Touch Shoring 2
Touch Shoring 2
Tutorials
from BridgeSight Software
BridgeSight Inc.
P.O. Box 19172
South Lake Tahoe, CA 96151
877-441-0346
www.BridgeSight.com
Title PGSuper Tutorial – Modeling Touch Shoring Publication No. BS02282011-2
Abstract
This document provides a discussion and step-by-step procedure for modeling precast-prestressed girder bridge
structures constructed with touch shoring.
Disclaimer
The information contained in this publication is believed to be accurate; however, it is being provided for
informational purposes only. Publication of this document by BridgeSight Inc. should not be construed as
BridgeSight Inc. engaging in or rendering engineering, legal or other professional services. Use of the information
contained in this publication should not be considered by the user as a substitute for the advice of a registered
professional engineer, attorney or other professional. If such advice is required, it should be sought through the
services of a registered professional engineer, licensed attorney or other professional.
Notes
The shoring is removed after the deck slab reaches a specified compressive strength. Any
force carried by the temporary shoring tower is then carried by the full span girder, which
is now a composite section. This method can reduce total stresses compared to when
touch shoring is not utilized.
Scenario
Our example is a fictitious design-build construction scenario where the builder has
realized a large cost savings by eliminating a bridge from a project. However, six girders
for the removed bridge have already been fabricated, and the cost savings would be even
greater if these girders can be used in a different bridge.
The six girders are AASHTO Type V with 32 straight and 8 harped strands. They were
constructed for a 130 ft span structure (127.33 ft between bearings). The design concrete
strengths are f’ci = 5.9 ksi and f’c = 6.6 ksi. The bridge where the builder would like to use
these girders is also 130 ft long, but slightly wider. The girders would be spaced at 8 ft
and the deck would have 4 ft overhangs. The girders were originally designed for a closer
spacing and thus might not have adequate capacity.
1
Our job is to assess the girders and determine if they can be utilized in a different bridge.
The purpose of this tutorial is to describe modeling technique, so we will limit the
engineering evaluation to flexural requirements. Of course, a full evaluation must be
performed if this were an actual bridge project.
1. Start BridgeLink
2. Select File > Configure BridgeLink… to activate the configuration wizard
3. The second step in the configuration wizard is the PGSuper configuration. Select
the WSDOT configuration server and the AASHTO Standard Girders from
PCI BDM configuration
4. Press [Next>] and proceed to through the wizard. Default configurations for the
other BridgeLink applications are acceptable
5. Press [Finish] to end the configuration wizard.
2
Create a New PGSuper Project
1. Select File > New
2. Under PGSuper Project Templates, select I-Beams
I Beams and then the Type V template.
3. Press [OK] to create a new project
3
2. On the General Tab input the girder spacing (8 ft)
4
4. On the Deck Geometry and Materials tab,
ta enter the left and right deck offset
(24ft)
5. The default value for the remaining parameters are sufficient for this tutorial.
Press [OK].
6. In a normal situation, the next step would be to use PGSuper’s bridge model view
and girder view to confirm that the bridge’s geometry has been input correctly.
This is covered in other tutorials, so we will skip model validatation and define
the girder properties.
5
2. Enter the concrete strength
6
3. Enter the strand configuration
4. The remaining parameters are not of significance for this tutorial. Check the Copy to
all girders
rders in this span box to copy thesee parameters to all other girders in Span 1.
Press [OK]
7
1. Select View > Reports > Spec Check Report
2. Select Span 1 and Girder B. Press [OK]
3. Reviewing
eviewing the analysis results, we see that the girder does not satisfy the service
level stress criteria.
With a conventional construction sequence, these girders have adequate strength but
are not within acceptable service level stress limits. We will investigate shored
construction as a means of reducing the service level stresses.
Shored Construction
Let’s see if the
he final service level stresses can be reduced through the use of shored
construction. Shoring
horing towers cannot be explicitly modeled in PGSuper; however they can
be simulated with user defined loads
load applied during key construction events.
events Two events
are of interest:
8
by applying downward user defined loads that are equal and opposite of the reaction
loads in Event 5.
Assume the shoring towers located at the 1/3 and 2/3 points in the span.
Slab Loading
Start by using PGSuper to compute the deck slab dead load that will be carried, in part,
by the shoring towers.
Create a Details Report for Girder B, with just the Loading Details chapter.
From the Details Report, the total slab load is 0.970 k/ft
9
w
127.33
42.44
3
10
3. Repeat this process to define the shoring tower reaction load at the 2/3 point of
the span.
The user defined loads can are listed in the Loads window. Select Edit > Loads.
Loads
11
The incremental DC moment diagram mimics that of a three span continuous span. The
DC moment is considerablyly less than the simple span “Slab” + “Haunch” moment
without the shoring towers.
Create a specification check report for Girder B using the same steps as described above.
Upon review of the service level stress checks, we see that the use of touch shoring has
reduced the final service level stresses to acceptable levels (NOTE:: Other specification
checks do not pass, this is ok since we are focusing on reducing flexural stresses in this
tutorial).
Further evaluation of exterior girders should be performed to ensure that they are also
adequate.
Conclusion
These
hese girders can be used in the new bridge structure. However, too keep the final service
level stresses within acceptable limits,
limits touch shoring must be utilized. The advanced
features available in PGSuper Professional make modeling these complex construction
constructi
scenarios quick and easy.
BridgeSight Inc
P.O. Box 19172
12
South Lake Tahoe, CA 96151
877-441-0346
[email protected]
13