0% found this document useful (0 votes)
181 views

Linear Programming Formulation Examples PDF

The document describes a linear programming formulation example involving allocating cargo among three airplane compartments to maximize profit. It defines variables for the amount of each cargo in each compartment, constraints for cargo availability, compartment capacities and balance, and an objective to maximize total profit. Using a software package to solve it offers advantages over manual judgement by finding the true optimal solution and allowing routine, automated solving with sensitivity analysis.

Uploaded by

Mohan Bolla
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
181 views

Linear Programming Formulation Examples PDF

The document describes a linear programming formulation example involving allocating cargo among three airplane compartments to maximize profit. It defines variables for the amount of each cargo in each compartment, constraints for cargo availability, compartment capacities and balance, and an objective to maximize total profit. Using a software package to solve it offers advantages over manual judgement by finding the true optimal solution and allowing routine, automated solving with sensitivity analysis.

Uploaded by

Mohan Bolla
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

9/17/2018 Linear programming formulation examples

OR-Notes
J E Beasley
OR-Notes are a series of introductory notes on topics that fall under the broad heading of the field of operations
research (OR). They were originally used by me in an introductory OR course I give at Imperial College. They
are now available for use by any students and teachers interested in OR subject to the following conditions.

A full list of the topics available in OR-Notes can be found here.

Linear programming formulation examples

Linear programming example 1996 MBA exam

A cargo plane has three compartments for storing cargo: front, centre and rear. These compartments have the
following limits on both weight and space:

Compartment Weight capacity (tonnes) Space capacity (cubic metres)


Front 10 6800
Centre 16 8700
Rear 8 5300

Furthermore, the weight of the cargo in the respective compartments must be the same proportion of that
compartment's weight capacity to maintain the balance of the plane.

The following four cargoes are available for shipment on the next flight:
Cargo Weight (tonnes) Volume (cubic metres/tonne) Profit (£/tonne)
C1 18 480 310
C2 15 650 380
C3 23 580 350
C4 12 390 285

Any proportion of these cargoes can be accepted. The objective is to determine how much (if any) of each cargo
C1, C2, C3 and C4 should be accepted and how to distribute each among the compartments so that the total
profit for the flight is maximised.

Formulate the above problem as a linear program


What assumptions are made in formulating this problem as a linear program?
Briefly describe the advantages of using a software package to solve the above linear program, over a
judgemental approach to this problem.

Solution

Variables

We need to decide how much of each of the four cargoes to put in each of the three compartments. Hence let:

xij be the number of tonnes of cargo i (i=1,2,3,4 for C1, C2, C3 and C4 respectively) that is put into
compartment j (j=1 for Front, j=2 for Centre and j=3 for Rear) where xij >=0 i=1,2,3,4; j=1,2,3

Note here that we are explicitly told we can split the cargoes into any proportions (fractions) that we like.
http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 1/16
9/17/2018 Linear programming formulation examples

Constraints

cannot pack more of each of the four cargoes than we have available

x11 + x12 + x13 <= 18


x21 + x22 + x23 <= 15
x31 + x32 + x33 <= 23
x41 + x42 + x43 <= 12

the weight capacity of each compartment must be respected

x11 + x21 + x31 + x41 <= 10


x12 + x22 + x32 + x42 <= 16
x13 + x23 + x33 + x43 <= 8

the volume (space) capacity of each compartment must be respected

480x11 + 650x21 + 580x31 + 390x41 <= 6800


480x12 + 650x22 + 580x32 + 390x42 <= 8700
480x13 + 650x23 + 580x33 + 390x43 <= 5300

the weight of the cargo in the respective compartments must be the same proportion of that compartment's
weight capacity to maintain the balance of the plane

[x11 + x21 + x31 + x41]/10 = [x12 + x22 + x32 + x42]/16 = [x13 + x23 + x33 + x43]/8

Objective

The objective is to maximise total profit, i.e.

maximise 310[x11+ x12+x13] + 380[x21+ x22+x23] + 350[x31+ x32+x33] + 285[x41+ x42+x43]

The basic assumptions are:

that each cargo can be split into whatever proportions/fractions we desire


that each cargo can be split between two or more compartments if we so desire
that the cargo can be packed into each compartment (for example if the cargo was spherical it would not
be possible to pack a compartment to volume capacity, some free space is inevitable in sphere packing)
all the data/numbers given are accurate

The advantages of using a software package to solve the above linear program, rather than a judgemental
approach are:

actually maximise profit, rather than just believing that our judgemental solution maximises profit (we
may have bad judgement, even if we have an MBA!)
makes the cargo loading the decision one that we can solve in a routine operational manner on a computer,
rather than having to exercise judgement each and every time we want to solve it
problems that can be appropriately formulated as linear programs are almost always better solved by
computers than by people
can perform sensitivity analysis very easily using a computer

http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 2/16
9/17/2018 Linear programming formulation examples

Linear programming example 1995 MBA exam

Briefly describe the main steps in using mathematical modelling to support management.

A canning company operates two canning plants. The growers are willing to supply fresh fruits in the following
amounts:

S1: 200 tonnes at £11/tonne


S2: 310 tonnes at £10/tonne
S3: 420 tonnes at £9/tonne

Shipping costs in £ per tonne are:


To: Plant A Plant B
From: S1 3 3.5
S2 2 2.5
S3 6 4

Plant capacities and labour costs are:


Plant A Plant B
Capacity 460 tonnes 560 tonnes
Labour cost £26/tonne £21/tonne

The canned fruits are sold at £50/tonne to the distributors. The company can sell at this price all they can
produce.

The objective is to find the best mixture of the quantities supplied by the three growers to the two plants so that
the company maximises its profits.

Formulate the problem as a linear program and explain it


Explain the meaning of the dual values associated with the supply and plant capacity constraints
What assumptions have you made in expressing the problem as a linear program

Solution

The main steps in using mathematical modelling to support management are:

1. Problem identification
Diagnosis of the problem from its symptoms if not obvious (i.e. what is the problem?)
Delineation of the subproblem to be studied. Often we have to ignore parts of the entire problem.
Establishment of objectives, limitations and requirements.
2. Formulation as a mathematical model
3. Model validation (or algorithm validation)
Model validation involves running the algorithm for the model on the computer in order to ensure:
the input data is free from errors
the computer program is bug-free (or at least there are no outstanding bugs)
the computer program correctly represents the model we are attempting to validate
the results from the algorithm seem reasonable (or if they are surprising we can at least
understand why they are surprising).
4. Solution of the model
Standard computer packages, or specially developed algorithms, can be used to solve the model.
In practice, a "solution" often involves very many solutions under varying assumptions to establish
sensitivity.
5. Implementation

http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 3/16
9/17/2018 Linear programming formulation examples

This phase may involve the implementation of the results of the study or the implementation of the
algorithm for solving the model as an operational tool (usually in a computer package).

To formulate the problem given in the question as a linear program we need to define:

variables
constraints
objective

Variables

We need to decide how much to supply from each of the three growers to each of the two canning plants. Hence
let xij be the number of tonnes supplied from grower i (i=1,2,3 for S1, S2 and S3 respectively) to plant j (j=1 for
Plant A and j=2 for Plant B) where xij >=0 i=1,2,3; j=1,2

Constraints

cannot supply more than a grower has available - a supply constraint

x11 + x12 <= 200


x21 + x22 <= 310
x31 + x32 <= 420

the capacity of each plant must be respected - a capacity constraint

x11 + x21 + x31 <= 460


x12 + x22 + x32 <= 560

Objective

The objective is to maximise total profit, i.e.

maximise revenue - grower supply cost - grower shipping cost - plant labour cost

and this is

maximise 50SUM{i=1,2,3}SUM{j=1,2}xij - 11(x11+x12) - 10(x21+x22) - 9(x31+x32) - 3x11 - 2x21 - 6x31 -


3.5x12 - 2.5x22 - 4x32 - 26SUM{i=1,2,3}xi1 - 21SUM{i=1,2,3}xi2

The dual values associated with the supply and plant capacity constraints in the optimal solution of the above
linear program tell us by how much the optimal objective function value will change if we change the right-hand
side of the corresponding constraints

The basic assumptions are:

can ship from a grower any quantity we desire


no loss in weight in processing at the plant
no loss in weight in shipping
can sell all we produce
all the data/numbers given are accurate

http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 4/16
9/17/2018 Linear programming formulation examples

Linear programming example 1993 UG exam

The production manager of a chemical plant is attempting to devise a shift pattern for his workforce. Each day of
every working week is divided into three eight-hour shift periods (00:01-08:00, 08:01-16:00, 16:01-24:00)
denoted by night, day and late respectively. The plant must be manned at all times and the minimum number of
workers required for each of these shifts over any working week is as below:

Mon Tues Wed Thur Fri Sat Sun


Night 5 3 2 4 3 2 2
Day 7 8 9 5 7 2 5
Late 9 10 10 7 11 2 2

The union agreement governing acceptable shifts for workers is as follows:

1. Each worker is assigned to work either a night shift or a day shift or a late shift and once a worker has
been assigned to a shift they must remain on the same shift every day that they work.
2. Each worker works four consecutive days during any seven day period.

In total there are currently 60 workers.

Formulate the production manager's problem as a linear program.


Comment upon the advantages/disadvantages you foresee of formulating and solving this problem as a
linear program.

Solution

Variables

The union agreement is such that any worker can only start their four consecutive work days on one of the seven
days (Mon to Sun) and in one of the three eight-hour shifts (night, day, late).

Let:

Monday be day 1, Tuesday be day 2, ..., Sunday be day 7

Night be shift 1, Day be shift 2, Late be shift 3

then the variables are:

Nij the number of workers starting their four consecutive work days on day i (i=1,...,7) and shift j (j=1,...,3)

Note here that strictly these variables should be integer but, as we are explicitly told to formulate the problem as
a linear program in part (a) of the question, we allow them to take fractional values.

Constraints

upper limit on the total number of workers of 60

SUM{i=1 to 7} SUM{j=1 to 3} Nij <= 60

since each worker can start his working week only once during the seven day, three shift, week

lower limit on the total number of workers required for each day/shift period

http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 5/16
9/17/2018 Linear programming formulation examples

let Dij be the (known) number of workers required on day i (i=1,...,7) and shift period j (j=1,...,3) e.g. D53=11
(Friday, Late)

then the constraints are


Monday: N1j + N7j + N6j + N5j >= D1j j=1,...,3

Tuesday: N2j + N1j + N7j + N6j >= D2j j=1,...,3

Wednesday: N3j + N2j + N1j + N7j >= D3j j=1,...,3

Thursday: N4j + N3j + N2j + N1j >= D4j j=1,...,3

Friday: N5j + N4j + N3j + N2j >= D5j j=1,...,3

Saturday: N6j + N5j + N4j + N3j >= D6j j=1,...,3

Sunday: N7j + N6j + N5j + N4j >= D7j j=1,...,3

The logic here is straightforward, for example for Wednesday (day 3) the workers working shift j on day 3 either
started on Wednesday (day 3, N3j) or on Tuesday (day 2, N2j) or on Monday (day 1, N1j) or on Sunday (day 7,
N7j) - so the sum of these variables is the total number of workers on duty on day 3 in shift j and this must be at
least the minimum number required (D3j).

Objective

It appears from the question that the production manager's objective is simply to find a feasible schedule so any
objective is possible. Logically however he might be interested in reducing the size of the workforce so the
objective function could be:

minimise SUM{i=1 to 7} SUM{j=1 to 3} Nij

where all variables Nij>=0 and continuous (i.e. can take fractional values).

This completes the formulation of the problem as a linear program.

Some of the advantages and disadvantages of solving this problem as a linear program are:

really need variable values which are integer


some workers will always end up working weekends
how do we choose the workers to use, e.g. if N43=7 which 7 workers do we choose to begin their work
week on day 4 working shift 3
what happens if workers fail to report in (e.g. if they are sick) - we may fall below the minimum number
required
the approach above enables us to deal with the problem in a systematic fashion
have the potential to reduce the size of the workforce by more effectively matching the resources to the
needs

able to investigate changes (e.g. in shift patterns, workers needed per day, etc) very easily.

Linear programming example 1991 UG exam

http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 6/16
9/17/2018 Linear programming formulation examples

A company manufactures four products (1,2,3,4) on two machines (X and Y). The time (in minutes) to process
one unit of each product on each machine is shown below:
Machine
X Y
Product 1 10 27
2 12 19
3 13 33
4 8 23

The profit per unit for each product (1,2,3,4) is £10, £12, £17 and £8 respectively. Product 1 must be produced
on both machines X and Y but products 2, 3 and 4 can be produced on either machine.

The factory is very small and this means that floor space is very limited. Only one week's production is stored in
50 square metres of floor space where the floor space taken up by each product is 0.1, 0.15, 0.5 and 0.05 (square
metres) for products 1, 2, 3 and 4 respectively.

Customer requirements mean that the amount of product 3 produced should be related to the amount of product
2 produced. Over a week approximately twice as many units of product 2 should be produced as product 3.

Machine X is out of action (for maintenance/because of breakdown) 5% of the time and machine Y 7% of the
time.

Assuming a working week 35 hours long formulate the problem of how to manufacture these products as a
linear program.

Solution

Variables

Essentially we are interested in the amount produced on each machine. Hence let:

xi = amount of product i (i=1,2,3,4) produced on machine X per week

yi = amount of product i (i=2,3,4) produced on machine Y per week

where xi >= 0 i=1,2,3,4 and yi >= 0 i=2,3,4

Note here that as product 1 must be processed on both machines X and Y we do not define y1.

Constraints

floor space

0.1x1 + 0.15(x2 + y2) + 0.5(x3 + y3) + 0.05(x4 + y4) <= 50

customer requirements

x2 + y2 = 2(x3 + y3)

Note here that as this is only an approximate (±5% say) constraint we might do better to express this constraint
as

0.95[2(x3 + y3)] <= x2 + y2 <= 1.05[2(x3 + y3)]

http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 7/16
9/17/2018 Linear programming formulation examples

available time

10x1 + 12x2 + 13x3 + 8x4 <= 0.95(35)(60) (machine X)

27x1 + 19y2 + 33y3 + 23y4 <= 0.93(35)(60) (machine Y)

Objective

maximise profit, i.e.

maximise 10x1 + 12(x2 + y2) + 17(x3 + y3) + 8(x4 + y4)

Linear programming example 1987 UG exam

A company is planning its production schedule over the next six months (it is currently the end of month 2). The
demand (in units) for its product over that timescale is as shown below:

Month 3 4 5 6 7 8
Demand 5000 6000 6500 7000 8000 9500

The company currently has in stock: 1000 units which were produced in month 2; 2000 units which were
produced in month 1; 500 units which were produced in month 0.

The company can only produce up to 6000 units per month and the managing director has stated that stocks must
be built up to help meet demand in months 5, 6, 7 and 8. Each unit produced costs £15 and the cost of holding
stock is estimated to be £0.75 per unit per month (based upon the stock held at the beginning of each month).

The company has a major problem with deterioration of stock in that the stock inspection which takes place at
the end of each month regularly identifies ruined stock (costing the company £25 per unit). It is estimated that,
on average, the stock inspection at the end of month t will show that 11% of the units in stock which were
produced in month t are ruined; 47% of the units in stock which were produced in month t-1 are ruined; 100% of
the units in stock which were produced in month t-2 are ruined. The stock inspection for month 2 is just about to
take place.

The company wants a production plan for the next six months that avoids stockouts. Formulate their problem as
a linear program.

Because of the stock deterioration problem the managing director is thinking of directing that customers should
always be supplied with the oldest stock available. How would this affect your formulation of the problem?

Solution

Variables

Let

Pt be the production (units) in month t (t=3,...,8)

Iit be the number of units in stock at the end of month t which were produced in month i (i=t,t-1,t-2)

Sit be the number of units in stock at the beginning of month t which were produced in month i (i=t-1,t-2)

http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 8/16
9/17/2018 Linear programming formulation examples

dit be the demand in month t met from units produced in month i (i=t,t-1,t-2)

Constraints

production limit

Pt <= 6000

initial stock position

I22 = 1000

I12 = 2000

I02 = 500

relate opening stock in month t to closing stock in previous months

St-1,t = 0.89It-1,t-1

St-2,t = 0.53It-2,t-1

inventory continuity equation where we assume we can meet demand in month t from production in
month t. Let Dt represent the (known) demand for the product in month t (t=3,4,...,8) then

closing stock = opening stock + production - demand

and we have

It,t = 0 + Pt - dt,t

It-1,t = St-1,t + 0 - dt-1,t

It-2,t = St-2,t + 0 - dt-2,t

where

dt,t + dt-1,t + dt-2,t = Dt

no stockouts

all inventory (I,S) and d variables >= 0

Objective

Presumably to minimise cost and this is given by

SUM{t=3 to 8}15Pt + SUM{t=3 to 9}0.75(St-1,t+St-2,t) + SUM{t=3 to 8}25(0.11It,t+0.47It-1,t+1.0It-2,t)

Note because we are told to formulate this problem as a linear program we assume all variables are fractional -
in reality they are likely to be quite large and so this is a reasonable approximation to make (also a problem
occurs with finding integer values which satisfy (for example) St-1,t=0.89It-1,t-1 unless this is assumed).

http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 9/16
9/17/2018 Linear programming formulation examples

If we want to ensure that demand is met from the oldest stock first then we can conclude that this is already
assumed in the numerical solution to our formulation of the problem since (plainly) it worsens the objective to
age stock unnecessarily and so in minimising costs we will automatically supply (via the dit variables) the oldest
stock first to satisfy demand (although the managing director needs to tell the employees to issue the oldest stock
first).

Linear programming example 1986 UG exam

A company assembles four products (1, 2, 3, 4) from delivered components. The profit per unit for each product
(1, 2, 3, 4) is £10, £15, £22 and £17 respectively. The maximum demand in the next week for each product (1, 2,
3, 4) is 50, 60, 85 and 70 units respectively.

There are three stages (A, B, C) in the manual assembly of each product and the man-hours needed for each
stage per unit of product are shown below:

Product
1 2 3 4
Stage A 2 2 1 1
B 2 4 1 2
C 3 6 1 5

The nominal time available in the next week for assembly at each stage (A, B, C) is 160, 200 and 80 man-hours
respectively.

It is possible to vary the man-hours spent on assembly at each stage such that workers previously employed on
stage B assembly could spend up to 20% of their time on stage A assembly and workers previously employed on
stage C assembly could spend up to 30% of their time on stage A assembly.

Production constraints also require that the ratio (product 1 units assembled)/(product 4 units assembled) must
lie between 0.9 and 1.15.

Formulate the problem of deciding how much to produce next week as a linear program.

Solution

Variables

Let

xi = amount of product i produced (i=1,2,3,4)

tBA be the amount of time transferred from B to A

tCA be the amount of time transferred from C to A

Constraints

maximum demand

x1 <= 50

x2 <= 60

http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 10/16
9/17/2018 Linear programming formulation examples

x3 <= 85

x4 <= 70

ratio

0.9 <= (x1/x4) <= 1.15

i.e. 0.9x4 <= x1 and x1 <= 1.15x4

work-time

2x1 + 2x2 + x3 + x4 <= 160 + tBA + tCA

2x1 + 4x2 + x3 + 2x4 <= 200 - tBA

3x1 + 6x2 + x3 + 5x4 <= 80 - tCA

limit on transferred time

tBA <= 0.2(200)

tCA <= 0.3(80)

all variables >= 0

Objective

maximise 10x1 + 15x2 + 22x3 + 17x4

Note we neglect the fact that the xi variables should be integer because we are told to formulate the problem as
an LP.

Linear programming example

A company makes three products and has available 4 workstations. The production time (in minutes) per unit
produced varies from workstation to workstation (due to different manning levels) as shown below:

Workstation
1 2 3 4
Product 1 5 7 4 10
2 6 12 8 15
3 13 14 9 17

Similarly the profit (£) contribution (contribution to fixed costs) per unit varies from workstation to workstation
as below

Workstation
1 2 3 4
Product 1 10 8 6 9
2 18 20 15 17
3 15 16 13 17

http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 11/16
9/17/2018 Linear programming formulation examples

If, one week, there are 35 working hours available at each workstation how much of each product should be
produced given that we need at least 100 units of product 1, 150 units of product 2 and 100 units of product 3.
Formulate this problem as an LP.

Solution

Variables

At first sight we are trying to decide how much of each product to make. However on closer inspection it is clear
that we need to decide how much of each product to make at each workstation. Hence let

xij = amount of product i (i=1,2,3) made at workstation j (j=1,2,3,4) per week.

Although (strictly) all the xij variables should be integer they are likely to be quite large and so we let them take
fractional values and ignore any fractional parts in the numerical solution. Note too that the question explicitly
asks us to formulate the problem as an LP rather than as an IP.

Constraints

We first formulate each constraint in words and then in a mathematical way.

limit on the number of minutes available each week for each workstation

5x11 + 6x21 + 13x31 <= 35(60)

7x12 + 12x22 + 14x32 <= 35(60)

4x13 + 8x23 + 9x33 <= 35(60)

10x14 + 15x24 + 17x34 <= 35(60)

lower limit on the total amount of each product produced

x11 + x12 + x13 + x14 >= 100

x21 + x22 + x23 + x24 >= 150

x31 + x32 + x33 + x34 >= 100

Objective

Presumably to maximise profit - hence we have

maximise

10x11 + 8x12 + 6x13 + 9x14 + 18x21 + 20x22 + 15x23 + 17x24 + 15x31 + 16x32 + 13x33 + 17x34

Production planning problem

Consider the production of tin cans which are stamped from metal sheets. A can consists of a main body and two
ends,. We have 4 possible stamping patterns (involving 2 different types (sizes) of metal sheet). as shown below
http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 12/16
9/17/2018 Linear programming formulation examples

We have the following information:


Pattern
1 2 3 4
Type of sheet used 1 2 1 1
Number of main bodies 1 4 2 0
Number of ends 7 4 3 9
Amount of scrap s1 s2 s3
s4
Time to stamp (hours) t1 t2 t3
t4

Note here that the si (i=1,2,3,4) and the ti (i=1,2,3,4) are not variables but constants (which have a known value).
Often in formulating LP's it is easier to use a symbol for a number rather than write out the number in full every
time it occurs in a constraint or in the objective function.

Let P be the profit obtained from selling one can, C be the cost per unit of scrap, T be the total number of hours
available per week, L1 be the number of metal sheets of type 1 which are available for stamping per week and
L2 be the number of metal sheets of type 2 which are available for stamping per week.

At the start of the week there is nothing in stock. Each (unused) main body in stock at the end of the week incurs
a stock-holding cost of c1. Similarly each (unused) end in stock at the end of the week incurs a stock-holding
cost of c2. Assume that all cans produced one week are sold that week.

http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 13/16
9/17/2018 Linear programming formulation examples

How many cans should be produced per week?

Production planning solution

Variables

Let

xi be the number of patterns of type i (i=1,2,3,4) stamped per week

y be the number of cans produced per week

Note xi >= 0 i=1,2,3,4 and y >= 0 and again we assume that the xi and y are large enough for fractional values
not to be significant.

Constraints

time available

t1x1 + t2x2 + t3x3 + t4x4 <= T

sheet availability

x1 + x3 + x4 <= L1 (sheet 1)

x2 <= L2 (sheet 2)

number of cans produced

y = min[ (7x1+4x2+3x3+9x4)/2, (x1+4x2+2x3) ]

where the first term in this expression is the limit imposed upon y by the number of can ends produced and the
second term in this expression is the limit imposed upon y by the number of can bodies produced. This
constraint (because of the min[,] part) is not a linear constraint.

Objective

Presumably to maximise profit - hence

maximise

revenue - cost of scrap - unused main bodies stock - holding cost - unused ends stock - holding cost

i.e. maximise

Py - C(s1x1 + s2x2 + s3x3 + s4x4) - c1(x1 + 4x2 + 2x3 - y) - c2((7x1 + 4x2 + 3x3 + 9x4) - 2y)

As noted above this formulation of the problem is not an LP - however it is relatively easy (for this particular
problem) to turn it into an LP by replacing the y = min[,] non-linear equation by two linear equations.

Suppose we replace the constraint

http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 14/16
9/17/2018 Linear programming formulation examples
y = min[ (7x1+4x2+3x3+9x4)/2,
(x1+4x2+2x3) ] (A)

by the two constraints


y <= (7x1+4x2+3x3+9x4)/2 (B)

y <= (x1+4x2+2x3) (C)

(which are both linear constraints) then we do have an LP and in the optimal solution of this LP either:

constraint (B) or constraint (C) is satisfied with equality, in which case constraint (A) is also satisfied with
equality; or

neither constraint (B) nor constraint (C) is satisfied with equality i.e. y < (7x1+4x2+3x3+9x4 )/2 and y <
(x1+4x2+2x3) - but in this case we can increase y (without changing any xi values), increasing the
objective function (assuming P + c1 + 2c2 >0) and contradicting the statement (above) that we already had
the optimal solution.

Hence case (b) cannot occur and so case (a) is valid - replacing constraint (A) by constraints (B) and (C)
generates a valid LP formulation of the problem.

Note that this problem illustrates that even if our initial formulation of the problem is non-linear we may be able
to transform it into an LP.

Note too that it is relatively easy to extend the LP formulation of the problem to cope with the situation where
can bodies/ends unused at the end of one week are available for production the following week.

Production planning problem

A company is producing a product which requires, at the final assembly stage, three parts. These three parts can
be produced by two different departments as detailed below.
Production rate (units/hr)
Part 1 Part 2 Part 3 Cost (£/hr)
Department 1 7 6 9 25.0
Department 2 6 11 5 12.5

One week, 1050 finished (assembled) products are needed (but up to 1200 can be produced if necessary). If
department 1 has 100 working hours available, but department 2 has 110 working hours available, formulate the
problem of minimising the cost of producing the finished (assembled) products needed this week as an LP,
subject to the constraint that limited storage space means that a total of only 200 unassembled parts (of all types)
can be stored at the end of the week.

Note: because of the way production is organised in the two departments it is not possible to produce, for
example, only one or two parts in each department, e.g. one hour of working in department 1 produces 7 part 1
units, 6 part 2 units and 9 part 3 units and this cannot be altered.

Production planning solution

Variables

We need to decide the amount of time given over to the production of parts in each department (since we,
obviously, may not make use of all the available working time) and also to decide the total number of finished
(assembled) products made. Hence let:
http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 15/16
9/17/2018 Linear programming formulation examples

xi = number of hours used in department i (i=1,2)

y = number of finished (assembled) products made

where xi >= 0 i=1,2 and y >= 0 and (as is usual) we assume that any fractional parts in the variables in the
numerical solution of the LP are not significant.

Constraints

working hours available

x1 <= 100

x2 <= 110

number of assembled products produced

1050 <= y <= 1200

production constraints relating the hours worked to the number of assembled products

We produce (7x1 + 6x2) part 1 units, (6x1 + 11x2) part 2 units and (9x1 + 5x2) part 3 units. Now to ensure that
the number of assembled products produced is exactly y we need at least y part 1 units, at least y part 2 units and
at least y part 3 units. Hence we have the three constraints

7x1 + 6x2 >= y

6x1 + 11x2 >= y

9x1 + 5x2 >= y

the total number of parts (of all types) produced is (7x1 + 6x2) + (6x1 + 11x2) + (9x1 + 5x2) = 22x1 +
22x2. Since we produce exactly y assembled products the number of parts left over at the end of the week
is (22x1 + 22x2) - 3y and hence the constraint relating to the limited storage space is given by

22x1 + 22x2 - 3y <= 200

Objective

minimise 25.0x1 + 12.5x2

Obvious extensions to this problem involve increasing (from the current value of 3) the number of parts needed
for the finished product and changing the ratio of parts used in a finished product from its current value of 1:1:1.

http://people.brunel.ac.uk/~mastjjb/jeb/or/lpmore.html 16/16

You might also like