Elect 09 Method Statement For MCC Modification and Recommissioning
Elect 09 Method Statement For MCC Modification and Recommissioning
1 OF 7
IRAG GATES CONTRACTING COMPANY
TABLE OF CONTENTS
1. Introduction
2. Definitions
3. Abbreviations
4. Methodology
5. MTO
6. HSE Requirements
7. Attachments
2 OF 7
IRAG GATES CONTRACTING COMPANY
As part of BGC development plan, Work Order (WO-026) to perform Refrigerated Export
(Method of Statement for
Modification/Recommissioning of LV Motor Control Centres at Um-Qasr)
At Storage Terminal has been issued to IGCC.
This Method Statement, aims to provide sufficient definition for Refrigerated Export
Project (Method of Statement for Modification/Recommissioning of LV Motor Control
Centres at Um-Qasr) Storage Terminal. Its intent is to also facilitate implementation in a safe
and efficient manner and for all involved parties to understand the risks, roles and
responsibilities associated with the Modification/Recommissioning of LV Motor Control
Centres.
2. Definitions
COMPANY BGC (Basra Gaz Company)
WORK Shall mean all and any of the work andor services andor materials
required to be provided by the CONTRACTOR under contract with
COMPANY.
3. Abbreviations
Abbreviation Definition
4. Methodology
4.1 Engineering Phase
- Preparation and Submission of Method Statement.
- Having TBT before start the work Explain the steps of work.
- Verify that each incoming cable that must have 0 voltage and all main
incomers rack out.
- Be sure that all grounding system tested and connected to main earthing
grid.
- Be sure that all testing equipment's are connected to trusted earthing grid
before start the test.
- Be sure that all control signal that connected to main control room are
disconnected avoiding the false operation.
4 OF 7
IRAG GATES CONTRACTING COMPANY
- Use the right hand tools, be sure that all tools are especially for electrical
works.
5 OF 7
IRAG GATES CONTRACTING COMPANY
- Check the LV circuit breaker closing and opening, charging circuit, manually.
- Perform the insulation resistance of circuit breaker with bus bars when at:
* Close position
R/S, T, G to ground
S/R, T, G to ground
T/R, S, G to ground
- Preform DC contact test for circuit breaker (closed position). Using primary
- Perform the insulation resistance, continuity test for control cables between
- Arrange all testing formats and necessary documents as hand over package.
using CPC100.
6 OF 7
IRAG GATES CONTRACTING COMPANY
5. MTO
N/A
6. HSE Requirements
Site Induction.
Preparation of first aid kits and fire extinguishers for emergency case.
Ensure to connect a local earth equipment, if practicable. The case earth must remain
connected to the system earth in order to maintain an acceptable single earth potential
PPE Requirement:
Use suitable barriers, barricades and warning signs on both sides of man lift to prevent
access to the working zone by persons not involved. If there is any danger of exposing
the public or staff to energized conductors or equipment a safety observer must be used.
Housekeeping.
7 OF 7