L1 Pepd PDF
L1 Pepd PDF
Cost Estimation
Dr. Rohidas Bhoi
Assistant Professor
Department of Chemical Engineering
MNIT Jaipur
Cost Estimation
• The aim of successful plant is to earn profit.
• Net profit is defined as total income my all expenses.
• A chemical engineer must be aware of types of cost
involved in manufacturing process.
• The investment required for chemical plant may be
decided based on new plant on new site, new plant on
existing site, addition/ modification in the existing plant
• An estimate of investment plays an important role in
taking the final decision.
• A chemical engineer plays an important role in
preparing the estimate.
2
Cash Flow for Industrial Operations
• Capital investment :source
and sink
• The cost shown is without
land
• Net cash flow = income –
expenses
• Gross profit
• Profit before depreciation
• Profit before tax
• Net profit
Aj=(sj - coj- dj)(1-Φ) + dj
3
Cumulative Cash Position
5
Break Even Chart for Chemical Processing Plant
• Fixed cost remain constant
• Total product cost as
production increases
• There is steady income
through sale of product
• The point at which sales
cost is equal to production
cost is called break-even
point (BEP)
• It is desirable to operate
the plant above BEP
6
Total Capital Investments (TCI)
8
Types of Capital Cost Estimate
• Order of magnitude estimate (ratio estimate)
– Based on previous cost data; accuracy level ±30%
• Study estimate (factored estimate)
– Based on the knowledge of major items of equipment; accuracy level
±30%
• Preliminary estimate (scope estimate)
– Based on sufficient data good enough to be budgeted; accuracy level
±20%
• Definitive estimate (project control estimate)
– Based on almost complete data but before finishing drawings and
specifications; accuracy level ±10%
• Detailed estimate
– Based on complete engg drawing and specifications; accuracy level
±5% 9
Types of Capital Cost Estimate
• Detailed estimate is
based on complete data
whereas order-of-
magnitude is based on
little information
• This represents two
extremes
• Based on detailed
estimate an approval
can be sought from
management
• Refer to figure 6.4
10
Cost Indexes
• A substantial time is required to prepare the estimates.
Some time it take years
• The price of items may change over this period
• To account for change in price, various cost indexes are
used to get present cost
Present cost = original cost (present index value/index value at time
original cost was obtained)
15
Cost Factors- Equipment cost by scaling
6/10th rule
16
Cost Factors- Equipment cost by scaling
17
Cost Factors- Equipment cost by scaling
18
Cost Factors- Equipment cost by scaling
• Purchased-equipment costs for vessels, tanks, and
process- and material handling equipment can often be
estimated on the basis of weight.
• The fact that a wide variety of types of equipment have
about the same cost per unit weight is quite useful,
particularly when other cost data are not available.
• Generally, the cost data generated by this method are
sufficiently reliable to permit order-of-magnitude
estimates.
19
Purchased-Equipment Delivery
• Purchased equipment prices are usually quoted as FOB
(free on board) meaning that the purchaser pays the
freight
• Freight cost depends on factors like weight and size of
the equipment, distance from the source to plant and
method of transport (Air, Water, Road)
• A delivery allowance of 10% of purchased equipment
cost is recommended
20
Purchased equipment installation
Installation cost for process equipment as a % of purchased
equipment cost (Table-6)
• The installation of Type of equipment Installation cost (%)
22
Instrumentation and controls
• Major portion of instrumentation and control cost
includes
– Instrument costs
– installation-labor costs
– expenses for auxiliary equipment
• Total depends on the amount of control required and
may amount to 6-30 % of the purchased cost for all
equipment investment
• For the normal solid-fluid chemical processing plant, a
13 % of the purchased equipment cost is normally used
to estimate the total instrumentation cost.
• This is approximately 3% of the total capital investment
23
Piping
• Pipes are basically used for steam, water, air, sewer, raw
material and products
• The cost for piping includes
– Labor - Valves
– Fittings - Pipe
– Supports and other items involved in the complete erection of
all piping used directly in the process
• The cost of piping can be as high as 80 % of equipment
cost
Estimated cost of piping
Type of process plant % of fixed capital investment
Solid (Coal briquetting plant) 4
Solid fluid (Oil exploration plant) 7
Fluid (Distillation unit) 13 24
Electrical installations
• The electrical installation consists of four major
components, namely,
– Power wiring
– Lighting
– Transformation & service and instrument & control wiring
• In ordinary chemical plants, this cost amounts to 10-
15 % of the value of all purchased equipment
• It may range to as high as 40 % of purchased-
equipment cost for a specific process plant
• The electrical installation cost is generally estimated
between 3-10 % of the fixed capital investment
25
Building including services
The cost consists of expenses for
– Labor
– Materials and supplies involved in the erection of all
buildings connected with the plant
– Costs for plumbing, heating, lighting, ventilation, and similar
building services
New plant at new site New plant at existing Expansion at existing
(grass root) site (Battery limit) site
Type of plant
% PEC %FCI % PEC %FCI % PEC %FCI
Solid 68 18 25 1 15 4
Solid-Fluid 47 12 29 7 7 2
Fluid 45 10 5-18* 2-4* 6 2
* Applicable to petroleum refining 26
Refer table 10 & 11
Yard improvements
• It includes costs for fencing, grading, roads, sidewalks,
railroad sidings, landscaping, and similar items
• Its cost for chemical plants approximates 10-20% of
the purchased-equipment cost
• This is equivalent to approximately 2-5 % of the fixed-
capital investment % of fixed capital investment
Components
Range Typical values
Site clearing 0.4-1.2 0.8
Road and walks 0.2-1.2 0.6
Railroads 0.3-0.9 0.6
Fences 0.1-0.3 0.2
Lighting 0.1-0.3 0.2
Parking areas 0.1 -0.3 0.2
Landscaping 0.1-0.2 0.1
27
Others 0.2-0.6 0.3
Service facilities
% of fixed capital investment
Service facilities
Range Typical values
31
Contractors fee
• The contractor’s fee varies for different situations, but
it can be estimated to be about 2 to 8 percent of the
direct plant cost or 1.5 to 6 percent of the fixed capital
investment
Contingency
•A factor to compensate for unpredictable events, such
as storms, floods, strikes, price changes, small design
changes, errors in estimation, and other unforeseen
expenses
•Contingency factors ranging from 5-15 % of the direct
and indirect plant costs are commonly used,
32
Start up expenses
• Expenses required to start and operate the plant at
maximum design capacity.
• Expenses are made for raw material and equipments.
• Expenses may be as high as 12 % of the fixed-capital
investment
• In general an allowance of 8-10 % of the fixed-capital
investment
33
Thank you
34