This document is a checklist for inspecting concrete pouring activities for the four laning project of the Hyderabad-Bangalore section of National Highway 7 between kilometers 336 and 376. The checklist contains 19 items to check including ensuring proper formwork, reinforcement, batching plant equipment, and concrete pouring procedures are followed to deliver uniform and adequately compacted concrete without cold joints or displaced forms. The engineer and consultant must sign off on the checklist to approve the concrete pour.
This document is a checklist for inspecting concrete pouring activities for the four laning project of the Hyderabad-Bangalore section of National Highway 7 between kilometers 336 and 376. The checklist contains 19 items to check including ensuring proper formwork, reinforcement, batching plant equipment, and concrete pouring procedures are followed to deliver uniform and adequately compacted concrete without cold joints or displaced forms. The engineer and consultant must sign off on the checklist to approve the concrete pour.
Original Description:
Check
Original Title
Check List for Inspection Before Approval to Concrete or Pouring of Concrete
This document is a checklist for inspecting concrete pouring activities for the four laning project of the Hyderabad-Bangalore section of National Highway 7 between kilometers 336 and 376. The checklist contains 19 items to check including ensuring proper formwork, reinforcement, batching plant equipment, and concrete pouring procedures are followed to deliver uniform and adequately compacted concrete without cold joints or displaced forms. The engineer and consultant must sign off on the checklist to approve the concrete pour.
This document is a checklist for inspecting concrete pouring activities for the four laning project of the Hyderabad-Bangalore section of National Highway 7 between kilometers 336 and 376. The checklist contains 19 items to check including ensuring proper formwork, reinforcement, batching plant equipment, and concrete pouring procedures are followed to deliver uniform and adequately compacted concrete without cold joints or displaced forms. The engineer and consultant must sign off on the checklist to approve the concrete pour.
No Description Engineer/ Contractor Consultant 1 Method statement approved Batching Plant mixers in working order. (Separate 2 dispenser for admixture, if required, available) Water, sand, coarse aggregate, cement, admixture 3 approved, storage of aggregate and cement Water, sand, coarse aggregate, admixture, cement 4 stock sufficient Concrete conveying arrangement (including transit 5 mixers) available in working condition and of sufficient capacity 6 Form work / Scaffolding approved 7 Reinforcement approved 8 Pre-Stressing sheathing approved Concrete gang present, including carpenter, steel 9 fixer, mechanics and electricians 10 Access like walkways are provided 11 Safety arrangements adequate 12 Lighting provided Name of the Work: Four Laning of Hyderabad – Bangalore Section Km: 336.000 to km: 376.000 of NH-7 Package-ADB-II/C-13
13 Curing arrangements made / Laboratory notified
a) Check whether the concrete is not segregated during pour. The height of dropping is 14 controlled. It should not exceed 2 – 3 m. b) Check whether the concrete is poured in layers of about 300mm a) check that the vibrator is applied systematically 15 to compact uniformly and adequately b) Avoid over vibration 16 Cold joints are not allowed to be developed The forms are not displaced or deformed during the 17 concrete pour and vibration The concrete is poured within the allowable time limits 18 from the time of batching 19 Concrete cubes will be taken as required
Status : Approved [ ] Not Approved and resubmit check list [ ]