Apta RT FS S 004 03
Apta RT FS S 004 03
Apta RT FS S 004 03
Abstract: This standard provides minimum requirements for inspecting, maintaining, and
testing rail transit system traction electrification substations.
No part of this publication may be reproduced in any form, in an electronic retrieval system or otherwise, without the prior written
permission of The American Public Transportation Association.
Volume 5 - Fixed Structures
APTA RT-FS-S-004-03 Rev-1
10/20/04
Introduction
(This introduction is not a part of APTA RT-FS-S-004-03, Standard for Traction Electrification Substation
Inspection, Maintenance and Testing.)
APTA rail transit safety standards represent an industry consensus on safety practices for rail transit
systems to help achieve a high level of safety for passengers, employees, and the general public. This
document was created by and for those parties concerned with its provisions; namely, rail transit systems
(operating systems), original equipment manufacturers, consultants, engineers, and general interest
groups. This standard provides procedures for inspecting, maintaining, and testing rail transit traction
electrification substations.
– Individuals or organizations that inspect, maintain, and/or operate rail transit systems
– Individuals or organizations that contract with others for the inspection, maintenance, and/or
operation of rail transit systems
– Individuals or organizations that influence how rail transit systems are inspected, maintained,
and/or operated (including but not limited to consultants, designers, and contractors)
– To help rail transit systems incorporate safety considerations during the inspection, maintenance,
and testing process
– To identify inspection criteria and maintenance standards that provide a high level of passenger
and personnel safety
The application of any standards, practices, or guidelines contained herein is voluntary. In some cases,
federal and/or state regulations govern portions of how an RTS operates. In such cases, the government
regulations override any conflicting practices this document requires or recommends.
Participants
APTA greatly appreciates the contributions of the following members of the Transit Standards Fixed
Structures Inspection and Maintenance Committee who provided the primary effort in drafting the
Standard for Traction Electrification Substation Inspection, Maintenance and Testing:
The following members of the Rail Transit Standards Fixed Structures Inspection and Maintenance
Committee contributed to the review and approval process of the Standard Traction Electrification
Substation Inspection, Maintenance and Testing:
APTA Rail Transit Standards Fixed Structures Inspection and Maintenance Committee project
consultants:
Contents
1. Overview................................................................................................................................................ 4.1
2. References.............................................................................................................................................. 4.2
1. Overview
This document establishes a standard for the periodic inspection, maintenance, and testing of the
major components of traction electrification substations for direct current (DC) rail transit
systems. This includes periodic visual, electrical, and mechanical inspections of components that
affect safe and reliable operation. This standard also identifies the necessary qualifications for
rail transit system (RTS) employees or contractors that perform periodic inspection,
maintenance, and testing tasks.
Annex A contains samples of checklists and/or recording forms used by rail transit systems to
perform inspections.
1.1 Purpose
The purpose of this standard is to verify that traction electrification substations are operating
safely and as designed through periodic inspection, maintenance, and testing, thereby increasing
reliability and reducing the risk of hazards and failures.
1.2 Scope
This standard applies to rail transit systems that operate light rail, heavy rail, or rail subway
systems and applies to normal operating conditions.
a) Identify the specific APTA rail transit safety standard requirements that cannot be met
d) Describe and substantiate how the alternate methods do not compromise safety and
provide a level of safety equivalent to the practices in the APTA safety standard
(operating histories or hazard analysis findings may be used to substantiate this claim)
2. References
This document shall be used in conjunction with the most recent version of the following
publications:
ANSI/IEEE C57.12.90 (1993), Standard Test Code for Liquid Immersed Distribution Power and
Regulating Transformers and Guide for Short Circuit Testing of Distribution and Power
Transformers.
ANSI/IEEE C57.12.91 (1995), Test Code for Dry Type Distribution and Power Transformers.
3.1 Definitions
3.1.1 arc: An electrical spark that occurs when current jumps across an air gap as a result of a
number of present conditions. Arcing is a common electrical hazard.
3.1.2 conductive personal article: A personal item that can conduct electricity. Examples of
conductive personal articles are metal watch bands, metal-framed safety glasses, finger rings,
jewelry, metal belt buckles, hearing aids with external wiring, etc.
3.1.3 contractor: Any individual(s) or entity under contract with the rail transit system
(including RTS and subcontractor personnel) to install, inspect, maintain, and/or test RTS
vehicles, systems, and components. Syn: consultant.
3.1.4 heavy rail system: An electric railway capable of a “heavy volume” of traffic
characterized by exclusive rights-of-way, multi-car trains, high speed and rapid acceleration,
sophisticated signaling, and high platform passenger loading. Syn: elevated railway, rapid rail,
rapid transit, subway.
3.1.5 light rail system: An electric railway with a lighter volume of train traffic than heavy rail
that may use shared or exclusive rights-of-way and may run trains intermingled with street
traffic. Light rail systems frequently operate with low platform loading and single car trains. Syn:
street car, tram, trolley car.
3.1.6 original equipment manufacturer (OEM): The enterprise that initially designs and
builds a piece of equipment.
3.1.7 personal protective equipment (PPE): All clothing and other work accessories designed
to create a barrier against workplace hazards. Examples include safety goggles, blast shields,
hard hats, hearing protectors, gloves, respirators, aprons, and work boots.
3.1.8 post-fault condition: Any condition caused by a system failure that causes either
repetitive faults or lockout trip of any subsystem.
3.1.9 rail transit system (RTS): The organization or portion of an organization that operates
rail transit service and related activities. Syn: operating agency, operating authority, transit
agency, transit authority, transit system.
3.2 Acronyms
AAS Associate in Applied Science
AC alternating current
ANSI American National Standards Institute
APTA American Public Transportation Association
DC direct current
IEEE Institute of Electrical and Electronic Engineers
NFPA National Fire Protection Agency
OEM original equipment manufacturer
PPE personal protective equipment
PM preventive maintenance
RTS rail transit system
SCADA supervisory control and data acquisition system
VPI vacuum pressure impregnated
4. Frequency of tasks
The inspection, maintenance, and testing procedures in this standard shall be performed as
specified in Table 1 below as otherwise deemed necessary by the RTS. Since age, type, operating
conditions, and environment vary from system to system and OEM maintenance intervals may
vary based on operating conditions, the RTS makes the final determination of inspection,
maintenance, and testing frequencies based on experience.
The RTS shall determine the need for additional inspection, maintenance, and testing frequencies
for traction electrification substations. A review of the following factors may be useful in making
this assessment:
– Industry experience
– Operating environment/conditions
– Historical data
– Failure analysis
– Regulatory requirements
The frequency of tasks shall comply with applicable federal, state, and local regulations.
Inspectors must have a minimum of two years experience working with traction and
electrification systems. All inspectors must be familiar with the installation and repair of the
components associated with traction and electrification systems.
Maintainers must have three or more years experience working on high voltage power
distribution or related traction and electrification systems either by in-house experience or
recognized trade school or apprenticeship training program.
Technicians must have three or more years experience working on high voltage power
distribution or related traction and electrification systems or possess an Associate in Applied
Science (AAS) degree in electrical systems or equivalent.
6. Tools
The following tools are required for inspection, maintenance, and testing of traction
electrification substations:
– Torque wrench
– Multi-meter*
– Megohm-meter*
7. Equipment lockout/tagout
Proper lockout/tagout procedures shall be followed as required by the RTS.
8. Safety
RTS safety rules, procedures, and practices shall be followed at all times during inspection,
maintenance, and testing.
Conductive personal articles shall not be worn when working on or about equipment.
Properly inspected and voltage-regulated insulating protective covers shall be used when
working on or near energized conductors and equipment. Insulating protective covers are to be
used only for their designated purpose.
b) Preventative maintenance (PM) and testing may require removing the equipment from
service and performing tests on the equipment or the materials to ensure proper operation.
This type of maintenance occurs on a regularly scheduled basis.
a) Verify cleanliness of substation site inside and outside. Particular attention should be
given to combustible rubbish material such as newspapers, drawings and storage of
materials not related to substation operations and maintenance in the same room.
b) Check for the presence of oil, dust or other material generated from traction power
equipment inside or outside the equipment room or building.
e) Check for presence of water or other material leaking into the substation from elsewhere.
f) Check for the presence of any “burning” smell, fumes, scorch marks or other material
that could be signs of a future breakdown.
g) Test emergency exit lighting and doors to verify they meet all applicable codes.
Post-fault conditions are defined as any condition where a system failure occurred that has
caused either repetitive faults or lockout trip of any subsystem.
Example: A DC circuit short circuit would require a thorough check of the circuit breaker,
distribution system, ground, and associated devices.
a) Exceeding the recommended number of operations under load conditions for circuit
breakers.
b) Defects found during monthly inspections that would generate a priority 1 or 2 as listed
in Section 12 of this standard.
10.5 Procedures
The RTS shall perform inspection, maintenance, and testing in accordance with this standard and
develop local policies and procedures to meet the requirements herein.
No work shall be performed unless proper procedures, documentation, and authorization have
been obtained from the RTS-designated authority to perform the prescribed task at the
designated location. Upon completion of the work, the RTS-designated authority must be
informed that the prescribed task is completed.
Each RTS shall develop specific written policies and procedures that take into account specific
equipment designs and local operating conditions to implement the inspection, maintenance, and
testing required by this standard. These policies and procedures shall give maintenance staff
clear guidance and criteria for performing these activities.
d) Perform all mechanical operations tests on both the circuit breaker and its operating
mechanism.
Copyright © 2004 APTA. All rights reserved. 4.7
Volume 5 - Fixed Structures
APTA RT-FS-S-004-03 Rev-1
10/20/04
g) Inspect bolted electrical connections using any one of the following methods:
f) Perform vacuum bottle integrity (over-potential) test across each vacuum bottle with the
breaker in the open positions in strict accordance with OEM published data. Do not
exceed maximum voltage stipulated for this test. Provide adequate barriers and protection
against x-radiation during this test. Do not perform this test unless the contact
displacement of each interrupter is within OEM tolerance.
NOTE: Be aware that some DC high-potential test sets are half-wave rectified and may produce peak
voltages in excess of the breaker OEM-recommended maximum.
g) Perform insulation-resistance test at 1000 volts DC on all control wiring. For units with
solid-state components, follow OEM recommendations.
a) Check each circuit breaker for proper operation. Perform the following checks as a
minimum:
– Open and close the breaker via remote control (SCADA if applicable)
– Local breaker indication: Ensure that the indication lamps and any mechanical
indications function properly
– Remote breaker indications: Ensure that the control center receives the proper
indications regarding breaker position if applicable. (i.e. open/closed and remote/local
condition)
c) Ensure microhm or milivolt drop values do not exceed the high levels of the normal
range as indicated in the OEM published data. If the OEM data is not available,
investigate any values that deviate from adjacent poles or similar breakers by more than
25 percent of the lowest value.
d) Ensure circuit breaker insulation resistance is in accordance with the OEM published
data.
d) Verify correct blade alignment, blade penetration, travel stops, and mechanical operation.
e) Verify that fuse sizes and types (if applicable) are in accordance with the drawings.
f) Verify that expulsion-limiting devices are in place on all holders having expulsion-type
elements.
g) Verify that each fuse holder (if applicable) has adequate mechanical support.
– Current-carrying parts
b) Perform an over-potential test on each pole with the switch closed. Test each pole-to-
ground with all other poles grounded. Test voltage shall be in accordance with OEM
published data.
c) Ensure microhm or millivolt drop values do not exceed the high levels of the normal
range as indicated in the OEM published data. If OEM data is not available, investigate
any values that deviate from adjacent poles or similar switches by more than 25 percent
of the lowest value.
f) Investigate fuse resistance values that deviate from each other by more than 15 percent.
c) Verify that control and alarm settings on temperature indicators are as specified.
e) Inspect all bolted electrical connections using one of the following methods:
h) While de-energized, operate any off-load or on-load tap changer through its complete
range three times.
1
For references in italics, see Section 2.
c) Measure core insulation-resistance if core is insulated and if the core ground strap is
removable.
c) Ensure microhm or millivolt drop values do not exceed the high levels of the normal
range as indicated in the OEM published data. If the OEM data isn’t available, investigate
any values that deviate from similar connections by more than 25 percent of the lowest
value.
d) Ensure insulation-resistance test values are no less than the values recommended in
ANSI/IEEE C57.12.91 - 1995.
e) Ensure core insulation resistance values are comparable to previously obtained results but
not less than one megohm.
b) Verify that control and alarm settings on temperature indicators are as specified.
d) Verify operation of all alarms, controls, and trip circuits from temperature and level
indicators, pressure relief devices, and fault pressure relays.
e) Inspect all bolted electrical connections using one of the following methods at a
frequency of no more than five (5) years:
i) While de-energized, operate any off-load or on-load tap changer through its complete
range three times.
c) Remove a sample of insulating liquid in accordance with the ASTM D923. Samples
should be sent to a certified test facility for all required testing.
c) Ensure microhm or millivolt drop values do not exceed the high levels of the normal
range as indicated in the OEM published data. If the OEM data isn’t available, investigate
any values that deviate from similar connections by more than 25 percent of the lowest
value.
d) Ensure insulation-resistance test values are no less than the values recommended in
ANSI/IEEEC57.12.90 – 1993.
f) Evaluate and trend recommendations and tests results from transformer liquid analysis.
10.5.2.5 Rectifiers
d) Inspect all bolted connections and verify that bolt-torque values are consistent with OEM
published data.
f) Verify that fuse blown indicators (where applicable) are properly mounted.
d) Verify correct blade alignment, blade penetration, travel stops, and mechanical operation.
e) Inspect all bolted electrical connections using one of the following methods:
i) Verify correct operation of all indicating and control devices for correct operation.
c) Ensure microhm or millivolt drop values do not exceed the high levels of the normal
range as indicated in the OEM published data. If the OEM data is not available,
investigate any values that deviate from adjacent poles or similar switches by more than
25 percent of the lowest value.
d) Perform all mechanical operations test on both the circuit breaker and its operating
mechanism.
g) Inspect bolted electrical connections and verify tightness of accessible bolted electrical
connections by calibrated torque-wrench method in accordance with OEM
recommendations. If connection shows any signs of corrosion it shall be cleaned or
replaced.
j) Inspect all DC traction circuit breaker contacts. Contacts include but are not limited to:
– main contacts
– arcing contacts
– auxiliary contacts
– Cleanliness: Ensure the contact surface is clean and kept free of any burrs and “spits.”
Use care if contacts are coated with silver or a silver alloy and when cleaning and/or
deburring the contact surface. To avoid damage to the contact surface, consult the
OEM-recommended procedure to determine the proper cleaning method.
– Wipe: Check contacts for proper wipe. Adhere to the OEM-recommended procedure
for checking contact wipe. Make necessary adjustments according to the OEM-
recommended practice.
– Inspect for any breakage to the inside sheet, arc plates, or arc runner.
– Inspect the interrupting structure for the presence of foreign particles such as chips of
insulation and metal.
– Inspect the exterior of the arc chute for any damage or deformation to the outside
sheets.
– Wipe the arc runner and arc horn with a dry cloth to remove dirt and dust
accumulation.
– Wipe all insulated parts with a cloth saturated with an oil free solvent to remove any
oil vapor film.
CAUTION: Use care when cleaning any arc chute. Some older arc chutes may
contain asbestos materials.
m) Check to ensure that each puffer provides a moderate amount of air at the contact when
the breaker is opened. Use a suitable media such as a piece of paper to detect air
movement. If the puffers do not show signs of puffing action, do not place the breaker in
service.
CAUTION: Care shall be exercised when performing this check. Keep clear of all
moving parts to avoid injury.
g) Perform insulation-resistance test at 1000 volts DC on all control wiring. For units with
solid-state components, follow the OEM recommendations.
a) Check each DC traction circuit breaker for proper operation. Check the following as a
minimum:
– Open and close the breaker via remote control (SCADA if applicable)
– Local breaker indication: Ensure that the indication lamps and any mechanical
indications function properly
– Remote breaker indications: Ensure that the control center receives the proper
indications regarding breaker position if applicable. (i.e. open/closed and remote/local
condition)
b) Inspect all bolted electrical connections using one of the following methods:
e) Measure each cell voltage and total battery voltage with charger energized and in float
mode of operation.
c) Ensure microhm or millivolt drop values do not exceed the high levels of the normal
range as indicated in the OEM published data. If the OEM data is not available,
investigate any values that deviate from similar connections by more than 25 percent of
the lowest value.
d) Ensure charger float and equalize voltage levels are in accordance with the OEM
published data.
g) Ensure cell voltages are within 0.05 volt of each other or in accordance with the OEM
published data.
b) Inspect the relay contacts for burns, damage, misalignment, corrosion, or other
contamination.
The RTS shall designate a person responsible for deciding whether or not to leave defective
equipment in service in order to operate. In the absence of a designated person, the RTS shall
take the equipment out of service.
The RTS shall review and develop a corrective action plans for documented system defects
monthly.
– Priority 1: The defect will endanger the safety of patrons and personnel and/or
continuation of revenue service. A permanent or temporary repair shall be made
immediately.
– Priority 2: The defect may cause disruption of revenue service. The repair shall be made
in a predetermined timeframe set by each system.
– Priority 3: The defect will not affect revenue service. The repair shall be made in a
predetermined timeframe set by each system.
13. Documentation
The RTS shall develop and implement a fully auditable process for recording and tracking
inspection, maintenance, and testing activities and outstanding system defects. Such
documentation shall be documented, reviewed, and filed in accordance with RTS procedures and
OEM recommendations. Documentation should be kept for the life of all in-service equipment.
Annex A contains a sample checklist and recording form that rail transit systems can adapt to
their specific equipment and operating environment.
Annex A
(Informative)
Sample checklist/recording form