Dot 30333 DS1 PDF
Dot 30333 DS1 PDF
Dot 30333 DS1 PDF
April 1982
Final Report
Prepared for
Sufficient copies of the report are being distributed to provide two copies
to each regional office, one copy to each division office, and two copies to
each State highway agency. Direct distribution is being made to the division
offices.
Charles F. Scheffey
Director, Office of Research
Federal Highway Administration
NOTICE
The contents of this report reflect the views of the contractor, who is
responsible for the accuracy of the data presented herein. The contents
do not necessarily reflect the official policy of the Department of
Transportation.
FHWA/RD-81/074
4. Title and Subtitle 5. Report Date
GROUNDWATER CONTROL IN TUNNELING
VOL. 2 Preventing Groundwater Intrusion into April 1982
6. Performing Organization Code
Completed Transportation Tunnels
8. Performing Organization Report No.
7. Author's)
Washington, DC
15. Supplementary Notes
16. Abstract
This is the second volume of a three-volume report. This Volume 2 describes
various groundwater control methods for keeping tunnels dry during the life of
the structure. The methods discussed include means employed to provide impervious
structural concrete, types of waterproofing membranes, methods used to seal
segmented tunnel linings, grouting of soils and rock, and sealing sunken tube
tunnels. Problems resulting from inadequate methods or failure of control
measures are discussed as well as maintenance programs to maintain the integrity
of various groundwater control systems.
19. Security Classif. (of this report) 20. Security Classif. (of this page) 21- No. of Pages 22. Price
li
VOLUME 2
TABLE OF CONTENTS
Section Page
PREFACE ii
1.00 INTRODUCTION 1
1.10 Purpose and Scope 1
1.20 Problems Caused by Inadequate Control of
Groundwater Intrusion 4
1.21 Sources of Water 4
1.22 Possible Causes of Water Inflow 5
1.23 Problems Caused by Water Inflow 6
1.24 Permissible Leakage 7
1.30 Evaluation of Site Conditions 9
1.31 Preliminary Studies 9
1.32 Detailed Studies 11
in
Table of Contents (Continued)
Section Page
IV
Table of Contents (Continued)
Section Page
5.14 Grouting Methods 97
5.15 Application 100
5.16 Verification of Grout Application 100
5.20 Consolidation Grouting of Rock Tunnels 102
5.21 Grouting During Excavation 102
5.22 Pregrouting Rock Before Excavation 103
5.23 Grout Mixes and Pumping Equipment 105
5.30 Annular Space Grouting and Contact
Grouting of Tunnel Lining 107
5.31 Annular Space Grouting 107
5.32 Contact Grouting of Concrete Linings
in Soft Ground Tunnels 109
5.33 Contact Grouting of Concrete Linings
in Rock Tunnels 110
5.40 Diaphragm Cutoff Walls 111
5.41 General Description 111
5.42 Cast-In-Place Reinforced Concrete
Diaphragm Walls 114
5.43 Cast-In-Place Soldier Pile and
Tremie Concrete Walls 115
5.44 Precast Concrete Segment Diaphragm Walls 117
5.45 Use of Diaphragm Walls as Permanent
Groundwater Control 118
5.50 Permanent Lowering of Groundwater Table 119
Section Page
REFERENCES 176
VI
LIST OF FIGURES
VI i
List of Figures (continued)
vm
List of Figures (continued)
IX
LIST OF TABLES
AREA
DENSITY
FLOW
FORCE
LENGTH
VOLUME
xi
1.00 INTRODUCTION
3. Examples of notation:
A/all: B/l = Class A overall, Class B over 1 m square
A/all: B/100A = Class A overall, Class B over 100 mm
square
8
Damp Patch: Discoloration of part of the surface of
a lining, moist to touch.
10
.
11
Careful visual photographic examination of soil and rock
samples can be useful in evaluating the potential variation
between vertical and horizontal permeabilities of soil units
and the size and condition of joints in rock units. Water
quality tests should be aimed at assessing possible effects on
construction methods and the completed structure. Chemicals or
contaminants in the water can have adverse effects on the use
of some grouts, bentonite slurries or waterproofing material.
Some chemicals will speed corrosion of embedded metal in the
event of leakage into the completed tunnel. Water quality
tests should include conductivity, temperature and pH tests.
12
2.00 WATER-RESISTANT CAST-IN-PLACE CONCRETE LININGS
2.10 GENERAL
2.11 Purpose
"6. Drains
13
2.12 Lining Thickness
When the tunnel must be kept dry the concrete lining must be
made strong enough to withstand the hydrostatic pressure as well
as ground loads. R. B. Peck (Ref. 102) demonstrates the magni-
tude of this change. The illustration assumes a 20-foot tunnel
built in fair to good quality rock at a depth of 2500 feet (760
m). Steel sets are used to support the rock load and 12 inches
(300 mm) of concrete, compressive strength 4,000 psi (30 MPa)
would be placed to protect the steel from corrosion, the water
draining around the tunnel into a drainage system. When this
is changed to an impervious lining the required thickness be-
14
comes 32-1/2 inches (830 mm) an increase of 1707o. He further
states, that were the lining shotcrete instead, the corrosion
protection coating could be 4 to 6 inches (100 to 150 mm) thick,
but if the shotcrete lining were to support the hydrostatic
load, at a thickness of 32-1/2 inches (830 mm), the increase
would be 5507o. Although most transportation tunnels are rela-
tively shallow, they may pass under hills or through mountains
where high water pressures must be considered.
15
during the design of the permanent lining of such a structure.
With the recent research efforts toward continuous tunnel
construction, with concreting of the lining following immedi-
ately after the excavation, these higher loads must be provided
for to avoid failures. Use of a preliminary lining of more
flexible shotcrete that allows redistribution of loads is pre-
cluded by this type of construction. In any type of ground, if
the concrete lining is to prevent groundwater infiltration, the
permanent lining is more likely to be free from cracks if it is
placed after the ground movement has become minimal (Ref. 14).
16
led by the paste from the groundwater the hardened concrete will
be porous. This porosity does not necessarily affect the
strength of the concrete.
Aggregates
Ideally the aggregates should come from rock of very low
porosity. This is especially important if the cement paste is
somewhat porous since it reduces the effective area through
which the water can flow and increases the length of the path
thus reducing the rate of flow (Ref. 89).
Cement Paste
17
released by the chemical reaction during hydration. The amount
of this shrinkage can be reduced by chilling the plastic con-
crete before placing, by replacing a portion of the portland
cement with a material such as pozzolan which will act as a ce-
ment but does not produce as much heat during its hydration,
using as little portland cement as possible while still meeting
the requirements for strength, impermeability, and workability,
spraying cooling water on the forms after the concrete has been
placed, and curing with cool water sprays (Ref. 15). Where ex-
treme measures are required to minimize temperature shrinkage
cracks cooling water can be piped through the new concrete low-
ering the temperature at the center thus keeping the entire pour
at a more uniform temperature (Ref. 73). While the reference by
Janssen describes this method being used for prefabricating sun-
ken tube tunnel sections, no reference has been found of its use
for a cast-in-place lining.
18
The compatibility of the concrete with any other material
to be embedded in it must be considered. If a chemical reaction
between the two is possible, it is likely that it will deterio-
rate the concrete. Aluminum, for example, reacts principally
with the alkali hydroxides in the cement. The resultant com-
pound occupies more space that its constituents and therefore
it can crack and spall the concrete. Iron when sufficient
oxygen is present, is also expansive in concrete. Aluminum
items must be coated but iron need not be unless oxygen will be
available at the location of the iron.
The higher the stress in the steel the more rapid the corro-
sion. To minimize the effects of corrosion, intermediate grade
steel should be used with higher than the theoretical design
area. This also aids in the reduction of shrinkage cracks.
19
(1) 1/2 3/4 (2) (3) 1 1/2 (5) 2
20
.
2.52 Waterstops
21
the central portion of the waterstop. The ability of the
material to withstand extensive elongation and return essen-
tially to its original configuration is important. The
materials used in the waterstops must retain this ability to a
sufficient degree to fulfill the waterstopping function for the
anticipated useful life of the structure. Materials are some-
times tested for the retention of this ability after artificial,
accelerated aging. A report on natural rubber indicated a life
of 100 years at 20oc and 400 years at 10oc (Ref. 44).
22
1
±: rx
c** %'
f\ u '* . ,
Wl4>
CAST-IN- PLACE
S5H"
jj jpr
*
SECONDARY
SEALANT
to
.
A
Rubber Waterstops Polyvinylchloride Waterstops
c o n_n_n_n_n
Lru-Lnj-u
n__n_n_n_n
Lru~-u~u~-d
0=0 p n n n n
Lr-U-LT-Lnj
y"?y
\3L))
n_n_n_n_n
U-J-TJ-U-J
ru-n_n__n_n 1 1 1 n_n_n_n_n
LrLr-Lr-Lru LrLrLn_ru
y K\S.\mvWiWw9
23
For horizontal joints where the concrete is dropped upon
the extended position it is sometimes recommended that a layer
of grout be placed over the waterstop just prior to the concrete
placement to prevent excessive movement and to insure against
honeycombing and voids. A special form of waterstop has been
developed for such joints (Ref. 88). It's much shorter and
wider than those discussed above with keys to grip the con-
crete. It is less susceptible to deflection by the second pour.
24
)
DETAIL A
DETAIL B
BENTONITESEAL
BENTONITE COMPOUND
DETAIL C
LONGITUDINAL JOINTS
(1 mi = 25.4 ram.
25
4 IN. TYP.
T&
^±1/3-— =-^
^ 1/3
4^ 30 IN. TYP.
PVC WATER
i
/ EARTH
STOP 7
*-
1/3
^typT
EARTH
TYP.
18 IN. TYP.
3 IN. TYP.
PVC WATER STOP'
4 IN. TYP.
ft
mw^^7&
<>
-><-
18 IN. TYP
-><-
^^//^///i///^m///*///y//i'///^/^///^//^^
TRANSVERSE JOINTS
26
<*-2IN.
•BENTONITE PANEL
BENTONITE COMPOUND
3-IN. DEEP
5/16
CONCRETE IS PLACED DI-
* IF
27
.
28
.
29
4. Place in shallow enough lifts so that they can be well
compacted and if internal vibrators are used the top
portion of the plastic lift below can be reached by the
vibrators.
5. Vibrate the concrete to compact it thoroughly using
internal vibrators or vibrators attached to the forms
or both. Compaction eliminates rock pockets and large
air bubbles, unifies each lift with the still plastic
lift below, completely surrounds the reinforcing steel
and other embedded items with the concrete, and moves
enough cement paste to the faces and the top surface to
seal these surfaces.
6. Use special care in compaction along joints and around
the reinforcing steel, and other embedded items.
7. Once pouring has begun on a section it should be com-
pleted without interruption.
30
RELATION OF CURING TIME TO PERMEABILITY
Days of Coefficient of
Curing Permeability
Fresh Paste 1, 150,000, 000
1 36, 300, 000
->
2,050, 000
3 191, 000
4 23, 000
5 5,900
7 1, 380
12 195
24 46
25
20
E
V
15 "r
C-rJ n
8 % 1.5
<r <=>
\°
\
1.0
an & \
\o
Vff 1
CM 00
\p
(VJ f>
0.5
31
.
32
If water leaks through a joint in the concrete, the repair
procedures taken should be suitable to the type of joint and
the reason the joint is not watertight.
2.90 INNOVATIONS
For many years a length of tunnel could be lined with rein-
forced concrete more rapidly than it could be excavated; now,
due to new developments in tunneling techniques, excavation
often outstrips the lining placement. Studies are being per-
formed to develop techniques for more rapid concreting using new
developments in concrete technology. These include regulated-
set portland cements, expansive Portland cements, polymer-
impregnated concrete, polymer concrete, f erro-cement and fiber-
,
reinforced concrete.
33
.
34
Table 2
Concrete with up to
6.7 wt % loading of
polymethyl methacrylate
Concrete control specimen Co 60 gamma radiation
(type II cement) polymerized
hardeners which can be used and the propert ies of the concrete
vary considerably (Ref. 42).
35
of the resin. This reduction in linear dimension can be as much
as 0.1% for furfural-acetone polymer concretes. Epoxy-polymer
concretes show the least shrinkage. This shrinkage ceases as
the hardening process is completed (Ref. 42). Until some
meansof avoiding this shrinkage is developed the polymer
concretes would be more useful in precast elements than in
cast-in-place linings.
Heat affects the different types of polymer concretes in
different ways. One type, polyester-polymer concrete, burns.
Many others show decomposition of the polymer with evolution of
gases (Ref. 42). Some tests have been done to evaluate the
effects of geothermal temperatures on certain polymer concretes
in which the effects of temperatures up to 238°C were studied
(Ref. 79). These reported about a 60% reduction in compressive
strength after 28 days of exposure and a loss in weight (Ref.
79).
2.95 Ferro-Cement
36
.
37
3.00 APPLIED WATERPROOFING ENVELOPES
3.10 GENERAL
When the underground structure is not of itself sufficiently
water-resistant, an envelope of waterproofing material may be
placed around the outside of the structure to prevent the infil-
tration of the groundwater into the structure. This is done
frequently in cut-and-cover construction but may also be applied
to soft ground or rock tunnels. When the groundwater head is
not great or when the only protection required is from water
seeping through the ground from above, often only the roof or
roof and walls receive waterproofing. However, when structures
are below the water table they may be completely surrounded by
a membrane made continuous by overlapping and sealing the sec-
tions of the membrane.
38
.
Relative Permeability
Permeability mm/sec f t/hr
impervious requirement.
39
3.21 Brick Set in Asphalt Mastic
40
, 1
4'Conc. Afosf/con/f/y/yfr
?7 ir4~C<y?c.
r
=S5BSS 31
2' Cone
1 e' t
•*4~Cor?c.
flbaea/OaOor de/wf/./MOor
IB
w
1
If
$rt>£jnc/M/a/<rrle7v/ Groundribfartere/ .
j=m
nfr-
fM
;i I
r. > * v» >
3ffytf/>#Jkrw. '^£5? d/ p
Tcpo/Zfy/Zormis
L oca/aa'te/w&? if £\j*tWl_
>
Est i-f
E/JOa0crfrvtjmt/ /rconc^
MiferUrfJjSobot* - /layer of£r7cr//7rfsp/?.Mbsf/c
*'&**:
*> -ryt^if -t-t | |
TT~if Z=X
5/DF Pifi7rmAts
L/p/
^p ^ 6tonc -
4"Conc.
Z"Conc.
4ffytYP.
» 4"Conc
flba'ef/./M.Oor Be/otY£//00aar
/ ''
6roc/rx?jVaforl ere/ Grourx/nb/erlek'e/ .
1 1^ §qs€j>f^o/^i
V
"\
-J
._*
*
*. *.'•.
»£.*!•
-. v^ //a^rof£rYcA/n&/rt#0*//c2 I
4%hrtC.-i T f j'.'
7"
7" i-
=2
T.Il J. 1
'
'
i i i
, i i i i j i i i
/P/</Wr? T
SECT/^5W£/9/?7//-S£7fr££^ ST/fr/0A/5
Figure 7 - BRICK AND MASTIC AND 3-PLY WATERPROOFING DETAILS FORMERLY
USED BY NEW YORK CITY TRANSIT AUTHORITY
(From Ret". 93)
41
pitch to which mineral fibers have been added to make the
material less susceptible to temperature extremes and more
stable in running water. These materials have performed well
buried in soils for 50 to 100 years. The coal tar products show
somewhat better waterproofing properties than do the asphalts.
The asphalts are somewhat more resistant to weathering which is
not of significance in tunnel waterproofing.
42
2" ALU LAPS
TYPE A -2 PLY
TYPE B —3 PLY
-FULL WIDTH
\pzzz2zzm. LOW POINT OF STRUCTURE
Vs Iv/IDTH
e
/a WlbYw.
FULL WIDTH
TYPE D - 5 PLY
Ezzzzzzaa DENOTES FELT
(1 in. = 2.54 cm) 1 iihi 11 DENOTES FABRIC
43
When the membrane is on the exterior and the surrounding
soil settles the waterproofing membrane may be stripped off.
To avoid this the waterproofing membrane can be sprayed with a
bituminous antifriction layer having a thickness of 8 to 10 mm
(0.3 to 0.4 in.). This new material allows the soil to slip
easily along the wall thus preserving the integrity of the
waterproofing (Ref. 43).
The New York City Transit Authority specifies the use of
asphalt and asphalt impregnated woven cotton (Ref. 93).
American Railway Engineering Association allows a choice of
asphalt or coal tar pitch with woven cotton fabric or felt
saturated with the appropriate bituminous substance (Ref. 4).
Another multi-ply system uses coal tar enamel, impregnated felt
plies as the outer plies and fiberglass reinforcing mats as the
inner plies. It is stated that these applications should last
over 100 years (Ref. 15).
44
In another development the bituminized rolls pass through
an electrically-heated bitumen bath and then directly onto the
tunnel surface (Ref. 43).
45
,
PROTECTIVE WEATHERCOATING
INERT REINFORCING PLY
FORTIFIED BITUMEN
PLASMATIC MATRIX
FORTIFIED BITUMEN
RELEASE PAPER
46
.
The materials which are most promising both in cost and pro-
perties are polyethylene, polyvinyl chloride, butyl rubber,
Hypalon, and Neoprene. Their advantages over built-up
membranes include:
47
Application possible without use of hot mastics
Resistance to puncture
Self-healing, to some degree especially the rubbers
Flexibility.
3.31 Polyethylene Sheeting
Polyethylene sheets can be joined by heat fusion to make
watertight sheets of any size and shape desired. If given
proper treatment it can also be bonded using epoxy or other
adhesives. This latter property makes it possible to attach
the sheets to almost any surface.
48
3.32 Polyvinyl Chloride Sheeting
49
BUTYL MEMBRANE SPLICES
RECOMMENDED IN ORDER LISTED FOR FIELD ASSEMBLY
NO.
FACTORY MADE HEAT /-»,
VULCANIZED SEAM ' L, , £.._ -BUTYL GUM TAPE EXTENDED
f |,
AT LEAST V
BEYOND
EDGE OF SPLICE
.0&25" GAUGE
^^<^V^NV^\\\\\XvSS3i
*///////////////. ////)/ //////////////////////a T77\
IOF SPLICE.
.0426 GAUCE-
N SS55SSSSSSSSSg5SSS5g5SS555SV
TOP \Z PIECE
B»>^^m^<x^m^
-i.
' zz:
"Base piece ^>
O.OG25"OR. HEAVIER 0.06>25'OR HEAVIER
BUTT SPLICE
NO.
.BUTYL GUM TAPE EXTENDED AT LEAST V BEYOMO EDGE OF SPLICt-
-*J- G" H
J.
ttOGES*
r
OR HEAVIER
VZZZZZZZZZZZZZZZZZ2.
l0.0425 gauge
—
O.CXiZS" OR HEA. iER.
NO. 4
i_
&ZZZZZZZZZZZZZZZZZZ1
•
50
surfaces is accomplished in much the same way as plastic water-
proofing sheeting is, but the rubber is highly abrasion resis-
tant and rarely needs protection during backfilling or concrete
placement. Of the synthetic materials butyl rubber is the most
impervious and most frequently used in the United States.
51
built-up membrane means of waterproofing is tremendous.
Furthermore no hot bituminous material need be handled.
i
I
52
Bentonite is a highly plastic clay resulting from the
decomposition of volcanic ash, and it is found in quantity in
Wyoming. Chemically it consists primarily of sodium mont-
morillonite. It is inorganic, nontoxic, fire-resistant, and
unaffected by freeze-thaw cycles. When unconfined its wet
volume can be from 10 to 25 times its dry volume and it is then
in a gel state rather than a solid state (Ref. 124). This
property is the one that makes the mineral useful in water-
proofing. When wet it expands and fills small voids and cracks
preventing the flow of water through them. Cracks that develop
in the structure, due to either temperature or drying shrinkage,
are filled and closed and even cracks due to movement of the
structure may be filled by the expanding bentonite.
53
corrugated kraft paper. These panels are usually four feet
square and 3/16 inch thick. American Colloid Company, manu-
facturer of Volclay Panels, gives the results of permeability
testing using standard soil testing procedures with a static
60-foot (18-m) head as:
to 78 1x10-7 8.47x10-9
78 to 122 2x10-7 1.69X10' 8
122 to 172 1x10-7 8.47x10-9
172 to 1324 0.5x10-7 4.23xl0"9
54
VOLCLAY TYPE I
vw FOUNDATION POURED AGAINST
TIE BACK SHORING WALL
T^ *] SOLDIER
BEAM
PANELS
3/16" THICK
WOOD
LAGGING
VOLCLAY
HYDROS AR TUBE
TIE BACK
ROD
V-
VOLCLAY TYPE I PANELS Vl6" THICK
-v^
PROTECTION AGAINST
VOLCLAY TYPE I PANELS COURSE BACKFILL
3/16" THICK ON SIDEWALLS
ANO UNDER-SLAB
X
HYDROSTATIC STRUCTURE
VOLCLAY TYPE 1 PANELS
3/16" THICK
ON WALLS
PROTECTION
BOARD
VA-J-
VOLCLAY PANELS
3/16" THICK (SLABS UNDER 8' CONCRETE WALL PLAN
THICK USE TYPE 3 -SLABS PANELS RECEIVE BACKFILL
OR THICKER USE TYPE 1 )
1
JL
FIRST POUR WATERSTOP SECOND POUR
55
wall panels with the slab panels is important and takes good
supervision. If backfilling cannot be done immediately the
installed panels must be protected from moisture.
Backfilling must be done with care to protect the kraft
paper from damage and movement. If the backfill contains
coarse or irregular gravel 1/4-inch hardboard or similar mate-
rial may be needed to preserve the integrity of the panels
during the backfilling operation. In order to prevent the
installed bentonite layer from loosening, the backfill should
be compacted to a minimum of 857o of the maximum as determined
by the Modified Proctor test.
Total Coefficient of
Water Head El apsed Time Permeability
Feet Meters Days ft/hr mm/sec
56
before the application of the waterproofing and the smoothing
and filling of the surface may be done at the same time as the
concrete for the slab or wall is placed. Typical applications
of the sprayed-on bentonite and associated products are illus-
trated in Figure 12. The sketch shows the application of
Bentonite directly on lagging. Here the recommended thickness
is 3/8 inch. The second sketch shows an underground structure
with Bentonize applied directly to the exterior of the concrete
wall and roof slab. If the concrete is not green a necessary
precaution for proper adhesion is that it be misted with
alcohol to remove surface dust before application of the
bentonite. Also shown in this sketch is the application of
Waterstop-Plus the Bentonize manufacturer's joint compound for
,
57
)
Footing
TUNNEL PLAZA OR
FLOOR SLAB UNDERGROUND ROOF SLAB
Wearing Surface
Waterproof
Waterproof
Membrane
Leak Localize) is placed over the waterproof membrane in Leak Localizer placed in a manner which will isolate and
a square grid pattern to isolate any water leak coming stop the horizontal migration of water under the water-
through the waterproof membrane. proof membrane, facilitating easy repair
58
3.60 CEMENTITIOUS WATERPROOF COATINGS
59
1/8 in. (3 mm.) thick is recommended. The manufacturer's
published data states that this thickness will resist a 50-
foot (15.2 m. )head of water.
60
FROST INSULATION
(ROCK WOOL)
OUTER AL PLATE
CONCRETE
61
4.00 SEGMENTED TUNNEL LININGS
62
63
JACKING STRUT
GROUT
WASHER
BOLT HOLES I DIA. H.T. BOLT
GROMMET
CAST IRON SEGMENT
SEALANT GROOVE
4 OUTSIDE SLAB
TYPICAL BOLT ASSEMBLY AND
GROUT PLUG CAULKING CONCRETE SEGMENTS
4 FLANGE
64
individual, contiguous, prefabricated pieces limits the methods
of waterproofing for groundwater control in the permanent struc-
ture. Covered in Volume 1 of this study are numerous diverse
methods of controlling groundwater during construction, many of
which could be used in conjunction with this type of tunnel
contruction. Keeping water out of the permanent structure how-
ever, means sealing thousands of short joints and bolt holes.
To give an idea of the relative lengths of joints to be sealed,
a typical single track rapid transit cast-in-place tunnel lin-
ing would have from one to five linear feet (0.3 to 1.5 m) of
joints for each foot (0.3 m) of tunnel, depending on the number
and lengths of pours. A comparable segmented lining would have
twenty to forty linear feet (6.1 to 12.2 m) of joints per foot
(0.3 m) of tunnel, depending on the size of segments. It is not
practical to surround the structure with a continuous membrane
outside the segmented lining, and it would add considerably to
the cost to place a membrane inside the lining and then add
another structural cast-in-place concrete lining inside that.
65
Caulking groove, 25.4 deep
117.5
machined from solid
chamfer
Circumferential joint
Machined faces
Note: All dimensions
in millimetres
Longitudinal joint
66
the space between bolt and hole. Prior to about 1960 hemp gas-
kets dipped in red lead were used for grommets but these have
been replaced by polyethelene gaskets which are more efficient
and much easier to handle.
67
max.
.Welds
min.
plate prepared as shown
f-*-3.1
00
<£>
— _co
E -n
^A\/7/>///////mv////////////////////////m
34.9 dia. bolt holes
\ Taper plug 31.75 dia.
B.S.pipe thread
Equal — Equal
0.61
68
of fabricated steel and cast iron had some advantage over those
bidding concrete. Because of the anticipated difficulty of
sealing concrete segments against relatively high heads of
water, only a portion of the total tunnel lengths involved could
be bid as precast concrete. The contract was let for all seg-
mented linings to be of fabricated steel.
On the WMATA system the linings were not let on a separate
contract but left to the individual construction contractor to
furnish. The contractors were given the option of providing a
fabricated steel segment lining, a cast iron and ductile iron
segmented lining, or a two stage primary lining with a secondary
cast-in-place lining. Since individual construction contract
packages were comparatively small compared to the system-wide
contract on BART, and the cost to mobilize a lining fabrication
plant is high, most contractors elected the two stage support
and lining system.
69
J*
mm
CD
W
w
Eh
oo
Q
W
Eh
<
O
M
P4
<
w
D^
Eh •
O
Q O
P^ w>
<
PQ 0)
>
s o
M k
CD
CD I
3 C
M rtf
^ 0)
D a
OS
Q <+h
< O
W
CD Q)
3 -H
H 5^
o 3
< o
o
J v^
PL,
00
•H
70
Filled with cement
mortar after erection
140mm
71
true of concrete segments also but concrete being brittle, there
is more of a possibility of leakage through cracks caused by
improper handling, shield shove loads, and ground loads. The
concrete material in segmented linings is generally superior to
a cast-in-place concrete lining. Precast segments are made in
casting yards where mixing, placing and curing of the concrete
is performed under much more favorable conditions than cast-in-
place tunnel concrete. Although the art of casting with steel
forms and controlled materials, ideal water-cement ratios and
steam curing results in very accurately dimensioned segments,
they cannot match that achieved by machined metal plates. To
compensate for this, designers of concrete segments often speci-
fy a sealing strip or gasket on all flange faces in addition to
caulking. This will be discussed in greater detail with other
methods of waterproofing concrete segments. Other designers
have come up with composite segments basically of concrete,
,
72
— —
Q
PS
O
U-t
J
H
O
H
55
O
H
Crt
53
w
Eh
X
w
w
55
H
J *-N
zf
J 00
Eh IM
55 cu
W PS
o rv
PS LO
O oo
P-l 00
cc E 5 CD +->
55 &
3, H o
55 ft
K T ! V» H
hi
.-UL —14-
H
_ lii — ii
•}!
|i;
a»
. ,i
4U m. —L_
.jji jii— _
—W
ft
lii ui--
- -w-
— —
f -ur - m
hi
"!
ill
- - Tf
ia,
<
J PS
<D
^ 'i
< QJ
ji
c W PS
o Eh PS
o J Eh
CO
O
CQ 6
^Yj^£]LLij W fc
i
Eh Ph
*_
r-."-rr^
i
Jw
co
CO
C CD
" H
^ r
ir-T-
^«-_
n In
o
4-<
a
CM
—a-.-^jsMM'
'< !>! !< |ii i" ,'!
i j! I !
" a>
-tii- -41.
-.^intrx.-.- «-
'
-4»l
CO QJ
-*> - at
[CO bO
•H
.2 o Ph
qiJ LJDB8 U99MJ3q
E - sdnjjijs -ejp luiug-^
E 5
73
Grout hole
Grout
groove
74
-
OT5B 00
>H
i3 <
WW ID
0)
-s-fi-fl-
f
—
:4L—
0)
O
S
J
H
O U
3 P <1
O ft ft
ft C -P^
C +J ,-s •H£ co J
•H 0] CD CD -P <
0)
S=!
0) -P ^ 6 H s
3- -€ k 6 H bO O o
bO O i i
0> CD A H
CD CD £» ft CO Eh
cr in en >, 4-> <
o -P -P CD r£ S
,£) 0) xi 1 -P bO
C
-p bt TD CD'H W
Z>
rS CD -H CD & nj CO
-P h ,Q O & W
(ti
s
a& o C
6 o
(70
a
o
Sh
-P
to
^
v.._J=--
nrnnr
-*HHH
£l
•HOW
ft ^
fi
O
-P
<
(X,r->
< >>
•"D -P
CD
>H'H
ft O
ft 00
W
•p 00
G
006 CD w
e ft
^ bO w
CD CD ft 1
3=f CD
O td -p
H
CO o
s l
U \5
in
O CO 0) o
o
ft O -P^
iC •p ft CD CD
•H e CD S p. to ft
CD CD /-\ p, O'H o
P. S co O £ -P
bfl-P O & oo
CD CD H CO CD O O w
-Ofcfr P. CO O -P P. 6 ft
O ft •H O X) >H <
A CD c ^1 C'O H'
-P T3 D C
rti
r- 1
CD CD ft m 1
-P P. > -P H
O P. CD c OJ
o C 3 CD O CD -H CN
ft
-ti — ft
ir
e o o
00 O
+J
O
g
oo
-P
to wft CD
p.
3
bO
•H
ft
75
Precast segment
Forming of joints
.
*' *.'*! '..* V*'. •.'. * ° '-•.• ..".
" .« '• ..*.*
. ° v " • • * '! • •'_••
./
;*•'
\ ••Direction in tunneling
1 Compressed solid rubber seal, 2 Compressed solid rubber seal prior to mounting, 3 Plastic packing, 4 Sealing of joints
76
limited success for applications where little or no joint
movement occurred. The second test used several shapes of
neoprene "0" rings with epoxy adhesive. This method proved a
more effective seal than the first. In Ref. 17, Birkmyer sug-
gests a variation to this second test method utilizing an
inflatable "0" ring pressurized by injecting a liquid filler.
Gasket seals fall into two categories. They may be fairly
firm and preformed or soft with adhesive qualities. Examples
of preformed gaskets are butyl rubber as used in the Tokyo and
Munich subways and cellular neoprene as used on some WMATA tun-
nels. For the concrete segments of the Metro de Caracas, the
contractors were given a choice of preformed gaskets of butyl
rubber, polysulfide, or neoprene. Soft plastic adhesive gas-
kets include polysulfide, semi-cured butyl rubber and coal tar
epoxy. These may be sprayed or troweled on the segment joint
face. In the United States, Commercial Shearing Inc. has
developed a gasket material called TSE consisting of a two-com-
ponent butyl-polymer material for use on its steel liners. It
can be manufactured in various degrees of hardness for spraying
or extrusion as a formed gasket. Gasket seals, whether formed
or plastic, are usually considered a primary sealant to be fol-
lowed by caulking. The soft plastic seals are more subject to
damage and contamination by dirt under adverse tunneling condi-
tions. A variety of current and proposed preformed gasket seals
are illustrated in Figure 24.
77
Proposed flexible joint
gasket between bolted
concrete segments, Ahmed
Hamdi Tunnel, Egypt
/'Courtesy Sir William
Hal crow and Partners)
r-.
/
/ *
l
/ v.
79
* •>
14.5 2.5
(3) —— 1
1
Gasket with misaligned T-joint
x Heavy leakage
2 3 4 5
Joint expansion (mm)
1 1 1 1 1 1 1 1
9 8 7 6 5 4 3 2 1
30 27 24 21 18 15 12
-* Profile displacement (%)
80
Leakage duct
gasket, UK
f Courtesy
Colebrand Ltd)
Experimental leakage
duct gaskets, West
Germany f Courtesy
STUVA) (a) (b) (d)
Leakage duct
gasket
Hard rubber
wedge
82
(127 mm) steel ribs embedded close to the inner face and pro-
truding from the ends of the concrete. The ribs were tempora-
rily bolted during construction and later welded to form
continuous circular ribs with concrete between. The project set
a record at the time, for completed tunnel, with an average of
112 feet (34 m) per day (Ref. 135).
The 5.5-mile (8.8 km) long San Fernando Tunnel, also built
for the MWDSC, through ground similar to Castaic Tunnel, was
only 2000 feet (610 m) short of completion in 1971 when a disas-
trous natural gas explosion and fire killed 17 men and delayed
completion more than two years. The lining system consisted of
precast, reinforced concrete segments. The segments were 4 feet
(1.2 m) wide and 10 inches (254 mm) thick, with four segments to
the ring for the 22-foot (6.7 m) excavated diameter. The seg-
ments were manufactured by the contractor with a unique no-slump
concrete and mobile casting machine method. The rate of tunnel
construction exceeded 3500 feet (1070 m) one month and set a
record of 277 feet (69 m) in one day. As in the Castaic
Tunnel, the mining machine shield was propelled forward by
jacking against the lining (Ref. 106). Both the Castaic and
San Fernando Tunnels were constructed in the relatively soft
rock of the California Coastal Range.
83
let, three alternate excavation and lining procedures were
designated: 1) drill and blast excavation with a variable thick-
ness cast-in-place lining, 2) machine boring with a constant
thickness, but variably reinforced lining, and, 3) machine bor-
ing with reinforced precast concrete lining. The third option
with a precast concrete lining proved to be least expensive.
ring gasket and butyl rubber sealant backup strips, while the
rounded longitudinal joints are sealed with a neoprene gasket.
Both have caulking grooves on the inside face filled with an
epoxy sealant.
84
E
o
<ht
CM
II
^fco:
CO
Q H
3
•
<
Eh
W
Ik) Q
CD
8:
H c
fc!bg
s ^ ci S; b < < Q)
t*j
W +J
CO CO
<~ 00 CD
S: U,*0 ^ CQ CQ Eh p 3:
< EhW Ph
H < S Hi
Eh
W CD EhMh
H
w p4 PS
2 W >1
CO
S O Eh CO
Eh
O < CD
H O SS-H
Eh J ^
O H
•-D
O MHO
O EhO
t"D 00^
<
Q LO
P OJ
Eh
H CU
CD
o bO
H
85
handling, and supporting the heavy segments, as well as sealing
problems and the prevention of cracked corners should be
improved with additional experience and experimentation. This
type of lining has many advantages over a two-stage process of
temporary support and cast-in-place secondary lining. Casting
and curing the concrete in a yard produces a stronger, more
dense and water-resistant concrete than can possibly be placed
in the tunnel. Other important factors are improved safety and
production. The entire concrete pour crew works in a plant out-
side the tunnel. With proper equipment the ring can be rapidly
erected and backpacked, producing a completed tunnel instead of
one with merely temporary support. Since the excavation and
support procedures are uniform throughout the tunnel the crews
and production need not vary depending on varying needs for tem-
porary support, and the crews can develop greater proficiency
performing uniform operations. There is no need for safety mi-
ners to keep the back scaled or retimbering crews to reblock or
add sets for taking increased weight. Cleanup is considerably
simpler and the light colored walls reduce lighting require-
ments. A flat invert can be cast in the lining, as was done in
Buckskin Mountain, Park River, and Stillwater with inserts to
simplify setting rail. Sidewall inserts can aid in carrying
ventilation, compressed air and water piping, and power lines.
86
5.00 OTHER METHODS OF CONTROLLING GROUNDWATER
87
0.001
88
..
other sealing method and does not require enlarging the tunnel
to accommodate the sealing materials. Grouting after excava-
tion is not considered as successful as grouting ahead of the
tunnel face (Ref. 60). In the United States grouting is
usually used only in real problem areas where water cannot be
controlled by other means (Ref. 124).
In cut-and-cover tunnel construction the soil outside of
the excavation ground supports (sheet piling, soldier piles and
lagging, slurry walls, etc.) can be grouted to control the
influx of groundwater both during and after construction (Ref.
48). The pressure used must not be great enough to damage the
ground support system.
Viscosity
89
requirements of the soil to be treated. If two grouts are
equally desirable for an application the one with the lower
viscosity will enter the soil pores at a lower pressure and
more rapidly than the more viscous, and would probably be the
better choice, if costs are similar.
Setting Time
Strength
Permeablity
90
Durability
For permanent control of the groundwater around a struc-
ture using chemically grouted soil as the primary control the
gel or solidified grout must not deteriorate with time or under
the influence of the soil and groundwater chemistry. The use-
ful life of transportation tunnels is generally around 100 to
150 years. Therefore, in the selection of chemical grouting as
a primary means of preventing the infiltation of groundwater
into the underground structure, the durabililty of the grout is
a prime criterion. Chemical grouting has not been used for a
sufficiently long time that its durability in field conditions
is well established.
Toxicity
Flammability
Cost
91
.
Silicate-Based Grouts
92
syneresis. Syneresis is an exudation of the water from the
gel, producing shrinkkage of the gel. In fine soils this
phenomenon does not occur. If the application is correctly done
and the grout well adapted to the soil to be treated syneresis
should be negligible.
Plant-Product-Based Grouts
Acrylamides
93
solution. It has the advantage of a viscosity of only 1.5 cP,
which is very close to that of water, so that it can be used
successfully to control the flow of groundwater through very
fine soils. This low viscosity is maintained almost to the
moment of complete solidification. Gel time can be controlled
very easily and accurately using varying amounts of the catalyst
initiator and/or a fifth ingredient which can inhibit setting.
Phenoplast Resins
These grouts have low viscosities, about 1.5 cP. This vis-
cosity remains almost constant up to the point of set. Setting
time is controlled mainly by the amount of dilution of the
grout - the more concentrated solutions setting faster - though
some control can be obtained by the use of expensive accel-
erators.
All the raw materials are toxic and caustic. If the prop-
er porportions are used these should be completely combined
into a practically inert mass. This material shows more
promise than polyacrylamides (Ref. 126). It was used in grout-
ing the "Beauchamp" sands encountered during the construction
of the Paris Area Regional Express Transportation System (Ref.
81, 107). Another application of this grouting material was in
the Boulby Potash Mine shaft. There the Bunter sandstone was
first injected with a cement grout till the groundwater flow
was reduced and then new' holes were drilled and the sandstone
was grouted with resorcinal-f ormaldehyde grout (Ref. 35).
94
Polyurethane
95
Emulsions, suspensions of very fine droplets of one liquid
in another, have also been used. Bitumens are the materials
most commonly used, dispersed in water. These can be used in
fine-grain, clayey sands. They leave a jelly-like substance in
the soil of low permeability and low strength (Ref. 56). Their
advantages are their relatively low price, ease of placement,
nontoxicity of ingredients, and good long term stability. They
do not add to the strength of the ground mass treated and are
petrochemically derived. Various resins and waxes can be put
into an aqueous emulsion. These materials are all quite
expensive.
96
4. Laboratory tests made on these grouts with soil.
5. Field testing these grouts for final selection.
97
rH
>. cd
4J •H
•H rl
CO QJ
O 4J
CJ
cu
10
•H
s QJ
^-N
QJ
4J
•H
> 60
•H
3
QJ
4-1
*H
•
•
(3
3 & /~\ •H 0) ^~\ fe 4<i 3 QJ •
O O 4J 44
o
is
4->
c
J
QJ
4J
•H
43
00
•H
(3
QJ
4-»
•H
II AS3 4-1
•H
3
CO
h
H rH 0J 43 3 rH 4J •H O 3 rH O QJ O QJ
25 QJ pq 4J o cd c QJ 4J O cd 4J PQ 4J 4-1
pL] o i •H
>
4J iH
a m
QJ & 3 4J •H «**>
3 CO
IE 4-* QJ 3 u CO QJ QJ
H
O + 3 /-N
43 43
QJ QJ
4J
1
cj
+ PQ QJ QJ QJ QJ PQ ,
QJ PQ 1 PQ 4J rl rH rH
Z OJ 00 4J 3 43
1
4J O
PQ
4J
•H
§
cj o
3° 3 CO
O 3
u&
o
43
4J
QJ
4J
•H «H
0)
4J
4->
3 3
qj a)
CO
3
U
O
2 4J cd
4-1
3 3
QJ 0)
fa
St
CO o + £ CO ~t?
>»iH
•H (3
O O
£3
§8 •H
CO
>»x 00
3 dmix
d
8 8 00
b tJa rH iH rH
(0
«. OJ
fa Cd 4J s
4J4J
a (3
CJ CJ
rH
QJ
(Kj
r*»T-
cd 4J < 3
CJ CJ 3
•H
rH mQJ <u o> rH 43 Cd QJ QJ QJ QJ QJ rH 43 cd QJ QJ CO
o pq o o O cj
•H
CJ 00
tH
O PQ PQ
H3 3 O CJ CJ 00 + o 3 3 QJ
i i 1 fa 1 1 «H •H •H •rl iH Pi
•U -U cd cd Cd rH 4J Q) 4-1 4J 4-1 fH (±4 Cd rH 4J QJ 4-1 -H Cx< Pm
c c o o
•H iH
CJ
•H
O
3
c rs 4J
3
(3 £3 (3 CJ O
3
3 & 3 3 >i
<u cu QJ QJ QJ QJ >> f>% •H QJ QJ rH >v t^ X
§ §
rH
•H
rH
iH
rH QJ
•H 43 I
+ O
ill rl (-1 f-l QJ + 8* U U o
rl QJ QJ iH 43 oj oj fa
cj cj CO CO CO fa o O CJ CJ CJ >> CO Ck CJ CJ > > w
rH 4J
a) 3 /-s
e> QJ QJ
I
H3
4J 4J CO QJ
cd ^n a a 4J 3 3
o T3 QJ QJ 3 •H CJ rH fa
•H a) O QJ QJ
o
rH
•H
4J
3
I
CJ
§
CJ
rH
Cd
U
o C
iH >» 4J
QJ O >s
M
85 CO r-i "H IK rH U «H
M •H
1
x-s
1
/-s H 00 cd QJ 3
cd
o
QJ
>
85
w + Q QJ
4J
QJ
4J
QJ
4J iH
(3 + -H
rl
> o
4-1
•H
rH CO
>-x
a CO
3 •H 3 3 3 3
B
e>
3
4-)
a)
H
rS
CU
-H
CO O
(3 *a
O
r-i
T-{
QJ
CCUm
4J
QJ
4J
QJ
QJ *J
3
QJ
oj
PQ
•H
CO iH
CO
4->
3
4J
3
CO
•H CO
3
•H
M rH > 1 QJ QJ CO
o
CO
H u cji ^
o rH rH
0J
<U
PS
4J
(3 %9 CO 8 8
s8
+
M O8 rH
/
o7
r-i
QJ
QJ
PJ 8 QJ
4J
3
0)
pej •H
CU
fa
a C 1 QJ
a>
pq
QJ
PQ
iH
4J U
4J
rH
CJ CJ
1 iH
3 O QJ
CJ CJ O
QJ CO
CO
rH 0)
H
<
QJ
4J o
QJ 4) <u qj *a JS O Cd QJ QJ -H QJ QJ fe QJ -3 CU CU CJ •3 r-t 3 •3
H O
CJ -H M U 00 43 4J 4J 4J 4J 4J -H •H •H
E* S'-H •H s o O iH 3 a «H «H 43 >«, H S
4-»
•H
4-»
•H T3 s
CU
u i
o o3 oa o cd cd <d >»• V-X QJ qja
4J <
a a tx> 3 cd u 3 cd 3 3 CU 8
1
* -y3 4J -H rH
CJ rH > O O Ti O U QJ O rH O O 4J rH -o rH
•H >s >*. 5>% cd 4J 4J QJ 4J «H > •U >S 4J 4J Cd ^ CU s >%
.H
cd
rj
tH •H
0)
fi
QJ
u
CJ
cd
H cd
rH
+
,
H
a>
4J
o
(3
CU
(3
QJ
^ 3 rH
QJ «H
<-> 3
QJ
rl
CJ
3
QJ
3
QJ
rl
QJ
rl
CJ
X
>H
4J
cd
m
o
O PQ PQ CO CO <tj CJ CJ <J 33 PQ PQ PQ CO PQ <: PQ pq <; <: s I-) <
CO
QJ
r>» rl
CO
H
3
*3
OJ
3
CO
A
CJ
CU O CO co cd
rl CO o •H h
3 CO fa CJ
^N
co
CO
QJ
U *| M
CO •H CO 3 «w o o
A £P fa QJ o O M
U CO O a a
a 5 cu 3 QJ
CO
•H 3 J2 QJ
T3 CO s 60 CO U Pu O 3 o p
a 73 a> rl CO 3 •H QJ cd
oa
m co C •H CO QJ 4J a. M s
CO iH
0)
cd
CO v-^
r3 fe CO
•H
3
•H
cd
M
o CO
CJ CO
iH
0) > M s 3° 43
ptl Pk CU 0J a) fa
co
P u
co CO r^ a 4J p •H 3° C U H >
*2 4J H3 CO •H cu >> rH •H QJ iH O •3 QJ
cd o 3 rH tH 3 M 3
H3
rl T3 rH 60 JS 3C 4J
o cd •H o CU •H QJ •H rH QJ CJ
CJ CO CO > £ » (±4 > (±< O oi < fa
98
.Metro box structure
hw
ht
Sheet pile or
hi concrete diaphragm wall
WSSB&fe
mmmgsm^mm
0.5 m
"Zone of grout injection
Depth
Road surface ft m
jL 1
Power, water & telephone services
Sand and
gravel
Grouted zone
16 -
10
16 ft 15
99
the construction sequence that it will be performed, the grouts
to be used, the above ground site conditions, and the available
injection equipment. The most commonly used methods for plac-
ing grout to assure complete coverage under a variety of ground
conditions is discussed in Volume 1 of this report.
5.15 Application
The application of chemical grouts is a very specialized
process which requires strict quality control and constant moni-
toring. The materials must be accurately measured and pumping
pressures must be accurately controlled. Records should be kept
of the elevations grouted, type of grouts, amounts injected, and
the pressures (Ref. 95). Besides checking the pressure on the
grout lines the ground surface and existing structures in the
vicinity of the grouting should be watched for surface heave.
Some grouting companies use electronic monitoring equipment
which will sound an alarm as soon as there is an elevation
change of a specified magnitude (Ref. 124).
100
After a chemical grout application has been completed it
would be helpful to determine the permeability of the treated
ground, whether there is proper distribution of the grout in
the soil, how complete the gelification is, and what materials,
if any, are moving from the grouted area into the untreated
soil and the groundwater.
101
So far no tests seem to have been developed to provide
information on the completeness of the solidifying reaction or
what materials were migrating from the treated area. If these
two things could be determined the safeness of chemical grouting
could be established and its use become more widespread.
102
5.21 Grouting, During Excavation
103
I I
71 -45
Rule of thumb
130 -40
4^
120 E
no Sound -35
*
stratified rock 1>
U 100 -30 <J
10 <o
90 «4-
80 -25 =3
</> tf»
104
Series Grouting. This is similar to stage grouting with
shallow holes drilled and grouted first, except that all sets of
holes are drilled and grouted at each stage. Holes are not
washed out but deeper staged holes are drilled through the
grouted zone. This results in more drilling than other methods
but assures that each successive zone is grouted tight before
advancing to the next zone depth.
bottom of the grout hole through a grout pipe filling the grout
hole. All zones are exposed to the grout under pressure at the
same time. A return line empties unused grout into a holding
tank.
Sand, clay, fly ash and even sawdust have been used as fil-
lers in cement grout mixes to extend the cement. Cement-sand
mixes are used for filling large voids but are not recommended
for grouting in rock with small cracks. Cement-clay grouts us-
ing local native clays are likewise not recommended for filling
small cracks, as they often contain fine sands. Bentonite, while
more expensive, does not have this drawback. The larger the
voids to be filled the thicker the mix, requiring a higher cement
content, and possibly mixed with sand. Thinner seams require
much thinner neat cement mixes and sometimes require a chemical
grout not restricted by cement particle size. Chemical grouts
105
may also be required in situations where faster or more
controlled set time is needed than is possible with cement.
There are situations where cement grouts can be used but
groundwater flow conditions are such that the grout would flow
long distances before setting. Under such conditions a smaller
quantity of more expensive, but fast setting grouts can prove
more economical. Occasionally it may be desirable to use both,
a chemical grout with fast set time to seal off flow and a
cement grout to fill the bulk of the voids.
As a general rule, to prevent bleeding of cement grout from
a seam, the lowest possible water-cement ratio of grout that
will flow, either neat or with a filler, should be used. Neat
cement-grout mixes vary from about five gallons (19 liters) per
sack of cement to twenty or thirty gallons (76 or 114 liters)
per sack. For pumping cement grouts with sand fillers, cement-
sand ratios vary from 1:0.5 to 1:2 by weight depending on the
void to be filled and the type of equipment used. Cement-clay-
water ratios may vary from 1:2:3 to 1:3:6 by weight. Additives
which may be used with cement clays include set time accelerators
or retarders. The most commonly used accelerator is calcium
chloride. If grout must travel a long distance calcium ligno-
sulfonate can be used as a set retarder, but in grouting most
tunnels it is more usual to need to accelerate set time.
Among the chemical grouts that have been used in rock tun-
nels are silicate grouts (waterglass) ,
polyester resins, and
AM-9. The earliest chemical grouts used in tunnels were sodium
silicate solutions. When used with proper reagents such as sod-
ium bicarbonate or sodium chloride these solutions set up as a
gel. Varying the type and quantity of reagent controls the grout
set time. Silicate grouts are among the safest chemical grouts
whether considering handling by the workmen or possible ground-
water contamination. They were the only chemical grouts
permitted in Japan at one time and served very well in driving
the Seikan Tunnel (Ref. 74). This 32.3 mile (52 km) long,doubl e
track railroad tunnel beneath the Tsugaru Strait was one of the
most challenging tunnel projects in the world. The silicate
grout was particularly adaptable to the heavy salt water infil-
tration of this site.
106
While the major consideration in these experiments is strengthen-
ing the rock through consolidation, the techniques could be used
in tunnels in similar sedimentary rock for water control as well
as rock reinforcement.
107
CD M
C 0)
4-1
CO
4-1 0) ix a
•- b o o
u
TJ TJ
o 0) 11 01 T3
a. co 4J 4J - C CJ CJ 41
M C 4-t CO CJ 4-1
u c 01 41 • OJ CO 01 01 U
CL'H M B 9 «-< u 0)
r4 4-1
CO 4) *p 01 CO •H H l-l
r4
x: tj tj » 4» (J S -H o TJ
u u C C to t- 13
u H (0 CD o iHD > 01 CO CO
(d S CO to • c 60 C 4-< CO CO CO
CO C to - (0 (0
M M U Id i- 0) B M u tc M
c D . 41 CO 4-1 4-1 "O OJ OJ cy 01 •o
tx 4-1 TJ 4J CD c ^tt-HTJ 4J CJ CJ CJ C
CD CU CO CO 0) Xi O Ih OJ o CO CO CO CO
5 P- 3 0) S a, o > » » 3 9 m
01 o • u 0) o <-•
Q TJ U >» TJ 41 O QJ
> o u a
Uh jn l-i TJ T3 TJ TJ TJ
c a i-t c c C E e B
X a a c CO a o a CO CO CO CO CO
to o lt-4 c h oi B f
X 4-1 4J -1-t CO a u 3 4J CJ CJ 4-1
C 0) CD c a 3 -h u c B C B c
O X) OJ 0) TJ CO 4J CJ 41 01 01 CJ OJ 41
B CD B P u X F-. J= B S B B 8
01 Q 0) (0 o CD *H (0 4J 01 01 li V u
U 4J U CJ CO Ou < X o O o o U o CJ
•H • 4)
CO TJ 00 »H
ft. 01 Ue GO
u co Cu
O
O
-H
3 O
CO h cr *- o
41 4-1 4> 01 O iTl CO
t-i CO U CM U «-i 41
3 0) 3 -H u
CO 09 •H co a CO •H 4J CO
CD CD O CO CD CU • CO CO a
11 ax TJ 0. 4> D •D TJ
B a a CO
uo -H
oP
o l. 41 01 01 01 CO
04 o
m
**-• 4J o
O
ao U CJ 4J
U
s 5
a o
H M
c vt-t U
U
41
U
t-< ^
4>
CJ
H O
CTl u
V
h
CJ
01
u
01
CJ
CO
o
o
o O
CO
CO
s
En a
O CO •H •
> u
•H
CJ CI 4J
4> CO
<
O
E
3
X
CO
r-
O
tj 4-1
a h
oi a.
•o
<
CO
TJ
0}
TJ
a, o a a
O
CJ
CO t->
H
Pn
l-l M H
o CD
t— CO
CO
a.
>»
4-1
w •r4
B
0)
>
41
a
>,
o
o C —i
CO
oi
DO
41
a.
>s ij U
P-, en to 4-t en -H X> -H CO 4-1 01 o>
co > &bO CO (0 CD o CO
c
01
E
41
C
c 4-t a. a. Jci
H
a a. - o 3 4-1 C o E • • l-l
CO
HCD CD u H O O
o
CO
H
CO CO u 00 60
CD o Q
01
co •H b£
U <H
u
CO
B 4i m
0)
CO
-H
B
(0
H
E
w
C
a a 1- r-l U a
3 •H I : •H
H c
41
B
o> as
•H
x
0) O
•
CD
H
l-i
O
u"i
u a
to
Cj
co
»
a • O Ox
CJ CN CO
a.
H 4JU
X
oi *
JO
0-. >.
X)
Eh a O. (0 1-4 q t- CN •O OJ J3 u u B CJ r-i
& TJ TJ
4-1
a « O X W >i-H o
D 3
•H -
to
B o
O 3 4-1
a.
o o
3
£
>^
O X u
01
u
1-
a
4-1
O
0)
01
E <
M
|
r-l o 3 U3
a
OJ
r>
4)
O u
O
Cu
C
>•,
to
-
a;
o
4- •• X
CO
3
cr
01
o
H
(0
oi
*s •-
U-l
£ - CO
•
l*H
H
Dm
a
rl
Cv
Ph" • • X U •• U (U ll-H O - 01
a
1- CO ••
a
r4 Cl
a.- oi OJ • o. a cu o r- > CL > oj v o> CO CO
C5 6 X 04 B X 1-t 4J g B r-i B X co X S X
3 'H CO s 1 3 "H O to OJ CO 3 CO 3 -H co 3 -rl CO CO
H Of
01
CJ
o
-J
CO
Eh to •H
<
•
.C CN O
*
Q 01 U
w
cj
C/3
CN
H X
O
CN
*-<.
CO 1
—
J 1
CO •
» O
CH z 1
O 01
0)
»H
TJ
0)
4J
t-i
0)
4* •H
CO
• CM
x.
CM
"
CO M p CJ
HC a CO
•H
O TI'J
CJ
ro
•ij CN
1
4-1
C/3
0>
l-l M D : u< 1
a
o 01
a.
cn
*-» tj
C
w
CM
C
CN
~- r
w an o>
c
CJ
CN
•^.
rH
r-l
4>
01
CJ >l 1 W -r< ipi a 1 *J
CU ^ < 03
|
J co 00 V43 m -» m CN 00 U-l
w Oil
4J
CO
qI
r*.
o>
vO
C*
NO
ON
sO
o
r-l
vO
O
^
SO
a>
"*
JD
O
en
CT*
" O
w
tO
X
D CO
L.
c
to
u CD
H
>s
CJ CO
4-1 cu
Eh 01 • 4-1 CQ r^
OJ
c o U-4
4-1
CO
C
U
r-i
CO
C
u.
CJ -
CO ro M
c
HU 0)
J Cl
V4
2 a a O C
W •H a.
o U
4) 41
J- •H - CM
o •D
E E
CO M
00 rl
4-t
Cl
3 CTi
J 9
UJ
M
u
0) CO
3
a at
4->
CO
C
tO
4J
4J
3
O
CJ
•h
C
4J
a
-H
-H
r-i
CO co
u
a.
u
c rH
4J *r4
U r-i
CO G
co g
O
CO j*
U
u
PL, U-4 x _* U-l 4-) •r4 (/J 3 k< U 1- CO u u CJ 4) >-
s |>4
01 u5
M
O
CO
O ^4-t
s « CO 1- o
1 4J
CO -
U C
C
CO •
3
co 3
< o
g
CD
a.
M
4)
C
3 4J
C
U
CO
» CO
-H
C
CU
O
M
CQ
«H
C
iJ
O
C
-rf
Q
o
4J
B
<
3
u o
TJ
CD
c
•H
Q
O
*J
C
•p4
r- -H
5S
01
CO U-4 41 4-t
a
o w-
3
o
O
tj
B U U
4-1 1-
3 4-t
4-1
41
as
(J
-H
l-l 0)
B
co
u
>*
-H
01
B
co
u-i O -0
o ^ ro
o u
OJ
i
CC
-^
" B
•HCO
41
Cl
O
CO
CO
t4 TJ
Ll_J
o H
X)
—
i-
t-.
CO
a «
'H
.-
i-
tO
«4-i
rH
c* n-t CJ ^o
CJ
o
r-l
u
u
r-l
H O
r4 U E
4J B
rl
CO 4J
r% CO
CO CO 01
6 01 01 to J= -H CO CO u co iJ ccj o to ui CD 41 O -H CU
D X
4)
CO Qq!U H Q O C03U1 O u to ? CO X U pa u
4J 4-1
35 (J 4>
u 3 01 4) C a
c •r-l 01 C 4-1
41 O CO c 3 4-1
0) B CO u
H01 c U H 4)
_tf CX (X 3 CU CD
CO *-* o c CJ H J= 3
w
^tf
_J Of <— n] w ki E u 00 XJ
C (1 'H 4-1 01 3 V 3 CJ 4-1 4>
u.
ID
« Ji U CO
H'"3 TJ •*
CO M
-
CO 00
id
CO
CO
3 co u 3
O
CO r~ &> CO 01 CO ft. I
o u c c c c c e ^ O j C i-o o 3 4-1O X rH OJ 4* -*
X)
>-
D-
CO to co
u
o
o o
co en
t-<
3
ta
4)
U 00 U
4i
C O
co
1- ^
-H
oi
a.
C
a: < u CO
CJ
E
CO
TJ
co
as -I
CO
£
o
0)u
n Orl Q
41 r4
Q
r4
CO
U
B B a. a. o — Uh < Uh •D £ < gj c. ch CO b CO U cw 3 XI
rtf
Eh
0)
c
c
BOO
tee
<4-<
B B
O
xi
r-4
QJ
00
'
-H
r-4 CO
*H
r-i
C u
0) O IB
CJ
h a ^
•
01 -H OJ
B
QJ
H r-i
QJ
a
u-
01
O
01
B.
"J
r-i
x: r*
U rl •<
4J
CO rH
CO (0
o o
(0 C CO tO ^ O j: a o CO Q. u o- co
3X3
CO (0 CO 01 4) 4) 01
3 CO to fSfS^ < O J U O fc. J 3 3 U 33 J U < 3 O 3 O
i nft
It would be naive to believe that the grout disperses itself
evenly through the gravel to form a water-resistant, uniform,
concrete lining around the tunnel. Grout follows the path of
least resistance and will disperse through any voids around the
tunnel rather than force its way through the small interstices
of the gravel. These paths may include the space between the
lining and the shield tail unless a grout dam or seal is pro-
vided. The dispersal through the gravel is further discouraged
by the presence of fines from the soil mixed with the gravel by
settlement or by forceful shooting of the gravel into the void.
The method of gravel placing does not promote uniform distribu-
tion, but leaves pockets of gravel with voids or settled soil
between. This nonuniform distribution has been observed outside
tunnels originally backpacked in this manner and later uncovered
by subsequent construction in the area (Ref. 128).
109
form doors and vibrators. The most difficult area is the arch
where air can become trapped above the concrete between ribs or
segment flanges. These voids must later be filled with a sand-
cement grout. Occassionally a small percentage of bentonite is
added to the grout. Eliminating these voids by filling them with
grout is a definite aid to promoting watertightness in the lining
by plugging off potential water courses.
110
In extremely bad ground where continuous lagging is required
it is important to place grout pipes through the lagging to in-
sure grouting any voids between lagging and rock as well as bet-
ween concrete and lagging. Drilling through the concrete (and
lagging if required) can be used as an alternate to setting grout
pipes prior to concrete placing. The location of potential
problem areas should be carefully recorded to aid in locating
drill holes later through the lining. As in the case of soft
ground tunnels it is important to fill all voids with grout to
eliminate possible water courses behind the lining.
Such walls have been built in short sections for some rapid
transit sections in Washington and Atlanta to support existing
111
i
Add Add
2Z wt. to wt. to
and
be and and
wt.
cement cement parts cement.
water. water water and
to to
mineral
to
by CO by
approved). CO by
water.
of
water.
of
2 possible:
sand
contain
of
sand
proportion
Engineer.
M sand proportion
Engineer.
4M
w and and
.
and
sand,
and
proportion
Engineer.
Bentonite CO
»
Bentonite
Pozzolan
Bentonite
wt. wt be to wt.
water water
of of
c not
DC to
cement cement, cement cement,
of by B cement cement,
by
sand
by sand
by cement
and water ash) by CO Mix
above
of of
0) and 2X and 22 by •o 2Z
A sand
Mix
Either
2Z
Mix B
CO
Either
22
cement,
(fly
X of
CO •
in
of: of: of:
part
filler
(proportions
of:
Portland Portland
Bentonite
of:
Portland Portland
determined
•
o of:
Portland Portland
determined
with
3C 41
Cement Cement, Cement Cement, when Cement,
U U cement. cement
Bentonite Bentonite
determined
E U
Either Either Either
1 filler Either
water.
Either Either
water.
contain
cement.
41
a u
41
Either
water.
contain
Water,
sand
1. 2. 1. 2. 1. min. And 2. 1. 2. of 1. 2. 41 'H 1. 2. of be of
be CJ 13
•iH •H
to CO
01 a a CO
u 4J CO
3 o o CO 4J >H U >H
tn en O co O co u o CO
(0 • H 41 s-> B a ss 6 a >, E a.
01 c B CO T-> J3 XI XI CO
h a CO a. o 4J O <-> o 4J O 0,
ft, JC X •C3 3 in •U 3 u-1 tj 3 m
u u O x
Of Of XI 41 XI o
ex en *w u E U C ti 4J B en
CO c V oi u U CO U M CO y> O M 03
H
u cm M-i of ai jr 01 01 JS 41 41 01 X
W
a o o o u M 01 *J M 01 u •H 4J IM 41 O
o S
3
a B
—
CO •H
•O -H
E
Of
•H E
TJ *H Of a
CO u
oi
rt
TJ -H
E
41
H a, <u
o
u
a
X
CO O
<
B
00
fl O
1-
CO
U
00
E O U-l
u
>H
<w
00
CO E O
IM
Xi
H z z X o w- e < W B CN *CJ a
<
CJ
M •
- -^
4J
0)
CO
01
h
01
01
IM
01
41
a
fin
aflj
u a X > E E o
H >> a.
H H>»
41
co
o. H
>, a.
>*
oj
O.
CJ *J
H>
•
>>!-!
co Of
•H
00
• H
00
o
en
CJ Q
U B
H m u
0)
E U
E
u
B
00 o
w a
B
O
4J O
v-
4J
to
CD
u O
to
H
4-i
«H
a
r*
6
CO
O.
CO
CO
CD
- •H
00
E
41
x:
T3
41>
T3
41
X.
41
3
O
IM
U
-H
CO
<D •H
CO
O « ^ o a Of CJ CO u u > O U ^ CO
GO H£ O O 1*
a. as a.
4-1 a. >,S i*. i>> h a. fl CO
B x 5 X S u-i jj K U XI XI a a XI •H O
m w
0) 0) 01 -H CJ 41 H-H •o u • a a n
— u o a "u a C MIS
-3
E <-< ti CO T3 •o TJ
a Cl U O. Q. CJ X: CO i- B 01 41 CO Of ts CO
3 W 3 co u a. •H CO 3 0) > o a «j
M 3 a o a •—So
.H o < c/> X fl
CJ 01 u h IM
a a X •
rH Ed
••
a-H
CQ
O
r->
x
..
a*H
CO
o •
•
CO
co
"Chi
a B
14
Of
* CO
oo
CL
a.
CO
a,
CO a. at
a
CO
••
a uo
Cm U
E 4J B — o B X 3 B X CO
O 3
r-l
41 -H
Cm
3 V
x
'
4-'
o)
oj
M
a p,
3 W -H O
O 33 o <
CO
<
CO
PK
§•3
X <
CO 3 -H o
CM X m
CD
ki IM o Mu
O
01 0) CJ
Eh u u a
u
• CO
U
*
O •l-t
>H
•H
MM Of j:
o
r*
CO 3
r-<
CO 3
II
< 0)
M-l
o
MM
O CO
Of
4J CO
w CO
•H JJ
T3
QJ
a
•H H TJU
CO £
N 00 00
Q a
S CO Hc B Jl!
(J UfO
. CJ\ CO in Cm
f
co
CJ!
O u CJ CO r-
co 3
O
1
CM 41 O
•o
41 Of CM
a^
41 O
IM
01
O at
a
•H
BM
CO
u
4J
CO
u
CJ
•H
a
m
• u
• cs
1
»0\h
O.^
a< 4-
O CN
i-c
I
U
cj
Of
u
of
CO
•O -H
cm
r-
CM J- 1
O •
01
E
H
B E CO <
CO : < u 00
O O CM •H CM ^ • •ri J; CM r-i • E
o U ~^ ii
a an ~» 41 J3
OH X TJ U ~~ 41 J5 X U
w 03 ca
1
i-i
: -h co
CN PU <
i-
I
-- CO
U
CO CO
<J
fl
w <
CO
a
^i
co
rM
I
41
4J CO
CJ H
CO -
a
SS
vl en CN en 00 M3
so IS MS lO
ID ul
C^ d ON a-
Eh
to cjn
r-t ,-1 r-f H
E
W CO C9
J Ho
u
c
O HOU E
h
QJ
01
M
01
4J E
1-
41
4J E
4J
•
,-1
H
|M
01
D-. U U a C U MM
>H
ME
-iM CO CO >-
a 3
S at
.-
4J
ca
<u
4J
JJ
CO 00
3
J3
Of
*z JS
u
oi
u
Of o
<
00
M
c a
CO
c s
rM CO U
B E
co
4J
u
3
O
B
CO
iJ
3
O
-
4J
h
01 CO
E
ca
<u
3 3 "
CO 01
CO
M-l O MM O CM •H CO •H CO X M •H CO MM VI
u Ot O 0) u O CO
O iw O *J <e o O MM
ot as
CO a o -Hco a o co 3 a o co 4J » CO
g 4J Mh« 4J MM a O
hue M u
-rf 41
hup -n B CO -H
B
o Q. O a o M
u u h
fl B MM
O MUM 41 41
o C
O *J o w
uB u a
01 IM
0)
Q 3 a s
co
U Of
Eh'"O -rt
X
41-H
U M-l
o 3
O TJ X
4) O *H
h MM Im MM 3
CO
-H 4J 4J -H XI 1- IM <H CO O >p4
C/3
• 01
t-< CO
• CD
M CO Of CO t-> 01 B H -i CO 41
X'H «
CO rM CM
41
CO -M
CO
3 • 9 fi -H CO Xi -H CO 41 4f
•
3 CO 3 h a o H O CJ X CO H O O a as cj
N N
35 S5 ,2 a
3 3 4J • 0) 3 a,
B O B
CM 01 z 41 Z 6
3 a.
E u Of co CO
I
CO
x: *j E U M •H
CJ H *H
B
CJ CJ 3 01 CO B E r-
CO
-.
0) H '? J CO
•- U
o -•
U
o
41
B 41
fM CO
-^
CO
4J
eg
4J
M
O 4J
0)
O a u • *+- 41 IM B f ^m tO 'H U-l o cs
0* l-l
3 Of M «H 3 u
1 ft. •H
E 0.
a
M
B o
3 <
ZtH 0)
0)
-H
CO
B
E
9 h
-H
H
ca
H Q
CO
K
CJ
O
ccj
Ot
O M
«-•
CO
TJ
41 3
B
<
- >.S5
CO
u E
CO
P co CO Of cj H 41 CJ CO M CO • « n o r- 3 O CO
3
0t
C *-
OJ 3 E O
3 N * CO
*J
Of
X3
4J Of
-o
41 -
U
u
4)
?
3
< ft< at *
41
E <
O-CJ
E •" - O -H W 00^ E • B CO CO -C 41 CO CO .H • 01 CD E a -
3 X 3 B u 3 CO E T) Of B Ca 01 >< OS - O-Ob u 3 CO
—4) CO
>
CO to
<
IM
3 O .- Z '- H -H -rf
H
CD t-i
—
-H
a
1- HH E
fl
-
•H
U
O.
OO
-H
E
M
3 B
H -H
J
01
00
CO
B
M
rN
r-*
--
CJ
00
EBB
OOl-
41
H M
(J
fi
CO
C
IM
If
00
fl
IM
-H
o Q ^ E CO M E 01 -H B 00 CO 3 •H -H B CO 41 O B O
« :,c<
CO CO
eQ 01 ^
CO
v- ^ CO
CO
14 O B B w 01 CS < U. £ < a a o
u eou
rM IM <J MM
01 «H -H Dm
u N B O O -H E 4J B B xi
B
c
x:
U CH -rl J*
O E
*J
»< C 6 E H B h co
-a
S O co O -m cs 3 O OO OO-- CO —
o o B O
Eh H
3
CM
eo 0)
O O
co 3
m o <
01 U
3
CO O O
co en cj
CO
H
O o
>• J
O O O
CO (j. J eSSx
1
U
to
01
fl
[K J <OJU co co
112
C P^
•H . .O
C0 4-1
4-1 C -O
C 01 0)
B C
U TJ O V **
4J
V C U B
U 00 O H c u
«0 u*h D (0 CO 0) u a> 09
2
u 5 TJ O '-< to B oi
u
at
c
CO CO
w CO) 0) C 01
u «H M
1
tj
C
to > • tj U
to *J
t-i
0)
<o
j:
10
S 00
tVi
0) 4)
H
OJ g
c
M
.«
-DO
*-»
JD
0)
4J
CD
4J
Im
C
OJ
U
a
4J il
u I- *D fd
c u
to
4-1
g
W *J >« » « S > 0) (0 01 C 3 s s
C C 4-" -Q O a oi u. a •U CO ^
01 0) 0) O 4J -o u o o CO J2 T3 *o TJ
Q BE
U V N
0)
t) C
C
CO
en
4J
C B
to
-- > *u
c -o
c
CO
C
to
c
CO IT)
c u u o
X
x U O 01
TJ TJ
X
*->
*H
C
O
'H
J-J C J= O-
DOW
C c
"O
C
to
co
*H
01
C TJ
C
TJ
c
TJ
c CN
•• C C -H u U CO 4J to *a
U
CO
a
CO
M-i Q Q U C O * to *-* a - c Uh 4J U • CO CO *
41 O O U *H O- C c 6 C o to 41 oj OJ -o C CJ c C <J
£ O *J O CJ 0) 41 4) oj at
U
ft* pk 0)
J
m
X
-H
00 BuC
cy -o 01
B
0)
u u
J=
4J CD B r- B S t-
-i
U f
>
CN
a
3
-H
CM X
c
UJ
o «
at
O Z to O
to -i-t
T3
eo
a UHNv
•H . . -*fl OJ
CJ TJ
«H 01
CJ
4)
CJ TJ
-H
4J »rt
u CD O P f«
O *M TJ o a. Mh (0
4->
01 to
•H o o at >> c
o
S
|h
3 CO o u J3
O
• H * CO
C to
TJ
*->
3
o
CO
a T3 •o X
. CO «H
3 TJ
4-1
3 ft
BO
a
CO
oj m
O 0)
h
0) JD
C
o
CO
0)
4J
0)
4J
« O
S w
O-
a)
o>
4J
X3
C O
u
CO MH
O
O ft.
*-)
01 0) J3 IW
u
Of
U
0) CO >H
M tj
oj
t-i
at
CO
jc
O D-
4J 09 CO
o M to CO 01
HU
(-<
*J
C
0)
C ••-4 •H o a to •H C O 41 ft. OJ
u
o TJ 4J
O «H
TJ -H
00
OJ 4-i OO
U O CO
x
CO CO c o CO CO to
<
ao
p r- a
co to
<
C O
w B
l-i
p
ft. CO O
m
CL
3 < W 6 X < r- to
o P-
H
En
<
O
u
0)
0)
at
a.
H c
00
>>
H
m
OJ
M
0)
0)
r4
0)
0>
Pn a
c to 0)
c c c
H a
1
UJ AS
C •
c
O cj 0)
X
a u
0) *J
CO
H
CO
'H
Q
(0
bo
c
00
c
w
00
c
W fcl
c
at P-,
•H 33
to 01
-
h
OS •H
(U
[d
>^
rO
-X r*»
Oh s to U CN to X Xi -O £i
CO a
JS CO
a. » oi
00
O MX a a)
TJ TJ TJ
TJ l-i
D O 0) to
Mh o a. 41 0) OJ
a
0)
o x o O O 3
CD H X < CM D O o
Mh
X CO
-
IH
U
a. ft.
M
ft. CO
Pu
O w o •• u Q. a. ft.
H a.
eo
X
-
a.
0)
>
f-
•
o.
B X
k.
at o
CD
a. 0)
x B x
to to CO
Eh
<
GO CO
X
3 CO
> ££5 tfl
X
3 -I*
X < < <
D fti fc
O at
a.
CD
V
4)
o
^
•H
fto
4J CO
CO
CM CM 41 ^v p
En 0)
w j: u 41 O
O CO
u
a
en
^ 1
4-»
CO
^f
<
01 1
N JH £-J
-^ *-> ca •
u 3 MH IM CJ U iTl
Eh
1
in
03 O .* O CM CO CO
O
| CN
0) •-* •
o HCO O f-> s-*
CM o
a *D /^ (S CN 0Q
O ft.
(O
UO H
< P
CO a T>
4J
CO
•
^
<
1
a
CO 1
CN
to 3 <
CJ « Z
O CM r-i
O 0) xU 3C
CN
•x 0) X U
•r-l
Q • X
H
X
ft
0)
ft. H C
«h tyj
a
a. ;
TJ
»- co 1
0)
*->
N ^< X
1
< X p CN CO < f* co
w ft.
r- CX
CM 00 M? U"l
0)1 iA •4 tn
O <>o
CT»
sO
a»
sD
(^
u-»
ON
iTl
CT>
iA
CJN
^
D Ol "* *^ 1—1
Eh ,c
>-i
u
CO jj CO 1- TJ
W 0)
4-1 C ^
• H
c
U
•H
o * r-
tO
• H
C
Vi
w
U
•H
to
OJ
J
4)
4J
to
<0
M
O
>.
ft.
3 OJ
to
a. o -a oo a o i- c 3 r-t a.
c c •rt - U-l •M O o ?
PL, 4J *H to "H O *J -H ft CJ «J*» r«
C *-> CJ
O r-l •si M
3 • iH
U i-* h •H CO
CO
4-1 O q -h to to o. C "H « o o HU ft. * M O
• H U) a w u t-< CO 3 V CJ
X w
CJ f OJ >*
u X 4J
M o *
c
*
0)
CD 3
CO o mh
O «H
CO
O
-
3 O -H
a)
O
CO
4J C c c 3 OJ
§ 'H UQ U <
tJ
<0 uQ
C
u
C
•H O
X Q
3 ai SB
o 1- c
U U M
*J c
0) >»
c
0) **-i
U
o *o a* > v O to
O r-t tO B aj e a. to M O
82
U r-«
§
U >,o o
O M CO
M
-H
r-l
CO
M
o
r'
-H
BJ
0)
>
to
Ji
TJ
|H t^
U "H O *J r-t o -«-t o •- 1
B C r4 4) 4J
jz -^ (Q 4J f0 •H M-l O to u to 0) o 0) o o ••-»
(-< Q u
to
103(0 CJ o u CO p CO X cj Q 3 CO CJ
u • *J H
£ u to o OJ
C CM
p 0) r-l
OJ
41
•!-» C
CD
*J
o to c o 3 W r-4 CO
h OJ c u H * 41 ai
td
EU H 3 ft. (0 C -H
C w
c H m
J=
Mr3
« 3 C
M M c
O 0) 3 a> 3 U 4J 6-1
2 at
ft.
O CD > • O CO 4J c
CJ B O -h U * 0) CO CJ c
tO JJ OS O to to 4-> 3
H ^ <0
o>
C C
ad
co
oi
C -H
a QW C S
X
r-
CO
X Xu
3
4) U
H B rS
at u
01
C
0) CJ
3 CO p C M < C - « p t-> J3 to < 0) u c •<
TJ
CO)* 3 U CO o «> u CO « to O ft* CO M « 3 CO
3 0) (0 H -H 3 X rC « as p CO >> O P
Jfi M CO h CO M 03 1 oo to 3 CO CJ
(D O 0) -H 41 «. jn o oj
B
-h *-*
u
3 CO
X Q « O h
to
j^
•H
.— o 6 c -a o 3 orf
oj at
H CO
I-
O
TJ .C
r-t
-H
<
<U
00
C
Q5 -5 u
o
j*:
OCT?
u
(0
(0 (U
M
ad
^ w u
to
<
**->
M
o
OJ
10
3 X>
M
O MH
O
TJ
r-t
*-»
-r4
TJ
<0
|-|
p
0) f M M
to to
-H JJ to a)
c c *j 0) 4> O 41 4) 4) J3 r-t
1 ° « >
O W •H CL U D. >— O M -< r-l r-l
c
x O.
a«
41 r-<
O o ft. o o. to CO <0 CO tO 3 O 41 4) 0) 0)
3 ft O O tfl
p p u 3 X P 3 Q Q
H U U« _) 53 o 33 rJ CJ <; 33 CO CJ SB
113
structures. Station and line section portions of the Red Line
Extention in Boston, presently under construction, include dia-
phragm walls. Acting as a semi-rigid ground support with appro-
priate bracing, this type of wall prevents outward movement of
the soil beneath the existing structure. Movement can occur
when a flexible support wall is used without underpinning the
structure. While this use serves its purpose, if the remaining
ground support walls permit drainage into the excavation these
short sections of solid wall cannot be effective in aiding to
control groundwater. In New York, a rapid transit line section
was constructed using continuous diaphragm walls as temporary
ground support and as an alternate to underpinning. The excava-
tion invert was in rock, but as the walls were not sealed to the
rock, they were ineffective in keeping water out of the excava-
tion. In San Francisco several stations were constructed with
deep cast-in-place diaphragm walls on all sides. They were
designed to serve all four basic functions listed above. They
proved competent for these purposes and were cost effective com-
pared to other construction methods (Ref. 129).
114
concreting to facilitate later installation of the bracing
system.
115
A. BUTT JOINT
.O
\ '
o -* :
d .
' -^-o O < •
o;
o /.,
Lo '
^ •'
o' '• A l4
f^^K^F^ «>. < a * o '•
*• V '« ' '-4 • ' . o '. "* ;£*
- <>* •.
^ * • > •
a
:<?.*.. :.<*•
F. WATERSTOP JOINT
'<. .
"?
CONCRETING OF CONCRETING OF
PRIMARY PANEL SECONDARY PANEL
Figure 31 - CAST-IN-PLACE SLURRY WALLS - TYPICAL JOINT DETAILS
116
digging bucket is used and the sides of the soldier beams serve
as guides. Tremie concrete is placed in the excavated slot. An
alternate method is sometimes used where every other pile is
placed in drilled holes and a double length slot is excavated.
The center pile is placed in the slot and tremie concrete is
used to fill the double slot using two tremie pipes. Care must
be exercised to raise the levels of concrete simultanelously to
avoid dislocating the center pile.
117
of the grout which is at least equal in strength to the surround-
ing soil, assures elimination of voids and filling of all irreg-
ularities in the trench, thus minimizing potential settlement in
the adjacent soil. The predominant use of this system to date
has been in relatively shallow to medium depth excavations uti-
lizing tieback bracing. The wall system appears to be readily
adaptable to the use of wales and struts which may be required
for deep cuts.
This type of diaphragm wall has not been used yet in the
United States There was a precast wall designed as an alternate
ground support for a recent cut-and-cover sewer project in
Baltimore, but the contractor elected to use a cast-in-place
wall. An extensive study of the design and potential use of pre-
cast panel diaphragm walls for transportation tunnels in the
United States was competed by Martin, et al in 1977 for the De-
partment of Transportation (Ref. 86, 87).
The grout slurry used for setting the precast panels in the
slot serves more than one purpose. Besides acting as a filler
in the sides of the slot, the slurry is impervious and, leaving
a wider gap on the outside face, provides a thicker water seal
than the thin coating on the cast-in-place wall. In addition,
if a deep slot is required for water cutoff, it is not necessary
to extend the precast panels to the bottom of the slot. The pan-
els are set sufficiently below the invert to meet structural
requirements with the less expensive hardened grout slurry below
to support the panels and fulfill the impervious cutoff require-
ments.
118
rock. If all these are present, groundwater will not be able to
reach the structure inside the walls. The practical problem
involved is the difficulty of being certain that these condi-
tions have been met. There is no problem checking for leakage
in the walls above the invert during excavation and correcting
defects by replacing concrete, or grouting through the walls.
If there is leakage in the wall below the invert, or the wall
bottom is not effectively sealed, it may not be detected unless
the quantity of flow is high.
For a diaphragm wall that is deep, but does not extend into
an impervious layer, or if there is leakage below the invert, the
walls will still aid in reducing groundwater flow to some extent.
A deep diaphragm lengthens the path of groundwater flow and sub-
sequently increases the impedence to flow. Although water will
continue to flow down under the wall and up to the invert, the
quantity of flow will be greatly reduced. Volume 1 of this re-
port, described how this factor aids in controlling groundwater
during construction and greatly reduces the need for pumping
water from the excavation. Eventually, after the structure is
built, water pressure under the structure and that outside the
walls will reach a state of equilibrium. If there is any leakage
into the structure during its lifetime however, the potential
maximum flow will be considerably less than it would be without
the diaphragm walls.
119
this situation the tunnel was used to raise and then maintain
water elevation at a fixed level, but the same principles could
be used to lower the water table. The system consists of a tun-
nel through rock with a series of holes drilled radially upward
from the tunnel to the rock-soil surface. Water level is main-
tained in a shaft used as a surge chamber. With the use of a
supply system this can be used to add or remove water as
required.
120
6.00 SUNKEN TUBE TUNNELS
6.10 INTRODUCTION
There are three basic methods that have been used for con-
structing underwater tunnels. In the past the most common
method has been the shield driven tunnel, usually used with
121
compressed air as described in Section 4.16 of Volume 1. Many
tunnels in this country and abroad have been constructed this
way. Another method is to place fill half way across the body
of water (river), dig a trench and construct half the tunnel by
cut-and-cover methods. The fill is removed, and the operations
repeated for the other half. This method has not been widely
used, but was employed on the first subaqueous vehicular tunnel
in the United States. This was built in Chicago, in 1866
(Ref. 88). One obvious drawback to this type of tunnel is the
adverse effect on shipping with more than half the river blocked
for the entire construction period.
122
YEAf- NAME FORM LOCATION !UBf CROSS-SECTION No Of LANES TYPL
LENGTH
A xl
1914 HARLEM RIVER NEW YORK. USA
TRACKS
CALIFORNIA.
POSEY ROAD 742 m
1928
U SA (8)
MICHIGAN. U.S.A./
1930 DETROIT- WINDSOR ROAD 670 m
ONTARIO. CANADA
ROTTERDAM.
1941 MAAS ROAD 587 in 2x2
NETHERLANDS
2x1
1942 STATE STREET RAILWAY ILLINOIS. US A 61 Hi
TRACKS
Wp^ *^P^
BRITISH COLUMBIA
IS 1959 DEAS ISLAND ROAD
CANADA
629 m OLJOD 2x2
I CALIFORNIA.
I 7 '
1962 WEBSTER STREET ROAD 732 m
USA
NOTES:
1. Date given is the date of completion.
2. 'Denotes part of an underground railway system.
3. Form of tunnel is denoted as follows:
S -Steel shell Figure 32 - SUNKEN TUBE TRANSPORTATION
R - Reinforced concrete box
P - Wholly or partly prestressed concrete box TUNNELS (1910-1975)
(From Culverwell, Ref. 37)
123
—
No YEAR NAME FORM LOCATION TUBE CROSS-SEC-'CN Ho Of LANES TYPE
LENGTH
CHESAPEAKE BAY
(a) 1750 m.
1963 la) THIMBLE SHOAL TUNNEL RCAD VIRGINIA USA.
(b) 1661 m
lb) BALTIMORE CHANNEL TUNNEL
ROTTERDAM.
452 m
QQ 2x3
2x1
25 1968 ROTTERDAM METRO RAJLWAY
* NETHERLANDS
1040m
CD TRACKS
AMSTERDAM.
26 1969 IJ RIVER ROAD 790 n 2x2
NETHERLANDS k 1 T oocr?/
BARENDRECHT.
28 1969 HEINENOORD ROAD
NETHERLANDS
614 m
C-2LZ3 2x3
ARLBORG/JUTLAND.
29 1969 LIMFJORD ROAD
DENMARK
5IO m
JCJ 2x3
OBQ
I
33 1973 EAST 63™ ST. TUNNEL RAILWAY NEW YORK. USA 2 x 229m CD 4 X I
* on TRACKS
-f
37 1975 |
ELBE ROAD HAMBURG. GERMANY IOS7m
aaoc 3x2
125
s
CD
S3
H
W
DQ
J
W
S3
S3
D
Eh
W
CQ
D
Eh
N S3
W
«
S3~
D oo
CO H
<j>
H /—
Ww c
f*J
> •H
HW^
« Eh -P
H
S CO H
W P-,
JJ
PS w •
<s CO
tn S3
D •
W Eh W
ffi
Eh H <Jh
ffi
Ph Eh
O >,
O CO
S3 Eh <D
O fJ
MQ in
Eh w 2
os
woo
CO Eh ^-^
oo
CD
u-
3
bO
•H
Pn
126
.
the trench and a sand foundation was jetted into this space.
Figure 34 shows the cross section of the Maas Tunnel. Figure
35 illustrates the method of sand jetting the foundation for a
rectangular box section.
This set the pattern for future development of this type
of sunken tube tunnel. Various improvements on the construction
techniques used will be discussed in the next subsection. The
largest individual units used to date of this type were those
of the Scheldt Tunnel in Antwerp, Belgium, which contained two
three-lane highway compartments and one two-track railroad com-
partment. Completed in 1969, the units were 27 feet (8 m) high,
157 feet (48 m) wide, 377 feet (115 m), long and weighed 55,000
tons each (Ref. 22). The longest individual tube sections used
were the straight portions of the Hemspoor Railway Tunnel in
Amsterdam, 879 feet (268 m) long for each of four units. The
rectangular section 70 x 29 feet (21 x 9 m) contains three sin-
gle track compartments.
6.31 General
127
24 -8m-
Bicycles
(f?
Pedestrians
1 H 6-Om *i
<m -6-Om-
/ )
many r
Air
I
1
Ducts
I
r
Air
I
Ducts
i
Trench
Sand layer foundation
k Trench
128
E
CO
o J
n <
4-> <
4—
r- 2
Eh
J
H
D
m
o
H
Eh
O
Oh
O
Eh
W
S
P
W
Eh
Eh^
O oo
oo
Cm"
Cm •
O 4h
(D
O
M *
Eh O
O >,
W rt
CO S
CO
CO O
O
CJ
CO
0)
bO
•H
Cm
129
was begun and developed in the United States; the rectangular
reinforced concrete method was first used in Netherland and is
now used by most countries outside the United States Actually
both methods use reinforced concrete as the major structural
component of the completed tunnel, and occasionally a precast
concrete box section will utilize a steel covering to act as
both outside form surface and waterproofing membrane. The major
difference between the two is in the fabrication sequence. The
steel shell is constructed with sufficient strength to withstand
launching and towing with a nominal amount of concrete in the
invert to act as ballast. Additional concrete is added with the
unit tied up to a dock, and the concreting is completed after
the unit has been sunk in place. With a precast unit all struc-
tural concrete is placed while the unit is in a dry dock. Pon-
toons are then used to help float the unit to the tunnel site.
130
Tremle concrete
Cap concrete
Ballast tremle
concrete
Carriageway -
Air duct
\ Hood S trough
plates
•U-plates
Steel shell
131
steel shell stiffeners, as shown in Figure 37. Protection
ofthis steel is not critical as corrosion after the outer
concrete is in place will not affect the integrity of the
structure or the main shell.
132
NYCTA EAST 6 3 STREET TUBE UNDER
EAST RIVER, NEW YORK CITY
' : PROJECT
BALLAST
133
nent seal which can be welded steel plates or a rubber Omega
profile (to be discussed in next section). If a gasket is not
used, divers place steel U-plate forms as shown in Figure 37
and tremie concrete is placed to encase the steel joint.
Gravel and/or selected fill is placed around and above the
unit, and the bulkhead of the new unit and adjoining bulk- head
of the previously laid unit are removed. The tunnel is now
ready to receive the next unit. If there is a possibility of
scouring action above the tunnel a rock blanket or layer of
rip-rap may be placed over the filled trench.
134
.
tasc kji. cue £>i_cci siieii units cnis win ue in cue oraer or sev
eral hundred tons depending on the size of the unit, the water
flow, and the water density. The sinking sequence is illustrat-
ed in Figure 39.
135
T3
QJ
-a
w
"0
cd
^>
u Eh
CO
IS
4J O
CQ
iH
o T3
n CD
<
•u
C
4J
CO
CO
O^g D
u rH
iH
I T3
a
aj
CO
-o <
Eh
O
[T^^^Se
1
cu
CD (-(
CO
cu 4J
o •H
u c 1=1
< ^> •H
c*
Ln
X)
cu
O '—»
U-t
CO
cu
o O
Usee rH S •
W 4n
CO
4-1
D CD
•H cy £*;
C w
^ 00 ^
H
CD H
r^-
s a)
u3 H 5
^ k
»o s cu
H >
S 6
H
PL, U
>H
EH ^
P-.
en
00
CD
bO
•H
136
On the other hand, the amount of concrete used in a sunken
tube is usually based on buoyancy considerations rather than
strength, so the strength of the steel shell is not necessarily
an important factor. In long tunnels the space above and/or
below the roadway compartment is used for ventilation. For
relatively short tunnels, with all traffic in one direction, a
piston effect is created by moving traffic eliminating the need
for forced ventilation and separate vent compartments, although
blowers may be required for slow or stopped traffic. In these
situations not only is the additional space wasted and costly,
but added concrete is needed to overcome the buoyancy of the
extra unused space. In addition, with or without ventilation
compartments, the circular shape is higher than an equivalent
rectangular section with ventilation compartments on the side.
Since the depth to the top of the tunnel is determined by
shipping lane requirements this could result in added dredging
and backfill.
137
An even more striking example of combining the two methods
are the similar Ohgishima (Keihin Canal) Tunnel under Kawasaki
Port (1974) and the nearby Tokyo Port Tunnel (1976) (Ref. 115).
Each are rectangular shaped multi-lane vehiclar tunnels of rein-
forced concrete with an outer steel lining, giving a similar
outward appearance. The units for the four-lane Ohgishima
tunnel, constructed for Nippon Kokan Company (Japan s largest
steel manufacturer) were fabricated by the steel shell method
with a 1/2 inch (13 mm) thick steel lining. After launching
the reinforced concrete lining was cast inside at a fitting
pier. The six-lane Tokyo Port Tunnel units were constructed as
reinforced concrete units with a thin steel membrane on the
outside. All nine units were built together in a large casting
yard, 2130 x 415 feet (650 x 126 m) formed by closing off the
,
6.41 General
138
dense and impermeable concrete and good construction joints
under such conditions makes the resulting concrete lining of
questionable aid in helping the steel shell to keep the tunnel
watertight. For most shell type tunnels corrosion of this steel
membrane is prevented by the surrounding tremie concrete
ballast. In the case of the Bay Area Rapid Transit Tunnel a
cathodic protection system was provided for the shell as there
was no outside ballast concrete. It was felt that this was
sufficient to provide against underwater corrosion.
The most common method for sealing the joints between the
units is for divers to place a U-plate cofferdam spanning the
joint as shown in Figure 37. Tremie concrete is placed between
the cofferdam and steel shell completely encasing the joint.
The space between bulkheads is then dewatered and steel plates
are welded across the joint gap to make the shell/membrane con-
tinuous and concrete is placed to make the lining continuous.
Two recent steel shell tunels, the BART Tunnel and the second
Mobile Tunnel used rubber gaskets for primary seals.
139
gresses upward in the wall. The temperatures are carefully
monitored and the flow can be altered, stopped and started to
match individual pour requirements. The steel cooling tubes
remain in the concrete to act as permanent shrinkage steel. See
Janssen, Ref. 73, for a more complete discussion of these
methods. Additional measures that are used include selecting
cement with a low heat of hydration and using timber facing on
forms instead of steel because of its insulating properties.
The joints between the sunken tube units are usually sea-
led with gaskets as shown in Detail D of Figure 40. The ini-
tial or primary gasket, known as the Gina profile, is made of
hard rubber with a relatively soft triangular tip. It is mount-
ed continuously around the circumference of the front end of a
tube unit being sunk. When in place it bears against a corre-
sponding continuous steel plate on the rear end of the prece-
ding unit set. When water is removed from between the bulk-
heads the water pressure acting on the rear end of the new tube
forces it forward compressing the seal. After removing water
from between bulkheads a secondary continuous rubber seal known
as an Omega profile is added as shown in Detail D of Figure 40.
This shape allows some flexibility in movement not possible
with the rigid shell type seals, permitting a degree of settle-
ment or ground movement.
140
Thiokol Airex
Polyu re thane
putty
Polyethylene
Steel angle
foam Detail B - EXPANSION JOINT WITH
A Glued butyl
strip RUBBER/METAL WATERSTOP
AND POLYURETHANE PUTTY
o
o
o
Rubber/metal
Airex strip waters top
141
Tempex Top of
Polystyrene bottom slab
QUl
Bar diam. 50
Sleeve diam
100/80- '
Foam rubber
Rubber -metal
waters top type W 90
142
7.00 CRITERIA FOR SELECTION OF GROUNDWATER CONTROL METHODS
7.10 INTRODUCTION
143
cover construction is competitive. Use of the newer slurry
shields or earth pressure balance shields help to offset the
higher tunneling costs in wet soil. Excess surface disruptions,
high utility density, and underpinning requirements could raise
the level where tunneling is competitive.
Once the basic tunneling method has been chosen the list of
appropriate permanent groundwater control methods is reduced to
a number of options compatible with that type of structure.
Each of the general control methods described in Sections 2
through 6 will be discussed in regard to use in one or more of
the four basic types of tunnels.
144
for steel shell sunken tube linings, the problems of placing in
a confined, possibly wet environment may invalidate the effec-
tiveness of such measures. These methods can be most effective
in cut-and-cover tunnels, precast reinforced concrete sunken
tubes, precast concrete segmented tunnel linings, and precast
concrete panel slurry walls. With proper care in applications
of these techniques it is possible to eliminate the need for
additional outer membrane waterproofing. This has been accom-
plished in some cut-and-cover tunnel structures in the United
States and in some sunken tube tunnels in the Netherlands.
Even in tunnels where other waterproofing measures are used,
good dense impervious concrete is an effective secondary ground-
water control measure as well as good practice for achieving
structural integrity.
145
first six types above have all been used at times for cut-and-
cover tunnels. Some materials such as brick in mastic and ben-
tonite clay sheets are more easily applied to vertical surfaces.
In general the bituminous materials are less expensive than
single-sheet man-made membranes, but depending on the number of
plies required, installation labor costs are higher. Item 7
above, cementitious coatings are not ordinarily used as a full
original membrane but rather for repair and maintenance. A thin
corrugated aluminum membrane (Item 8) was used for a tunnel in
Norway, but a more common use is of steel membranes on the out-
side of sunken tube tunnels. For precast concrete sunken tubes,
multi-ply membranes may be used in lieu of a steel membrane.
146
final caulking. These gaskets are usually of man-made mate-
rials and may be preformed of fairly firm material or a softer
material sprayed or troweled on the flange. Care must be
exercised to prevent contamination of these gaskets in the
tunnel environment. It is anticipated that current and future
research will continue to improve the manufacture and sealing
techniques of precast concrete segments.
The grouts that have been used for consolidating and seal-
ing soil can be grouped in the following categories:
1) Silicate-based grouts, 2) Plant product-based grouts,
3) Acrylamides, 4) Phenoplast resins, 5) Aminoplast resins, and
6) Petrochemical derivative grouts. The choice and use of these
grouts, either singly or in combinations is dependent on many
factors of soil, groundwater flow, location and working condi-
tions. Grouting is usually performed by a specialty contractor,
and workmen must be skilled in the use of grouts to insure they
perform effectively. During application constant monitoring of
grouting, and sampling of grouted soil, is necessary to insure
complete coverage and uniform dispersion of grout.
147
material filler. For special application for filling thin seams
or where a controlled set time is required one of the chemical
grouts mentioned above may be used in lieu of, or in conjunction
with, a cement grout. In most rock formations, water flow takes
place through joints, seams or cracks rather than through the
rock material. The grout prevents this by physically filling
joints and cracks in the rock around a tunnel.
Leakage through the wall above the invert can be found and
repaired during excavation. Finding possible leakage sources
through the wall below the invert or under the wall is extremely
148
difficult, and repairing such leaks, even worse. With a small
amount of leakage through the wall the volume of leakage pos-
sible in the structure is considerably less than it would be if
the wall were not present, but the same head of water would be
acting against the structure. A continuous reinforced concrete
wall or precast concrete panel wall will probably leak less
than a soldier pile and concrete wall provided special care is
taken with the joints. The soldier pile and concrete wall is
more susceptible to leakage at the many steel/concrete inter-
faces where continuous bonding is difficult when placing con-
crete under slurry. If the invert of the structure is in bed-
rock, all of the wall is exposed during excavation and any pos-
sible leakage can be repaired, but the problem of sealing the
wall to rock is expensive and difficult. If the rock is not
sound and water leakage can take place through the rock addi-
tional measures such as grouting, impervious concrete, or a
membrane covering will still be required.
7.38 Permanent Lowering of the Water Table
149
Precast concrete sunken tube units may have a thin steel
outer membrane, a multi-ply membrane, or a combination of the
two. Some recent units in the Netherlands, contructed of dense
impervious concrete were considered sufficiently waterproof that
the membrane could be eliminated. Double rubber seals are
usually used between precast units, the outer called a Gina type
seal and the inner an Omega type seal. These give this type of
tube a degree of flexibility.
150
) ^ - '
o
z
CD -J < co r- H CN
4J
O
z
111
01
C/3
4J
00 00 X Oh
c c OL
444 14-1 U - 0J
H
4J rH rH 3
o O rH rH O
4J o
On
OX O
01 03
4J »N
03
CJ
03
u
c rH rH CO :>>
D. C K 1- c I- C CO CO
g
01 o.
t-l 4-1
01
C MOB
rH co
r-
co
3 H M O t-H
p 4-1 01 01 CO
u
3
I— 4J
-rH 03 ft, 3
f-H
TH 3 "rH
rH 4J
a. oo
01 c
D. 00
03 C
w CO
01 CO
4J
CO X to CJ
CJ
CJ
03 4-1
OJ O C/3
4-1
CJ to CJ PS 'rH OS TH
H rH
f-H
3 3 B
01 01
0)
"I
<
rH
C
03
01
T-} 0) •*-)
01
rH
4-1
rH
O
14-1
rH CL
O CO
JX
O O • rH
O r^X
4JX <J
'r^
CO
TH
4J
o
4J
^
X
o
4J
:>n
X CO
rH
03
•H
CO
U
03
H CO
cu
01
q
01
r—
c
CO
a.
01
C O
cu a.
4J
co
Ou
01
t-
o
c o
cu a
c
0) o.
au
01 CO
CL.4J
01 CO
PL,
_3 r-l Pi pa w o< Pi 0. pa w CQ W Pi3 Pi 3
00
CO
Q 4-h •
O O
c
oo o
c cj u. r«H
Eh
W 01
•v
c a
X
•
in
o
C/3
o
01 CO
4J lu o o
to o o
r-iCNJ
u5 X) X3 XI C XI x> XJ
CO
01 01 0) 0) 01 01 01 -— ~— £
^
P4 J z c u c U
XCN X M
CO W 14-1 M-H H-i t-H tH 14-1 u-t
is
4J
PM--Z z:
4J
tlH •— X
W En 0,
X
CJ U u
•
t-n
03
4J CJ o CJ —
C
r-- ^ —^
C
1—1
CO r-l
~—
f^ <
01 OJ >H CO 03 01 03 CO rH
01
3 a a TO H CJ X CO nCJ X
P -S CO
3
ft.
C/3 1/3 C/3 to in to o -J -- CJ J in co
Eh Q o CN o in
01
,J 4J 4J 1- 03 4J 4_i 4J OJ Or-HE •
M o o •in • CNi
o o o FNOvO o CN O CM
< z z z rH rb z z z,
PP
P< O
Eh &
CO CD *
HI
00
4-1 ^ ?N
1-J 03 X
-o
a^
X 03 01 X
>1 01
00
01
>
c c S CO O
Q P-.
CO 01
> o o z
B *3
po o z
o
z
o a B
3O c CO r4 tb -3
4J Pi
01
£
P o
X
O hJ u £ r?
01
c •
m
P^ O o
01
c -
^3 C 4J
o H o
0)
«H
CO rS 3 -£ -o- 03
c ro
cu rH -J P -J rJ to
^ OkS o o- •
DERG ONTR CJ
03
4J
X)
10 CO O to >-) z pa m3 oa u <: ^ uo Uh ^j in
- 4J
n
00
•
4J
c
03
o
o C
3o XI •
P Ph
u
.
p< M -z
P^ o
4-H
o o p o -p
kH
^ S ^ O & o Z
W Ph Ph o
pi
o
o <
> 3 pa o i/j ta o CO "0 CO -9 CO <h9 tu ^3 Uh U0
o 03
6
(JO
CJ 0)
o o CJ o CJ CJ CJ M-l U O rH
UD c c c c c C C C
o O
0)
CH o
o
o O
o
Oo X Co
G.W CJ X CJ pi
Co Cc
Bo>
Eh 3 Box
X
P a
0i 4J
Ph Ph Oh
• pa
Oh
• CO
Oh
•
O
ix-Multi
Single
O >>
c-,
U-i
O 3
CJ Oh
l—l X rH X r-l X
l.P. 1. low
M<
• rH l.P. vel l.P. •Dbl
03 03
P
01 XI
C
01
• o • • o • XI X • 03
OP
• -a CJ UJ
H g
X)
th O
10
H to u pa o pa cj pa CJ P cj p oa (J 3 cj co -J CJ CNI
O
01
r-H 14-1 O
TO
-O
J rH
l*-l
03 r-l
X4J 3
CO
rH
0J
In
01
Ph « hSUJ
2 C >M-n
II
CO X
<
CO
O
•H
4J
r-i
O
O 3 3
a
CX-— X3 --
rH
m
01
t co 3 C 3
rH
i ion ion CH 3 MJ
3 ion 00-rH CO O tO
01 4J Transit
Transit
•rt B 0J rH 01
u >
Transit
4-1
.. LO CO I 03
01 CO
Sn
LO c
4J 4J
U CO
01
D. r-
01
a. £
CO CO
1-1
C
01 th 03 'H
4J
< in >H P JhCh>Ph en
CD c Hi— H in *
H CU O m H CN
Pi ^o IV 143
Atlant Atlant
Br- <£ r- 3 r- 1967- WMATA
1967-
rQ
c
3
«3 CO MARTA
1976
MARTA
1976
X> O X on 01 o WMATA
1975 1975
•< o> <£ C3>
trJ
O
01
>H W r-l 3 r~ l
Z r-H CO r-l CO r-l
Eh
151
Table 5SAMPLE CUT & COVER UNDERGROUND STRUCTURES
& METHODS SPECIFIED FOR CONTROL OF GROUNDWATER
(Continued)
WATERPROOFING
WATERPROOFING PROTECTION
G Concrete slab
H Concrete slab, both sides of membrane
I Hardboard
J Insulation board
K Cement powder
L Plywood at joint niche
JOINT TREATMENT
152
structure specification requires a stringent waterproofing
membrane of brick in asphaltic mastic and built-up asphalt ply
membrane. Although the concrete specifications are as exacting
as other agencies, the steel-concrete interfaces are difficult
to bond completely and may allow possible leakage. Thus it is
necessary to rely on more severe waterproofing measures, which,
though relatively expensive, have proved effective over many
years of use.
153
o> o z
00 z
c to c to
O
ooO
•H •H
O CJ
XI XJ a 4J
-^ 01 01 01
10 60 to 60 •rl OS o
01 to 0) 10 CM c 4-1
-> a J B •H M £60
3 o 4-1w Mc to o O to
S •H •*Q 0> C 1H
M C 01 o. M O U
Pn •r* , O w ^ 3.C 3.C CO •rt -H l-l
u X to o (0 U TO 4-1 0)
w to
a oa
x
c
to
<u
U
o
o.
u -u
01 to
U
01
4-1
CO
4J
O
au
01 O
u
CO
Eh 01
w MOW
oi
OS Oh OS o. z OS Oh 3
< OS
^
Q
U& S
D c
•H
CO O H 3 Cn M
X
In
4-1
H Ph tou
H 60S CO "»
o > rC-'
•
c l- CO
1
CO
(X CD to 6£ c--~ i-"
O O
3 m OX OJ <* CJ
£ O J* O O C o to o O O
H Ph 35 0«*CO
3 -<•
cm o tN CM
J-l
O o
.
oO OS v£>H CM ©1^ d -i
P
<X p
Eh o
CO Ph co arc?
Eh
p S <*0 u3 k3
w o O
n
sec X OS
Eh o —H '
Ph
Q CO oc
S P US OS
D w n3 *3 *«3
-H
O H O
P4 P-.
CD H
aepe.
O
Eh H
Ph PL,
o CO CO
60
>,*
>- XI
Cv, (i,
CO c to c
CO H fci
o o •D3
w p B 'H '.J
0)
O m3
J o _l Cu CO
Ph p 60 C
s Eh o
< W
co S 4-1 60
01 c
CU 4-1
O 60
D.u-1 O i-i 0) 0)
PQ iH 60
>, O 3 3 > t-J
01 CO Q O 60
H M O C 60 H«|J a h i-i co
U 1-1 C £> ~- o os < c
QW3 4-1
cm OQ to
• u
co t*,'-' -a
C J3 01
c .*
•1H X) C CJ
4J 01 3 CO
XI P 01 XI 10 Q-H 41 44
M 01
to
c c •rtC • C -1 4-1
01 C C •H C 0) 01
a c 60 O-
3 -h C CX to c 3 -H C co 01
U -rl 01 CO 3 COP 1H ih O, O 01
01
to
to
XH
3 tO
OS H -J CCHJ OS HJ CO ZH oSHJ to
01
3
CO
CO
UH
>
"i-l
XI CO
to XJ C
l-i 4-1 01 01
01 C X 4J
4J C 4J 01 -i-l X
to 4J a X W
CO
a-H •H "H ^ J
01 60
01 i-4
Q to H
O * co
01 s~*^~.
to -o
CO C
(1) P -O
Q O -H O >>
H Lv,
3 to
0< JX <^ H on Hm p g 4-1 CT* m
01 >-<
4-1 B CO lO 3 "i
P C
3
^3 to
01
CO
Un OOi
U 03
t-i r>»
OS
< f-
<£>
CT> 0>
SU
O
03
o>
r-4 Z
01 CT.
r-i
rd O >• r->
ca 1
Eh
154
Table 6 SAMPLE SOFT GROUND TUNNEL STRUCTURES & METHODS
SPECIFIED FOR CONTROL OF GROUNDWATER
(Continued)
TUNNEL LINING
Primary
A Steel ribs and lagging
B Steel liner plates
C Fabricated steel segmented lining
D Precast concrete segmented lining
Secondary
E Cast-in-place lining, structural
F Cast-in-place lining, finish only
G Cast-in-place invert and walkway only
WATERPROOFING
JOINT TREATMENT
M PVC waterstop
N Copper waterstop
Bentonite panels & triangular niche tube
P Joint sealant (to be approved)
Q Caulking (to be approved)
R Lead caulking
S Rubber or Neoprene waterstops
T Bolts with washers and plastic grommets
155
Cast-in-place linings require PVC or copper waterstop at
the joints although the contractor on the New York Subway pro-
ject received approval to omit the copper waterstop and provide
remedial grouting where required instead. Those projects call-
ing for steel segmented linings required protective coatings
inside and outside. Most segmented linings additionally
required plastic grommets for connecting bolts and caulking
between segments. On the Baltimore tunnel a joint sealant was
specified in lieu of caulking.
Where the allowable leakage permitted in the transit tunnels
was specified, it was comparable to those given for cut-and-
cover structures in Table 5. The allowable leakage given for
the San Francisco sewer tunnel was about eight times that
allowed for transit tunnels. Leakage treatment requirements
were also comparable to those for cut-and-cover tunnels,
consisting of pressure grouting, bentonite slurry, or epoxy
injection.
156
i 1
DUO 0) •
i— 1— ^
oz
01
Z
;
C/5
4-1 u 4J
X X J3
00
00 Ml
p •H •H
4J u 4J
co ao P p p
4-1 a -Hc 01 01
U
cu oi
p CO
01
CJ
01
-•
c 01 oO oo 60 CJ CJ
B
c c c CO
01
H 4J
OS 4-1
co •rH
CO
^3 CO
^3
CO CO
•H
P
^3 CO
4J 3 T3 o P 4J 4J a. a. o.
o o 3 3 3 4J 01 4J 3 cu p
p 10
01 P
o
01 ••
p O
P
O O
P
CU
OS o OS o
B
O
p
OS
E
w H
p cp
•H
01
6
01
o
P
CJ O p
c
P CJ P
H 0)
4-1
3
3 CJ
01
•H
H
CJ
CD
l-J 4-1 4J 4J
O co
B
O CO
B 4-1
O
E
CO
P4 u O P a a CJ CJ CJ P O P O CJ P O
H CD
^
p
o
•H c/j r-4 01 CO
u
CO CO •H >rt
4J
•H >H
4J
CO
u
•H 'H
U
O (0 1 a
CO
4J
01
01
OS
c
4-1
C
4J
C
CO
O.P
CO
ap B
O
CO
ap
o
W J
0) 41
OS
01
OS Z
4J
C/j
p
cj O
o
CJ
01
OS(n
01
as o< u
o>
oS a.
P-.
CO
T) "V TJ TJ •o •v TI -o v T3
CO 01 01 0) 0) 01 01 01 V 01 01
Q IP CN
•rH
cp cp lp cp cp tp IP
^
o P^ 01
CM 4-1
• r4
—B •H •H 'H H
U
•»H H
o
ffi W r-J
.O o£
CU o CJ CJ
01 p
CJ
01
CJ
01
CJ
01 0)
CJ
4) OI
CJ
01
a
H H CO co
01
a
01
Ch
W OS
a X a a a a a D.
to to
W < 3.*
O CO
CO to oS
r-J
to to
u
to C/J
p
to
p p
a s r- 01 4-1
o
4J m3
O
4J
o
i/) a 4J
o o
4-1
o o
4J
o o
Q < z ZE ZJ \r\ z z z z z z z
<jc5 S
D
CO o
w &> J
U.
-H J
<& en «J
X
D «
01
00
4-1
P
id -3 «3 •J}
O"
X X Xo n
OO CO
p >
01 x" to 01
B
01
B
o
41
B
O
D 41 C
o o
- P
O -J
-
J M
"
J z
o
z 04 Z 01
Pi J
> CJ CJ
B •
O 4J
HO u
c
01
01
P
01
cn pi; O) >
H 4J
c
'r-t
o
w o 01 CO
00
B
E
so
i-t
4-1 01 OS OS
o •o M p
2 p «3 •J}
-J -H -4 j -J -J J o CO
^
CO
Oi
D P^ C/J
J £ -J X ^
Eh O
f—l
143 «3 «3 W9 >o «« l/) «3 149
-O" XL
hh Xu
uS
x" x" X cj to X X X X X X X LD
TJ a.
*-0
Cm 3= o 01
p - p -
c
o < CJ o" cj CJ o" cj" CJ o" CJ 0-, CJ
p 3
01
o IU
a
Pi
n CO
p 41 C
w M-i * o
^
•lH O
j O 01
M P P In P P In P In Ln P p
01
o tn
01
O
CD
OJ4
X
4J
o to
<+-
•H 10
Ph V CO
u
3 CO O <D O
*8 -!
n) CO CO J= X. J=
CO
CJ
CO OS (0 X
CJ
01
'H
>
I^J
d)
Cl C
0i)
cj In
r-l
3 a CJ
u9 <->
3 3
«3 ^O I-1
3 In 3 In
CO
oi
•J} CO
41 U. 0) P Ut tn 01 a o
CD DC CO W CO CO 4J CO CO H
HEP3
^•r- CJ CJ CJ
1
u9 p -0 P «3 P "3 P p ^3 P -a u -3 P a.
CO •H P -H
Circ Circ
•H « o 0~3- p O ti
•H 4J
H CJ to u B, or
A, A, wo wx CO X 00 x-^ CO < 03 X o3 a 01
l-J </)
p oo
IP n>
c
m
C CD
01
u 4J C 4J 4-1 B P p O p
M 4-1 4-1
•H O •ih o ~o
3
l_i
r-4
fll P
1—1
01 P
1-4
01 T> CO T3 CO c CO V CO TH t; co •O CO -rt T3 CO XI CO P
O'M (J 01 c 01 c H C CO
B u
JX
3 O 3 Main Tunm
4-1
3
C 4J E
3
a. co
P Rapi Tran Line Rapi Tran Line Rapi Tran Stat Rapi Tran Line Rapi Tran Stat Rapi Trar Line Rapi Trar Line ao co
P Sewe:
CO co CO
4J
C/l
3H 3H OS H
CM
B t O CO
3
r~- CO •
P O oi B CO 01
p CO UH P c p p
(1) 01 3 H O 01 p u-l p
o o
H O cj
•ft
CO CJ
CO
01
c <
3
o < i < 1 < I >> >• p >4
157
: :
Primary
A Steel ribs
B Steel ribs and lagging (as req'd)
C Steel liner plates
D Shotcrete
E Rock bolt reinforcement
Secondary
F Cast-in-place lining, structural
WATERPROOFING
JOINT TREATMENT
L PVC waterstop
M Rubber waterstop
N Steel waterstop
Copper waterstop
P Bituminous filler
Q Paraplastic filler
R Sponge rubber and mastic filler
S Caulking (as approved)
T Bolts with washers and plastic grommets
158
8.00 MAINTENANCE REQUIREMENTS DURING THE LIFE OF A TUNNEL
159
particularly advisable if the structure will be at considerable
depth, in a highly pervious aquifer, or covered with surface
structures. One writer suggests that if the water table is
higher than the tunnel axis more protection than just good con-
crete is needed (Ref. 125).
160
Mixing and Transporting. For watertightness, the specifi-
cations should call for thorough mixing and chilling of ingre-
dients when needed. Transportation should be done in such a
way that the large aggregate is not segregated.
Placing.
- The specifications should be specific about place-
in ent oFThe concrete.
b. Placing requirements:
1. Consolidate around waterstops.
2. Prevent segregation of large aggregate.
3. Deposit as near to final position as possible.
4. Place in lifts the vibrators can reach through.
5. Vibrate for thorough consolidation.
6. Consolidate carefully along joints and around rein-
forcing steel and other embedded items.
7. Place the whole pour without interruption.
Continuous Placement. Tunnels, in which the permanent lin-
ing consists of continuously-poured concrete, will probably not
be completely watertight. Even with the use of expansive
cements the lengths of continuous pours are sufficiently long
that shrinkage cracks are probable. In addition, the placement
of concrete within a tunnel is always difficult, often result-
ing in concrete of inferior quality. The design should include
another means of restraining the groundwater if the advantages
of continuous lining outweigh its disadvantages. If no other
means of waterproofing is included in the design, remedial mea-
sures will have to be taken if the tunnel is to be dry.
161
a protective cover, if it will be subjected to backfill
abrasion and punching loads.
162
Fabricated Steel Segmented Linings. For tunnels using a
fabricated steel segmented lining special design consideration
should be given to the first four items above as needed for cast
iron segmented linings. In addition, a well-designed cathodic
protection system is required and suitable coatings for the
exterior and interior faces, to help prevent any attack on the
steel from ground chemistry and chemicals produced by the use
to which the tunnel is put if no secondary concrete lining is
used.
163
3. Material for joint filler should be selected for long
life in the local ground environment and for good
resiliency during its lifetime.
4. Design of mating edges of the segments should be able
to accommodate movements caused by differences of trans-
verse and longitudinal loading.
164
the grout which in turn may be the design criterion for adding
a chemical grout to a particulate grout. The design of the
minimum pressure to be used in grout placement should be based
on the pressure of the water to be displaced by the grout.
The maximum pressure should be determined based on the charac-
teristics and condition of the rock mass.
165
to excavation) it can be determined approximately how successful
the operation has been. If there is considerable discrepancy
between these volumes, settlement is likely to occur. A program
of monitoring surface elevations should also be specified.
Slurry Walls.
166
personnel experienced in slurry wall construction to
supervise placement.
167
the vertical steel is the principal reinforcement. The
design of the joint must be based on the loads to be
resisted at the joint and the watertightness required of
the joint. There are a number of joint designs to guide
the engineer including special provisions to transfer loads
from one panel to the next and to put a water sealing
section, such as a waterstop, across the joint. In all
cases, however, the slurry has wetted the concrete surface
and a coating may be left that allows water to leak
through. One advantage that mitigates this is that the
bentonite mud cake on the unexcavated face of the wall will
tend to fill and seal the leakage path if it is not too
wide.
168
that of a cut-and-cover or driven tunnel. The tunnel sections,
waterproofing, and bulkheads control the groundwater while the
sections are lowered into place, but sealing the sections to
one another must be done under water which poses entirely
different problems from those confronting the designer of a
cut-and-cover or driven tunnel. Many of the concerns of
designers of tunnels using different types of construction are
the same though their solutions may be different. The major
design concerns for watert ightness of sunken tube tunnels
include:
1. Impermeability of walls.
169
should be sealed as a backup measure, using polyurethane putty
or a multi-ply membrane, since the placement of concrete around
a waterstop is difficult, frequently producing gravel pockets.
The designer may choose to use a new method -- to inject an
epoxy sealant into the waterstop location through preset pipes
in order to fill the voids in the gravel and consolidate the
material. The volume treated becomes impervious and the
exterior sealant may be eliminated.
170
If monitoring is not done, a regular maintenance crew should
periodically patrol the tunnel correcting sealant deficiencies
as they are noticed.
171
2. Constant seepage from a narrow crack
3. Sheet flow from area less than 1 m2
5. Flow more than faucet leak but less than garden hose
flow
172
8.23 Repair Methods
Once it has been decided that the time has come to stem the
flow of water, the repair method chosen will depend on the
waterproofing method originally used, the type of failure of
that waterproofing, and the type of ground surounding the tunnel
at the location of the leak.
173
.
174
integrity of the waterproofing over an extensive area without a
collapse of the tunnel. The extent of the damage will determine
the necessary remedial work. Portions of the tunnel linings
that have been damaged must be replaced. If the integrity of
the waterproofing has been breached it would probably be
difficult or impractical to replace. Extensive grouting of the
soil outside may be necessary.
175
REFERENCES
176
13. Bieniawski, Z. T. Tunnelling in Rock 2nd Ed., South
, ,
177
26. Centre d'Etudes des Tunnels du M.A.T.E.L.T. Tunnel ,
52-54.
701-716.
39-40.
Mines, 1971.
27-33.
178
38. Culverwell, D. R. "Immersed Tube Tunnels", Tunnels &
,
28-30.
179
50. "Flexible Tunnel to Ride With Quakes," Engineering
News-Record Sept. 21, 1978, p. 64. (Daiba Railway
,
Tunnel)
Communications, 1976.
180
62. Halvorsen, G. T. et al. Concrete for Tunnel Liners:
, ,
384.
181
73. Janssen, W. "Efficient Waterproofing of Immersed
,
25-26.
287-313.
pp. 669-689.
182
85. Martin, D. , "Report from Atlanta," Tunnels &
Tunnelling , Vol. 11, No. 8, October 1979, pp. 41-42.
TTTT.
183
96. Ounanian, D. W. and C. E. Kesler, Design of Fiber
Reinforced Concrete for Pumping University of ,
51-63.
184
108. Research News, Tunnels and Tunnelling , Vol. 9, No. 1,
Jan. 1977, p. 43.
185
120. Streit, J., "Design, Construction and Maintenance of
Rail Tunnels in Czechoslovakia," Tunnels & Tunnelling ,
186
.
1978.
187
144. Wickham, G. E. and H. R. Tiedemann, Cut-and-Cover
Tunneling, Volume 2, Cost Analysis and Systems
Evaluation Jacobs Associates, Contract
,
188
ADDRESSES OF SUPPLIERS, COMPANIES, AND AGENCIES
189
ADDRESSES OF SUPPLIERS, COMPANIES, AND AGENCIES
responsible for a broad program of staff and contract impacts, and protection and enhancement of the
research and development and a Federal-aid environment.
program, conducted by or through the State highway
transportation agencies, that includes the Highway 4. Improved Materials Utilization and
Planning and Research (HP&R) program and the Durability
National Cooperative Highway Research Program Materials R&D is concerned with expanding the
(NCHRP) managed by the Transportation Research knowledge and technology of materials properties,
Board. The FCP is a carefully selected group of proj- using available natural materials, improving struc-
ects that uses research and development resources te
tural foundation materials, recycling highway
obtain timely solutions to urgent national highway materials, converting industrial wastes into useful
engineering problems.* highway products, developing extender or
The diagonal double stripe on the cover of this report substitute materials for those in short supply, and
represents a highway and is color-coded to identify developing more rapid and reliable testing
the FCP category that the report falls under. A red procedures. The goals are lower highway con-
stripe is used for category 1, dark blue for category 2,
struction costs and extended maintenance-free
light blue for category 3, brown for category 4, gray operation.
for category 5, green for categories 6 and 7, and an 5. Improved Design to Reduce Costs, Extend
orange stripe identifies category 0.
Life Expectancy, and Insure Structural
FCP Category Descriptions Safety
1. Improved Highway Design and Operation Structural R&D is concerned with furthering the
latest technological advances in structural and
for Safety
hydraulic designs, fabrication processes, and
Safety R&D addresses problems associated with
construction techniques to provide safe, efficient
the responsibilities of the FHWA under the
highways at reasonable costs.
Highway Safety Act and includes investigation of
appropriate design standards, roadside hardware, 6. Improved Technology for Highway
signing, and physical and scientific data for the Construction
formulation of improved safety regulations. This category is concerned with the research,
development, and implementation of highway
2. Reduction of Traffic Congestion, and
construction technology to increase productivity,
Improved Operational Efficiency
reduce energy consumption, conserve dwindling
Traffic R&D is concerned with increasing the
resources, and reduce costs while improving the
operational efficiency of existing highways by
quality and methods of construction.
advancing technology, by improving designs for
existing as well as new facilities, and by balancing 7. Improved Technology for Highway
the demand-capacity relationship through traffic Maintenance
management techniques such as bus and carpool This category addresses problems in preserving
preferential treatment, motorist information, and the Nation's highways and includes activities in
rerouting of traffic. physical maintenance, traffic services, manage-
3. Environmental Considerations in Highway ment, and equipment. The goal is to maximize
Design, Location, Construction, and Opera- operational efficiency and safety to the traveling
the National Technical Information Service, Springfield, Va. 22161. Single HP&R and NCHRP studies not specifically related
copies of the introductory volume are available without charge from Program
to FCP projects. These studies involve R&D
Analysis (HRD-3), Offices of Research and Development, Federal Highway
Administration, Washington, D.C. 20590. support of other FHWA program office research.
DDDS71EM