ID WBS Task Name Notes Duration Start Finish Predecessors Successors 2019 2020
8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2
1 1 THE DETAILED DESIGN AND SUPERVISION WORKS FOR 1484 days Sun 26/1/20 Thu 2/10/25
PALEKBANG BRIDGE KOTA BHARU, KELANTAN DARUL NAIM FOR
THE EAST COAST ECONOMIC REGION DEVELOPMENT COUNCIL
2 1.1 (ECERDC)
COMMENCEMENT OF WORK 0 days Sun 26/1/20 Sun 26/1/20 17 26/1
3 1.2 PROJECT MILESTONE 1484 days Sun 26/1/20 Thu 2/10/25
16 1.3 DETAIL DESIGN STAGE 499 days Mon 27/1/20 Thu 23/12/21
17 1.3.1 Site Visit 14 days Mon 27/1/20 Thu 13/2/20 2 18SS,20SS+8 days 27/1 13/2
18 1.3.2 Data Gathering 21 days Mon 27/1/20 Mon 24/2/20 17SS 20SS 27/1 24/2
19 1.3.3 INCEPTION REPORT 15 days Thu 6/2/20 Wed 26/2/20
20 1.3.3.1 Preparation 5 days Thu 6/2/20 Wed 12/2/20 17SS+8 days,18SS 21SS,22SS,23SS 6/2 12/2
21 1.3.3.2 TOR for Engineering Survey Works 26 Feb 2020 10 days Thu 6/2/20 Wed 19/2/20 20SS 24 6/2 19/2
22 1.3.3.3 TOR for Soil Investigation Works 26 Feb 2020 10 days Thu 6/2/20 Wed 19/2/20 20SS 24 6/2 19/2
23 1.3.3.4 TOR for Hydraulic Study 26 Feb 2020 15 days Thu 6/2/20 Wed 26/2/20 20SS 24 6/2 26/2
24 1.3.3.5 TOR & Inception Report Submission 26 Feb 2020 0 days Wed 26/2/20 Wed 26/2/20 21,22,23 27,39,49,62,57,71,82 26/2
25 1.3.4 PRE-DEVELOPMENT WORKS 64 days Thu 27/2/20 Tue 26/5/20
26 1.3.4.1 ENGINEERING SURVEY 64 days Thu 27/2/20 Tue 26/5/20
27 1.3.4.1.1 Documentation Preparation (RFP) 5 days Thu 27/2/20 Wed 4/3/20 24 28 27/2 4/3
28 1.3.4.1.2 Submission 1 day Thu 5/3/20 Thu 5/3/20 27 29 5/3 5/3
29 1.3.4.1.3 Review 5 days Fri 6/3/20 Thu 12/3/20 28 30 6/3 12/3
30 1.3.4.1.4 Final RFP 1 day Fri 13/3/20 Fri 13/3/20 29 32 13/3 13/3
31 1.3.4.1.5 Tender & Award Stage 5 days Mon 16/3/20 Fri 20/3/20
32 1.3.4.1.5.1 Work Order 5 days Mon 16/3/20 Fri 20/3/20 30 34 16/3 20/3
33 1.3.4.1.6 Fieldwork 47 days Fri 20/3/20 Tue 26/5/20
34 1.3.4.1.6.1 Commencement 0 days Fri 20/3/20 Fri 20/3/20 32 35,36,139,146 20/3
35 1.3.4.1.6.2 Topographical Survey 42 days Mon 23/3/20 Tue 19/5/20 34 37,154,159 23/3 19/5
36 1.3.4.1.6.3 Bathymetric Survey 30 days Mon 23/3/20 Fri 1/5/20 34 37 23/3 1/5
37 1.3.4.1.6.4 Field Survey Report 26 May 2020 5 days Wed 20/5/20 Tue 26/5/20 36,35 20/5 26/5
38 1.3.4.2 SOIL INVESTIGATION 64 days Thu 27/2/20 Tue 26/5/20
39 1.3.4.2.1 Documentation Preparation (Quotation) 5 days Thu 27/2/20 Wed 4/3/20 24 40 27/2 4/3
40 1.3.4.2.2 Submission 1 day Thu 5/3/20 Thu 5/3/20 39 41 5/3 5/3
41 1.3.4.2.3 Review 5 days Fri 6/3/20 Thu 12/3/20 40 42 6/3 12/3
42 1.3.4.2.4 Final RFP 1 day Fri 13/3/20 Fri 13/3/20 41 44 13/3 13/3
43 1.3.4.2.5 Tender & Award Stage 5 days Mon 16/3/20 Fri 20/3/20
44 1.3.4.2.5.1 Work Order 5 days Mon 16/3/20 Fri 20/3/20 42 46 16/3 20/3
45 1.3.4.2.6 Field Work 47 days Mon 23/3/20 Tue 26/5/20
46 1.3.4.2.6.1 Commencement 32 days Mon 23/3/20 Tue 5/5/20 44 47 23/3 5/5
47 1.3.4.2.6.2 S.I. Interpretavie Report 26 May 2020 15 days Wed 6/5/20 Tue 26/5/20 46 6/5 26/5
48 1.3.4.3 HYDRAULIC STUDY REPORT 64 days Thu 27/2/20 Tue 26/5/20
49 1.3.4.3.1 Data Gathering (Historical Data & Topographical Data) 21 days Thu 27/2/20 Thu 26/3/20 24 50 27/2 26/3
50 1.3.4.3.2 Hydraulic Analysis 10 days Fri 27/3/20 Thu 9/4/20 49 51 27/3 9/4
51 1.3.4.3.3 Scour Analysis 10 days Fri 10/4/20 Thu 23/4/20 50 52 10/4 23/4
52 1.3.4.3.4 Sediment & Transport Analysis 10 days Fri 24/4/20 Thu 7/5/20 51 53 24/4 7/5
53 1.3.4.3.5 Bridge Deck Drainage Design 10 days Fri 8/5/20 Thu 21/5/20 52 54 8/5 21/5
54 1.3.4.3.6 Report Submission 26 May 2020 3 days Fri 22/5/20 Tue 26/5/20 53 22/5 26/5
55 1.3.5 DESIGN BRIEF 87 days Thu 27/2/20 Fri 26/6/20
56 1.3.5.1 Bridge Design Brief 51 days Thu 27/2/20 Thu 7/5/20
57 1.3.5.1.1 Architectural Design & Bridge Aesthetics 21 days Thu 27/2/20 Thu 26/3/20 24 58 27/2 26/3
58 1.3.5.1.2 Functional Requirements 5 days Fri 27/3/20 Thu 2/4/20 57 59 27/3 2/4
59 1.3.5.1.3 Main Superstructure Elements 20 days Fri 3/4/20 Thu 30/4/20 58 60 3/4 30/4
60 1.3.5.1.4 Deck & Wearing Surface 9 days Fri 1/5/20 Wed 13/5/20 59 66 1/5 13/5
DETAILED MASTER IMPLEMENTATION PROGRAM Page 1 REVISED MIP : PRELIMINARY DATED 25 JAN 2020
THE DETAILED DESIGN AND SUPERVISION WORKS FOR PALEKBANG BRIDGE, KOTA BHARU, KELANTAN DARUL NAIM
ID WBS Task Name Notes Duration Start Finish Predecessors Successors 2019 2020
8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2
61 1.3.5.2 Geotechnical Design Brief 34 days Thu 27/2/20 Tue 14/4/20
62 1.3.5.2.1 Slope / Ground Treatment Design 7 days Thu 27/2/20 Fri 6/3/20 24 63 27/2 6/3
63 1.3.5.2.2 Embankment Design 14 days Mon 9/3/20 Thu 26/3/20 62 64 9/3 26/3
64 1.3.5.2.3 Structural Foundation 8 days Fri 27/3/20 Tue 7/4/20 63 65 27/3 7/4
65 1.3.5.2.4 Culvert Foundation 5 days Wed 8/4/20 Tue 14/4/20 64 66 8/4 14/4
66 1.3.5.3 Presentation to ECERDC 19 days Thu 14/5/20 Tue 9/6/20 65,60 67 14/5 9/6
67 1.3.5.4 Review & Comment / Submission 8 days Wed 10/6/20 Fri 19/6/20 66 68 10/6 19/6
68 1.3.5.5 Approval for Design Brief 26 June 2020 5 days Mon 22/6/20 Fri 26/6/20 67 113,82 22/6 26/6
69 1.3.6 SCHEMATIC DESIGN 107 days Thu 27/2/20 Fri 24/7/20
70 1.3.6.1 Bridge Design 84 days Thu 27/2/20 Tue 23/6/20
71 1.3.6.1.1 Foundation Design 14 days Thu 27/2/20 Tue 17/3/20 24 72 27/2 17/3
72 1.3.6.1.2 Pier Design 7 days Wed 18/3/20 Thu 26/3/20 71 73 18/3 26/3
73 1.3.6.1.3 Abutment Design 7 days Fri 27/3/20 Mon 6/4/20 72 74 27/3 6/4
74 1.3.6.1.4 Bearings 7 days Tue 7/4/20 Wed 15/4/20 73 75 7/4 15/4
75 1.3.6.1.5 Main Superstructure Design 21 days Thu 16/4/20 Thu 14/5/20 74 76,81SS,79SS 16/4 14/5
76 1.3.6.1.6 Deck & Deck Wearing Surface 7 days Fri 15/5/20 Mon 25/5/20 75 77 15/5 25/5
77 1.3.6.1.7 Bridge Traffic Barriers 14 days Tue 26/5/20 Fri 12/6/20 76 78,80SS 26/5 12/6
78 1.3.6.1.8 Expansion Joints & Relieving Slabs 7 days Mon 15/6/20 Tue 23/6/20 77 82 15/6 23/6
79 1.3.6.1.9 Services, Lighting, Miscellaneous 14 days Thu 16/4/20 Tue 5/5/20 75SS 82 16/4 5/5
80 1.3.6.1.10 Paint System & Structural Steel 14 days Tue 26/5/20 Fri 12/6/20 77SS 82 26/5 12/6
81 1.3.6.1.11 Bridge Modelling 28 days Thu 16/4/20 Mon 25/5/20 75SS 82 16/4 25/5
82 1.3.6.2 Presentation to ECERDC 7 days Mon 29/6/20 Tue 7/7/20 24,68,81,80,79,78 83 29/6 7/7
83 1.3.6.3 Review & Comment / Submission 8 days Wed 8/7/20 Fri 17/7/20 82 84 8/7 17/7
84 1.3.6.4 Approval Schematic Design 26 July 2020 5 days Mon 20/7/20 Fri 24/7/20 83 113,94,88,121,122,123,124 20/7 24/7
85 1.3.7 DETAILED DESIGN 66 days Mon 27/7/20 Mon 26/10/20
86 1.3.7.1 Drawing Preparation 47 days Mon 27/7/20 Tue 29/9/20
87 1.3.7.1.1 Geotechnical Works 22 days Mon 27/7/20 Tue 25/8/20
88 1.3.7.1.1.1 Relocation Works 2 days Mon 27/7/20 Tue 28/7/20 84 89 27/7 28/7
89 1.3.7.1.1.2 Slope / Ground Treatment 5 days Wed 29/7/20 Tue 4/8/20 88 90 29/7 4/8
90 1.3.7.1.1.3 Reinforced Soil Structure (RSS) Wall 5 days Wed 5/8/20 Tue 11/8/20 89 91 5/8 11/8
91 1.3.7.1.1.4 Structural Foundation 5 days Wed 12/8/20 Tue 18/8/20 90 92,98SS 12/8 18/8
92 1.3.7.1.1.5 Culvert Foundation 5 days Wed 19/8/20 Tue 25/8/20 91 106 19/8 25/8
93 1.3.7.1.2 Bridge Components 42 days Mon 27/7/20 Tue 22/9/20
94 1.3.7.1.2.1 Foundation 7 days Mon 27/7/20 Tue 4/8/20 84 95 27/7 4/8
95 1.3.7.1.2.2 Pier 5 days Wed 5/8/20 Tue 11/8/20 94 96 5/8 11/8
96 1.3.7.1.2.3 Abutment 5 days Wed 12/8/20 Tue 18/8/20 95 97 12/8 18/8
97 1.3.7.1.2.4 Bearings 5 days Wed 19/8/20 Tue 25/8/20 96 104 19/8 25/8
98 1.3.7.1.2.5 Main Superstructure 10 days Wed 12/8/20 Tue 25/8/20 91SS 99 12/8 25/8
99 1.3.7.1.2.6 Deck & Deck Wearing Surface 5 days Wed 26/8/20 Tue 1/9/20 98 100 26/8 1/9
100 1.3.7.1.2.7 Bridge Traffic Barriers 5 days Wed 2/9/20 Tue 8/9/20 99 101 2/9 8/9
101 1.3.7.1.2.8 Expansion Joints & Relieving Slabs 5 days Wed 9/9/20 Tue 15/9/20 100 102 9/9 15/9
102 1.3.7.1.2.9 Paint System & Structural Steel 5 days Wed 16/9/20 Tue 22/9/20 101 104 16/9 22/9
103 1.3.7.1.3 Mechanical & Electrical Services 5 days Wed 23/9/20 Tue 29/9/20
104 1.3.7.1.3.1 Services, Lighting, Miscellaneous 5 days Wed 23/9/20 Tue 29/9/20 102,97 106 23/9 29/9
105 1.3.7.2 Final Detail Engineering Design Report 19 days Wed 30/9/20 Mon 26/10/20
106 1.3.7.2.1 Preparation 5 days Wed 30/9/20 Tue 6/10/20 104,92 107 30/9 6/10
107 1.3.7.2.2 First Submission 2 days Wed 7/10/20 Thu 8/10/20 106 108 7/10 8/10
108 1.3.7.2.3 Presentation 1 day Fri 9/10/20 Fri 9/10/20 107 109 9/10 9/10
109 1.3.7.2.4 Comments 4 days Mon 12/10/20 Thu 15/10/20 108 110 12/10 15/10
DETAILED MASTER IMPLEMENTATION PROGRAM Page 2 REVISED MIP : PRELIMINARY DATED 25 JAN 2020
THE DETAILED DESIGN AND SUPERVISION WORKS FOR PALEKBANG BRIDGE, KOTA BHARU, KELANTAN DARUL NAIM
ID WBS Task Name Notes Duration Start Finish Predecessors Successors 2019 2020
8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2
110 1.3.7.2.5 Second Submission 2 days Fri 16/10/20 Mon 19/10/20 109 111 16/10 19/10
111 1.3.7.2.6 Approved by ECERDC 26 October 2020 5 days Tue 20/10/20 Mon 26/10/20 110 164,134FF 20/10 26/10
112 1.3.7.3 Tender Documentation Preparation 66 days Mon 27/7/20 Mon 26/10/20
113 1.3.7.3.1 Instruction to Tenderers (prepared by QS) 5 days Mon 27/7/20 Fri 31/7/20 68,84 114SS,128,125SS 27/7 31/7
114 1.3.7.3.2 Condition of Contract (prepared by QS) 5 days Mon 27/7/20 Fri 31/7/20 113SS 115SS,128 27/7 31/7
115 1.3.7.3.3 Form of Tender (prepared by QS) 5 days Mon 27/7/20 Fri 31/7/20 114SS 116SS,128 27/7 31/7
116 1.3.7.3.4 Specification of Structure 5 days Mon 27/7/20 Fri 31/7/20 115SS 117SS,128 27/7 31/7
117 1.3.7.3.5 Specification of Pipe Work 5 days Mon 27/7/20 Fri 31/7/20 116SS 118SS,128 27/7 31/7
118 1.3.7.3.6 Specification of Mechanical 5 days Mon 27/7/20 Fri 31/7/20 117SS 119SS,128 27/7 31/7
119 1.3.7.3.7 Specification of Electrical 5 days Mon 27/7/20 Fri 31/7/20 118SS 120SS,128 27/7 31/7
120 1.3.7.3.8 Specification of Instrumentation 5 days Mon 27/7/20 Fri 31/7/20 119SS 128 27/7 31/7
121 1.3.7.3.9 BOQ Structure (prepared by QS) 10 days Mon 27/7/20 Fri 7/8/20 84 128FF 27/7 7/8
122 1.3.7.3.10 BOQ Pipeworks (prepared by QS) 10 days Mon 27/7/20 Fri 7/8/20 84 128 27/7 7/8
123 1.3.7.3.11 BOQ Mechanical 10 days Mon 27/7/20 Fri 7/8/20 84 128FF 27/7 7/8
124 1.3.7.3.12 BOQ Electrical 10 days Mon 27/7/20 Fri 7/8/20 84 128 27/7 7/8
125 1.3.7.3.13 Schedule of Particulars Civil 10 days Mon 27/7/20 Fri 7/8/20 113SS 126SS,128 27/7 7/8
126 1.3.7.3.14 Schedule of Particulars Mechanical 10 days Mon 27/7/20 Fri 7/8/20 125SS 127SS,128 27/7 7/8
127 1.3.7.3.15 Schedule of Particulars Electrical 10 days Mon 27/7/20 Fri 7/8/20 126SS 128 27/7 7/8
128 1.3.7.3.16 Appendices 1 day Mon 10/8/20 Mon 10/8/20 113,114,115,116,117,118,119,120,121FF,122,123FF,124,125,126,127
130 10/8 10/8
129 1.3.7.3.17 Document & Drawing Compilation 55 days Tue 11/8/20 Mon 26/10/20
130 1.3.7.3.17.1 1st Draft 1 day Tue 11/8/20 Tue 11/8/20 128 131 11/8 11/8
131 1.3.7.3.17.2 Review by ECERDC 5 days Wed 12/8/20 Tue 18/8/20 130 132 12/8 18/8
132 1.3.7.3.17.3 2nd Draft 5 days Wed 19/8/20 Tue 25/8/20 131 133 19/8 25/8
133 1.3.7.3.17.4 Review by ECERDC 5 days Wed 26/8/20 Tue 1/9/20 132 134 26/8 1/9
134 1.3.7.3.17.5 Final 26 October 2020 5 days Tue 20/10/20 Mon 26/10/20 133,111FF 136FF,164,135SS 20/10 26/10
135 1.3.7.3.17.6 Cost Review by ECERDC 5 days Tue 20/10/20 Mon 26/10/20 134SS 164,6 20/10 26/10
136 1.3.7.3.18 Tender Evalution Criteria 7 days Fri 16/10/20 Mon 26/10/20 134FF 164 16/10 26/10
137 1.3.8 AUTHORITY SUBMISSION & ENGINEERING APPROVALS 499 days Mon 27/1/20 Thu 23/12/21
138 1.3.8.1 Land Alienation 145 days Mon 27/1/20 Fri 14/8/20
139 1.3.8.1.1 Drawing Preparation by ES 20 days Mon 23/3/20 Fri 17/4/20 34 140,147 23/3 17/4
140 1.3.8.1.2 Land Valuation Report 26 April 2020 5 days Mon 20/4/20 Fri 24/4/20 139 20/4 24/4
141 1.3.8.1.3 Submission to Land Office for Approval Land Alienation 1 day Mon 27/1/20 Mon 27/1/20 142 27/1 27/1
142 1.3.8.1.4 5A Notice 100 days Tue 28/1/20 Mon 15/6/20 141 143 28/1 15/6
143 1.3.8.1.5 Final Approval of Land Alienation by Land Office (Before 31 days Tue 16/6/20 Tue 28/7/20 142 144 16/6 28/7
Tender)
144 1.3.8.1.6 Final Report of Land Alienation Status 13 days Wed 29/7/20 Fri 14/8/20 143 29/7 14/8
145 1.3.8.2 Land Acquisition 459 days Mon 23/3/20 Thu 23/12/21
146 1.3.8.2.1 Drawing Preparation by ES 20 days Mon 23/3/20 Fri 17/4/20 34 147 23/3 17/4
147 1.3.8.2.2 Land Valuation Report 26 April 2020 5 days Mon 20/4/20 Fri 24/4/20 139,146 148 20/4 24/4
148 1.3.8.2.3 Submission to Land Office for Approval Land Acquisition 1 day Mon 27/4/20 Mon 27/4/20 147 149 27/4 27/4
149 1.3.8.2.4 Obtaining Borang K 200 days Tue 28/4/20 Mon 1/2/21 148 150 28/4 1/2
150 1.3.8.2.5 Final Approval of Land Acquisition by Land Office (Before Tender) 22 days Tue 2/2/21 Wed 3/3/21 149 151FS+200 days 2/2 3
151 1.3.8.2.6 Final Report of Land Acquisition Status 11 days Thu 9/12/21 Thu 23/12/21 150FS+200 days
152 1.3.8.3 Submission to Authorities 114 days Wed 20/5/20 Mon 26/10/20
153 1.3.8.3.1 JABATAN PENGAIRAN & SALIRAN (JPS) 114 days Wed 20/5/20 Mon 26/10/20
154 1.3.8.3.1.1 Drawing Submission for Approval 34 days Wed 20/5/20 Mon 6/7/20 35 155 20/5 6/7
155 1.3.8.3.1.2 Review & Comment 40 days Tue 7/7/20 Mon 31/8/20 154 161,156 7/7 31/8
156 1.3.8.3.1.3 Approval 26 October 2020 40 days Tue 1/9/20 Mon 26/10/20 160,155 162FF,164 1/9 26/10
157 1.3.8.3.2 MAJLIS PERBANDARAN / DAERAH (OSC) 114 days Wed 20/5/20 Mon 26/10/20
DETAILED MASTER IMPLEMENTATION PROGRAM Page 3 REVISED MIP : PRELIMINARY DATED 25 JAN 2020
THE DETAILED DESIGN AND SUPERVISION WORKS FOR PALEKBANG BRIDGE, KOTA BHARU, KELANTAN DARUL NAIM
ID WBS Task Name Notes Duration Start Finish Predecessors Successors 2019 2020
8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2
158 1.3.8.3.2.1 Building Plan Approval 114 days Wed 20/5/20 Mon 26/10/20
159 1.3.8.3.2.1.1 Drawing Submission for Approval 34 days Wed 20/5/20 Mon 6/7/20 35 160 20/5 6/7
160 1.3.8.3.2.1.2 Review & Comment 40 days Tue 7/7/20 Mon 31/8/20 159 161,156 7/7 31/8
161 1.3.8.3.2.1.3 Approval 26 October 2020 40 days Tue 1/9/20 Mon 26/10/20 160,155 162FF,164 1/9 26/10
162 1.3.8.3.2.1.4 Documents / Drawing Approval by Authorities 5 days Tue 20/10/20 Mon 26/10/20 161FF,156FF 164 20/10 26/10
163 1.4 TENDER STAGE 74 days Tue 27/10/20 Fri 5/2/21
164 1.4.1 Final Tender Document 1 day Tue 27/10/20 Tue 27/10/20 162,134,111,136,161,135,156
165,8SS 27/10 27/10
165 1.4.2 Tender Process Approval 5 days Wed 28/10/20 Tue 3/11/20 164 166 28/10 3/11
166 1.4.3 Tender Advertisment 5 days Wed 4/11/20 Tue 10/11/20 165 167 4/11 10/11
167 1.4.4 Tender Period Untill Closing Date 20 days Wed 11/11/20 Tue 8/12/20 166 168 11/11 8/12
168 1.4.5 Tender Opening 1 day Wed 9/12/20 Wed 9/12/20 167 169 9/12 9/12
169 1.4.6 Tender Evaluation Report 10 days Thu 10/12/20 Wed 23/12/20 168 170 10/12 23/12
170 1.4.7 Tender Evaluation Committee Meeting 5 days Thu 24/12/20 Wed 30/12/20 169 171 24/12 30/12
171 1.4.8 Tender Clarification (If Any) 6 days Thu 31/12/20 Thu 7/1/21 170 172 31/12 7/1
172 1.4.9 Proc Board A 5 days Fri 8/1/21 Thu 14/1/21 171 173 8/1 14/1
173 1.4.10 Letter of Award (LOA) 5 days Fri 15/1/21 Thu 21/1/21 172 174FS+10 days 15/1 21/1
174 1.4.11 Site Possession 1 day Fri 5/2/21 Fri 5/2/21 173FS+10 days 176SS,9FF 5/2 5/2
175 1.5 CONSTRUCTION STAGE 695 days Fri 5/2/21 Thu 5/10/23
176 1.5.1 Construction (32 Months) 695 days Fri 5/2/21 Thu 5/10/23 174SS 177SS,11SS,180FF 5/2 5/
177 1.5.2 Preparation of Construction & Contract Drawings 30 days Fri 5/2/21 Thu 18/3/21 176SS 178 5/2
178 1.5.3 Issued Contract Documents 30 days Fri 19/3/21 Thu 29/4/21 177 194 19/3
179 1.5.4 Testing & Commissioning 15 days Fri 15/9/23 Thu 5/10/23
180 1.5.4.1 Mobilisation 15 days Fri 15/9/23 Thu 5/10/23 176FF 181SS
181 1.5.4.2 1st Submission 3 days Fri 15/9/23 Tue 19/9/23 180SS 182
182 1.5.4.3 Presentation 1 day Wed 20/9/23 Wed 20/9/23 181 183
183 1.5.4.4 Comments 8 days Thu 21/9/23 Mon 2/10/23 182 184
184 1.5.4.5 2nd Submission 3 days Tue 3/10/23 Thu 5/10/23 183 185FF
185 1.5.4.6 Final Approval 1 day Thu 5/10/23 Thu 5/10/23 184FF 187FF,194
186 1.5.5 Operation & Maintenance (O&M) Manual 30 days Fri 25/8/23 Thu 5/10/23
187 1.5.5.1 Mobilisation 30 days Fri 25/8/23 Thu 5/10/23 185FF 188SS
188 1.5.5.2 1st Submission 7 days Fri 25/8/23 Mon 4/9/23 187SS 189
189 1.5.5.3 Presentation 1 day Tue 5/9/23 Tue 5/9/23 188 190
190 1.5.5.4 Comments 10 days Wed 6/9/23 Tue 19/9/23 189 191
191 1.5.5.5 2nd Submission 7 days Wed 20/9/23 Thu 28/9/23 190 192
192 1.5.5.6 Final Approval 1 day Fri 29/9/23 Fri 29/9/23 191 194
193 1.6 POST CONSTRUCTION STAGE (12 Months - DLP end on 21/10/20) 520 days Thu 5/10/23 Thu 2/10/25
194 1.6.1 Performance Review Report 0 days Thu 5/10/23 Thu 5/10/23 192,185,178 195,196SS,201
195 1.6.2 Report on Project Assets Management and Integration Works with 0 days Thu 5/10/23 Thu 5/10/23 194 201
Existing System
196 1.6.3 Defect Inspections & Reports 0 days Thu 5/10/23 Thu 5/10/23 194SS 197SS,201
197 1.6.4 Approval & Recommend the Method to Carry Out of Remedial / 0 days Thu 5/10/23 Thu 5/10/23 196SS 201,198
Defects Rectification Works
198 1.6.5 Inspect & Witness Defect Rectification Works 0 days Thu 5/10/23 Thu 5/10/23 197 201,199FS+520 days
199 1.6.6 Issuance of Certificate of Making Good Defects (CMGD) 0 days Thu 2/10/25 Thu 2/10/25 198FS+520 days 201,200
200 1.6.7 Project Final Account Report 0 days Thu 2/10/25 Thu 2/10/25 199 201
201 1.6.8 Project Closing 0 days Thu 2/10/25 Thu 2/10/25 200,194,195,196,197,198,199
14SS,15FF
DETAILED MASTER IMPLEMENTATION PROGRAM Page 4 REVISED MIP : PRELIMINARY DATED 25 JAN 2020
THE DETAILED DESIGN AND SUPERVISION WORKS FOR PALEKBANG BRIDGE, KOTA BHARU, KELANTAN DARUL NAIM
DETAILED MASTER IMPLEMENTATION PROGRAM Page 5 REVISED MIP : PRELIMINARY DATED 25 JAN 2020
THE DETAILED DESIGN AND SUPERVISION WORKS FOR PALEKBANG BRIDGE, KOTA BHARU, KELANTAN DARUL NAIM
DETAILED MASTER IMPLEMENTATION PROGRAM Page 6 REVISED MIP : PRELIMINARY DATED 25 JAN 2020
THE DETAILED DESIGN AND SUPERVISION WORKS FOR PALEKBANG BRIDGE, KOTA BHARU, KELANTAN DARUL NAIM
1/2
2/2 3/3
9/12 23/12
DETAILED MASTER IMPLEMENTATION PROGRAM Page 7 REVISED MIP : PRELIMINARY DATED 25 JAN 2020
THE DETAILED DESIGN AND SUPERVISION WORKS FOR PALEKBANG BRIDGE, KOTA BHARU, KELANTAN DARUL NAIM
1
8/12
9/12
23/12
30/12
2 7/1
8/1 14/1
15/1 21/1
5/2 5/2
5/2 5/10
5/2 18/3
19/3 29/4
15/9 5/10
15/9 19/9
20/9 20/9
21/9 2/10
3/10 5/10
5/10 5/10
25/8 5/10
25/8 4/9
5/9 5/9
6/9 19/9
20/9 28/9
29/9 29/9
5/10
5/10
5/10
5/10
5/10
2/10
2/10
2/10
DETAILED MASTER IMPLEMENTATION PROGRAM Page 8 REVISED MIP : PRELIMINARY DATED 25 JAN 2020