Checklist Remarks Acceptance Criteria/ Requirement Reference Date of Inspection
Checklist Remarks Acceptance Criteria/ Requirement Reference Date of Inspection
PREPARATORY WORKS
1. Check condition of floor Floor must be leveled, dry and free
from debris
2. Check condition of wall behind wardrobe. Wall areas behind wardrobe should
be painted before installation of
wardrobe
INSTALLING WARDROBE
4. Check dimensions of wardrobe carcass Conform to approved shop drawing
11. Check alignment and plumb of door panel Door panel is horizontally and vertically
and consistent gap between door panel and aligned.
wardrobe carcass Consistent gap between door panel and
wardrobe carcass
13. Patch nail holes All nail holes are properly patcheds
PREPARATORY WORKS
1. Check condition of ceiling Ceiling should be painted
2. Check condition of wall and floor Wall behind upper kitchen cabinet
should be plastered
Kitchen wall and floor tiles should be
completed
4. Check pressure test on gas and water pipes Pressure test on gas and water pipes
running behind the cabinet must be
successfully completed
5. Check water inlets and outlets Water inlets and outlets should be
plugged off
11. Check alignment and plumb of cabinet Cabinet carcass is horizontally and
carcass vertically aligned
12. Install worktop base panel and cut out Conform to approved shop drawings
opening for installation of appliances
15. Install shelves and accessories Shelving are properly adjusted and rests
firmly on the shelf studs.
Conform to approved shop drawings
Checklist Acceptance criteria/ Date of Remarks
Requirement reference Inspection
17. Check alignment and plumb of door panel Door panel is horizontally and
and consistent gap between door panel and vertically aligned.
cabinet carcass Consistent gap between door panel
and cabinet carcass
19. Patch nail holes All nail holes are properly patched