Sample Quality Control KPIs For Construction Project

This document contains a status register for key performance indicators (KPIs) for a construction project. It tracks 10 KPIs across various areas like construction safety, management, design, materials, and more. Each KPI lists targets and actual performance on a monthly basis. Overall performance is good, with most KPIs meeting their targets for the period reported. Some variances are noted and referred to more detailed reports for additional information.

Uploaded by

Navneet Soni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (8 votes)
4K views2 pages

Sample Quality Control KPIs For Construction Project

This document contains a status register for key performance indicators (KPIs) for a construction project. It tracks 10 KPIs across various areas like construction safety, management, design, materials, and more. Each KPI lists targets and actual performance on a monthly basis. Overall performance is good, with most KPIs meeting their targets for the period reported. Some variances are noted and referred to more detailed reports for additional information.

Uploaded by

Navneet Soni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

QUALITY KEY PERFORMANCE INDICATORS (KPI) - STATUS REGISTER

COMPANY CLIENT
LOGO/NAME LOGO/NAME
CONSTRUCTION WORKS FOR XYZ PROJECT

KPI Avg.
Key Performance KPI KPI Review
Sr. No. Measurement Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Achievement Remark
Indicator Target (Plan) Frequency
Method (%)

CONSTRUCTION SAFETY (HSE)

Number of LTIs 0 0 0 0 0 0 0 0 0 0 0 0

1 Lost Time Injury Man-hours Worked 0 Monthly 10 18,771 41,843 42,300 56,153 65,132 89,581 94,245 99,558 104,871 100.00% For Details, Refer Detaailed HSE Statistics Report

Achieved - % 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

No. of Persons Planned for Training 1 63 139 141 187 217 299 314 332 350

2 HSE Trainings No. of Persons Actually Trained 100% Monthly 1 60 129 135 180 210 280 300 332 350 96.64%

Achieved - % 100% 96% 92% 96% 96% 97% 94% 95% 100% 100%

No. of HSE Meeting Planned 1 2 2 4 4 4 4 4 4 4

3 HSE Meetings No. of HSE Meeting Performed 100% Monthly 1 2 2 4 4 4 4 4 4 4 100.00%

Achieved - % 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

No. of Near Miss Observed 1 2 2 1 3 4 5 4 4 6

Near Miss
4 No. of Near Miss Reported 100% Monthly 1 2 1 1 2 3 2 3 2 4 72.33% For Details, Refer Detaailed HSE Statistics Report
Reporting

Achieved - % 100% 100% 50% 100% 67% 75% 40% 75% 50% 67%

CONSTRUCTION MANAGEMENT

Progress Planned (%) 0.50% 1.00% 3.00% 5.00% 7.50% 8.15% 7.60% 7.00% 6.10% 5.90%

5 Construction Progress Earned Progress (%) > 05% Variance Monthly 0.45% 0.98% 2.00% 4.50% 7.37% 8.10% 7.50% 6.90% 6.00% 5.85% 93.71% For delay analysis of progress variance, refer Weekly Progress Report

Achieved - % 90% 98% 67% 90% 98% 99% 99% 99% 98% 99%

No. Scheduled Milestones 1 2 4 8 10 12 10 8 6 4

For detailed list of milestones refer Complete Milestone List submitted


6 Major Milestones No. of Achieved Milestones </=2 Nos. Monthly 1 2 3 6 8 9 8 5 3 3 77.25%
along with Weekly Progress Report

Achieved - % 100% 100% 75% 75% 80% 75% 80% 63% 50% 75%

CONSTRUCTION DESIGN & DRAWINGS

No. of AFC Drawing Issued - 50 100 175 200 250 200 100 75 50

Error Free Engineering


7 No. of AFC Drawings Revised </=02% Monthly - 0 2 4 4 2 1 2 2 2 1.81% For details, refer Engineering Drawings & Deliverable Register
Drawings (AFC)

Achieved - % - 0% 2% 2% 2% 1% 1% 2% 3% 4%

No. of Drawing Scheduled for Issue - 50 100 175 200 250 200 100 75 50

Drawing Issuance as per </=03%


8 No. of Drawings Actually Issued Monthly - 40 75 125 150 200 195 95 80 60 88.96% For details, refer Engineering Drawings & Deliverable Register
Approved Schedule Variance

Achieved - % - 80% 75% 71% 75% 80% 98% 95% 107% 120%

No. of Site Queries Raised - 0 1 1 2 1 1 1 2 2

Within
9 Site Queries Closure No. of Site Queries Closed Monthly - 0 1 1 2 1 1 1 2 2 100.00% For details, refer Site Quesries Register
5 Days

Achieved - % - 0% 100% 100% 100% 100% 100% 100% 100% 100%

CONSTRUCTION MATERIALS (VENDORS/SUPPLIERS)

No. of Documents Required as per Schedule - - - 25 50 75 100 75 50 25

Vendor Quality Records &


10 Nos. of Documents Received </=03% Monthly - - - 24 50 72 102 71 45 24 96.38% For details, refer Vendor Document Register
Data/Documents

Achieved - % - - - 96% 100% 96% 102% 95% 90% 96%

Prepared by: MUJAHID AKHTAR 1 of 2


QUALITY KEY PERFORMANCE INDICATORS (KPI) - STATUS REGISTER
COMPANY CLIENT
LOGO/NAME LOGO/NAME
CONSTRUCTION WORKS FOR XYZ PROJECT

KPI Avg.
Key Performance KPI KPI Review
Sr. No. Measurement Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Achievement Remark
Indicator Target (Plan) Frequency
Method (%)

CONSTRUCTION SAFETY (HSE) No. of Withness/Hold Points Scheduled - - - 25 50 75 100 75 50 25

ITP Witness & Hold Points


11 No. of Withness/Hold Points Missed 0% Monthly - - - 25 50 75 100 75 50 25 100.00% For Details, refer ITP's Witness/Hold Points register
for Vendor Works

Achieved - % - - - 100% 100% 100% 100% 100% 100% 100%

Items Planned for Delivery at Site - - - 25 50 75 100 75 50 25

On Time Delivery of
12 Items Actually Delivered at Site 0 Monthly - - - 20 45 70 90 72 50 20 89.90% For Details, Refer Procurement Status Register
Materials

Achieved - % - - - 80% 90% 93% 90% 96% 100% 80%

CONSTRUCTION QUALITY MANAGEMENT SYSTEM

Planned 1 1 1 1 1 1 1 1 1 1

13 Audits and Reviews Performed >=95% Monthly 0 1 1 1 1 1 1 1 1 1 90.00% For Details, Refer Audits Plan and Schedule

Achieved - % 0% 100% 100% 100% 100% 100% 100% 100% 100% 100%

No. of NCR/CAR Raised 1 2 2 4 4 4 4 4 4 4

14 Closure of NCRs & CARS No. of NCR/CAR Closed >=90% Monthly 0 3 2 4 4 4 4 4 4 4 95.00% For Details, Refer NCR & CAR Status Register

Achieved - % 0% 150% 100% 100% 100% 100% 100% 100% 100% 100%

CONSTRUCTION & INSTALLATION

No. of Spots Radiographed - - - - - 200 300 400 300 200

</=5% Repair for


15 No. of Spots Marked for Repair Monthly - - - - - 10 30 40 30 10 8.00%
Pipeline

Achieved - % - - - - - 5% 10% 10% 10% 5%


Weld Repair (%)
No. of Spots Radiographed - - - - - 200 300 400 300 200

16 No. of Spots Marked for Repair </=3% Monthly - - - - - 5 15 10 8 15 4.03%


Repair for piping
Achieved - % - - - - - 3% 5% 3% 3% 8%

Nos. of RFI Raised - - - 25 50 75 100 75 50 25

17 RFI Rejection Rate (%) Nos. of RFI Rejected </=3% Monthly - - - 24 49 74 98 73 46 24 96.57%

Achieved - % - - - 96% 98% 99% 98% 97% 92% 96%

Man-Hours Consumed - - - 250 500 750 1000 750 500 250

18 Construction Rework Man-Hours Consumed for Re-Work </=01% Monthly - - - 5.0 10.0 10.0 10.0 5.0 15.0 10.0 2.00%

Achieved - % - - - 2.0% 2.0% 1.3% 1.0% 0.7% 3.0% 4.0%

No. Samples Offered - - - 25 50 75 100 75 50 25

19 Concrete Cube Testing No. Samples Accepted 100% Monthly - - - 25 50 75 100 75 50 25 100.00%

Achieved - % - - - 100% 100% 100% 100% 100% 100% 100%

YOU CAN ADD, OTHER MAJOR CONSTRUCTION COMMODITIES AND THEIR PRODUCTIVITIES AS KPIs e.g Steel Structure, Equipment Erection, Cabling etc.
Close to Below
On Target
Target Target

Prepared by: MUJAHID AKHTAR 2 of 2