitutes a complete list of report frequency and avail-
ability. Assistance in interpreting and analyzing these reports is available
from the Program Support Division.
Each project should submit a weekly report to the Director. The objects of
this report are:
A . A concise summary of -
1. Major and important happenings.
'3.- Contr'oversial items -do not hide them under the rug. Get them
out in the open where management can deal with them.
2-15
C. Each report should be one page in length, with a Wo-page Limit. Flag
problems - do not t r y to e.xplain them in detail.
E. Functional and project offices may report on the same item if both the
functional Division Chief and the Project &Tanagerhave personal mes-
sages on that item.
These reports are intended for information and communication and do not nec-
essarily.reflect official Center position.
2.6.1 Purpose
2.6.2 Applicability
Xemoruncla of Agreement for functional support shall be used unless '3 Project
>Imager decides to the contrary. They shall be prepared in the faliowing
manner.
2-16
P r i o r to the release of the guidelines for semi-annual project involvement in
manpower POPS (grass roots and mark-up) the Project &Imager (PPI) o r Prin-
cipal Investigator (PI) shall prepare or update a statement of support require-
ments for each Division from which support is required. and fonvard it to the
pertinent Division Chiefs. This statement must be consistent with or modifica-
tions to other official agreements, particularly the Project Plan and the SIRD
(see para. 2.12.15). It should also include the Project Manager's latest asses-
'
sment of critical dates which affect planning requirements. The Division Chiefs
through discussions with each Project Manager or Principal Investigator shall
estimate the manpower required to be responsive to the Project Manager's
statement.
If, after assimilating all the inputs from the PM/PI, the Division Chief finds
that he has sufficient resources to support all projects, he and the Project
Managers sign memoranda of agreement in the format of Appendix E which shall
include a designation of both the man-years as well a s the identification by name
of those key individuals deemed essential for performance of the task. In deal&=
with Code 800 (Networks Directorate) all Memoranda of Agreement shall be be-
tween &e Project and the Xetworks Directorate, Requirements and Plans Office.
If the Division Chief has insufficient manpower to support all projects, he pro-
vides a.memorandum to his Director of- which (a) validates the requirements,
(b) reports the critical skill shortage, and (c) indicates the impact on his organi-
zation if required to support at the desired level. Copies of these memoranda
are supplied to the appropriate Director of- in which the project or experiment
is located.
At the same time, the appropriate Project Manager will prepare a memorandum
-
for his Director of which (a) validates the requirement and (b) indicates the
impact on the project of support at the level proposed by the functional Division
Chief. Copies of these memoranda a r e supplied to the appropriate functional
Director of -. Resolution should be attempted by the Directors of - prior to the
Director's manpower review. It is e4xpected that critical shortages and the im-
pact of such shortages as well as agreed upon requirements will be identified
through this process at the Director's review of the manpower POP for eventual
resolution.
Between POP' s the .PM/PI and the Division Chiefs have collective responsibility
-
for t e s t i q the validity of the estimates in executing the requirements was the
estimate too high o r too low so that manpower usage can become increasingly
effective through each succeeding POP. The PM'PI will be e-xpected to track
the actual vs the estimates at the' MICS reviews.
2-17
2.6.4 Management Responsibility
The relative responsibility of the Project Manager and the. Division Chief varies
with the nature of the task:
expected that the PM/PI will advise the functional supervisor on the
performance of those functional personnel residing with the project.
However, the Division Chief is responsible for periodic reviews of the
adequacy of the technical performance of their co-located personnel.
Differences of judgment between the project and functional personnel
can and should be appealed with the burden on the Project iManager and
the functional Division Chiefs to resolve such differences if possible.
I
0 In those cases where one functional man is assigned only part time to
a project o r splits his time between two projects, the functional chief's
responsibilities a r e greater. It is his responsibility to supervise the
time spent in the applicable areas and resolve any conflicts arising
from concurrent project. requirements.
When project goals can best be attained by using the capabilities, equipment, o r
other resources of an installation other than GSFC, the'office of the Director
wdl, at the request of the Project &Maaager,initiate each new request for such
support.
2.7.1 Project Manager's Responsibiiity
The Project Manager will submit requests for inter-Center support to the Office
of the Director with complete detailed justification. The justification shall in-
clude each of the following, if applicable:
d. Dates requested
~ t e the
r request has been approved, the Project Manager will provide liaison
with the other installation.
2.8.1 Purpose
. .2.8.2 Applicability
2.8.3 Responsibility
The Project Manager shall be responsible for establishing and updating a system
for interface documentation. The Project Manager may delegate this responsibility
2-19
to another individual such a s the Project Documentation Manager. Formal sign-
off procedures for each document must be established.
2.8.4 Scope
.
2 A4.1 Spacecraft Systems, Subsystems and E.xperiments Interface documents
shall specify all interface items required to define the complete integration of
a l l spacecraft systems, subsystems, and experiments, including;
a. Method of installation
c. Thermal (environmental)
2.3.4.2 Spacecraft and Vehicle. Each launch vehicle (Delta, Atlas-Xgena, Titan,
Atlas-Gentaur , Thor-Xgena, and Scout) has interface documentation which is
-
- * .
.. 2-50
e-
-
required of a spacecraft project. These documents control the mechanicai,
electrical, and operational interfaces for these vehicles. A'spacecraft con-
straints document f o r the Delta vehicle defines the interfaces of the vehicle and
spacecraft, in general. To augment this, a vehicle/spacecraft integration and
documentation schedule lists the detailed interface information which must be
exchanged by the spacecraft and the vehicle projects.
For Agena, a mission requirements and restraints document sets forth the.
Agena restraints. An interface planning and scheduling document serves as the
interface control medium for the spacecraft and'vehicle.
F o r Scout, the GSFC mission interface data book serves as the interface control
document.
2.8.4.3 Spacecraft and Special Ground Service.. This documentation shall specify
d1 interface items between the spacecraft (including experiments) and the
ground-support equipment (GSE), including project-unique. ground stations and
project-unique equipment at existing ground stations. Typically, it includes
electrical and mechanical. input and output characteristics, operational restraints,
and computer hardware and software interfaces.
3.8.4.6 Spacecraft and Launch Site. The PRD shall outline requirements for
spacecraft support at t h e launch site (such a s space, clean-room facilities,
power, a i r conditioning, and personnel facilities).
2-21
subsequent changes will require the joint conc.urrence of the Networks Direc-
torate and the project. Component and subsystem tests will be performed to
verify compliance with this document. These tests will be performed on engi-
neering models early in the spacecraft implementation schedule. The Interface
Control Document will utilize the Aerospace Data Systems Standards as' a guide-
line in establishing the interface between the spacecraft/launch vehicles, and the
network.
2.9 CONFIGURATION . .
2.9.1 Policy
2.9 2 Definition
2 J0.1 Objectives
2 J0.2 Applicability
2-23
g.' Submit a documentation inventory report (Figure 2-1) to the Chief,
Technical Information Division, on July 1 and January 1. (This report
should include all significant scientific and technical papers published .
by the project and e'xperimenters.) Send to the GSFC Library a copy
of each document listed on the inventory report.
The wording of the mission objectives statement should be simple and concise
and should reflect the true project goals and maturity. As indicated above, the
mission objectives should be established and agreed to by GSFC and OSSA early
in the implementation cycle. If, during implementation, circumstances dictate a
basic change in p1ans;the mission objectives statement should be e&xaminedto
determine if a change in wording is required. Such changes require the approval
of the GSFC Deputy Director and the &OSSA.
Approximately one year before launch, the GSFC Project Manager and the OSSA
Program ,Manager should review the mission objectives statement and either -
certify to GSFC and OSSA management that the statement is valid o r recommend
appropriate changes . r
In every case, the ,Division Director will schedule a specif3 review of mission
-
objectives about one year prior to launch readiness. The Project Manager will .
--
2-24 . -
e-
.
c
c
b
a
Q
t
z
r
C
Q
->
e .
0". .
5
Y
.-
c
0
CL c
C
;
a
r
t 8"
2-25
display such a milestone on Level 2 milestone charts prepared for PXR sub-
mittal to Headquarters.
2.12.6 NASA Design Criteria, NASA Policy Directive 8070.1, August 17, 1967
a. Environmental Criteria:
2-27 '
b. Structural Criteria:
2-28
SP-SO27 - Spacecraft Radiation Torques, October 1969.
SP-8028 - Entry Vehicle Control, November 1969.
SP-8033 - Spacecraft Earth Horizon Sensors, December 1969.
SP-8034 - Spacecraft Mass Expulsion Torques, December 1969.
SP-8036 - Effects ofStructural Flexibility on Launch Vehicle Control
Systems, February 1970.
0 Telemetry
0 Command
0 Tracking
0 'Communications
0 Data Processing
0 Associated Systems
2-29
that the standards be cited a s applicable documents in procurement
actiond whenever appropriate.
a. General Content
(1) Project Manager's right to concur in all final Goddard and outside
e.xperiment specifications
~ 3-30
a. General Content
2.12.12.1 XASA Policy and Procedures for Use of Contracts for Nonpersonal
Services (NPC-401). This publication is used in conjunction with NASA Procure-
ment Regulation (NHB 5100.2). It does not apply to contracts for
- c
experts covered by existing regulations.
2-3 1
a. The basic policy requiring use of source-evaluation boards for com-
petitively negotiated processes
2.12.13 Budget Execution and Review at the Goddard Space Flight Center
(X-Document 210-67-80)
This document describes the system used at GSFC for ensuring funds control at
job-order, project-appropriation, fiscal-year. and total Center level. It de-
scribes both the overall X G A system and the GSFC system.
2.12.15 Documentation of Tracking and Data Acquisition Support for NASA Un-
manned Space Flight Projects (mlI8430.1A. September 12, 1969)
2-32
2.12.16 Xanagement Procedures for Automatic Processing Equipment
(NHB2410.U)
Specifications for Phase B, C , and D contracts must include the GSFC ADP
procedural requirements in anticipation of possible inclusion of ADP equipment
f o r such uses as integration and test, simulation, displays, recording, control '
b. It is the policy of this Center to have a System Safety Plan for all flight
projects. The implication of ,WB 1700.1 (V3) is that system safety
assess the risk associated with space flight hardware systems with a
purpose of avoidance of injury to people and property loss regardless
2-33
of cause and this policy extends to post-launch operations. At GSFC it
is the policy on unmanned flights to concentrate our attention on the
avoidance of injury to people. Therefore, Systems Safety is defined as
those engineering and management practices and procedures necessary
to avoid personnel injury and property loss to the maximum extent
practical. Systems Safety includes the protection through launch of
flight hardware from loss o r damage from extrinsic factors, but does
NOT include property loss o r damage to flight hardware due to internal
component malfunctioning. The latter is considered a design reliability,
a n d o r quality responsibility.
2-34
.
In general, NASA is responsible for providing the launch vehicle, support by the
T&DA facilities, one o r more U.S. experiments, spacecraft advice, and unique
test facilities. The foreign country generally provides the spacecraft, the ma-
jority of the scientific experiments and most of the data processing. Therefore,
the principal project maqagement efforts on an international project a r e directed
towards insuring on behalf of the United States that the various Centers respon-
sible for the three areas of "3.4 responsibilities (spacecraft advice/ experiments,
launch vehicle. T &DA) perform satisfactorily within the written n,ords and spirit
of the Memorandum of Understanding. This generally results in active manage-
ment of the US. effort and directing the passive advice and counsel provided on
the foreign effort (usually limited to a general surveillance of the foreign effort,
culminating in a joint flight-worthiness approval of its efforts).
2-35 .
e
In all cooperative projects the principal mechanism for coordination and infor-
mation exchange and transfer is the Joint Working Group (.JlI’G). This group is
co-chaired by the U.S. and foreign project managers and consists of working
representatives of each system and major subsystem. It usually meets semi-
annually in alternate countries and exerts a major influence on the successful
execution of an international cooperative project.
2.14 EXPERIMENTS
The Project Manager shall establish project requirements and schedule mile-
stones for all e-qeriments. These shall include:
d. Configuration management
2-36
f. Progress reporting
h. Design reviews
Through formal and informal means, the Project Manager shall monitor the
progress of the experiment effort.
In general, the requirement f o r the sensors and the format of the data output a r e
generated by means of working groups representing the e.xperimenters, (guest
observers) who will ultimately make use of the data and project personnel. It is
2-37
the responsibility of the Project Scientists to chair the working group and to see
that these requirements a r e generated early in the program.
Once the requirements a r e established, the Project and the Technical Officer a r e
responsible for the procurement of the sensor hardware and any ground equip-
ment necessary to present to the experimenters the sensor output in a usable
format. The Technical Officers for the sensors will in general be provided by
the Earth Observations Systems and Systems Engineering Division and assigned .
to the project.
2-38
PART 3
SYSTEM TESTS
3.1 PHILOSOPHY
GSFC has endorsed the full-system test approach, in which the entire system is
tested under conditions as realistic as possible. Systems tests senerally fall
into one of two categories:
3-1
performance baseline with which the spacecraft can be compared
throughout the environmental test phase.
3 -2
3.3.1 Environmental Test
These tests determine the ability of components, subsystems, and the entire
spacecraft to withstand environmental rigors that may be experienced before
and during launch, and during orbital operation. The tests may be conducted at
any o r all levels of assembly, but a r e required at the spacecraft Level. The
severity and duration of the tests are related to the purpose of the tests a s indi-
. cated below. At times it is difficult to distinguish between functional testing
and environmental testing, particularly when a specific environmental, e;g.,
high vacuum, is required for the performance of a functional test (see para. 3.4).
3.3.1.2 Qualification Testing. A prototype model (i.e., the actual flight con-
figuration) is e'xposed to an environment intended to produce loading conditions
and stresses in excess of those errpected in flight. The purpose of prototype
testing is to ensure a margin in the design to provide for uncertainties in areas
such as analyses, materials, and workmanship. For qualification, test levels
are chosen such that, again in theory, there i s one chance in one hundred of
their being exceeded in flight.
While the establishment of test levels is defined above in terms of overall risk,
the paucity of applicable data makes this task one which does not yield exact
numerical values.
The full-systems test approach does not eliminate the desirability, o r in some
cases the necessity, of black-box and subsystem qualification and acceptance
testing. Several inherent limitations of systems testing are best overcome by
testing at the subsystem o r black-box level:
3 -3
a. Lf only systems tests a r e run,marginal conditions e.xisting at subsystem
o r black-box interfaces may remain undetected. Only information on
the input/output characteristics of the individual black boxes can estab-
lish the presence of adequate control margins.
Where ail edxperiment is one of many in a spacecraft, and where its failure will
not endanger the mission requirements, it may be treated the same a s a sub-
system (see above). Where an e-xperiment is essential to the accomplishment
of the mission or costs $2,000,000 (approx) o r more, the mandatory testing
program called out in the General Environmental Specifications w i l l be required
before assembly into the spacecraft. In cases when two models of the e-xperi-
ment are available, one can be used for qualification and one for flight accep-
tance. In cases where constraints permit only one experiment to be made, it
must be subjected tc protoflight level tests at the e'xperiment and spacecraft
(observatory where applicable) configuration levels.
3 -4
c
' 3.4 GENERAL EXVIROXXESTAL TEST SPECIFICATIONS
.Mandatory tests a r e listed in paragraphs 1.6.4 and 1.6.5 of the general test
specification and careful consideration should be given to other tests listed in
those paragraphs and in paragraph 1.6.6 on the basis of spacecraft design and
mission. The test program is not rigid but provides for alternate methods for
satisfying test requirements, including the mandatory tests. Deviation from
mandatory tests, or the recommended alternate, requires prior approval from
the Director of Systems Reliability as well as the cognizant Director of -. The
general test specification serves as a model in format and as a source document
in content for the writing of particular test specifications for individual projects.
3 -5
PART 4
OPERATIONAL REQUIRMEiVTS
4.1 GE'NERAL
_.
. 4-1
are proven and incorporated into standing capability, they become part of the
resources each following new mission may draw upon. In this manner, each
new operation contributes to the development and improvement of ground oper-
ations and ground systems.
4 . 2 INTERFACES
The execution of the third and fourth steps a r e the responsibility of the Project
Manager and are accomplished in parallel with the other principal elements of
4-2
the mission. The objective in these steps is to prepare specific and detail plans
for the day-to-day, orbit-to-orbit, flight operations and is done by the 31OSM and
the Mission Operations Staff (310s). These requirements should define overall
functions and performance including each support area. This definition cannot
consist of simple demands for specific equipments by model number o r name,
however, this type of detail must be recognized as the ttlinguafrancaflof the
business'. The members and participants of the MOS from the support areas
must be prepared and capable of providing detailed information about the facili-
ties: what each consists of; what each will consist of; how they function individu-
ally and collectively; etc. Once established, the requirements and commitments
must. remain reasonably fixed.
The Mission Support (para. 2.4.8.4) and Network Support Manager (para. 2.4.8.5)
a r e e.upected to have an acquaintance with operations in all areas they represent.
The utilization of technical capability of the M&DO cadre, and the other support
personnel and the resources they represent a r e , to a great extent, dependent
upon the practices and desires of the project management. At times, the hlSM
and the iUSM are used as a single point of contact by the Mission Operations
Systems Manager (MOSM) and at other times f u l l interplay with all support
personnel is exercised. No restriction is placed by management other than that -
outlined above. The M&DO cadre is considered an integral part of the project
team, and is expected to participate to the fullest extent possible in the project
operations by providing substantial knowledge and skill in ground operations.
The Radio Frequency Management Manual (formerly NPC 102-1, presently being
revised) sets forth the procedures covering management requirements for the
control of radio frequencies for NASA. These procedures a r e adhered to by all
NASA frequency users and Field Installation Frequency %a, mers.
NAMI1138.6 assigns the authority for management of radio frequencies for NASA
to the Associate Administrator, OTDA, NASA Headquarters.
The Radio Frequency Management Manual (NPC-102-1) will be issued under the
authority of NMI 2570.2A, which establishes the policy and responsibilities in
,radio'frequency management.
NMI 5104.2 Establishes the NASA policy for ensuring that no equipment
radiating radio frequency energy is acquired prior to obtaining
frequency support for its operation.
4-4
N M I 1052.25 Establishes procedures relative to the coordination of frequencies
in NASA projects requiring range support.
4.3 DOCUMENTATION
4.3.1 SIRD/NSP
The SlRD is NASA Form 987 revised and dated January 1965. The elements
covered by this document can be categorized as follows:
0 Requirements:
Information flow
Orbit determination accuracy
Telemetry data acquisition
Ground command
Support computing
Communications
Data processing
4-5
a single page basis. GSFC forms and procedures Bre given in Appendix D of this
handbook. bfemoranda and "understandings" play a role in the interplay and
dynamics of support preparation, however, they do not and cannot replace or
eliminate the formal, approved (Center and Headquarters) statement of require-
ments that these documents represent.
Study/Project managers should plan and schedule the issuance of an initial SIRD
(Support Instrumentation Requirements Document) concurrent with the Project
Plan. This first SIRD should meet the minimum requirements established in
the SIRD preparation instructions and contain the new m d continuing require-
ments placed by the Tracking and Data activities of the project. It is attached
to the Project Plan and sent to OSS o r OA, a s appropriate for approval purposes,
and after their action, it is sent by the program office@) to OTDA for informa-
tion, review and commitment of support and future resources. Additionally,
GSFC sends OTDA information copies of the project plan and SIRD concurrent
with the transmittal of the same documents to the OSS o r 0.4 program approving
office.
4.3.2.1 Mission Operations Plan (MOP). The MOP is the governing document
covering the mission specific plans arid procedures for each mission. A s such,
it relies heavily on the related documents prepared for the T&DA support facili-
ties outlined below. It should reference these documents and only duplicate their
content where necessary for complete understanding of the e.xpected reader. All
aspects and phases of flight mission operations should be covered from the point
of view of the MOSM. The MOP is prepared by the 310s with the assistance of
the support elements and approved by the Project Manager. It should be pub-
lished at least 90 days prior to the e=q>ectedlaunch date of the mission.
4-6
appropriate section in the OPPLAN may suffice. The M&DO O P P U N is pre-
pared by the MS31 and the support cadre, with the assistance of the operational
elements and approved jointly by the Project blanager and the Associate Director
of Mission Operations, Mission and Data Operations Directorate. It should be
published at least 60 days prior to the expected launch date of the mission.
4.3.2.3 Nebvork Operations Support Plan (NOSP). The NOSP is the governing
document which directs the network during support of a specific mission. NOSP's
a r e prepared for each mission and define the station configuration and operational
procedures along with project peculiar items a s derived from mission require-
ments. The NOSP is prepared by the Network Support Manager and will nominally
be published 60 days prior to the expected launch date of the mission.
4- 7
management. The various operations plans may specify the detailed require-.
ments for these documents. They a r e prepared as required and necessary 3s
the operations a r e executed.
These tests and simulations a r e started somewhat after the previous tests
mentioned and use certified o r conditionally certified segments of the system to
enlarge upon the scope of technical certification and to introduce the expected
time dynamics of the mission. They a r e typically cooperative o r joint exercises
between operating elements and include the appropriate interfaces. They cul-
minate in system simulation as realistic as practical, such a s network data flow,
command execution, etc., but do not deal directly in mission contingencies o r
full system interaction; since the objective is to validate and certify the capabil-
ity to support any given support phase -and the interactions, interrelationships,
and effects unique o r peculiar thereto. These tests and simulations. a r e the
responsibility of the operating elements, however, the Mission Operations Staff
(310s)should participate and cooperate in these activities. They should be
completed 3 to 6 months before the expected launch date.
These simulations a r e the final exercises intended to fully show flight readiness
from a ground operations/ground system point of view. A s such, they should
,culminate in operations involving f u l l mission time dynamics for a period of
time sufficient to allow all significant normal situations and conditions to occur,
and mission contingencies to a reasonable practical extent consistent with mis-
sion objectives, anticipated inter-mission constraints and conflicts, and resources.
Mission simulations shall involve all participatam elements and operating personne
(project and support elements) including all shifts where applicable. They a r e
the responsibility of the MOSltI and the BIOS and shall be conducted for a period
of 90 to 120 days before the expected launch. A minimum of two full simulations
will be carried out - one approximately 30 days before launch and one 3 to 7
days before launch.
These tests are intended to verify mission technical parameters where they
relate to the interface with the operational ground system. They are designed
.to establish feasibility of the intended ground operational support configurations
and to evaluate areas of potential support difficulty. They also verrfy compliance
with the Spacecraft-to-Ground Performance Interface Control Document and with
the GSFC Aerospace Data Systems Standards (see para. 2.12.10).
These tests are not design validation or proof tests of either the spacecraft o r
ground equipment; but, they a r e a thorough evaluation of the.degree to which
support requirements can be met when the spacecraft and ground equipment,
each meeting their respectit-e performance specifications, are interfaced.
The tests will be conducted by the Networks Directorate using standard ground
support equipment and flight hardware to the maximum extent possible. A sep-
arate compatibility verification test is required for each spacecraft in a multiple-
launch program. The test results will be the primary basis on which the Director
of Networks and the Director of blission and Data Operations will verify f i d l
compatibility o r identify interface limitations. Compatibility verification tests
will be conducted as early in the program as possible after the flight spacecraft
tracking, telemetry, and command subsystems a r e finalized. The compatibility
verification tests must be completed prior to the Network Readiness Test (NRT).
4-9
PART 5
PROJECT REVIEWS
3.1 PROJECT MANAGER'S REVIEWS
The Project Manager shall formally review and document the status of the
hardware at times coincident with the key milestones in the design and develop-
ment of the items. These Project Ma-uer reviews will, in general, focus on the
spacecraft subsystems. Reviews a r e recommended f o r components and black
boxes of subsystems that a r e either unique o r particularly vital to the mission.
The primary objective of these reviews is to evaluate the design and performance
of the subsystem o r component. They also provide an opportunity to evaluate
and update the interface specifications.
5 2.1 Definition
52.2 Purpose
The purpose of the design review program is to enhance the probability of success
of GSFC spacecraft and launch-vehicle missions.
3.2.3 Implementation
3- 1
a. Conceptual Design Review. This review, keyed to the end of the study
phase, will evaluate the preliminary design and design approaches which
resulted from the study.
b. Detail Design Review. This review usually takes place after the design
is frozen and before assembly begins. Emphasis is on the implementation
of the design approaches which result from the study and the plani for
the systems and prototype testing.
d. Flight Readiness Review. This review usually takes place before the
flight spacecraft is shipped to the range, and emphasis should be on the
performance of the flight spacecraft during acceptance testing.
In addition, to the foregoing reviews, the review team will include on its agenda
safety aspects of flight systems.
3-2
L€ serious in-orbit o r operational failures occur in GSFC missions, the Director,
GSFC, may conduct, at his discretion o r at the request of the cognizant Head-
quarters Program Office, independent investigations to determine causes and
make recommendations (see G X I 8621.1, dated June 28, 1971).
On some projects there has been a review after the spacecraft has been in orbit
for an appreciable period to assess its performance. For some projects this
review has only covered e?cperiments, while for others all the spacecraft sub-
systems have been reviewed. Reviews, a s complete as practical, provide infor-
mation on how to conduct future projects and are encouraged.
PART 6
RELIABILITY AND QUilLITY ASSURANCE
6.1 RELIABILITY
b. Quality assurance
The Project Plans for the individual projects describe in some detail the project
and supporting functional organizations which implement the reliability proam r a m .
At GSFC, the term ffreliabilityffis considered to be design-oriented; it is Center
policy to place responsibility for the design on the same group from start to
finish. Accordingly, on large projects, the reliability engineers on project staffs
report administratively to the Projects Directorate.
6-1
6.2 QVALITY ENGIXEERIXG
All quality-assurance policy and procedural matters, which impact other NASA
Centers, XASA Headquarters, o r Government inspection agencies, a r e coordi-
nated by the Project Quality Assurance Support &-mer through the Quality
Assurance Division Off ice.
6-2
6.3 SLALFL7CTION REPORTIZG (Failure Reporting)
GSFC policy is to use a uniform malfunction reporting system for all GSFC
spacecraft projects. GSFC Management Instruction 5310.M describes this
system and the procedures to be followed.
This reporting procedure shall be used for all prototype and flight hardware on
all spacecraft projects. . Malfunction reportbg shall begin with the f i r s t functional
test of an assembly (subassembly if it exists) and continue throughout the mission
until spacecraft power is turned off. Hardware level, not contractor level, shall
define the starting point f o r reporting. Malfunction reports shall be submitted
on GSFC Malfunction Report Form (GSFC 4-2,June 1970) and shall be closed out
by the Project Manager. GSFC Specification for Contractor Malfunction Re-
porting, s-312-P-1, shall be used on GSFC contracted programs.
6.4.2 Scope
The GSFC P P L must be used on all flight and prototype launch vehicles, space-
craft, and e.xperiments of new design. The P P L may be required on equipment
of existing design and critical ground support equipment at the option of the
Project Manager. Non-PPL parts may be used in they a r e approved in accordance
with GMI 5330.5.
The GSFC PPL, updated on an "as-needed" basis, lists recommended parts and
their respective procurement specifications. Each part listed has a history
either of satisfactory qualification testing o r of e.xtensive past usage in GSFC
flight programs. The appendix of the GSFC P P L contains nominal screening .
tests and derating f o r electronic parts. Additional parts bformation appears in
the document, Application Noted for Preferred Parts and Materials, Volume 1,
February 1967.
6-3
The PPL may be distributed to NASA contractors and foreign e.qerimenters on
NASA programs o r to the Project Manager of International Cooperating Programs.
The GSFC Project Manager may use the facilities and manpower of the Inspection
Section for the performance of electrical, electro-mechanical, and mechanical
inspection of parts and assemblies to ensure compliance with the requirements
of the procurement specification. In addition, screening and evaluation tests can
be performed by this organization on both planned and emergency basis.
The Project ,Manager may use the facilities and manpower of the Failure Analysis
Section to perform analyses and evaluation of failed parts and components. He is
encouraged to do so.
XASA has developed and published a series of reliability and quality assurance
publications setting forth stringent requirements for space program procurements
from research and development concepts to space operations. These publications
implement NASA policies and should be utilized to the extent necessary for hard-
ware procurements a s contractor, subcontractor, and Government agency control
documents.
Official NASA policy and detailed procedure for implementing these NASA publi-
cations a r e set forth in NASA Procurement Regulation NHB 5100.2, Part 1, Subpart
50, "Integration of Quality Requirements in NASA Procurements," and Part 1,
Subpart 51, "Integration of Reliability Requirements into NASA Procurements".
6 -4
a. NH.B 5 3 0 0 . - ~ ( l B )"Quality
, Program Provisions.for Aeronautical and .
Space System Contractors,'' April 1969. This publication sets forth
broad quality system requirements for prime contractor quality pro-
grams necessary to ensure that flight equipment and associated ground
support equipment meet the quality requirements of the program.
Complete implementation of this document requires control from initia-
tion of design to operational use; however, variations in detailed control
elements should be tailored to the circumstances of individual procure-
ment s.
6-5
g. Quality Assurance Brief. A monthly issuance of the Parts Branch,
Quality Assurance Division, discusses current parts problems, alerts,
failed part analyses completed, and recently published parts specifica-
tions which have come to their attention during the month. These pub-
lications a r e widely distributed to both GSFC personnel and approved
NASA contractors and e'xperimenters, including foreign e.xperimenters
in cooperating NASA programs.
6-6
PART 7
DATA UTILIZATIOIV AND MAl\iAGEMEST
7.1 EXPERIMENT DATA ANALYSIS, UTILIZATION, AND REPORTING
7.3 FUNDING
The project will fund the Principal Investigator so that he can meet his responsi-
bilities (para. 7.2). Funding will normally cover the period from e.qeriment
approval to submission of data to the NSSDC. The project will not fund the
Principal Investigators for data analysis after the data.are in the NSSDC without
specific approval by the Office of the Director. The data will normally be sub-
mitted to the NSSDC within two (2) years of the date they a r e taken.
7-1
7.5 DATA REQLTREMEXTS REVIEW COhIlIITTEE
The GSFC Data Requirements Review Committee has been established by the
Director to review and approve for him the requirements for data reception
and processing, including telemetry, orbit and attitude data, established by
each GSFC flight project. Reviews are carried out at various stages of the
project a s follows:
annually. The review will be organized and prepared for Headquarters by the
Data Requirements Review Committee. In it, the Project Manager will be
e-xpected to provide the statement of spacecraft status and prospects for
continued satisfactory operation. The Project Scientist will be expected to
review the scientific output of the spacecraft and its prospects for continued
production of good science, and the Data Requirements Review Committee will
address the question of the requirements levied by the mission on Center
facilities.
7-3
PART 8
PROCUREMENT
.8.1 PROCUREiMENT FUNCTIONS AlW ORGANIZATION
,,
17
iif
J
C
.-0In
.->
a
I
Q)
8-2
8.2 PROCC'REJIENT REWTIOKSHIPS
.-
-
c
. - 8-3
c
8.3 PROC'LRELIENT CYCLE A+XD LEAD TIJIES
The procurement cycle is the total elapsed time from the initiation of a project .
(by formally submitting a project approval document) until the hardware is de-
livered and the contract is complete. In many cases, this cycle covers several
years. The term "procurement administrative lead time'' is frequently confused
with the term "procurement cycle.'' Lead time refers to the span between the
receipt of a Procurement Request (PR) by the Procurement Division and the issu-
ance of a signed contractual document. The following is a list of the steps in a
sample l'procurement cycle" of a new competitive procurement of $2,500,000
from receipt of the PR to contract award and distribution.
b. R F P to Selection
(15) O r a l s complete
(16) final technical evaluation
(17) Final business evaluation
(18) Final BMC-TAC presentation to SEB
(19) SEB first presentation t_o GSFC
--
. -
e-
* 8-5
c
(20) Review by Director A&M
(21) SEB final presentation to GSFC
(22) SEB presents to NASA administrator Hdqts.
(23) Source selection
(24) Prepare statement of source selection (GSFC)
(25) Sign off of statement by Administrator ,
c. Selection to Award
(1) Price analysis requested
(2) Price analysis received
(3) Preparation of prenegotiation plan
(4) Prenegotiation plan. approved
.
( 5 ) Start negotiations
(6) Complete negotiations
(7) Prepare memo of negotiations
(8) Draft contract and prepare file
(9) Policy and regulation review
(10) Legal office review
(11) Changes and preparation for transmittal
(12) To contractor for signature
(13) Signed contract returned
' (14) GSFC review of any changes
(15) Forward contract to Hdqts.
(16) Hdqts review and approval
(17) A m r d spopized
(18) Contract distributed
8-6
NASA Procurement Regulation (NHB 5100.2) establishes approval levels. for
various contractual matters to be performed at Field Installations. For GSFC,
-
this level is generally established 3t $2,500,000 above which NASA Headquar-
t e r s approval is necessary.
Figure 8-2 is the current procurement administrative lead time usually neces-
s a r y for 'a specific requirement. Lead time standards are also included in the
GSFC publication, Procurement Request Handbook, GHB 5150.1C.
Because yarious Acts of Congress require many of the steps shown previously
it is difficult to shorten the time cycle. However, the lead-time cycle can be
shortened by influencing action in several key areas:
a. Ensure that procurement request packages are complete (i. e. , specifi-
cations, required justifications, o r approvals)
b. Exercise active control over the technical evaluation being conducted
within the project and, where possible, appoint someone to monitor
the overall effort
c . Schedule requirements realistically and use emergency procurement
action when necessary
d. Most important, .promote early coordination among the Technical
Representative, the Negotiator, the Financial Analyst, and the Project
Support Business Representative
A number of open-end contracts already e.&t which may be used to speed up the
placement of contract coverage:
Quick-reaction work-order contracts
a. Contracts for Off-Site Engineering Design Supporting Fabrication and
. Associated Technical Writing Services (see GMI 5104-lB)
b. Contracts for Off-Site Fabrication Services (GMI 5104.3)
c. Off-Site Computer Programming and Systems Analysis. These con-
tracts provide for performance of off-Center requirements in: orbit
determination; ground system operations ; satellite control; and scien-
tific data processing (see GMI 5104.1B as revised). -The Technical
Services Branch will assist in the use of these contracts.
This sectipn covers the procurement cycle from the time initi'ator begins rout-
ing the PR through his own management, financial management, other groups
+
. -
8-7 e-
c
Type ?mcurement
Action Code
CONTRACT m I
I
I I ' I ! I 1 I
1
I
!
1
I
R x u L 9 P / N O ? ! ~ @ N LA I I I 1 i 1 1 ; .
sx<vxm I I 1 I t 1 1 1 *I 1 I
S2.W and over ' 9 - 7 - 1-6-7 -1-2-3- I.-N!h-2
SloOM t o f2*5E! . 7 - 5- 1-5-5 -1-2-3- l-![/A-Z
JiooK t o SLOM 6- S- 1-5-5 -1 --1-2- 1- 2 - 2
S2.5K t o 31ooK L- 3- 1-3-3 -l-l-.l- 1- 1 - 2
f 0 to S2.5ii 1- 1- 1-1-1 -1-1-1- I- 1 - 2
bo Should you need a lead t i m e f o r a contract type aot mentioned above, such
W: Construction, A r r h i t e c h t u e ' & Wineer-24 Sexvices, teases, or
.
Automatic 3aLa Processing Scuipment Contracts, contact procurement bxanch
pc=onnel
C. Use only t k e t n e p n c u n n e n t action codes fobnd above.
8-8
necessary because of any special approvals, the Property Branch for certification
of nonavailability from stock, and Center management when the dollars involved
warrant it, until the Procurement Division receives it for processing. The pre-
planning and control of PR's during their early life is a vital element of a re-
sponsive, successful project procurement program.
The Project Operating Plan (POP) is a valuable tool for procurement planning.
Requirements should be carefully planned, not only as to their technical content
but also as to the availability of a complete package: procurement request,
specification, work statement, and any required justification. If availability data
and type of procurement action a r e accurately forecast and e'upressed in the
POP, the Procurement Division can, in coordination with the project, plan con-
tractor go-ahead dates.
The Project Manager should be familiar with the Procurement Requests Hand-
book, GHB 5150.1C, to supervise the assembly of the PR package. If time per-
mits, he should discuss with the assigned negotiator the detail of the PR before
starting the papers through the approval cycle.
8-9
b. The package should include provisions for preservation and packaging.
NHB 6000.1 o r Military specifications on this subject can be refer-
enced for the necessary coverage.
Each R&D procurement over twenty-five ($25,000) dollars requires a valid in-.
house estimate, that may be prepared in accordance with the ,guidelines set forth
in GHB 3150.1C, para. '2-4, a s revised. The estimate is required for several
purposes, one of which is to evaluate prospective offerors' proposals when ade-
quate e.xperience o r competition is lacking.
Gal1 5310.2A (para. 2-34) establishes the policy that all PR's for material, sup-
plies, and equipment intended for space flight use will be reviewed by Quality
Assurance Division personnel to assure that adequate reliability and quality
requirements a r e included commensurate with program needs, the intended ap-
plication of the item, and NASA and GSFC policy. Quality Assurance Division
personnel will, when requested, assist the PR initiator in developing R&QA re-
quirements f o r all spaceflight hardware procurements? ensuring the compati-
bility of these requirements with the needs and intended use of the equipment.
Special PR's include planning PR's and blanket PR's. Planning PR's (planning
I stubs, as they a r e frequently called) a r e used to minimize the impact of fiscal
I constraints by allowing concurrent processing of the procurement action while
I the funding problem is being resolved. They a r e used primarily when fiscal
constraints a r e present but w i l l be alleviated.
TO the Project >Ianager, planning PR'S , a r e effective weapons against fiscal con-
straint. Planning PR's should be used for large procurements which require
8-10
extensive administrative planning and work which, if carried on while the funding
problem i s being overcome, can lessen procurement lead time.
The blanket PR provides a source of funds within the Procurement Division for
mandatory immediate changes, pursuant to GHB 5104.2% (paragraph 7 . 7 ) . The
advantage is that the individual PR's go directly to the negotiator who draws the
necessary funds from the blanket PR already processed. A new blanket PR is
issued when the available balance is exhausted. Because they w i l l be obligated
as a series of actions over a prolonged period, blanket PR's must be handled
carefully in the Project Operating Plan.
Various Automatic Data Processing (ADP) reports issued by the Business Data
Branch may be useful in keeping track of PR's. Project Managers and PR
Initiators receive copies of these reports regularly. Among the most important
are:
b. -
Report 1233A Status of PR's in fiscal year/program-project/PCN
sequence (bi- w eekly)
Buyer Description
Procurement control number Type PR (routine/emergency/planning/
Job order number oblig. authority)
Budget line item Date PR received
Fiscal year of funds Type procurement action
Commitment dollars Next milestone due
No. of days hence
Milestone is due o r is late
-This section deals with procurement administrative lead time, which begins
when the Procurement Diviqion receives the procurement request and ends with
the award of the contract.
8-11
1, 8.5.1 Types of Contracts
The proper business environment requires the selection of the appropriate type
of contract. The objective is to negotiate a type of contract and a price that in-
cludes reasonable contractor risk, and provides the Government a means of
achieving maximum technical return from the dollars being invested. During
the preparation of the procurement plan the Contract Negotiator with the assis-
tance of the Project Manager makes some preliminary decision on what type of
contract that will be specified within the solicitation document. Technical input
must consider matching the nature of the requirement with the ability of the
Government to describe the end-product required. Generally, the spectrum from
basic research to production in the requirements end, affords an opportunity to
'
choose from a range of standard cost-reimbursement contracts to firm *fixed
price. '
The GSFC practice is to utilize a firm fixed-price and/or an incentive type con-
tract to the e.xtent feasible and practicable. If the Contract Negotiator and the
Project Manager (or his representative) believe that there are possibilities for
incentive contracting they should secure the advice of the Special Assistant for
Incentive Contracting early in the planning stages of the procurement process.
The NASA Procurement Regulation, NHB 5100.2 (formerly NPC 400), 3.852, .de-
scribes procurement plans in detail. A procurement plan outlines the method by
which the Contracting Officer expects to accomplish the procurement task. The
procurement plan must be approved before a request for proposal can be issued.
The procurement plan is also a means of justifying a particular approach and of.
obtaining management approval of the proposed action. Usually, procurement
plans a r e required when a contract estimate exceeds $100,000. Procurement
plans a r e particularly significant to the Project Manager because of the admin-
istrative processing time r e w i r e d for coordination.
The Procurement Officer (Procurement Division Chief) approves plans for amounts
up to $ 1 , 0 0 0 , 0 0 0 ; the Installation Director approves those over-$1,000,000; the..
Associate Administrator for Organization and Management approves those of
32,300,000 and above. It now takes appro.ximately 30 days to process aplan from
receipt of the PR to approval by the Associate Administrator For more informa-
tion. refer to "Contents of the Procurement Plan, " SHB 5 1 0 0 . 2 , part 3 . 9 5 2 - 3 .
9-12
a. Any electronic digital computer, regardless of use, and any peripheral
or auxiliary equipment used with it o r in support of it.
When it falls within the authority of the Contracting Officer, a D & F does not gen-
erally present a time problem. However, for an R&D contract, estimated at over
$100,000, the law e'xpressly states that the Administrator o r Deputy'Administra-
tor of NASA must approve the D&F. The administration lead time for this
process will be 4 to 6 weeks o r more. When GSFC authority can review and
approve the D&F, the process will usually be less than 1week.
8-13
8..3.4 Request for Proposals, Request for Quotations, 'and lnvitations for Bids
3-14
and place the Government in a position to be justifiably critized. Goddard has
adhered strictly to the NASA policy on the matter of RFQ's; therefore, none a r e
to be utilized except with the prior approval of the Procurement Officer.
8.5.4.3 Invitations for Bids (IFB's). IFB's are used when the sealed-bid
method of procurement can be utilized. Very definitive specifications a r e re-
quired. One of their distinct advantzges is the speed with which large amounts
of orders may be placed. GSFC edxperience has been to use the IFB primarily
for large quantities of developed items, off-the-shelf equipment and supplies,
construction of facilities, o r standard commercial ser;ices such as printing.
Technical discrepancies must be kept to a minimum in order to avoid official
protests when the contract award is made.
8-15
a. Contractor's understanding of the scope of the work, as shown by the
proposed scientific and technical approach
. b. Availability and competence of experienced engineering, scientific, o r
other technical personnel
3-16
,
See the GSFC publication entitled "GSFC Source Evaluation Board Handbook -
July 1971."
The number of labor hours required to perform a job and the span of time over
which these hours will be applied, are factors that assist in determining whether .
or not the company has an understanding of the job. Also, the list of a a t e r i a l s
and equipment, including Government- Furnished Equipment (GFE), a r e important
and both labor hours and materials will measurably assist in the technical evalu-
ation. However, aside from that, a technical analysis considers the quantities
in relation to each task proposed by the offerors or their subcontractor, and
compares these and other elements with the Government's estimates, other
offeror's proposals, and historical information, if available. Technical analysis
occurs usually in the later phases of technical evaluation when it is certain, o r
fairly certain, which prospective contractors will be in the competitive range.
Some type of technical analysis is usually required even on noncompetitive
procurements.
A good technical analysis will cover the following points and comment on areas
which require further clarification, e.uplanation, o r revision:
8- 17
Subcontracts
Travel expense
Transportation: Number of persons travelling, and number of trips
from where to where
Per diem: Number of persons and number of days
C a r rental: Number of days and estimated mileage
Other direct costs
Consultants
Freight
Comments a r e not required on labor, overhead, and G&A rates, because the
price analyst will review and recommend the rates that make up the Government's
position. The price analyst is also responsible for using the technical analysis
and rate data to assist the negotiator in establishing the negotiation objective.
8- 18
8.5.8 Preaward Surveys and Fact Finding
8-19
8.5.10 Prenegotiation Plans
A prenegotiation plan draws upon all information and facts developed during the
evaluation process and establishes a firm negotiation position with respect to
each segment of the contractor's proposal. Prenegotiation plans a r e required
for all procurements over $10,000 and must be approved at the following levels:
0 $10,000 to $100,000 - Procurement Section Head
$100,000 to $500,000 - Procurement Branch Head
$500,000 to $1,000,000 - Procurement Division Chief
0 $ 1 , 0 0 0 , 0 0 0 and over - Procurement Division Chief with the concur-
rence of the Director .A&M
The technical representative is usually requested to review, concur in, o r com-
ment upon prenegotiation plans over $500,000. Incentive arrangements included
in prenegotiation plans must be approved By the NASA Director of Procurement
when the proposed contract exceeds $2.5 million except when approval authority
has been delegated to GSFC under the Master Buy Plan Procedures (see para.
8 . 3 , above).
The GSFC contract negotiator should ascertain from the company negotiator the
e?ctent of his authority to bind the company, a s it is futile to reach agreements
'that will later be set aside,
8-20
appropriate and one should not hesitate to break off negotiations when disagreeing
on a key point. When the disagreement concerns a nonessential point, defer the
discussion and proceed to the next point. As the opposing positions move closer,
the points of earlier disagreement usually diminish in significance. In all fair-
ness to the company negotiator, if he inquires he should be advised that if the
amount negotiated exceeds GSFC authority, the amount and other terms will re-
quire ratification by Headquarters authority. .
Occasionally, the agenda for the negotiation is established prior to the confer-
ence when it appears that such a procedure may be necessary to conduct the nec-
essary business within a specified time frame. However, the agenda when estab-
lished is rather general in order that the Government does not divulge its position
with regards to the total matters it may wish to consider. Discussions with con-
tractor personnel should be businesslike, and only one member of the Govern-
ment's team should speak at a time.
8.5.12 Award
. .
8-21
b. SXSA Source Evaluation Board Manual (NPC-402, .August 2964)
Because of the sensitive nature of source evaluation in g.eneral, and the applica-
bility of the principles used in formal boards to lesser procurements, the fore-
going documents are suggested reading for the Project Manager.
The postcontract stage of the procurement cycle spans the period from award of
the contract through delivery of the hardware o r services and successful com-
pletion of all related items of work. This period continues until the contractor
is paid in full and the contract file is closed out.
8 .G .2 Technical Direction
8-22
assigned to contractor and supplier plants to perform Government quality
assurance functions. NASA has an agreement with DOD for use of these field
offices, and has established a policy to make m a x i m u use of the contract-
administration services and related field-support capabilities of DOD. It for-
bids the assignment of NASA personnel to a plant site to perform contract-
administration services without justLfication to the Institutional Director and
Director of Procurement. The directive lists the functions to be delegated
and, generally, the functions to be retained (see NASA P R 51-310). Many
agencies become involved in enforcing statutory provisions (e.g., Department
of Labor for compliance with Davis Bacon, Walsh Healy, and Service Contract
Act, the Health and Safety Act of 1970, and the Equal Employment Opportunity
Program).
Other provisions of the contract can be enforced by DOD field offices, which a r e
usually under the Defense Contract Administration Services of the Defense
Supply Agency. A limited number a r e U d e r the Department of A i r F0rc.e and
Navy. A Defense Contract Audit Agency is widely used in gathering negotiation
data and auditing cost-reimbursable contracts and fixed-price contracts which
involve progress payments.
After the award of a contract, the Contract Management Branch of the GSFC
Procurement Division reviews the contract in coordination with the Project
Manager and prepares the necessary letters to DOD field offices delegating
functions which include contract administration, property administration, pro-
duction SweiLlance, quality control, security, health and safety, small business
monitoring, engineering, and audit. It arranges for any necessary post-award
conference with the DOD field offices which is encouraged by NASA and manda-
tory for all contracts over 5 million dollars. It is to the interest of the Project
Manager o r the Technical Officer to participate in such conference.
8.- 23
The Property Administrator monitors the contractor's control of Government
property. A Technical Officer should ship property to the contractor with ap-
propriate documentation to the Property Administrator, in order to ensure that
. it is received under a control system and recorded as Government inventory.
The Property Administrator can be helpful in ensuring proper use of GSFC prop-
erty on the GSFC contract.
I The auditor verifies the contractor's costs and helps to maintain regularity of a
contractor's books of accounts.
DOD staff engineers have proven useful because of their e.qerience with design
drawings and material review boards. When these engineers a r e available in a
plant, advantage can be taken of their talents on the spot and they can save many
project trips.
The Contract Management Branch. has available for consultation, staff counter-
parts for administration of contracts, property, and production surveillance.
The Branch is also the focal point for receiving complaints concerning the per-
formance of DOD activities with respect to GSFC contracts.
4 quality engineer from the Quality Assurance Division will assist the Project
>Imager in the foregoing activities.
. 8-24
pre-emption of project work by a higher DOD priority. Help may also be ob-
tained through the Defense Contract Administration Service group assigned to
the particular contract (see para. 8.6.3, Contract Management). X limited
e.xpediting capability exists within the Contract Management Branch of the
Procurement Division. Whatever is done, the Project Support Representative
and the Project Negotiator must be aware of the difficulty.
Parts, materials, and electrick instruments ordered for project use may be
tested and inspected by the Incoming Inspection Facility managed by GSFC's
Quality Assurance Division.
8-25
8.7 .I Relationships with Industry
When it has been determined that contracting for services is proper and essen-
tial, it is imperative that requirements for either new contracts, or e.xtensions
to eAsting contracts, be initiated at the earliest possible date. A review of the ,
Justification for Nonpersonal Services, the need for a staffing plan, and a Cost
Comparison study, takes considerable processing time. The policy and proce-
dures relating to support service contracts are set forth in NASA Document
NPC 401 and GHB 5150.1,C.
8.7.4 Summary c
This part of the Project 3lanager's Handbook is not the last word on matters of
'
procurement; it merely zssembles information and points out some important
a r e s for consideration. Changes in language, practice, and interpretation a s
a
to what can be done a r e a way of life. If you have a unique procurement prob-
lem, ask procurement personnel to discuss it and assist in the matter.
3-26
PART 9
FINANCIAL MANAGEMENT
9.1 NASA FUNDING POLICY-DLRECT TO PROJECT
The Project Manager is responsible for the business mnnn-pement of his project,
including the review, approval, o r disapproval of all dollar, civil senrice and
contractor personal support manpower budgets submitted as part of the Center's
semiannual grass-roots budget call for financing of support of his project. If
the Project Manager disapproves dollar o r manpower budgets for work to be
performed on his project, he must prepare a memorandum to the Division Chief
affected, with copy to the Chief, Financial Management Division (FMD),of all
revisions made to the budgets. Changes to the grass-roots budgets will not be
made without such memoranda. The Chief, FMD,will be responsible for deter-
mining whether the affected Division Chief concurs in the change. If the Division
Chief does not concur, then the Chief, FMD, is responsible for bringing the
problem to the attention of the appropriate Directors of-. Any problems they
cannot resolve will be brought to the attention of the Director.
9-1
The PAD summarizes the results of previous flight missions apd mission objec-
tives for spacecraft to be launched. It also specifies the Center responsible for
project management, the number of spacecraft, the type of booster, and the cur- '
The resources authority warrant is the official dollar authorization to the field
center by individual projects, which allows the Financial Management Division
to certify that funds a r e available at the Center for project requirements. After .
the Financial Management Division has certified funds, the Procurement Division,
Experimental Fabrication and Engineering Division, and Management Seflices
and Supply Division, are authorized to contractually obligate the United States
Government for materials and services ordered by the project.
In essence, a Form 506 represents a deposit to a job order which allows com-
mitment and obligation of Government funds.
9.5 SUBAUTHORIZATIONS
The subauthorization is the official document with which NASA field centers
finance services requested by one field Center of another NASA Center. A sub-
authorization transfers Form 506 and allotment dollars to the Center for the
services requested. Because it is NASA policy that work cannot begin without a
Form 506, the NASA Center, from which services a r e requested, must receive
a subauthorization before beginning the effort.
The NASA Center receiving the subauthorization is responsible for funds control
and reporting for the services rendered. However, the policy of Headquarters
is that the Center with project management responsibility for a project must ~
9.6 REIXBURSABLE'S
9-2
to issue the Form 506 authoSity and allotment authorization. Upon receipt of
these, procurement requests may be initiated subject to Financial Management
Division certification that funds a r e available. GSFC cannot subauthorize any
portion of a resource authorization received for a reimbursable order.
The Project Manager is responsible for assuring that all expense attributed to
reimbursable effort is charged to the resources authority warrant. This includes
a l l costs for purchases for material o r services, Civil Service manpower
travel, facility usage and overhead expenses when applicable.
NASA has one of the simplest appropriati'on (budget) structures in the Federal
Government in that NASA uses only three appropriation titles as contrasted with
other agencies which have as many a s 70 appropriation titles. The three NASA
appropriation accounts are Research and Development, Construction of Facilities,
and Research and Program Management.
9-3
involving new structures wherein the costs exceed Sl0,OOO and modifica-
tions to existing structures costing in excess of 525,000 a r e financed by
this appropriation. C of F funds a r e not limited by Congressional action
as to life duration. However, NASA has the option of establishing ex-
piration dates for field centers' use of these funds.
POP Submission to
NASA Headquarters Requirement
The Government's fiscal year is the 12-month period from July 1 to June 30.
9-4
ul
Q ) '
c
0
e
ul
Q)
5
Q)
c
.-
e
4)
Q)
9
a
m
b
;
0
a
c
s
c
0;
2a
.-
Q)
i
a
I I
9-5
9.7.3 Budget Estimating- Dollars
A very critical element in the budget process is the problem associated with the
initial estimates of the total cost of a new project and the time-phasing of resource
requirements by fiscal year. There a r e various types of data available for use in
estimating the costs of new projects. Cost data a r e available for completed and
on-going projects, and actual costs for similar systems o r subsystems may be
used for costing purposes. Estimates may also be prepared based on projections
of contractor manpower required to design, fabricate, and test the spacecraft,
experiments, and associated ground support equipment. A very useful tool in the
pricing of new projects is the technique of "cost modeling."
Once the total project cost has been established, spending profiles a r e prepared
which relate program s t a r t and length to fiscal year funding requirements. A
typical funding profile is a function of the total project length in that the percent-
age of contractor spending in any given year will vary when the length of the
project is either extended o r shortened.
Through the utilization of available cost data and sophisticated estimating tech-
niques, the reliability of cost estimates f o r new projects is improving.
. 9-6
funding of contracts each fiscal year a s opposed to fully funding cost reimbursable
contracts at the total negotiated value at the time of award.
Proposed new-start projects should also consider cost growth factors such a s
labor union agreements and their impact on labor costs. This is important be-
cause development, fabrication, and flight operations involve several years and
we do not have contractor proposals which anticipate these factors for estimating
and pricing purposes,
The Office of Manpower and Budget (OMB) prescribes that five-year estimates
should be based on projections of cost (in constant dollars at prices existing at
the time estimates a r e prepared) which (1)a r e not intended to predict future
economic conditions, and (2) do not reflect possible changes in the scope of
quality of the program which might result from experience gained in actual
practice.
9.7.4 iManpower
9-7
The manpower POP generally follows this decision cycle and normally comes
out in August. 'The basic plan is put together once a year, through the line
organization, and is documented in a Program Operating Plan and is updated at
least on 6 month centers. Individual project agreements a r e documented by
Memorandum of Agreement (see para. 2.6.3).
As stated above, the grass roots budget estimates a r e generally prepared at the
second level of line management,. the branches. The branches submit individual
"j&-order:' estimates for the various projects, and the total of all applicable
job-order estimates becomes the total project budget. The individual job-order
estimates for the R&D budget must be submitted in considerable detail; in fact,
each procurement costing $15,000 o r more must be described and the month the
commitment and obligation of funds a r e expected must be stated. The detail
required is as follows:
All job order budget items a r e also assigned job order numbers. The Center's
job order structure is basically the same a s the standard NASA system.
The job order budget reviews 2re very extensive with the following levels of
Center management involved in the review cycle:
9- 8
.0 Budget Office
0 F i r s t Level Line iManagement
0 Project Managers
0 Directors of -
0 Director
The Program Operating Plan (POP) is the key to the budget system. Prior to
formal implementation, each project must have a financial and Performance Plan
o r Project Plan which covers the entire life of the project. The formal device
for initiating and updating resource and funding requirements, and against which,
progress and status i s compared, i s the POP. The POP'S a r e time-phased
budgets which are updated twice annually and show detailed 5-year forecasts of
funding requirements for each project.
9-9
9.8.1 Program OfEices' Use 6f POP'S
The Program Office reviews the POP'S to ascertain progress, workload, adher-
ence to schedules, and ability to provide the requested funds to the projects. The
POP is then consolidated with POP'S of other centers which perform work for
the same Program Office. The consolidated POP becomes the Program Office's
official budget request to the Administrator.
b. Grant Program Office the program authority (funding) for executing its
POP.
C. Request funding authority from the Office of Management and Budget (OSIB);
this funding represents aportion of the previously approved NASA budget.
d. Review the budget for the ne.* fiscal year with the OMB.
A continuing resolution is an agreement passed by both the Senate and the House
of Representatives allowing Federal agencies to continue in operation beyond
June 30. This resolution is required when the appropriation act has not been
passed and funds a r e not legally available to finance Government operations.
For example, most appropriations for the .salaries of Government perscnnel
e-qire each June 30; an appropriation o r continuing resolution provides for
personnel salaries beyond that date.
9-10
9.10 GSFC'S JOB-ORDER STRUCTURE
71 2 831 21 75 03
I I I I I I
Responsible division
I I I
I I I I I
(spacecraft technology) I I I I
I I
I I I
Branch (spacecraft electronics) I I I I
I I I
Unique project (OAO) I I
I I ' '
I
I I
System (spacecraft) I
I I
Subsystem (spacecraft support) I I
I
Serial number I
Project -Managers cannot reprogram funds between projects (i.e., OAO versus
-
_.
Om).
9-11
A l l reprogrammings between projects, regardless of dollar amount, can be ap-
proved only by the Headquarters Program Office on the basis of a written request
from the Center Director,
9.13 COMMITMENTS
9.14 OB LIGATIONS
I
Accruals a r e total costs incurred by contractors for services rendered o r
I
materials delivered in support of a contract. Accruals do not include purchase
orders issued by a contractor for se-rvices o r materials that he has not received.
I
9- 12
,
The difference between the total funded value of a contract and the actual accruals
under that contract is referred to a s uncosted obligation.
9.18 DISBURSEMENTS
It is Goddard policy that the cost of operating the Center's Test and Evaluation
(T&E)and Quality Assurance (QA) Dhisions will be borne by the research and
development program.
9-13
. --
Each project bears the same percentage of the total T&E annual operating budget
as the percentage its planned manpower is of the total manpower available in
each division for direct flight-program support. Each project bears the same
percentage of the total QA annual operating budget a s the percentage of their
budget dollars in relation to the total R&D budget dollars.
After Center management approves the annual operating budget and the Project
Manager agrees to the manpower assignment, a fixed project cost is established
which cannot be changed. As they become available through Form 506 authority,
these funds a r e used to establish an R&D c a r r i e r account which is e'xpended a s
needed by the T&E and QA Divisions in accordance with the approved plan. .
This funding process does not include the cost of major procurements by T&E
and QA Divisions for unique requirements of a project. Each Division determines
these needs and negotiates f o r funds directly with the Project Manager. When
approved, the funds a r e identified a s a separate line-item entry in the project's
operating budget.
GSFC policy dictates that the cost of operating SES computers at GSFC be borne
by the several R&D flight projects. Costs will be shared by the Physics and
Astronomy and Space Applications Projects a s well a s the Delta Project.
d. Machine maintenance
9- 14
contribution of each project is based on the percentage of its total individual
budget to the total budget of each program area.
After Center management approves the total dollars required, the budget SES
'
computer support becomes a fixed assessment to the project. The Office of the
Director of SES manages the computer program.
The Financial Management Dvision through the Business Data Branch provides
the Project Manager with various reports that reflects both budgetary and actual
commitment, obligation, disbursement, and accrued cost experience. These
reports &e listed in the GSFC Machine Reporting Register, published periodically
by the Business Data Branch of the Program Support Division. Copies a r e
available by request.
These reports reflect the official accounting records for GSFC at a particular
time and may be used for reports o r statistical data.
9- 15
. --
APPENDIX A
A-1
APPENDIX A
Program Managers
1. The Program Manager is the senior NASA Headquarters staff official ex-
clusively concerned with the projects which compose his program.
3. The Program Manager's specific functions include, but are not limited to
the following:
(1)Objectives
(2) Missions
' (3) System concept
(4) Experiments
( 5 ) Schedules
(6) Funding
(7) Manpower
(8) Organization
A-3
(9) Procurement arrangements
(10) Interfaces among centers, agencies, ercperimenters, and contractors
(11)Facilities
(12)Reporting and review
(13) Controls
. -
/
A-4
L
(6) Congressional backup statements
(7) Budget material
(8) Mission status reports
(9) Other
Project Managers
1. The Project Manager is the senior NASA line official exclusively concerned
with the execution of his project.
3. The Project Manager's specific functions include, but a r e not limited to,
the following:
a. Developing and/or updating the Project Plan, which specifies the plans
for execution of all elements of the project, including:
(1)Objectives
(2) Technical plan, including systems concepts
(3) Reliability and qualie assurance provisions
(4) Management plan
(5) Bianagement report&
(6) Documentation management
(7) Procurement arrangements
(8) Configuration and change control
(9) Schedules
A-5
(10) Resource requirements
(11)Coordinated operations plan
(12)Experiment integration
(13) Data handling
(14) Facilities
c. Organizing and supervising his Center Project Office which directs the
execution of this plan.
g
-. Preparation and dissemination of working agreements.
h. Establishment of working groups and coordination committees. Suy-
porting design review groups and fiiilure analysis groups, established
by Center and Headquarters, etc., as required.
/
. -
A-6
I. c
i. Preparation of specifications.
j. Review of changes and approval within his authority.
k. Preparation of necessary documentation in support of his project.
1. Providing other necessary support to Center management.
m. Keeping Center management and the Headquarter's Program Manager
fully apprised of the status of his project, particularly with regard to
adherence to:
(1) Schedules
(2) Funding -
(3) Performance
A-7
APPENDIX B
B-1
APPENDIX B
PROJECT MANAGER
DEPUTY/OR
SCIENTIST ASSIST.
PROJECT MANAGER
1 I I
i
-- -
SYSTEMS RELIABILITY
SUPPORT
I - - - - - - (CODE 300)
EXPERIMENT MISSION
SPACECRAFT
*
OR SYSTEM OPERATIONS
SENSOR SYSTEM MANAGER SYSTEMS
MANAGER MANAGER
f I MISSION NET’NO R K
SUP PORT
MANAGER MANAGER
(CODE 500) (CODE 800)
SUBSYSTEM
EXPERIMENT SUPPORT I 1
COO RDINA TO RS (CODE 700)
B-3
APPEiVDIX C
c-1
.
CONTENTS
Page
c-3
.
APPENDIX C
1.0 GENERAL
1.1 Introduction
Identify the project and state the mission to which the Systems Safety Plan
applies. Describe briefly the spacecraft, its payload, and the ground system
involved. Identify the launch vehicle and the launch facility to be employed. .
. 1.3 Definitions
Under this paragraph define the safety team used in the plan. Examples a r e
given below. Of particular interest is definition of "systems safety" to be
used by the Projects Directorate, GSFC. This definition clearly differen-
tiates between extrinsic factors which subject flight hardware to hazards,
and intrinsic factors resulting in component o r subsystem malfunction. The
latter one to be considered a design, reliability a n d o r quality responsibilities
rather than safety responsibilities.
a. Safety -
Freedom from chance of. injury o r loss to personnel, equip-
ment, or property.
b. -
System safety Systems safety is defined a s those engineering and man-
agement practices and procedures necessary to avoid personnel injury
and property loss to the maximum extent practical. Systems safety in-
cludes the protection through launch of flight hardware from loss o r
damage from e.utrinsic factors, but does not include property loss or
c-5
.
State to whom the plan i s applicable and that this plan represents the safety
requirements planned for inclusion in contract work statements and System
Safety Plans from other Government organizations and contractors for
Project X. The planned implementation for each phase of the project may
, be outlined here.
~
List applicable NASA documents, project, and program documents and make
a statement of their applicability. Reference documents may be listed here
o r in an appendix.
Examples are:
a. Applicable Documents -
The following documents, of the latest approved
issue, form a part of this specification to the e-xtent described herein.
_ . C-6
c. NASA Documents
NHB 1700.1, Vol. I NASA Safety Manual, Basic Safety Requirements.
- NHB 1700.1, Vol. III - System Safety
- NMI 7100.4 Authorization and Control of Research and Development
Programs,Projects, other Activities, and Sources Related thereto. '
f. Reference Documents
A list of reference documents is contained in Appendix A.
In this section of the plan, describe the safety organizations and the respon-
sibilities for the GSFC project and associated contractors, the launch vehicle
project, the range, and other activities when involved. U s e organizational
charts where appropriate and identify personnel where possible.
The Project Safety OBicer should be named, his position in the project
organization delineated, and his responsibility as the overall systems safety
focal point established.
The relationship to the GSFC Health and Safety Engineering Office should be
established concerning the Industrial Safety responsibilities under Clause 86
of NASA PR 1.5204.
c-7
.
This section of the Safety Plan should include a chart of the prime contrac-
tors organization showing the relationship of the systems safety function.
The safety responsibilities of the prime contractor at all sites should be
stated. Indicate the prime contractor's responsibility for implementing
safety requirements on critical subcontracts.
This section should clearly establish the scope of the safety analysis to be
performed under the Systems Safety definition provided in 1.3-h above.
Consideration should be given to methodical examination and review of hard-
ware designs, test plans and procedures', and operating practices for the
purpose of identifying and controlling'hazards. '
c-9
.
The System Safety Program shall include coordination with the GSFC Health
and'Safety Engineering Office to ensure an effective and integrated total
Safety Program.
c-10
.
Each project will audit prime contractors' safety performance. The prime .
contractors will audit their own conformance to safety requirements and the
performance of their subcontractors and suppliers, a s required. These
audits will evaluate the degree of conformance to the established safety re-
quirements. Requirements audited will also include safety requirements
specified in design, manufacturing, test, and operational specifications.
c-11
.
ATTACHMENT I - APPENDLY C
HAZARD LEVEL CATEGORIES
A. Safety Catastrophic
B. Safety Critical
Condition(s) such that environment, personnel e r r o r , design characteristics,
procedural deficiencies, o r subsystem o r component maifunction w i l l cause
personnel injury, o r will result in a hazard requiring immediate corrective
action for personnel .
C. Safety Marginal
D. Safety Negligible
c-12
ATTACHMENT II - APPE'NDIX C
SYSTEM SAFETY PRECEDENCE
B. Safety Devices
C. Warning Devices
D. Special Procedures
E. Residual Hazards
Residential hazards for which safety o r warning devices and special pro-
cedures cannot be developed o r provided for counteracting the hazard shall
be specifically identified to safety and program management. Continuation
of effort to eliminate o r reduce such hazards shall be accomplished
throughout the p r o g r m by maintaining awareness of new safety technology . '
c-13
o r devices being developed and their application to the residual hazards.
Justification for the retention of residual hazards shall be documented.
c-14
. --
APPENDIX D
D-1
APPENDIX D
RELEASE PROCEDURES
2. Copies are provided to the NSM and MSM for concurrence within their
respective directorates.
4. The Project Manager signs page 010 (in the case of a revision the Project
Manager also initials the "validate" block(s) on page 030 for the correct
revision).
7. The documents attached to the memo consist of three copies of the SIRD
plus the original of page 010. (A11 the rest of the originals a r e retained by
the project office.) .
D-3
continuing requirements placed by the Tracking and Data activities of the
project. It is attached to the Project Plan and sent to OSS o r OA, as ap-
propriate for approval purposes, and after their action, it is sent by the
program office(s) to OTDA for information, review, and commitment of
support and future resources. Additionally, GSFC sends OTDA informa-
tion copies of the project plan and SIRD concurrent with the transmittal of
the same documents to the OSS o r OA program approving office.
The Office of the Director signs the memorandum and page 010 of
the SIRD and forwards the package to the Associate Administrator,
OSS o r OA.
The Associate Administrator, OSS o r OA, signs page 010 and for-
wards the package t o the Office of Tracking and Data Acquisition
(OTDA).
A copy of the SIRD and authority for use is sent to the Headquarters
Program Office in OSS o r OA along with original of page 010.
D-4
. --
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
GODDARD SPACE FLIGHT CENTER
GREENBELT. MARYLAND20771
SAMPLE
. .
SIRD (or Revision) Memorandum
E nc lo sur es
. Three copies of the ATS-F&G SIRD (Ftevision)
Original page 010 "Approval" page
GB:lh (8/18/70)
ATS Project, Code 460 ,
D-5
. .
APPENDIX E
.-
.-
. - E-1
c
c
.
0
0
1'
0
9
0
.
0
0
91 9
0 0
. .
I:E:
n
(?
5,
N
w v )
&
U
I
0
*
=I
E ' 31
0
d
c
w
z
z
0
v)
o?
W
a
4
EI 4
w H
.- .e+ X
.
I-
c
-
u
s0
u
2:
p 1 '
/
E-3
c
. .
E
0
d
.
0
0 7 .
0
0
0
ul
0
0 I'
0
0
0
n
0
l-4
rl
U
=/
*L* .
0
0
.
0
0 . "I
o
0
0
o
N
*
. m. O
n
d
h
E
v)
<
0
- 0
*T
- c ?
h
=I
*LL
0 0 0 0
5,
In
.
E -4
cy
0. 0
.
cy
d
.
rn 0. 0
w
c9
0 d
.
ro
0
e4
2 :
rn
U
ro
W ey
m
d
. m
d
cy
b
d
..
uo
04
Qo
0
9
0
cy
El 0
.
e4
4
-“I
m
m
0
d d
w
u
% ; 2 2
m L i v l w
co
I
0
e
0
E-5
i
9
I;
3
d
x 0
0
0
91 9
0 0
=jE
V m
0
d
.
0
Q
?I
0
9
0
CJ
0
0
I
z
.a-
s .
m
?I
n
rl
\o
pc
v
=I
*cr wd
d
0
"!
0 .
d
h
E
VI
c
c
cn
cy
rn
.
w
0 a
z
s zz c
cn U
J Llc
cr
w
2
E-c CJ 0
0 u c F+r Y
4 u zs,
kl
ic
U
w n
C J .
Z Lr
U U
v)
C
r(
pc
U
IJ
IJ
A
w
+i
3
w
3 1
0
CJ
* .
t: k
l W &
VI
5
e
d
d
u
s0
u
E -6