V 102 N 03 P 151
V 102 N 03 P 151
V 102 N 03 P 151
The Journal of The South African Institute of Mining and Metallurgy APRIL 2002 151
A long hole stoping system for mining narrow platinum reefs
➤ Sizes of development ends are crucial to make this
system profitable (drill raise @ 1.6h x 3.2w m; holing
raise @ 1.0 x 1.5 m)—this to prevent excessive waste
rock dilution
➤ System planned as support-free, man-free stope panel
environment based on throw-blast-cleaning and a total
of 5 people per production panel.
Support requirements
1m
Planned 0.65 m
● ● ●
1m
● ● ●
Main 1. Footwall damaged due to blast ● ● ●
access way 2. Pre-install 1.8 m rockbolts to pin
footwall to ensure it is not damaged by ● ● ●
blast
3. This will ensure a 0.65 m stoping width ● ● ●
All bolts to be installed on a 1 m
square pattern, measuring 1.8 m for
height up to 2.4 m. If excavation height
Bolts to overlie stoping more than 2.4 m install 2.4 m
activity rockbolts. Please note, rockbolts are
mechanical end anchored bolts.
152 APRIL 2002 The Journal of The South African Institute of Mining and Metallurgy
A long hole stoping system for mining narrow platinum reefs
➤ Electrical supply: 525V and ±65kW (Pilot wire system) correct and safe blasting practices. This training was done by
➤ Sufficient lighting required African Explosives Limited.
➤ Mine required technical specifications on the drill rig
from Tamrock
Project site
➤ Tamrock had to provide a service technician for the rig
maintenance and one operator for the drill rig for a The site was situated in the old trackless area of
three month trial period. Boschfontein Shaft of Anglo Platinum, Rustenburg Section.
The project began in January 2000 and trial work was
Operation, ore removal and cleaning requirements completed in July 2000. See Figure 4 for more detailed
information on the project site.
Drilling accuracy was well within the desired 0.5% specified,
though drilling rate was slightly slower than anticipated. At
an early stage drilling straight holes was shown to be the Project achievement
easy part of achieving the necessary hole accuracy. The
Safety
difficulty was ensuring that the drill feed was pointed in the
correct direction. An angle indicator was mounted on the drill During the 6-month project trial period there were no injuries
feed that gave a vertical angle read out of 0.01% of slope; recorded.
setting the horizontal was more complex and involved setting
the drill feed relative to survey lines
Throw blasting of stoping ore into the strike loading drive
was achieved with broken ore removed by LHD.
The final cleaning of the stope was done by means of Production
water jetting from a remote position in the drilling drive after Plan Actual
completion of the blasting process. This practice is consistent
with our aim of creating a man-free stope. Face advance 2 m per blast 1.5 m per blast
Metres per shift 125 m 105 m
Square metres per shift 60 m2 40 m2
Training requirements Hole deflection 75 mm/15 m 45 mm/15 m
Shaft head cost reduction 15% 10.9%
Tamrock provided a three-week training period for all Stoping width 65 cm 45 cm (not optimum)
relevant engineering and mining personnel. The engineer on Holes blasted 7 7
Hole burden 0.5 m 0.45 m
the mine had to identify artisans that could be trained as drill
Cleaning water jet Yes Achieved
rig operators. Due to the complexity of the blasting process,
Throwing blasting Yes Achieved
detailed training had to be given to relevant personnel on the
Numerical modelling
results showed, this
area required long
Mined out
anchors
1 2 3 4 5
Indicate access from
top reef drive
Mined out
The Journal of The South African Institute of Mining and Metallurgy APRIL 2002 153
A long hole stoping system for mining narrow platinum reefs
Advantages of this mining method Actual achievement January 2001 to July 2001
It allows for a low safety and health risk as well as improved Total
working environment. Physical work is reduced and it is
easier to motivate the workforce. Another advantage is the Total possible area (m2) 4.317
Extraction @ 62% (m2) 2.545
improvement in grade due to better control of dilution, as
Grade (g/t) 7.00
only the channel width of the orebody is mined. This reduces Stoping width (cm) 99.8
ore transport costs and improves cost efficiency per ounce. Tons milled 22.182
Ounces 1.655
Revenue (R) 8.627.515
Disadvantages of this mining method Contract payment 326.725
Stores 469.341
Due to the lack of support in the mined-out areas, careful Purchasing long hole drill rig 280.000
production planning and rock engineering design is required. Development payment 853.893
Where horizontal fractures exist in the immediate Total cost (R) 1.929,959
hangingwall, such as the triplets above the UG2 chromitite at Shaft Head Cost:
Rustenburg Section, critical spans will need to be reduced— Direct cost per ton hoisted (R) 87.01
Direct cost per ounce (R) 1.166,14
this will impact on development replacement rates and
therefore also on cost per ounce.
A high-competency workforce with multi-skilled mining
and engineering personnel is required. It is probably this Economic viability of the project
issue that is the most challenging—ensuring the operators Total
have the relevant skills is a training issue, ensuring all levels
Total possible area (m2) 25800
of mine management have the necessary understanding of
Extraction @ 62% (m2) 16000
the new mining process is a paradigm shift. Grade (g/t) 7.63
Stoping width (cm) 65
Tons milled 32.240
Conclusions Ounces 4.023
Revenue (R) 20.115.000
The results achieved exceeded our expectations. We have
Contract payment 579.780
demonstrated that narrow, tabular orebodies can be Stores 513.000
mechanized and perhaps more important, that it is possible Purchasing long hole drill rig 2.400.000
to create a man-free/support-free stoping environment. It has Development payment 2.218.974
significant potential in terms of gaining both scale and Total cost (R) 5.711.754
154 APRIL 2002 The Journal of The South African Institute of Mining and Metallurgy