MAS Problem Variance
MAS Problem Variance
P&G uses a traditional standard costing system to control costs and has established the
following materials, labor and overhead standards to produce one box of Detergent-DX:
During August 2012, company produced and sold 3,000 boxes of Detergent-DX. 8,000
pounds of direct materials were purchased @ $11.50 per pound. Out of these 8,000
pounds, 6,000 pounds were used during August. There was no inventory at the beginning of
August. 1600 direct labor hours were recorded during the month at a cost of $40,000. The
variable manufacturing overhead costs during August totaled $7,200.
Required:
1. Compute materials price variance and materials quantity variance. (Assume that the
materials price variance is computed at the time of purchase.)
2. Compute direct labor rate variance and direct labor efficiency variance.
3. Compute variable overhead spending variance and variable overhead efficiency
variance.
Solution:
(1). Materials variances:
F = Favorable; U = Unfavorable
F = Favorable; U = Unfavorable
F = Favorable
During the month, the company purchased 21,120 kilograms of materials from its vendors.
There was no inventory of materials in stock at the start and at the end of month.
Required:
= $141,504 – $152,064
= $10,560 Favorable
= $152,064 – $138,240
= $13,824 Unfavorable
c. Journal entries:
(2) Variances and journal entry relating to direct labor:
(Actual hours worked × Actual rate) – (Actual hours worked × Standard rate)
= $65,184 – $60,480
= $4,704 Unfavorable
b. Labor efficiency variance:
(Actual hours worked × Standard rate) – (Standard hours allowed × Standard rate)
= $60,480 – $69,120
= $8,640 Favorable
*4,800 units × 1.6 hours per unit
c. Journal entry:
(Actual hours worked × Actual rate) – (Actual hours worked × Standard rate)
= $28,896 – $24,192
= $4,704 Unfavorable
(Actual hours worked × Standard rate) – (Standard hours allowed × Standard rate)
= $24,192 – $27,648
= $3,456 Favorable
The answer to requirement 4 is ‘no’. Although the total unfavorable cost variance of $576 is
only 0.25% of the total standard cost, it is made up of many individual variances and some
of them may be large enough to require immediate investigation. A summary of variances
computed in part 1, 2 and 3 is given below:
(5) Reasons of variances:
There are many causes of materials, labor and overhead variances. Some usual causes of
the variances computed in part 1, 2 and 3 of this problem are given below:
The direct materials to produce this product is available in liquid form. During May, 60,000
liters of direct materials were purchased and 38,000 liters were sent to production
department. The production for the month of May was 6,000 containers.
Required:
1. Compute actual direct labor hours worked during the month of May.
2. Compute variable manufacturing overhead spending variance.
3. Prepare journal entries to record materials and labor related activities during May.
Solution:
= $40,950 – $39,000
= $1,950 Unfavorable
= $114,000 – $120,000
= $6,000 Favorable
= $76,000 – $72,000
= $4,000 Unfavorable
= $55,900 – $58,500
= $2,600 Favorable
= $58,500 – $54,000
= $4,500 Unfavorable
During the month of August, the company produced 1,400 units of product X. A total of
6,000 pounds of direct materials was purchased at a total cost of $33,000. The total direct
labor cost for the month was $57,000. All materials purchased during the month was used
in production. There was no direct materials inventory on hand at the start and at the end of
August.
Someone from the company’s management has computed the following three variances:
Required:
Standard price per pound of materials = Actual quantity purchased at standard price/Actual
quantity purchased
$36,000/6,000 pounds
= $6 per pound
Standard quantity allowed for actual production = Standard quantity allowed at standard
price/Standard price per pound
= $33,600/$6*
= 5,600 pounds
Standard quantity allowed per unit = Standard quantity allowed for actual production/Actual
production
Actual direct labor hours worked = Actual direct labor hours worked at standard
rate/Standard rate per hour
= $54,000/$18
= 3,000 hours
(Actual hours worked × actual rate) – (Actual hours worked × standard rate)
= $57,000 – $54,000
= $3,000 Unfavorable
The following costs and variances information relates to the month of May:
During the month of May, 900 direct labor hours were actually worked and 500 units of
product K were manufactured. The actual cost per unit manufactured during May was $0.28
higher than the standard cost.
The following costs and variances information relates to the month of May:
1. Total standard cost of materials used for actual production during May.
2. Standard quantity of materials per unit of product K.
3. Materials price variance for May.
4. Standard direct labor rate per hour.
5. Direct labor rate and efficiency variance.
6. Variable overhead spending and efficiency variance.
Solution:
(1) Standard cost of materials used:
Standard quantity of materials per unit = Standard cost of materials per unit/Standard cost
of materials per pound
= $45.60/$12
Total materials variance is made up of materials price variance and materials quantity
variance. Total materials variance is $2,800 favorable and materials quantity variance is
$1,200 unfavorable. Therefore, the materials price variance must be $4,000 as computed
below:
(4) Standard direct labor rate per hour:
In order to compute the standard direct labor rate per hour we need to compute the
standard direct labor hours first. Since variable manufacturing overhead cost is based on
direct labor hours, we can compute standard direct labor hours as follows:
Standard direct labor rate per hour = Total standard direct labor for May/Total standard
direct labor hours for May
= $16,000/800 hours
(Actual hours worked × Actual direct labor rate) – (Actual hours worked × Standard direct
labor rate)
= $18,900 – $18,000
= $900 Unfavorable
= 42,140 – 23,240
= $18,900
**See requirement 4
(Actual hours worked × Standard direct labor rate) – (Standard hours allowed × Standard
direct labor rate)
= $18,000 – $16,000
= $2,000 Unfavorable
*See requirement 4
(Actual hours worked × Actual variable overhead rate) – (Actual hours worked × Standard
variable overhead rate)
=$3,240 – $3,600
= $360 Favorable
(Actual hours worked × Standard variable overhead rate) – (Standard hours allowed ×
Standard variable overhead rate)
= $3,600 – $3,200
= $400 Unfavorable