Elect 03 Method Statement For Testing of MV Cables For CSE at SS1
Elect 03 Method Statement For Testing of MV Cables For CSE at SS1
Method Statement
Rev: A
Testing MV Cables at Um-Qasr
xxxxxxxxxxxxx Doc. Cat. EXT
Method Statement of
Testing MV Cables at Um-Qasr
1 OF 8
IRAG GATES CONTRACTING COMPANY
Method Statement
Rev: A
Testing MV Cables at Um-Qasr
XXXXXXXXXXXXX Doc. Cat. EXT
TABLE OF CONTENTS
1. Introduction
2. Definitions
3. Abbreviations
4. Methodology
5. MTO
6. HSE Requirements
7. Attachments
2 OF 8
IRAG GATES CONTRACTING COMPANY
Method Statement
Rev: A
Testing MV Cables at Um-Qasr
XXXXXXXXXXXXX Doc. Cat. EXT
Method Statement
Testing MV Cables at Um-Qasr
1. Introduction
As part of BGC development plan, Work Order (WO-026) to perform Refrigerated Export
Project (Testing MV Cables at Um-Qasr) at Um-Qasr Storage Terminal has been issued to
IGCC.
This Method Statement, aims to provide sufficient definition for Refrigerated Export Project
(Testing MV Cables at Um-Qasr) Storage Terminal. Its intent is to also facilitate
implementation in a safe and efficient manner and for all involved parties to understand the
risks, roles and responsibilities associated with the Testing MV Cables at Um-Qasr.
2. Definitions
COMPANY BGC (Basra Gaz Company)
WORK Shall mean all and any of the work andor services andor materials
required to be provided by the CONTRACTOR under contract with
COMPANY.
3. Abbreviations
Abbreviation Definition
3 OF 8
IRAG GATES CONTRACTING COMPANY
Method Statement
Rev: A
Testing MV Cables at Um-Qasr
XXXXXXXXXXXXX Doc. Cat. EXT
4. Methodology
4.1 Engineering Phase
- Preparation and Submission of Method Statement.
- Having a valid confined space entry permit, with people trained & authorized
to work in confined space.
- Having approved rescue plan and to be discussed with the CSE team.
- Make sure all the control system mentioned in JHA for CSE is in place.
Method Statement
Rev: A
Testing MV Cables at Um-Qasr
XXXXXXXXXXXXX Doc. Cat. EXT
4.4.2.3 IR Test
- By utilizing calibrated Megger tester, IR test will be performed
by qualified electrician.
- IR Testing voltage shall not exceed the cable operating voltage;
for 3.3KV cables the test will be done at 2.5KV and the 11KV
cables will be tested at 5KV.
- Record the measured value on related ITR form.
Method Statement
Rev: A
Testing MV Cables at Um-Qasr
XXXXXXXXXXXXX Doc. Cat. EXT
6 OF 8
IRAG GATES CONTRACTING COMPANY
Method Statement
Rev: A
Testing MV Cables at Um-Qasr
XXXXXXXXXXXXX Doc. Cat. EXT
5. MTO
N/A
6. HSE Requirements
Site Induction.
Where it is not possible to isolate the cable from other equipment, ensure that Surge
Arresters and VT’s are disconnected from the cable
The ‘Cable Tester’ must be the authorized tester who has been appropriately trained
and authorized to conduct Testing of HV Cables in accordance with accepted
standards. It is the responsibility of the ‘Cable Tester’ to have a clear understanding and
comply with the requirements of this ‘Voltage Testing of HV Cables’ technique
Job Risk Analysis must be done by the work team before commencing any switching and
tests near the underground cables and all parties concerned are in agreement upon that
assessment
The tester in charge shall ensure that drawings are made available to familiarize himself
with the work area and equipment locations prior to commencing work
Ensure to connect a local earth on the test equipment, if practicable. The case earth
must remain connected to the system earth in order to maintain an acceptable single
earth potential
After the cable is tested (SI, IR and VLF) cable cores must be then discharged. If
applicable, close the Earth switch and then the test set leads may be removed
PPE Requirement:
7 OF 8
IRAG GATES CONTRACTING COMPANY
Method Statement
Rev: A
Testing MV Cables at Um-Qasr
XXXXXXXXXXXXX Doc. Cat. EXT
Use suitable barriers, barricades and warning signs on both sides of the cable to prevent
access to the cable by persons not involved with the testing. If there is any danger of
exposing the public or staff to energized conductors or equipment a safety observer must
be used.
Housekeeping.
8 OF 8