Acceptance Test For Transmission Distrib
Acceptance Test For Transmission Distrib
Acceptance Test For Transmission Distrib
Distribution Substations
Page | 2
Introduction
The Acceptance Test for Transmission and Distribution substation application is to show
the importance of acceptance testing in electrical substations. The substation is the
most important part of an electrical generation, transmission, and distribution system. A
substation consists of a group of equipment that’s performs an important position of the
power transfer. Some important substation components are: transformers, breakers,
surge arresters, PT’s, CT’s and grounding system.
The priority of this project is to search the various acceptance tests requirements for a
new substation equipment such as: transformers, breakers, surge arresters, P. T’s, C.
T’s and ground systems also to illustrate how vital it is for these tests to occur before
and after. The information about each piece of equipment with a thorough breakdown of
how they operate in the substation and what acceptance test are required to be done in
order to know if the piece of equipment will be able to contribute its essential role in the
substation or if it will have to changed.
Page | 3
Electrical Substation
In a substation that has a step-up transformer the application is to increase the voltage
while decreasing the current, while a step-down transformer decreases the voltage
while increasing the current for domestic and commercial distribution. The word
substation comes from the days before the distribution system became a grid. The first
substations were connected to only one power station, where the generators were
housed, and were subsidiaries of that power station.
The substations generally have switching, protection and transformer, and control
equipment. The large substation is composed of circuit breakers that are used to
interrupt any short circuits or overload currents that may occur on the network. In the
other hand, smaller distributions stations may use reclose circuit breakers or fuses
for protection of distribution circuits. Substations themselves do not usually have
generators, although a power plant may have a substation nearby. Other devices such
as capacitors and voltage regulators may also be located at a substation.
Current Transformers(C.T.’s)
Transformer
Potential transformer(P.T.’s)
Surge arrester
Page | 4
Circuit breakers
Grounding System
Acceptance Test
The first acceptance inspection, testing and start-up procedures is the most critical. The
initial inspections, both internal and external, should reveal any missing parts or items
that were damaged in transit; they should also verify that the transformer is constructed
exactly as specified. The acceptance tests reveal any manufacturing defects, indicate
any internal deficiencies, and establish baseline data for future testing on the
equipment.
The start-up procedures should ensure that the transformer is properly
connected, and that no latent deficiencies exist before the transformer is
energized. Ensuring that the transformer starts right is the best way to guarantee
dependable operation throughout its service life span.
Some manufacturers recommend a wide range of acceptance and start-up
procedures.
Page | 5
Transformer
The device that changes AC electric power at one voltage level to AC electric power at
another voltage level through the action of a magnetic field is a transformer. It consists
of two or more coils of wire wrapped around a common ferromagnetic core. These coils
are not directly connected. The only connection between the coils is the common
magnetic flux present within core.
One of the transformers winding is connected to a source of AC electric power, and the
second transformer winding supplies electric power to loads. The transformer winding
connected to the power source is called the primary winding or input winding, and the
winding connected to the loads is called the winding connected to the loads is called the
secondary winding or output winding.
Figure 1: Transformer
Page | 6
The transformation has a direct relation with the turn’s ratio, where the turn ratio can
define a, and simplify:
N 1 V 1(t)
= =a
N 2 V 2(t)
The relation between the i1 flowing into the primary side of the transformer and the
current i2 flowing out of the secondary side of the transformer is:
N 1 I 1=N 2 I 2
I1 1
=
I2 a
Page | 7
Figure 2: Transmission transformer
This work is limited in scope to standard testing procedures for transformers before the
installation, with their general purpose and methodology. Testing of the transformers is
done to determine their electrical, thermal and mechanical suitability for the system
where they will be applied or used. Most of the tests performed on power transformers
are defined in national standards created by IEEE, NEMA and ANSI, whose purpose is
to define a uniform set of tests recognized by both the manufacturer and the user.
When a transformer fails, the time of failure tests will decide whether the unit can be
repaired at the site or whether it needs to be returned to the manufacturer, or a
specialized center for repair. By comparing the results of the tests with the established
norms, a 'history' of the transformer can be compiled, and the reasons for failure can be
diagnosed. Some transformer acceptance tests are:
The Transformer Turns Ratio test is used to make sure that the Turns Ratio between
the windings of the transformer is correct. This ratio decides what the output voltage
of the transformer will be with respect to the input voltage. The ratio is calculated
under no-load conditions, with ratios calculated at the tap positions for each winding
and for the winding as a whole. A voltage is applied to one winding and the
voltmeters connected to both low voltage and high voltage windings are read
simultaneously. The transformer ratio is the ratio of the HV voltmeter and the LV
voltmeter readings. The ratio tests on three-phase transformers, is taken on one
phase at a time, and the measured ratio should be compared with the ratio
calculated using nameplate voltages. Any variation should be within 5%.
Page | 8
Figure 3: 3-phase Transformer Turns
Ratio Meter Unit
Power Factor
The winding insulation resistance test (also known as the Megger test) is a
measure of quality of insulation within the transformer. It can vary due to
moisture content, cleanliness and the temperature of the insulation parts.
All measurements are corrected to 20'C for comparison purposes. It is
recommended that tank and core are always grounded when this test is
performed. Each winding should be short-circuited at the bushing
terminals. Resistances are then measured between each winding and all
other windings and ground (for 2 winding transformer - H-LG, L-HG and
Page | 9
HL-G and three winding transformer H-LTG, L-HTG, T-HLG, HL-TG, HT-
LG, LT- HG and HLT-G).
Oil Test
The sample of insulating oil from a transformer in service can reveal much
information about what is taking place inside the transformer. There are
three basic enemies to insulating oil - oxidation, contamination and
excessive temperature. The following tests can be done:
Acid number
Dielectric breakdown
Power factor
Moisture content
Interfacial tension
After performing the tests the oil can classified as reusable; reusable with
minor reconditioning; or disposable.
Resistance
Page | 10
Kelvin bridge or similar bridge capable of measuring fractional ohms
accurately. For Wye connected values, measurements should be made
between each pair of bushings, then summed and multiplied by three-
halves to get the comparison value.
Figure 4: Insulation
Resistance and Polarization Index System
Phase Relation
The phase relation test is carried out for poly-phase (for instance, three-
phase) transformers to make sure that they have been connected in such
a way that their phase relationship is correct. A phase relation test
calculates the angular displacement and relative phase sequence of the
transformer, and can be carried out in conjunction with ratio and polarity
tests. The voltages of the phase of primary and secondary can be
recorded and comparisons made to get the phase relation.
Polarity
The polarity of a transformer is either additive or subtractive. In order to
find out the polarity of a transformer, a voltage is applied between the
primary bushings. If the resultant voltage between the secondary
bushings is greater than the applied voltage that means that the
Page | 11
transformer has additive polarity. If it is lower, the transformer has
subtractive polarity. Polarity is not important for a single connected
distribution transformer, but it is a vital concern if transformers are to be
paralleled or bank connected. Three phase transformers are also checked
for polarity by the same means.
Circuit Breakers
Page | 12
Types circuit breakers
Vacuum circuit breakers: have minimal arcing, so the arc quenches when it is
stretched a very small amount. Vacuum circuit breakers are frequently used in
modern medium-voltage switchgear to 35,000 volts.
Oil circuit breakers: are high-voltage circuit breakers in which the arc is drawn
in oil to dissipate the heat and extinguish the arc; the intense heat of the arc
decomposes the oil, generating a gas whose high pressure produces a flow of
fresh fluid through the arc that furnishes the necessary insulation to prevent a
restrike of the arc. In an oil circuit breaker with simple interruption under oil, the
duration of arcing is 0.02-0.05 sec. To extinguish the arc more efficiently, arc-
quenching chambers are used.
Page | 13
Figure 5: GCB Breaker Figure 6: Vacuum Circuit Breaker
Page | 15
Oil Circuit Breaker: Insulation test
● Power factor
High AC voltage test to detect insulation conditions.
● Insulation resistance
TEST DESCRIPTION: High DC voltage test to detect insulation conditions.
● Contact resistance
Test to measure the resistance between contacts and other electrical
connections.
● Ground & Integrity
TEST DESCRIPTION: Test to measure the effectiveness of ground systems and
its connections.
● Oil test
Test to measure acidity, power factor, and break down of the oil.
● Bushing tests
Test to measure capacitance and power factor
● Mechanical inspection and adjustments
Inspection of the adjustments of all mechanical parts.
● Velocity and time.
Test to measure velocity and the operating time of a power interrupter.
● Alarms checks
Test to verify the operation of all alarms devices such as oil temp, winding temp,
oil level, gas level, and others.
● Mechanical Interlocks
Test to verify the operation of all mechanical interlocks in power breakers, air
circuit breakers, grounding switches, and other electrical equipment’s.
● Oil / Gas leaks test
Test to verify oil or gas leaks.
● Valve final status.
Inspection of valve final position.
Soil resistivity
Test to measure soil resistivity.
Control and Protection test
● Electrical interlocks
Test to check the electrical interlocks equations.
● High voltage breaker general test
Test to check breaker devices and accessories such as: 52a and b
contacts, 69 switch, alarms, and control signals.
● Transmission line breaker control
Test to check the proper operation of a transmission line breaker
according to the application and design requirements.
● Distribution line breaker control
Test to check the proper operation of a distribution line breaker
according to the application and design requirements.
● Transformer breaker control
Test to check the proper operation of a transformer breaker according
to the application and design requirements.
● Capacitor bank breaker control
Test to check the proper operation of a capacitor bank breaker
according to the application and design requirements.
● Scada signals.
Test to checks all digital and analog signals included in the SCADA
signal list such as: digital inputs (alarms and status), digital outputs
(control), and analogs (measurements).
Page | 17
Vacuum circuit breaker (VCB): Insulation test
● Power factor.
High AC voltage test to detect insulation conditions.
● Insulation resistance.
High DC voltage test to detect insulation conditions.
● Contact resistance.
Test to measure the resistance between contacts and other electrical
connections.
● Ground & Integrity.
Test to measure the effectiveness of ground systems and its
connections.
● Hi-pot.
High DC voltages test to detect insulation conditions in cables, vacuum
bottles, GIS equipment, and others.
● Mechanical inspection and adjustments.
Inspection of the adjustments of all mechanical parts.
● Alarms checks.
Test to verify the operation of all alarms devices such as oil temp,
winding temp, oil level, gas level, and others.
● Mechanical Interlocks.
Test to verify the operation of all mechanical interlocks in power
breakers, air circuit breakers, grounding switches, and other electrical
equipment’s.
Page | 18
Control and Protection test
● Electrical interlocks.
Test to check the electrical interlocks equations.
● High voltage breaker general test.
Test to check breaker devices and accessories such as: 52a and b
contacts, 69 switch, alarms, and control signals.
● Transmission line breaker control.
Test to check the proper operation of a transmission line breaker
according to the application and design requirements.
● Distribution line breaker control.
Test to check the proper operation of a distribution line breaker
according to the application and design requirements.
● Transformer breaker control.
Test to check the proper operation of a transformer breaker according
to the application and design requirements.
● Capacitor bank breaker control.
Test to check the proper operation of a capacitor bank breaker
according to the application and design requirements.
● Breaker replacement.
Test to check the proper operation of auxiliary contacts (52a & 52b),
alarms, and its control wiring. Primary current injection and polarity test
is required as well.
● Scada signals.
Test to checks all digital and analog signals included in the SCADA
signal list such as: digital inputs (alarms and status), digital outputs
(control), and analogs (measurements).
Page | 19
Surge Arresters:
The primary function of a surge or lighting arrester is to limit the voltage stresses on the
insulation of the equipment being protected by permitting surges voltage to drain to
ground before damage occurs. The surges in voltage generally are caused by lighting or
by switching. Figure X shows a transformer with some surge arrester.
The arresters have two basic components: a spark gap and a nonlinear resistance
element (for a valve type) or an expulsion chamber (for an expulsion type). When a
surge occurs, the spark gap breaks down or sparks over, and permits current to flow
through the resistance (or chamber) element to ground. Since the arrester at this point
presents a low impedance path, a large current, referred to as 60 cycle follow current,
flows through the arrester. The nonlinear resistance, at the higher voltages, will tend to
restrict this current and eventually cause it to stop to flow. At this moment, the
magnitude of the follow current is independent of the system capacity. The expulsion
chamber will confine the arc, build up pressures that eventually blow out the arc, and
cause the follow current to stop to flow. At this moment, the follow current is a function
of the system capacity and the expulsion chamber must be suitably designed. After
each such operation, the arrester must be capable of repeating this operating cycle.
Types of Arresters
Surge arresters consist basically of an air gap in series with another element which has
the special characteristic of providing a relatively low resistance or impedance to the
current produced by a high-voltage surge, and a high resistance or impedance to the
flow of power current at the relatively low operating voltage of the distribution line to
which it is connected. In some later units, the air gap may be omitted.
Pellet Type: In the pellet type of the arrester, the second element is made up of
a tube full of lead pellets. The lead pellets are actually lead peroxide coated with
lead oxide. The pellets normally act as insulation preventing current from flowing
to ground. When a high-voltage surge is impressed on them, a current will flow
that heats them and turns the lead oxide (a poor conductor) into lead peroxide (a
good conductor). After the surge is discharged to ground, the surface of the
Page | 20
pellets is changed by the discharge current back to lead oxide and restores the
arrester to its original condition.
Valve Type: in the valve type of arrester, the second element may be made of
some particular substance such as ceramic material containing conducting
particles, such as metal oxides or other substances having characteristics under
surge-voltage conditions similar to those described above. Many of these are
built in modular units, several connected in series to accommodate the line
voltage impressed on them.
Expulsion Type: the expulsion type of arrester may employ a second air gap
enclosed in a tube made of fiber in series with a fixed air gap. As with fuse
holders made of fiber, when a high voltage occurs creating an arc across the
gap, the heat acting on the fiber gives off a no conducting gas under pressure
that blows out the arc, interrupting the flow of surge current and restoring the
arrester to its original condition.
Installation
Page | 21
Acceptance Test for Surge Arrester in Transmission and Distribution
Substations
There are three primary acceptance tests required for the installation of surge arresters
at new substations. These acceptance tests are focus in the insulation and mechanism
of the surge arresters. The three acceptance tests are:
Power Factor
High AC voltage test to detect insulation conditions
Insulation Resistance
High DC voltage test to detect insulation conditions.
Grounds & Integrity
Test to measure the effectiveness of ground systems and its connections.
Page | 22
Potential Transformers (P.T.)
The Potential Transformers is design for the monitoring single-phase and three-phase
line voltage in a power system. Also he calls a voltage transformer because is used for
a line and circuit protection. The primary terminals can be connected either in line-to-
line or in line-to-neutral configuration. A Potential Transformer is a special type of
transformer that allows meters to take readings from electrical service connections with
higher voltage (potential) than the meter is normally capable of handling without at
potential transformer. Potential transformers are designed to provide as accurate a
voltage step-down ratio as possible. To aid in precise voltage regulation, loading is kept
to a minimum: the voltmeter is made to have high input impedance so as to draw as
little current from the PT as possible.
Figure 9:
Potential Transformers (PT’s) in a substation
Page | 23
Potential Transformer Testing
Constant resistance
Test to measure the resistance between contact and other
electrical connection.
Ratio/ Polarity
Test to measure the turn ratio and polarity to transformers.
Other Testing:
Page | 24
Current Transformers (C.T.)
Current transformers measure power flow and provide electrical inputs to power
transformers and instruments. Current transformers produce either an alternating
current or alternating voltage that is proportional to the measured current. There are two
basic types of current transformers: wound and toroidal. Wound current transformers
consist of an integral primary winding that is inserted in series with the conductor that
carries the measured current. Toroidal or donut-shaped current transformers do not
contain a primary winding. Instead, the wire that carries the current is threaded through
a window in the toroidal transformer.
Page | 25
Current transformers have many performance specifications, including primary current,
secondary current, insulation voltage, accuracy, and burden. Primary current, the load
of the current transformer, is the measured current. Secondary current is the range of
current outputs. Insulation voltage represents the maximum insulation that current
transformers provide when connected to a power source. Accuracy is the degree of
certainty with which the measured current agrees with the ideal value. Burden is the
maximum load that devices can support while operating within their accuracy ratings.
Typically, burden is expressed in volt-amperes (VA), the product of the voltage applied
to a circuit and the current.
There are a variety of applications for current transformers. Some devices are used to
measure current in electronics equipment or motors. Others are used in street lighting.
Larger devices are used in many three-phase systems to measure current or voltage.
Commercial class current transformers that monitor low-power currents are also
available. Some current transformers are weatherproof or are rated for outdoor use.
Page | 26
Current Transformer Test (C.T.)
Normally to test a CT we do these tests:
Burden Testing
The CT secondary current is measured to determine a reference "no
applied burden" current output. A resistive burden of 0.1 ohm is
automatically applied to the current path and the CT secondary current is
again measured. Additional resistance values from 0.1 to 4.0 ohms are
sequentially applied up to the limit specified by the operator.
Power Factor
CTS insulation resistance test at BKRS, Trans. & Generators
Insulation Resistance
Primary Current Injection and Polarity Test
Burden and DC Resistance
Page | 27
For Bushing type current transformer:
Page | 28
Grounding System:
The ground mats are engineered to achieve impedance levels that provide adequate
protection and stability for a facility, and once installed they remain physically and
electrically stable. The ground mat protects the personal employee and property from
injury or damage by high voltage surges resulting from lightning, switching, or other
causes. Also the ground mat handles discharge currents from lightning arrestors,
overvoltage gaps, and so on. Provide stable ground conditions for protective relays. The
following are valid reasons for considering such tests:
To obtain realistic resistance data for use in calculating actual ground potential
rise (GPR) values for the mat, and for determining the step and touch potentials
which may occur within a station during fault or surge conditions.
To help to resolve the instability of equipment relays or communications, which
might be caused by inadequate grounding.
Page | 29
To determine the continued adequacy of the ground mat wherever system
changes are implemented which increase the available fault current at the
station.
In all types of work station mat pads station the specific requirements and test intervals
should establish benchmark data for all substation ground mats. Ground mats from new
electrical facilities will be tested to verify their intended design and adequacy. Whenever
the ground mat is modified, the ground mat should be tested. Ground mats should be
tested whenever there is a concern about the continued performance of the grounding
system.
Personal Protective Grounding for Electric Power Facilities and Power Lines
Most of the grounding cable in use actually is manufactured as welding cable. These
extra-flexible copper cables and their insulating jackets are suitable for grounding cable.
Grounding cable must be sized adequately to carry the maximum available fault current
at the worksite. Most transmission level switchyards and substations are electrically
configured grounded-wye and therefore electrical faults can involve ground (earth). Both
three phase and single-phase-to-ground faults should be considered when determining
the maximum available fault current at a grounded worksite.
Page | 30
Grounding System Tests
Page | 31
Test to check the proper operation of the ground directions over current
relay. In some medium voltage distribution lines and almost all high
voltage transmission lines, a fault can be in two different directions from a
relay, and it can be highly desirable for a relay to respond differently for
faults in the forward or reverse direction. Directional over current relaying
would not be useful in a system with only one source. Overload test is to
be carried out as a type test for generators as proof of overload capability
of generators and the excitation system, for motors as proof of momentary
excess torque as required. The over-load test can be replaced at a routine
test by an overcurrent test. The overcurrent test is to be proof of the
current capability of the windings, wires, connections, etc. of each
machine. The overcurrent test can be performed at reduced speed motors
or at short-circuit generators.
The relay will trip whenever the overcurrent and directional units issue a
trip permission simultaneously, being the first trip time delayed (definite
time from 0 to 3 sec) and the next instantaneous during the associated
reclosing cycle, minimizing in this way the damages caused by a close
over fault. The relay continues operating in instantaneous trip mode for 10
sec, after the first time delayed trip. After these 10 sec the relay
automatically goes back to the time delay mode. The election of values
which determine the operation curve characteristic for the overcurrent unit
is made from the relay frontal nameplate and depends on the
characteristics or needs of the system in which the relay is going to be
applied. The possibility of delaying the trip up to a maximum of 3 sec is
included, being such election made from the front of therelay.
Page | 32
Figure 12: Substation Grounding Mat
Switchgear
Switchgear is a device used solely to open and close electric circuits, especially one
used to control a high-current application, e.g. a power and transforming station or an
electric motor.
Page | 33
2 and phase 3 with phase 1 to grounded, and phase 3 and 1 with phase 2
grounded.
DC Hi-Pot Test
The DC hi-pot test is normally not made for AC electrical switchgear and
therefore may be considered only when AC hi-pot cannot be performed.
The hi-pot testing of switchgear involves testing of the circuit breakers and
switchgear buses separately. This is a major test and determines the
condition of the insulation of the switchgear assembly. The DC hi-pot test
is not preferred for testing AC switchgear because the application of DC
voltages does not produce similar stress in the insulation system as is
produce under operating conditions.
AC Hi-Pot Test
This test should be conducted separately for circuit breakers and
switchgear buses (stationary gear). It should be made only after the DC
insulation resistance measurement test has been passed satisfactorily and
all cleanups has been finished. The AC test will stress the switchgear
insulation similarly to the stresses found during operating conditions. Hi-
pot test are made with the circuit breaker in both open and closed
positions.
Page | 34
Power Factor Testing
The power factor testing of an insulation system is useful in finding sings
of insulation deterioration. The absolute values of power factor measured
little significance. However, comparative analysis of values from year to
year may very good show insulation deterioration. Therefore, when a
power factor test is maid, it should be made under the same conditions of
temperature and humidity.
Circuit breaker contact resistance measurement test
Stationary and moving contacts are built from alloys that are formulated to
endure the stresses of electrical arcing. However, if contacts are not
maintained on a regular basis, their electrical resistance due to repeated
arcing build up, resulting in a significant decrease in the contact ability to
carry current. Excessive corrosion of contact is detrimental to the breaker
performance. One way to check contacts is to apply DC and measure the
contact resistance or voltage drop across the closed contacts. The
breaker contact resistance should be measured from bushing terminal to
bushing terminal with breaker in closed position. It is recommended that
for MV and HV the resistance test be made with 100A or higher DC. The
use of a higher current value gives more reliable results than using lower
currents values. The resistant value is usually measured in micro ohms.
The average resistance value for 15KV class circuit breakers is
approximately between 200 and 250 micro ohms. Several companies
make good, reliable micro ohmmeter to perform testing. One such
instrument is the megger DLRO 200. It can generate test currents from 10
to 200A and can measure resistance ranging from .1 to 1 Ohm.
Page | 35
Circuit Breaker Time-Travel Analysis
This test is usually performed on MV and HV circuit breakers, usually
34KV and above, to detect problems in the breaker operating mechanism.
This test can be conducted with a mechanical or electronic time travel
analyzer. With the analyzer information on the breaker operating
mechanism is provided in form of charts or graphs which can be used to
assess the mechanical and electrical condition of the breaker. There are
nine tests that are usually conducted on the breaker with the circuit
breaker analyzer.
Closing time and opening time
Contact bounced
Opening and closing synchronization
Closing and opening speed (velocity and displacement)
Trip operation
Trip-free operation
Closed operation
Trip-closed operation
Page | 36
Pictures
Page | 37
Conclusion
The Acceptance Test Transmission Lines and distributions substation are part of the
electrical companies looking every day the most efficient form of energy generation to
ensure availability, quality of service and reliability. An example of this is the advances
in the control and protection. The electrical substation facilities are intended to enhance,
modify and energy levels of an electrical infrastructure to facilitate the transmission and
distribution of electrical energy. Thanks to the experience and knowledge of engineers
and professional on this field are able to develop and meet all areas which help to
satisfy any need to improve the performance. For this reason all areas presented are
essential for high quality and with this power to protect retailers have mayor damage to
computers as they are expensive, its more feasible and cost effective.
Page | 38
Bibliography
1. http://electrical-engineering-portal.com/download-center/books-and-guides/power-
substations
2. http://pgti.net/acceptance-testing/
3. http://www.indeed.com/q-Transmission-Substation-Test-Engineer-jobs.html
4. http://www.electrical4u.com/electrical-power-substation-engineering-and-layout/
5. https://books.google.com.pr/books?id=fN9mQcROfBsC&pg=SL9-PA3&lpg=SL9-
PA3&dq=Acceptance+Test+for+Transmission+
%26+Distribution+substations&source=bl&ots=FTiak4NXtU&sig=9yyQ_cXKfhEaSQv
wOOM2xJff4oc&hl=es&sa=X&ved=0ahUKEwidhIuLl6rMAhUC9x4KHQiyD68Q6AEI
YzAJ#v=onepage&q=Acceptance%20Test%20for%20Transmission
%20%26%20Distribution%20substations&f=false
6. http://www.electricityforum.com/forums/substation-maintenance-onsite.html
7. http://www.eig-llc.com/about-eig/people/scott-wilson/
8. http://www.aetco.us/about-american-electrical-testing-services/
9. https://www.linkedin.com/in/phillip-kerry-07b59a92
10. http://www.jobs4people.org/JobDetail.aspx?jobid=14201
11. http://www.energy.siemens.com/hq/en/power-transmission/high-voltage-substations/?
stc=wwcg100550&s_kwcid=AL!462!3!75043495735!p!!g!!distribution
%20substations&ef_id=VsnG9gAAAOZCqwqJ:20160425161535:s
12. http://www.iskra.eu/fields_of_work/energy_sector/2012062812494762/
13. http://www.lipower.org/pdfs/company/projects/energyplan10/energyplan10-e6.pdf
14. http://www.energy.nsw.gov.au/electricity/networks/safety/electricity_transmission_asset_
mgt_code_of_practice.pdf
Page | 39
15. http://www.mannvit.com/PowerTransmissionDistribution/
Page | 40