Estimates
Estimates
1.b Mobilization/Demobilization
Mobilization/Demobilization 1.00 lot 50,000.00 50,000.00
Direct Cost= 50,000.00
Contractor's Profit (10%)= 5,000.00
Contingencies (5%)= 2,500.00
Tax (12%)= 6,900.00
64,400.00
Unit Cost= 1.00 /lot ₱ 64,400.00
1.c TEMPORARY FACILITIES
Fence Enclosure
Qty= 1.00 lot
Labor:
Fence Enclosure 1.00 lot 30,000.00 30,000.00
Electricity/Water
Qty= 1.00 lot
Electricity/Water 1.00 lot 40,000.00 40,000.00
Direct Cost= 70,000.00
Contractor's Profit (10%)= 7,000.00
Contingencies (5%)= 3,500.00
Tax (12%)= 9,660.00
90,160.00
Unit Cost= 1.00 /lot ₱ 90,160.00
2.b Excavation
Qty= 101.613 cu.m
Labor:
Excavation 101.61 cu.m
Manpower No. of Persons No. of Days Wage/Days
Foreman 1 13.00 600.00 7,800.00
Unskilled 8 13.00 350.00 36,400.00
Labor Cost Php 44,200.00
Concreting
Manpower No. of Persons No. of Days Wage/Days
Foreman 1 7.00 600.00 4,200.00
Skilled 6 7.00 500.00 21,000.00
Unskilled 10 7.00 350.00 24,500.00
Labor Cost Php 49,700.00
3.b Column
Qty= 21.50 cu.m
Material:
Portland Cement 194.00 bag 250.00 48,500.00
Washed Sand 11.00 cu.m 900.00 9,900.00
Screened Gravel 22.00 cu.m 1,200.00 26,400.00
16mmØ x 6m RSB 1,960.29 kgs 45.00 88,213.05
12mmØ x 6m RSB 506.35 kgs 40.00 20,254.00
10mmØ x 6m RSB 1,737.12 kgs 40.00 69,484.80
#16 G.I Tie Wire 85.00 kgs 70.00 5,950.00
Material Cost Php 268,701.85
Concreting
Manpower No. of Persons No. of Days Wage/Days
Foreman 1 15.00 600.00 9,000.00
Skilled 7 15.00 500.00 52,500.00
Unskilled 10 15.00 350.00 52,500.00
Labor Cost Php 114,000.00
Rental of Equipments: # of Days Rent/Day
1 units 1 Bagger Mixer 7.00 450.00 3,150.00
1 units Cut Off wheel machine 7.00 450.00 3,150.00
1 units Concrete Vibrator 7.00 350.00 2,450.00
Cost of Rentals Php 8,750.00
Concreting
Manpower No. of Persons No. of Days Wage/Days
Foreman 1 8.00 600.00 4,800.00
Skilled 6 8.00 500.00 24,000.00
Unskilled 10 8.00 350.00 28,000.00
Labor Cost Php 56,800.00
Concreting
Manpower No. of Persons No. of Days Wage/Days
Foreman 1 8.00 600.00 4,800.00
Skilled 6 8.00 500.00 24,000.00
Unskilled 9 8.00 350.00 25,200.00
Labor Cost Php 54,000.00
Concreting
Manpower No. of Persons No. of Days Wage/Days
Foreman 1 11.00 600.00 6,600.00
Skilled 6 11.00 500.00 33,000.00
Unskilled 8 11.00 350.00 30,800.00
Labor Cost Php 70,400.00
Concreting
Manpower No. of Persons No. of Days Wage/Days
Foreman 1 25.00 600.00 15,000.00
Skilled 12 25.00 500.00 150,000.00
Unskilled 20 25.00 350.00 175,000.00
Labor Cost Php 340,000.00
3.h Stairs
Qty= 10.63 cu.m
Material:
Portland Cement 96.00 bag 260.00 24,960.00
Washed Sand 6.00 cu.m 900.00 5,400.00
Concreting
Manpower No. of Persons No. of Days Wage/Days
Foreman 1 6.00 600.00 3,600.00
Skilled 4 6.00 500.00 12,000.00
Unskilled 4 6.00 350.00 8,400.00
Labor Cost Php 24,000.00
Concreting
Manpower No. of Persons No. of Days Wage/Days
Foreman 1 3.00 600.00 1,800.00
Skilled 5 3.00 500.00 7,500.00
Unskilled 8 3.00 350.00 8,400.00
Labor Cost Php 17,700.00
Installation
Manpower No. of Persons No. of Days Wage/Days
Foreman 1 9.00 600.00 5,400.00
Skilled 10 9.00 500.00 45,000.00
Unskilled 12 9.00 350.00 37,800.00
Labor Cost Php 88,200.00
3.n Roofing
Qty= 229.10 li.m
Material:
0.6mm Pre-Painted G.I Long Span Roofing 229.10 li.m 750.00 171,825.00
Tekscrew 2,000.00 pcs 3.00 6,000.00
Touch up Paint 5.00 gal 750.00 3,750.00
0.6mmx2.4m thk. G.I Flushing 20.00 pcs 650.00 13,000.00
0.6mmx2.4m thk. False Gutter 30.00 pcs 650.00 19,500.00
Double Sided Insuation 5.00 roll 4,000.00 20,000.00
#16 G.I Tie Wire 10.00 kgs 70.00 700.00
Material Cost Php 234,775.00
Installation
Manpower No. of Persons No. of Days Wage/Days
Foreman 1 10.00 600.00 6,000.00
Skilled 8 10.00 500.00 40,000.00
Unskilled 15 10.00 350.00 52,500.00
Labor Cost Php 98,500.00
4.0 Architectural
4.a Masonry Works
Qty= 709.96 sq.m
Material:
CHB 4" 9,230.00 pcs 15.00 138,450.00
Portland Cement 412.00 bag 250.00 103,000.00
Washed Sand 35.00 cu.m 900.00 31,500.00
Screened Gravel 22.00 cu.m 1,200.00 26,400.00
10mmØx6m RSB 2,099.33 kg 40.00 83,973.12
#16 Tie Wire 42.00 kg 70.00 2,940.00
Labor
150.00 sq.m 709.96 106,493.55
5 Electrical Works
Qty= 1.00 lot
Wires and Conduits 1.00 lot 90,000.00 90,000.00
Switches and Outlets 1.00 lot 15,000.00 15,000.00
Juncton,Utility Boxes and uPvc lines 1.00 lot 25,000.00 25,000.00
Panel Boards 1.00 lot 75,000.00 75,000.00
Labor 1.00 lot 61,500.00 61,500.00
Direct Cost= 266,500.00
Contractor's Profit (10%)= 26,650.00
Contingencies (5%)= 13,325.00
Tax (12%)= 36,777.00
343,252.00
Unit Cost= 343,252.00 /lot ₱ 343,252.00
Labor
Construction of SV & CT 1.00 lot 38,000.00 38,000.00
Direct Cost= 133,000.00
Contractor's Profit (10%)= 13,300.00
Contingencies (5%)= 6,650.00
Tax (12%)= 18,354.00
171,304.00
Unit Cost= 171,304.00 /lot ₱ 171,304.00
8 Electronics Works
Qty= 1.00 lot
PABX, TELEPHONE, CCTV & SPEAKER SYSTEMS 1.00 lot 150,000.00 150,000.00
Labor
Installation 1.00 lot 60,000.00 60,000.00
Direct Cost= 210,000.00
Contractor's Profit (10%)= 21,000.00
Contingencies (5%)= 10,500.00
Tax (12%)= 28,980.00
270,480.00
Unit Cost= 270,480.00 /lot ₱ 270,480.00
SUMMARY:
General Requirements ₱ 193,200.00
Site Works ₱ 412,559.28
Structural Works ₱ 5,317,178.32
Architectural Works ₱ 2,526,568.00
Electrical Works ₱ 343,252.00
Plumbing Works ₱ 477,895.66
Electronics Works ₱ 270,480.00
₱ 9,541,133.26
37.97%
42.43%
16mmØ x 6m RSB 1,268.71 kgs 38.00 48,211.06
10mmØ x 6m RSB 894.43 kgs 35.00 31,305.12
#16 G.I Tie Wire 44.00 kgs 70.00 3,080.00
34.45%
41.37%
40.69%
10mmØ x 6m RSB 979.44 kgs 38.00 37,218.72
#16 G.I Tie Wire 20.00 kgs 70.00 1,400.00
38.54%
35.50%
16mmØ x 6m RSB 151.49 kgs 40.00 6,059.52
10mmØ x 6m RSB 170.02 kgs 38.00 6,460.61
#16 G.I Tie Wire 3.40 kgs 70.00 238.02
41.80%
44.16%
10mmØ x 6m RSB 170.88 kgs 35.00 5,980.80
12mmØ x 6m RSB 122.59 kgs 35.00 4,290.65
#16 G.I Tie Wire 2.45 kgs 70.00 171.63
40.22%
30.10%
41.96%
25.1111111
251.111111 120 30,133.33
28.5
85.5
170.88
122.59
Bill of Quantities
Unit of Total Amount
ITEM D E S C R I P T I O N QTY. Cost UNIT COST
Measure (PhP)
### #NAME? 1.00 Lot 98,532.00 98,532.00
### #NAME?
II.1 Site clearing grabbing & Layout 280.00 sq.m 24.61 6,891.21
II.2 Excavation 67.40 cu.m. 111.46 7,512.51
II.3 Backfilling 57.29 cu.m. 103.50 5,929.52
Gravel Bedding of Column Footing, Tie Beam, and
II.4 12.77 cu.m. 1,780.94
Slab on Fill 22,742.66
### #NAME?
III.1 #NAME? 15.36 cu.m. 8,310.89 127,655.23
III.2 #NAME? 909.12 kgs 82.55 75,044.27
### #NAME? 14.40 cu.m. 17,537.46 252,539.45
### Reinforcing Steel for Column 2111.70 kgs 82.33 173,865.71
### Tie Beam/ Wall Footing 9.47 cu.m. 10,347.19 97,987.94
### Reinforcing Steel for Tie/Wall Footing 337.15 kgs 90.04 30,356.89
### 2nd Floor Beam 11.90 cu.m. 12,769.13 151,952.59
### Reinforcing Steel for 2nd Floor Beam 2064.54 kgs. 89.33 184,415.72
### Roof Beam/Lintel Beam 11.92 cu.m. 14,873.10 177,287.32
### Reinforcing Steel for Roof Beam/Lintel Beam 1455.44 kgs. 96.07 139,825.95
### Stair Case 3.34 cu.m. 10,982.90 36,682.88
### Reinforcing Steel for Stair Case 526.64 kgs. 84.55 44,528.54
### Ground and 2nd Floor Sab 28.80 cu.m. 12,145.66 349,795.04
III.14 Rienforcing stee for ground and 2nd foor slab 3953.39 kgs. 67.82 268,127.43
### #NAME?
### #NAME? 650.00 sq.m. 802.15 521,400.31
### #NAME? 1.00 lot 890,307.93 890,307.93
### #NAME? 1,300.00 sq.m. 262.41 341,126.80
### #NAME? 1,740.00 sq.m. 266.34 463,431.13
### #NAME? 440.00 sq.m. 1,099.00 483,558.31
### #NAME? 60.00 li.m 1,006.79 60,407.20
### #NAME? 1.00 lot 256,233.94 256,233.94
### #NAME?
### #NAME? 212.48 sq.m. 1,273.87 270,672.85
### #NAME? 229.10 sq.m. 1,291.75 295,939.24
### #NAME?
### #NAME? 1.00 lot 350,017.51 350,017.51
### #NAME? 1.00 lot 27,161.34 27,161.34
### BILLBOARD 1.00 set 5,280.28 5,280.28
TOTAL 6,217,209.66
Prepared by: #NAME?
55,880.75
169,884.68
208,991.66
467,570.52
167,643.81
470,857.84
154,644.63
163,712.59
60,660.82
209,960.82
372,885.74
602,370.73
793,984.04
747,545.91
820,400.37
-
-
426,618.12
-
-
-
-
-
61,816.97
488,435.09
127,269.47
303,712.20
92,333.90
207,524.57
7,291,795.57
-
DETAILED UNIT PRICE ANALYSIS
PAY ITEMS : III.12 Reinforcing Steel for Stair Case Production Rate 48.180 kgs/hr.
COST SHEET ID : III.12
QUANTITY : 526.64 kgs. 419.00 408.78 Number of Hours 10.93
PAY ITEMS : III.14 Rienforcing stee for ground and 2nd foor slab Production Rate 48.180 kgs/hr.
COST SHEET ID : III.14
QUANTITY : 3,953.39 kgs. Number of Hours 82.05
-
SUB - TOTAL (C) -
D. TOTAL DIRECT COST (A+B+C) 375,433.47
23,147.10
A) MATERIALS : COST/UNIT Unit Quantity Unit Rate Total Cost
0.6mm Pre-Painted G.I Long Span Roofing li.m 176.40 750.00 132,300.00
Tekscrew pcs 1,500.00 3.00 4,500.00
Touch up Paint gal 5.00 750.00 3,750.00
0.6mmx2.4m thk. G.I Flushing pcs 20.00 650.00 13,000.00
0.6mmx2.4m thk. False Gutter pcs 30.00 650.00 19,500.00
Double Sided Insuation roll 5.00 4,000.00 20,000.00
#16 G.I Tie Wire kgs 10.00 70.00 700.00
SUB TOTAL (A) 193,750.00
B) LABOR COST Quantity
Hourly Rate Total Cost
No. Personnel Total Hours
Foreman 1 35.14 68.75 2,415.74
Carpenter 9 35.14 56.25 17,788.63
Laborer 12 35.14 37.50 15,812.12
SUB - TOTAL (B) 36,016.49
C. EQUIPMENT COST Quantity
Hourly Rate Total Cost
No. of Equipt. Total Hours
SUB - TOTAL (C) -
D. TOTAL DIRECT COST (A+B+C) 229,766.49
E. ADD INDIRECT COST
1. OCM 11,488.32
2. Contractor's Profit 22,976.65
3. VAT 31,707.78
SUB - TOTAL (E) 66,172.75
TOTAL COST (D+E) 295,939.24
UNIT COST 1,291.75
DETAILED UNIT PRICE ANALYSIS
VII. PLUMBLING WORKS
JOB : PROPOSED TWO-STOREY RESIDENTIAL
PAY ITEMS : VII.1 Laying of Cold Water Line Production Rate 0.017 lot/hr
COST SHEET ID : VII.1 Number of Hours 60.61
QUANTITY : 1.00 lot
A) MATERIALS : COST/UNIT Unit Quantity Unit Rate Total Cost
Fittings
Water Coset sets 3 9,000.00 27,000.00
Lavatory sets 3 8,000.00 24,000.00
Floor Drain pcs 3 250.00 750.00
Water Line
1" PPR Pipe 3.0m lght 24 1,500.00 36,000.00
3/4" PPR Pipe 3.0m lght 12 1,200.00 14,400.00
1/2" PPR Pipe 3.0m lght 10 950.00 9,500.00
1" PPR Elbow 90ᵒ pcs 9 160.00 1,440.00
3/4" PPR Elbow 90ᵒ pcs 9 140.00 1,260.00
1/2" PPR Elbow 90ᵒ pcs 11 120.00 1,320.00
PPR Tee 1" pcs 4 160.00 640.00
PPR Tee Reducer 1"x3/4" pcs 4 150.00 600.00
PPR Tee Reducer 3/4"x1/2" pcs 6 130.00 780.00
PPR Elbow Reducer 3/4"x1/2" pcs 7 130.00 910.00
Union Patente 1" pcs 4 250.00 1,000.00
Water Pump 2HP unit 1 20,000.00 20,000.00
Water Tank 5000 liters unit 1 50,000.00 50,000.00
Sanitary Line 0.00
6" PVC Pipe 3.0m lght 30.00 650.00 19,500.00
#NAME? #NAME?
BID= 6,217,209.66
AREA= 1127.9
PRICE/AREA= 5,512.20
LESS= 5,875,790.34
%LESS 48.588%
PROFIT/OCM= 7%
TAX= 7%
LABOR=
painting= 120/sq.m
masonry= 120/sq.m
plastering= 120/sq.m
steel works= 8/kg
concreting= 25%
plumbing= 20%
electrical= 20%
MATERIAL
RSB= 38/kg
ANGLE BAR= 28/kg
CEMENT= 230/bag
SAND= 600/cu.m
GRAVEL= 700/cu.m
CHB 4" 13/pcs
material labor equipment ocm profit tax
70,000.00
6,500.00
3,825.00
7,650.00
10,557.00
98,532.00
5,350.32
267.52
535.03
738.34
6,891.21
5,832.69
291.63
583.27
804.91
7,512.51
4,603.66
230.18
460.37
635.31
5,929.52
16,601.00
1,056.34
882.87
1,765.73
2,436.71
22,742.66
66,500.00
21,360.00
11,251.20
4,955.56
9,911.12
13,677.35
127,655.23
41,855.81
11,188.75
5,219.62
2,913.21
5,826.42
8,040.46
75,044.27
156,525.00
18,450.00
21,096.00
9,803.55
19,607.10
27,057.80
252,539.45
94,047.78
28,814.13
12,126.99
6,749.45
13,498.89
18,628.47
173,865.71
49,590.00
15,388.75
11,098.84
3,803.88
7,607.76
10,498.71
97,987.94
17,032.40
4,600.44
1,936.18
1,178.45
2,356.90
3,252.52
30,356.89
82,025.00
26,475.88
9,474.73
5,898.78
11,797.56
16,280.63
151,952.59
91,401.04
33,992.52
17,786.35
7,159.00
14,317.99
19,758.83
184,415.72
87,487.50
31,176.63
18,981.30
6,882.27
13,764.54
18,995.07
177,287.32
65,566.01
30,451.20
12,543.30
5,428.03
10,856.05
14,981.35
139,825.95
20,712.50
6,438.35
1,329.65
1,424.02
2,848.05
3,930.31
36,682.88
25,256.18
7,993.06
1,322.61
1,728.59
3,457.18
4,770.91
44,528.54
181,580.00
90,000.00
13,579.00
27,158.00
37,478.04
349,795.04
171,577.13
36,596.35
10,408.67
20,817.35
28,727.94
268,127.43
297,402.25
107,411.65
20,240.70
40,481.39
55,864.32
521,400.31
587,399.00
103,833.87
34,561.64
69,123.29
95,390.14
890,307.93
86,100.00
178,750.00
13,242.50
26,485.00
36,549.30
341,126.80
142,390.00
217,416.78
17,990.34
35,980.68
49,653.34
463,431.13
141,492.50
233,940.97
18,771.67
37,543.35
51,809.82
483,558.31
26,900.00
20,000.00
2,345.00
4,690.00
6,472.20
60,407.20
155,000.00
43,939.39
9,946.97
19,893.94
27,453.64
256,233.94
104,790.00
90,304.00
15,055.73
10,507.49
21,014.97
29,000.66
270,672.85
193,750.00
36,016.49
11,488.32
22,976.65
31,707.78
295,939.24
231,980.00
39,772.73
13,587.64
27,175.27
37,501.88
350,017.51
14,480.00
6,608.00
1,054.40
2,108.80
2,910.14
27,161.34
4,260.00
352.00
115.30
207.54
345.44
5,280.28
-
-
`
12,434,419.33 6,447,402.17 2,929,229.89 278,445.02 482,523.25
9,655,077.08 482,523.25
10,137,600.34
12,093,000
1,955,399.66 16.17%
846,510.00
2,801,909.66 6,217,209.66
11,246,490.00
1,209,300.00
10,883,700.00
1.a Excavation
Qty= 101.61 cu.m
Labor:
Excavation 101.61 cu.m 150.00 15,241.95
Direct Cost= 15,241.95
Contractor's Profit= 1,524.20
Contingencies= 762.10
Tax= 2,103.39
19,631.63
Unit Cost= 193.20 /cu.m ₱ 19,631.63
2.c Backfilling
Qty= 78.72 cu.m
Labor:
Backfilling 78.72 cu.m 150.00 11,808.36
Direct Cost= 11,808.36
Contractor's Profit= 1,180.84
Contingencies= 590.42
Tax= 1,629.55
15,209.17
Unit Cost= 193.20 /cu.m ₱ 15,209.17
2.d Embankment
Qty= #REF! cu.m
Material:
Embankment #REF! cu.m 150.00 #REF!
Gravel Bedding #REF! cu.m 1,200.00 #REF!
Labor
Manaul Spreading/Compacting 1.00 lot #REF! #REF!
Direct Cost= #REF!
Contractor's Profit= #REF!
Contingencies= #REF!
Tax= #REF!
#REF!
Unit Cost= #REF! /cu.m #REF!
3.b Column
Qty= 23.46 cu.m
Material:
Portland Cement 212.00 bag 260.00 55,120.00
Washed Sand 12.00 cu.m 700.00 8,400.00
Screened Gravel 24.00 cu.m 1,200.00 28,800.00
20mmØ x 6m RSB 4,411.70 kgs 45.00 198,526.68
10mmØ x 6m RSB 1,918.22 kgs 38.00 72,892.51
#16 G.I Tie Wire 126.60 kgs 70.00 8,861.90
Labor
concreting 1.00 lot 111,780.33 111,780.33
Direct Cost= 484,381.42
Contractor's Profit= 48,438.14
Contingencies= 24,219.07
Tax= 66,844.64
623,883.27
Unit Cost= 26,593.49 /cu.m ₱ 623,883.27
3.h Stairs
Qty= 18.53 cu.m
Material:
Portland Cement 167.00 bag 260.00 43,420.00
Washed Sand 10.00 cu.m 700.00 7,000.00
Screened Gravel 19.00 cu.m 1,200.00 22,800.00
16mmØ x 6m RSB 151.49 kgs 45.00 6,816.96
10mmØ x 6m RSB 170.02 kgs 38.00 6,460.61
#16 G.I Tie Wire 3.40 kgs 70.00 238.02
Steel Decking 7.06 l.m 750.00 5,295.00
Labor
concreting 1.00 lot 26,020.68 26,020.68
Direct Cost= 118,051.27
Contractor's Profit= 11,805.13
Contingencies= 5,902.56
Tax= 16,291.07
152,050.03
Unit Cost= 8,205.06 /cu.m ₱ 152,050.03
3.k Canopy
Qty= 1.00 lot
Canopy 1.00 lot 35,000.00 35,000.00
Direct Cost= 35,000.00
Contractor's Profit= 3,500.00
Contingencies= 1,750.00
Tax= 4,830.00
45,080.00
Unit Cost= 45,080.00 /cu.m ₱ 45,080.00
3.m Roofing
Qty= 212.48 sq.m
Roofing 212.48 sq.m 950.00 201,856.00
Labor
installation 1.00 lot 60,556.80 60,556.80
Direct Cost= 262,412.80
Contractor's Profit= 26,241.28
Contingencies= 13,120.64
Tax= 36,212.97
337,987.69
Unit Cost= 1,590.68 /cu.m ₱ 337,987.69
4.0 Architectural
4.a Masonry Works
Qty= 855.80 sq.m
Material:
CHB 4" 11,126.00 pcs 15.00 166,890.00
Portland Cement 497.00 bag 260.00 129,220.00
Washed Sand 42.00 cu.m 700.00 29,400.00
Screened Gravel 26.00 cu.m 1,200.00 31,200.00
10mmØx6m RSB 2,531.76 kg 38.00 96,206.88
#16 Tie Wire 51.00 kg 70.00 3,570.00
Labor
1.00 lot 136,946.06 136,946.06
Direct Cost= 593,432.94
Contractor's Profit= 59,343.29
Contingencies= 29,671.65
Tax= 81,893.75
764,341.63
Unit Cost= 893.13 /cu.m ₱ 764,341.63
4.h Cabinetry
Qty= 1.00 lot
Cabinetry 1.00 lot 50,000.00 50,000.00
Direct Cost= 50,000.00
Contractor's Profit= 5,000.00
Contingencies= 2,500.00
Tax= 6,900.00
64,400.00
Unit Cost= 64,400.00 /cu.m ₱ 64,400.00
5 Electrical Works
Qty= 1.00 lot
Electrical Works 1.00 lot 180,000.00 180,000.00
Direct Cost= 180,000.00
Contractor's Profit= 18,000.00
Contingencies= 9,000.00
Tax= 24,840.00
231,840.00
Unit Cost= 231,840.00 /cu.m ₱ 231,840.00
ABC #REF!
SQ.M 398.15
PRICE/SQ.M #REF!
243,583.39
₱ 17,361.28
6,000,000.00
180,000.00
PHYSICAL
Wt. % PREVIOUS AMOUNT
Item Description Amount
%
1 GENERAL REQUIREMENTS
### #NAME? #NAME? #NAME? 100.00% #NAME?
1.a Building Permits 38,640.00 #NAME? 100.00% 38,640.00
1.b Mobilization/Demobilization 64,400.00 #NAME? 90.00% 57,960.00
1.c TEMPORARY FACILITIES 90,160.00 #NAME? 90.00% 81,144.00
2 SITE WORKS
2.a Site clearing grabbing & Layout 60,278.40 #NAME? 100.00% 60,278.40
2.b Excavation 56,929.60 #NAME? 100.00% 56,929.60
2.c Backfilling 35,033.60 #NAME? 100.00% 35,033.60
2.d Embankment 232,496.88 #NAME? 80.00% 185,997.50
2.e Soil Poisoning 27,820.80 #NAME? 70.00% 19,474.56
3 Structural Works
3.a Foundation (Footing) 240,651.75 #NAME? 100.00% 240,651.75
3.b Column #NAME? #NAME? 85.00% #NAME?
3.c Tie Beam/ Wall Footing 293,598.72 #NAME? 100.00% 293,598.72
3.d 2nd Floor Beam 500,854.29 #NAME? 100.00% 500,854.29
3.e Roof Beam 246,911.02 #NAME? 85.00% 209,874.36
3.f Ground Floor Slab #NAME? #NAME? 0.00% #NAME?
3.g 2nd Floor Slab #NAME? #NAME? 100.00% #NAME?
3.h Stairs #NAME? #NAME? 90.00% #NAME?
3.j Concrete Base Tank #NAME? #NAME? 0.00% #NAME?
3.k Canopy (Pre Casted Trilles) #NAME? #NAME? 0.00% #NAME?
3.m Roof Framing #NAME? #NAME? 100.00% #NAME?
3.n Roofing #NAME? #NAME? 0.00% #NAME?
3.o Forms and Scaffoldings 354,554.20 #NAME? 90.00% 319,098.78
4 Architectural
4.a Masonry Works 634,670.59 #NAME? 85.00% 539,470.00
4.b Plastering Works 458,155.25 #NAME? 70.00% 320,708.68
4.c Paint Works 573,549.75 #NAME? 0.00% .00
4.d Ceiling Works 302,240.79 #NAME? 0.00% .00
4.f Steel Tubular 1"x1" Railings (Balcony & Viewing Deck) 63,112.00 #NAME? 0.00% .00
4.g Wall Panel 14,016.34 #NAME? 0.00% .00
5 Electrical Works 343,252.00 #NAME? 30.00% 102,975.60
6 Plumbing & Sanitary
6.A Laying of Cold Water Line 239,188.04 #NAME? 0.00% .00
6.B Laying of Sanitary Line 67,403.62 #NAME? 15.00% 10,110.54
0 Septic Vault & Cistern Tank 171,304.00 #NAME? 80.00% 137,043.20
Total #NAME? #NAME? #NAME? #NAME?
Prepared by:
#NAME?
#NAME? #NAME?
90
0.00%
0.00%
0.00%
0.00%
#NAME?
#NAME? 0.00%
0.00%
1% 0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
1.13% 0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
KRIS DB CONSTRUCTION & SUPPLY
Lot 6, Block 2, Phase 5, Bankers Village, Tabuc Suba, Jaro, Iloilo City
Tel . No. (033) 508-1236/09483664461
Email Add: [email protected]
Sir/Madam;
Greetings of Peace!
We would like to request for the 3rd progress billing of 80.36% Accomplishment of the project, "Proposed Two-
Storey Residential Building , located at Riverville, Yulo Drive, Arevalo, Iloilo City, which amounted to
Four Million Five Hundred Ninety Four Thousand Three Hundred Eighty Six Pesos and 68/100 (P4,594,386.68)
only computed as follows:
Thank you so much for your kind consideration and prompt action on this matter.
Material:
Portland Cement 26.00 bag 260.00 6,760.00
Washed Sand 2.00 cu.m 900.00 1,800.00
Screened Gravel 3.00 cu.m 1,200.00 3,600.00
Steel Decking 6.67 li.m 750.00 5,002.50
12mmØ x 6m RSB 106.60 kgs 38.00 4,050.80
16mmØ x 6m RSB 151.49 kgs 40.00 6,059.52
#16 G.I Tie Wire 6.00 kgs 70.00 420.00
labor
installation 1.00 lot 11,077.13 11,077.13
Direct Cost= 38,769.95
Contractor's Profit= 5,815.49
Contingencies= 3,101.60
Tax=
47,687.04
Unit Cost= 17,092.13 /cu.m ₱ 47,687.04
1.d Canopy Slab Extension
Slab = 0.03 cu.m
Material:
Portland Cement 1.00 bag 260.00 260.00
Washed Sand 1.00 cu.m 900.00 900.00
Screened Gravel 1.00 cu.m 1,200.00 1,200.00
12mmØ x 6m RSB 5.33 kgs 38.00 202.54
#16 G.I Tie Wire 1.00 kgs 70.00 70.00
labor
Concreting 1.00 lot 1,053.02 1,053.02
Direct Cost= 3,685.56
Contractor's Profit= 552.83
Contingencies= 294.84
Tax=
4,533.23
Unit Cost= 151,107.80 /cu.m ₱ 4,533.23
Note:
Final Price is Exclusive of Taxes if the Owner will not demand for reciept.
8 350 2800
156 28 4368
144 28 4032
10 70 700
11,900.00
Project Title: PROPOSED TWO-STOREY RESIDENTIAL
Owner: Lauro Inquit
Subject: ADDITIVE/DEDUCTIVE
Item Description Qty Unit Unit Price Subtotal Total
ORIGINAL PLAN
I. Deductive
4.f Steel Tubular 1"x1" Railings (Balcony & Viewing Deck)
Qty= 163.15 l.m
Material:
Steel Tubular 1"x1" 30.00 lght 350.00 10,500.00
12mmx6m Round bar 2.00 lght 250.00 500.00
Welding Rod 2.00 box 2,200.00 4,400.00
Color Black Paint 2.00 gal 550.00 1,100.00
Consumable 1.00 lot 2,000.00 2,000.00
labor
installation 1.00 lot 7,400.00 7,400.00
Direct Cost= 25,900.00
Contractor's Profit= 3,885.00
Contingencies= 2,072.00
Tax=
31,857.00
Unit Cost= 195.26 /l.m ₱ 31,857.00
REVISED PLAN
II. Additive
4.f Stainless Tubular Railings (Balcony,Viewing Deck,Inside Realings)
Material:
Stainless Tubular 1 1/2"x1 1/2x6.0m" 15.00 lght 1,300.00 19,500.00
Stainless Tubular 1"x1"x6.0m 20.00 lght 1,020.00 20,400.00
Stainless Flange 1 1/2"x1 1/2" 2.00 pcs 280.00 560.00
Stainless Flange 1"x1" 10.00 pcs 230.00 2,300.00
Stainless Welding Rod 25.00 kls 550.00 13,750.00
Grinding Stone 10.00 pcs 45.00 450.00
Flap Disk 10.00 pcs 40.00 400.00
Sanding Paper #220 30.00 pcs 25.00 750.00
Sanding Paper #240 30.00 pcs 25.00 750.00
Sanding Paper #600 30.00 pcs 25.00 750.00
Sanding Paper #1000 30.00 pcs 25.00 750.00
Sanding Paper #1500 30.00 pcs 25.00 750.00
Sanding Paper #2000 30.00 pcs 25.00 750.00
Buffing Stone 2.00 pcs 320.00 640.00
Consumable 1.00 lot 2,000.00 2,000.00
labor
installation 1.00 lot 25,800.00 25,800.00
Direct Cost= 90,300.00
Contractor's Profit= 13,545.00
Contingencies= 7,224.00
Tax=
111,069.00
Unit Cost= #REF! /l.m ₱ 111,069.00
4.g Stainless Tube Railings (Stair)
Material:
Stainless Tube 1 1/2"Øx6.0m" 3.00 lght 1,185.00 3,555.00
Stainless Tube 1"Øx6.0m 6.00 lght 850.00 5,100.00
Stainless Tube 1 1/2"Ø elbow 4.00 pcs 120.00 480.00
Stainless Tube 1 1/2"Ø flange 3.00 pcs 250.00 750.00
Stainless Tube 1"Ø flange 8.00 pcs 160.00 1,280.00
Stainless Tube 1 1/2"Ø cap 2.00 pcs 90.00 180.00
Stainless Welding Rod 10.00 kls 550.00 5,500.00
Grinding Stone 2.00 pcs 45.00 90.00
Flap Disk 3.00 pcs 40.00 120.00
Sanding Paper #220 15.00 pcs 25.00 375.00
Sanding Paper #240 15.00 pcs 25.00 375.00
Sanding Paper #600 15.00 pcs 25.00 375.00
Sanding Paper #1000 15.00 pcs 25.00 375.00
Sanding Paper #1500 15.00 pcs 25.00 375.00
Sanding Paper #2000 15.00 pcs 25.00 375.00
Buffing Stone 1.00 pcs 320.00 320.00
Consumable 1.00 lot 1,000.00 1,000.00
labor
installation 1.00 lot 8,250.00 8,250.00
Direct Cost= 28,875.00
Contractor's Profit= 4,331.25
Contingencies= 2,310.00
Tax=
35,516.25
Unit Cost= #REF! /l.m ₱ 35,516.25
Note:
Final Price is Exclusive of Taxes if the Owner will not demand for reciept.