Jsa For Applying Bituminous Roof Treatment On Buildings

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 3
At a glance
Powered by AI
The document describes a Job Safety Analysis (JSA) for applying bituminous roof treatment on buildings. It identifies potential hazards and controls at each step of the process.

Potential hazards identified during mobilization include using unauthorized equipment/tools, unskilled or uninducted personnel starting work, and workers starting in an unfit state. Controls include inspecting equipment, ensuring training and fitness for work.

Precautions during heating of bitumen near the accommodation block include having a fire extinguisher and first aid kit available, taking proper care while handling bitumen, and having a fire watcher stationed.

f _____

JOB TITLE / AIM: Jsa For applying bituminous roof treatment on buildings
JSA DATE: 21/02/2007 JSA NO./ REVISION:
SUPERVISOR/ JSA LEADER: Zahid Masood SCRIBE: Abdullah Khan
PARTICIPANTS: Aghas Saeed , Muhammad Ramzan
LIST ASSOCIATED PROCEDURES/WORK INSTRUCTIONS OR TEMPORARY WIs:
Attach copies of any relevant documentation/ drawings.
Part 2: Job Safety Analysis
Job Steps:
1.Mobilization of tools workers and equipments
2.Cleaning of roof surface
3.Heating bitumen near block C
4.Applying primer coat, asphalt bitumen flood, and lying of jute felt on to bituminous coat.
5.Sprinkling of PEA Gravel
6.Demobilization

Now undertake the JSA and record in the table below. Use prompts on JSA Prompt Sheet and Hazard Checklist PA-HSEC-02-040-002-F03.
Part 3: Contingency Plans. Standard PPE,S : First aid kit must be present at the area and the HSE personnel is the first response in case of
emergency

Part 4: Review. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? Any practices
that need to be captured in the OMS? List action items, changes, and transfer any changes to the Change Management system.

File: 10.30
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
1 Mobilization of workers, equipments Unauthorised equipment/tools brought to site Before mobilizing any equipment/tools make sure
and tools that the E &P Personnel got inspected the
equipment.
All the hand tools must be colour coded prior to
mobilization.
Unskilled and uninducted personnel starting Ensure that all personnel prior to start the have
the job been inducted and oriented about the hazard in the
job site
Workers starting the job unfit to work All personnel not fit to work shall not be allowed
to work at the project site.
Workers starting the job without JSA Prior to work all participants of activity must be
Participant toolbox meeting discussion. Persons
signed at the back of JSA

2 Cleaning of roof surface Hand Injury Ensure proper hauling of materials/get help if
required/Wear leather gloves
Back Injury Ensure workers/operators properly inducted about
the proper positioning
Ensure workers are complying with the min. PPE
req. Safety shoes, helmet, safety glass, and dust
mask.
Dust Wear dust mask at all times.

3 Heating bitumen near Fire  Fire extinguisher shall be in place


Accommodation block C  First aid box shall be present
 Proper care shall be taken while handling
the bitumen.
 DEL fire watcher shall be stationed as fire
watch man
4 Applying primer coat, asphalt MSDS  MSDS shall be attached with the JSA and
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
bitumen flood, and lying of jute felt all the instructions to be followed.
on to bituminous coat.
Spillage of Bitumen o Bucket shall not be filled full. While
transporting it to the top.
o Slow movement shall be maintained
(No haste work)
o Gumshoes shall be worn.
o Wood spreader shall be used while
spreading of hot bitumen.
5 Sprinkling of sand Dust Dust mask shall be worn at all times.

6 Work at height Fall of person  Certified and approved platform shall be


used
 Green card shall be worn
 No stacking of materials on to the scaffold.
7 Demobilization Same Proper house keeping shall be done prior to
demobilization

You might also like