Rate Analysis-Kalika
Rate Analysis-Kalika
1002
Earthwork in backfilling (with earth available at site); analysis for 1m3
sources Level Qty Unit Rate/unit cost
labour unskilled 0.5 nos 675.00 337.50
Actual rate
Rate per m3 Rs. 388.13 15% conctractor overhead
Rate per cu. ft Rs. 10.9989210926 Total (Rs.)
1003
Earthwork in backfilling (with imported earth) ;analysis for 1m3
sources Level Qty Unit Rate/unit cost
labour unskilled 0.8 nos 675.00 540.00
Actual rate
Rate per m3 Rs. 621.00 15% conctractor overhead
Rate per cu. ft Rs. 17.5982737482 Total (Rs.)
1004
Flat Brick soling works ;analysis for 1m2
sources Level Qty Unit Rate/unit cost
labour skilled 0.1 nos 930.00 93.00
un skilled 0.05 nos 675.00 33.75
materials a.local bricks 44 nos 14.50 638.00
b. sand filling 0.07 m3 2183.34 152.83
Actual rate
15% conctractor overhead
Rate per m2 Rs. 1055.22137 Total (Rs.)
Rate per sq. ft Rs. 98.0834854625
1006
Brick work in 1:6 ratio ;analysis for 1m3
sources Level Qty Unit Rate/unit cost
labour skilled 1.5 nos 930.00 1395.00
un skilled 2.2 nos 675.00 1485.00
un skilled 0.2 nos 675.00 135.00
a.Brick 530 nos 14.50 7685.00
materials b.sand 0.3 m3 2183.34 655.00
c. Cement 1.4 bags 780.00 1092.00
Actual rate
15% conctractor overhead
Rate per m3 Rs. 14314.0523 Total (Rs.)
Rate per cu. ft Rs. 405.6402750749
1007
Brick work in 1:4 ratio ;analysis for 1m3
sources Level Qty Unit Rate/unit cost
labour skilled 1.5 nos 930.00 1395.00
un skilled 2.2 nos 675.00 1485.00
un skilled 0.7 nos 675.00 472.50
a.Brick 560 nos 14.50 8120.00
materials b.sand 0.28 m3 2183.34 611.34
c. Cement 2 bags 780.00 1560.00
Actual rate
15% conctractor overhead
Rate per m3 Rs. 15690.41048 Total (Rs.)
Rate per cu. ft Rs. 444.6443459722
1008
PCC M20 (1:1.5:3) ;analysis for 1m3
sources Level Qty Unit Rate/unit cost
labour skilled 0.8 nos 930.00 744.00
un skilled 7 nos 675.00 4725.00
a.cement 8 bags 780.00 6240.00
b.20mm aggregate 0.57 m3 2075.00 1182.75
materials c.10mm aggregate 0.29 m3 2085.00 604.65
c. sand 0.425 m3 2183.34 927.92
d. water 200 lt. 0.25 50.00
Actual rate
15% conctractor overhead
Rate per m3 Rs. 16645.467425 Total (Rs.)
Rate per cu. ft Rs. 471.7093275555
1009
PCC M15 (1:2:4) ;analysis for 1m3
sources Level Qty Unit Rate/unit cost
labour skilled 0.8 nos 930.00 744.00
un skilled 7 nos 675.00 4725.00
a.cement 6.4 bags 780.00 4992.00
b.40mm aggregate 0.52 m3 2075.00 1079.00
c.20mm aggregate 0.22 m3 2085.00 458.70
materials d.10mm aggregate 0.11 m3 2085.00 229.35
d. sand 0.445 m3 2183.34 971.59
e. water 150 lt. 0.25 37.50
Actual rate
15% conctractor overhead
Rate per m3 Rs. 15222.706745 Total (Rs.)
Rate per cu. ft Rs. 431.3902745365
1010
Plywood and Pipe post Formwork;analysis for 100m2
sources Level Qty Unit Rate/unit cost
labour skilled 17.2 nos 930.00 15996.00
un skilled 25.7 nos 675.00 17347.50
a.19mm board 16.5 m2 1350.00 22275.00
b.local wood 0.232 m3 36000.00 8352.00
c.metal pipe 4.4 no.s 1771.00 7792.40
materials d.nails 25 kg 100.00 2500.00
Actual rate
15% conctractor overhead
Rate per 100m2 Rs. 85402.335 Total (Rs.)
Rate per 1m2 Rs. 854.02335
Rate per sq. ft Rs. 79.3820038296
1011
Reinforcement;analysis for 1 MT
sources Level Qty Unit Rate/unit cost
labour skilled 12 nos 930.00 11160.00
un skilled 12 nos 675.00 8100.00
materials TMT rod 1.05 MT 85000.00 89250.00
Binding wire 10 kg 94.00 940.00
Actual rate
15% conctractor overhead
Rate per MT Rs. 125867.5 Total (Rs.)
Rate per kg Rs. 125.8675
1012
20 mm thick plaster work ;analysis for 100m2
sources Level Qty Unit Rate/unit cost
labour skilled 14 nos 930.00 13020.00
un skilled 19 nos 675.00 12825.00
a.cement 11.4 bags 780.00 8892.00
materials b.sand 2.35 m3 1900.00 4465.00
Actual rate
15% conctractor overhead
Rate per 100m2 Rs. 45082.3 Total (Rs.)
Rate per 1m2 Rs. 450.823
Rate per sq. ft Rs. 41.9042794468
1014
38 mm thickscreeding in 1:2:4 ratio;analysis for 10m2
sources Level Qty Unit Rate/unit cost
labour skilled 1.25 nos 930.00 1162.50
un skilled 2 nos 675.00 1350.00
a.Cement 2.6 bags 780.00 2028.00
materials d.sand 0.18 m3 1900.00 342.00
c.12 mm aggregate 0.36 m3 2085.00 750.60
Actual rate
15% conctractor overhead
Rate per 10m2 Rs. 6478.065 Total (Rs.)
Rate per 1m2 Rs. 647.8065
Rate per sq. ft Rs. 60.2140188132
1015
cement punning in 1:1 ratio;analysis for 100m2
sources Level Qty Unit Rate/unit cost
labour skilled 10.5 nos 930.00 9765.00
un skilled 12 nos 675.00 8100.00
a.Cement 6.32 bags 780.00 4929.60
materials d.sand 0.22 m3 1900.00 418.00
Actual rate
15% conctractor overhead
Rate per 100m2 Rs. 26694.49 Total (Rs.)
Rate per 1m2 Rs. 266.9449
Rate per sq. ft Rs. 24.8126951963
1018
salwood frame ;analysis for 1m3
sources Level Qty Unit Rate/unit cost
labour skilled 34 nos 930.00 31620.00
un skilled 3.4 nos 675.00 2295.00
a.sal wood 1.1 m3 174840.00 192324.00
materials b.hold fast 92 no.s 16.00 1472.00
c. nails/screw 184 no.s 2.00 368.00
Actual rate
15% conctractor overhead
Rate per m3 Rs. 262290.85 Total (Rs.)
Rate per cu. ft Rs. 7432.9568115125
1019
paneled door shutter ;analysis for 1 m2
sources Level Qty Unit Rate/unit cost
labour skilled 1.76 nos 930.00 1636.80
un skilled 0.176 nos 675.00 118.80
a.ready made teak door 1 m2 2230.00 2230.00
materials b.wooden llisti 4 m2 43.29 173.16
c. gum appro. no.s 20.00
d.100 mm hinge 3 no.s 30.00 90.00
e. mortise lock 1 no.s 550.00 550.00
e.100 mm cheskini(door
latch lock) 2 no.s 40.00 80.00
f. screw/nails appro. 50.00
Actual rate
15% conctractor overhead
Rate per 1m2 Rs. 5691.074 Total (Rs.)
Rate per sq. ft Rs. 528.98888
1020
Glass window shutter ;analysis for 1 m2
sources Level Qty Unit Rate/unit cost
labour skilled 0.06 nos 930.00 55.80
un skilled 0.01 nos 675.00 6.75
a.4mm glass 1 m2 450.00 450.00
materials b.wooden llisti 4 m2 43.29 173.16
c. gum appro. no.s 10.00
d.100 mm hinge 1 no.s 30.00 30.00
f. screw/nails 0.15 no.s 100.00 15.00
Actual rate
15% conctractor overhead
Rate per 1m2 Rs. 851.8165 Total (Rs.)
Rate per sq. ft Rs. 79.17688
1021
Distemper paint ;analysis for 100 m2
sources Level Qty Unit Rate/unit cost
labour skilled 8 nos 930.00 7440.00
un skilled 5 nos 675.00 3375.00
materials b.color 9 lt. 357.50 3217.50
Actual rate
15% conctractor overhead
Rate per 100m2 Rs. 16137.375 Total (Rs.)
Rate per 1m2 Rs. 161.37375
Rate per sq. ft Rs. 14.9997908611
1023
1024
PCC M15 (1:3:6) ;analysis for 1m3
sources Level Qty Unit Rate/unit cost
labour skilled 1 nos 930.00 930.00
un skilled 5 nos 675.00 3375.00
a.cement 4.4 bags 780.00 3432.00
b.40mm aggregate 0.65 m2 2075.00 1348.75
c.20mm aggregate 0.24 m3 2085.00 500.40
materials d.10mm aggregate 0.11 m3 2085.00 229.35
d. sand 0.47 m2 1900.00 893.00
e. water 150 lt. 0.25 37.50
Actual rate
15% conctractor overhead
Rate per m3 Rs. 12357.9 Total (Rs.)
Rate per cu. ft Rs. 350.2056475893
1029
emulsion paint ;analysis for 100 m2
sources Level Qty Unit Rate/unit cost
labour skilled 8 nos 930.00 7440.00
un skilled 5 nos 675.00 3375.00
a.aster 8.1 lt. 236.00 1911.60
materials b.color 9 lt. 715.00 6435.00
Actual rate
15% conctractor overhead
Rate per 100m2 Rs. 22035.84 Total (Rs.)
Rate per 1m2 Rs. 220.3584
Rate per sq. ft Rs. 20.4824509221
1016
Roofing with 0.5mm Corrugated CGI Sheet ;analysis for 10m2
sources Level Qty Unit Rate/unit
labour skilled 1 nos 930.00
un skilled 1 nos 675.00
a.
Corrugate
dSheet 12 m2 1238.00
materials d.38mm Bol 33 m3 5.46
Actual rate
15% conctractor overhead
Rate per 10m2 Rs. 19137.17 Total (Rs.)
Rate per 1m2 Rs. 1913.717
Rate per sq. ft Rs. 177.8812
1020
CI Pipe Truss with metal Primer and Enamel Colour;analysis for 1kg
sources Level Qty Unit Rate/unit
CI Pipe Tru 1 kg 150.00
Fabrication
CI Pipe
Truss and
colour In
Installation local 1 kg 31.85
Actual rate
15% conctractor overhead
Rate per 1kg Rs. 209 Total (Rs.)
Sub Total
(C) Total A+B
Sub Total
(C) Total A+B
Item: 2 cm thick (1:4) cement sand mixture with water proof compound
Quantity: 10 Sq.m
Sub Total
(C) Total A+B
472.50
70.88
543.38
337.50
50.63
388.13
540.00
81.00
621.00
Total Cost
126.75
790.83
917.58
137.64
1055.22137
1006
Stone work in 1:6 ratio ;analysis for 1m3
Total Cost sources Level Qty Unit Rate/unit
labour skilled 1.5 nos 930.00
un skilled 2.2 nos 675.00
3015.00 semi skilled 0.2 nos 730.00
a.stone boulder 1.1 m3 1250.00
materials b.sand 0.28 m3 1900.00
9432.00 c. Cement 1.4 bags 780.00
12447.00 Actual rate
1867.05 15% conctractor overhead
14314.0523 Rate per m3 Rs. 6928.75 Total (Rs.)
Rate per cu. ft Rs. 196.351109876
1007
Stone work in 1:4 ratio ;analysis for 1m3
Total Cost sources Level Qty Unit Rate/unit
labour skilled 1.5 nos 930.00
un skilled 2.2 nos 675.00
3352.50 semi skilled 0.7 nos 730.00
a.stone boulder 1.1 nos 1250.00
materials b.sand 0.28 m3 1900.00
10291.34 c. Cement 2 bags 780.00
13643.84 Actual rate
2046.58 15% conctractor overhead
15690.4105 Rate per m3 Rs. 7886.7 Total (Rs.)
Rate per cu. ft Rs. 223.498076602
Total Cost
5469.00
9005.32
14474.32
2171.15
16645.4674
Total Cost
5469.00
7768.14
13237.14
1985.57
15222.7067
m2
Total Cost
33343.50
40919.40
74262.90
11139.44
85402.335
Total Cost
19260.00
90190.00
109450.00
16417.50
125867.5
Total Cost
25845.00
13357.00
39202.00
5880.30
45082.3
m2
Total Cost
2512.50
3120.60
5633.10
844.97
6478.065
Total Cost
17865.00
5347.60
23212.60
3481.89
26694.49
Total Cost
33915.00
194164.00
228079.00
34211.85
262290.85
Total Cost
1755.60
3193.16
4948.76
742.31
5691.074
Total Cost
62.55
678.16
740.71
111.11
851.8165
Total Cost
10815.00
3217.50
14032.50
2104.88
16137.375
Total Cost
4305.00
6441.00
10746.00
1611.90
12357.9
Total Cost
10815.00
8346.60
19161.60
2874.24
22035.84
alysis for 10m2
cost Total Cost
930.00
675.00 1605.00
14856.00
180.02 15036.02
16641.02
2496.15
19137.17
31.85 31.85
181.85
27.28
209.1275
2,555.00
465.00
3,020.00
9,516.00
807.50
1,334.40
437.85
75.00
289.50
10.80
1,125.00
25.00
13,621.05
16,641.05
2,496.16
19,137.21
o (Floor tile)
9,490.00
4,185.00
13,675.00
288.80
873.60
13,750.00
76.67
14,989.07
28,664.07
4,299.61
32,963.67
2,106.00
342.00
519.23
2,967.23
4,258.73
638.81
4,897.54
nalysis for 1m3
cost Total Cost
1395.00
1485.00
146.00 3026.00
1375.00
532.00
1092.00 2999.00
6025.00
903.75
6928.75
nalysis for 1m3
cost Total Cost
1395.00
1485.00
511.00 3391.00
1375.00
532.00
1560.00 3467.00
6858.00
1028.70
7886.70
1001
Earthwork in excavation and disposal wi
sources Level Qty
labour unskilled 0.7
Actual rate
Rate per m3 Rs. 466.90 15% conctractor overhead
Rate per cu. ft Rs. 13.23129 Total (Rs.)
1002
Earthwork in backfilling (with earth availabl
sources Level Qty
labour unskilled 0.5
Actual rate
Rate per m3 Rs. 333.50 15% conctractor overhead
Rate per cu. ft Rs. 9.450925 Total (Rs.)
1003
Earthwork in backfilling (with imported e
sources Level Qty
labour unskilled 0.8
Actual rate
Rate per m3 Rs. 533.60 15% conctractor overhead
Rate per cu. ft Rs. 15.12148 Total (Rs.)
1004
Flat Brick soling works ;analy
sources Level Qty
labour skilled 0.1
un skilled 0.05
materials a.local bri 44
b. sand fill 0.07
Actual rate
15% conctractor overhead
Rate per m2 Rs. 1193.125 Total (Rs.)
Rate per sq. ft Rs. 110.9017
1006
Brick work in 1:6 ratio ;analy
sources Level Qty
labour skilled 1.5
un skilled 2.2
un skilled 0.2
a.Brick 530
materials b.sand 0.3
c. Cement 1.4
Actual rate
15% conctractor overhead
Rate per m3 Rs. 15224.85 Total (Rs.)
Rate per cu. ft Rs. 431.451
1007
Brick work in 1:4 ratio ;analy
sources Level Qty
labour skilled 1.5
un skilled 2.2
un skilled 0.7
a.Brick 560
materials b.sand 0.28
c. Cement 2
Actual rate
15% conctractor overhead
Rate per m3 Rs. 16610.6 Total (Rs.)
Rate per cu. ft Rs. 470.7212
1008
PCC M20 (1:1.5:3) ;analysis for 1m3
sources Level Qty
labour skilled 0.8
un skilled 7
a.cement 8
b.20mm ag 0.57
materials c.10mm ag 0.29
c. sand 0.425
d. water 200
Actual rate
15% conctractor overhead
Rate per m3 Rs. 18894.21 Total (Rs.)
Rate per cu. ft Rs. 535.4356
1009
PCC M15 (1:2:4) ;analysis for 1m3
sources Level Qty
labour skilled 0.8
un skilled 7
a.cement 6.4
b.40mm ag 0.52
c.20mm ag 0.22
materials d.10mm ag 0.11
d. sand 0.445
e. water 150
Actual rate
15% conctractor overhead
Rate per m3 Rs. 17168.06 Total (Rs.)
Rate per cu. ft Rs. 486.5189
1010
Plywood and Pipe post Formwork;analy
sources Level Qty
labour skilled 17.2
un skilled 25.7
a.19mm bo 16.5
b.local wo 0.232
c.metal pip 4.4
materials d.nails 25
Actual rate
15% conctractor overhead
Rate per 100m2 Rs. 82094.94 Total (Rs.)
Rate per 1m2 Rs. 820.9494
Rate per sq. ft Rs. 76.30775
1011
Reinforcement;analysis for 1 MT
sources Level Qty
labour skilled 12
un skilled 12
materials TMT rod 1.05
Binding wi 10
Actual rate
15% conctractor overhead
Rate per MT Rs. 121313.5 Total (Rs.)
Rate per kg Rs. 121.3135
1012
20 mm thick plaster work ;analysis f
sources Level Qty
labour skilled 14
un skilled 19
a.cement 11.4
materials b.sand 2.35
Actual rate
15% conctractor overhead
Rate per 100m2 Rs. 45591.18 Total (Rs.)
Rate per 1m2 Rs. 455.9118
Rate per sq. ft Rs. 42.37728
1014
38 mm thickscreeding in 1:2:4 ratio;anal
sources Level Qty
labour skilled 1.25
un skilled 2
a.Cement 2.6
materials d.sand 0.18
c.12 mm a 0.36
Actual rate
15% conctractor overhead
Rate per 10m2 Rs. 6979.35 Total (Rs.)
Rate per 1m2 Rs. 697.935
Rate per sq. ft Rs. 64.87349
1015
cement punning in 1:1 ratio;analysis
sources Level Qty
labour skilled 10.5
un skilled 12
a.Cement 6.32
materials d.sand 0.22
Actual rate
15% conctractor overhead
Rate per 100m2 Rs. 24976.39 Total (Rs.)
Rate per 1m2 Rs. 249.7639
Rate per sq. ft Rs. 23.21571
1018
salwood frame ;analysis
sources Level Qty
labour skilled 34
un skilled 3.4
a.sal wood 1.1
materials b.hold fast 92
c. nails/sc 184
Actual rate
15% conctractor overhead
Rate per m3 Rs. 243454.5 Total (Rs.)
Rate per cu. ft Rs. 6899.162
1019
paneled door shutter ;analys
sources Level Qty
labour skilled 1.76
un skilled 0.176
a.ready ma 1
materials b.wooden ll 4
c. gum appro.
d.100 mm 3
e. mortise 1
e.100 mm
cheskini(d
oor latch
lock) 2
f. screw/na appro.
Actual rate
15% conctractor overhead
Rate per 1m2 Rs. 9626.524 Total (Rs.)
Rate per sq. ft Rs. 894.7914
1021
Distemper paint ;analysis f
sources Level Qty
labour skilled 8
un skilled 5
materials b.color 9
Actual rate
15% conctractor overhead
Rate per 100m2 Rs. 14685.5 Total (Rs.)
Rate per 1m2 Rs. 146.855
Rate per sq. ft Rs. 13.65026
1023
1024
PCC M15 (1:3:6) ;analysis for 1m3
sources Level Qty
labour skilled 1
un skilled 5
a.cement 4.4
b.40mm ag 0.65
c.20mm ag 0.24
materials d.10mm ag 0.11
d. sand 0.47
e. water 150
Actual rate
15% conctractor overhead
Rate per m3 Rs. 13869 Total (Rs.)
Rate per cu. ft Rs. 393.0281
1029
emulsion paint ;analysis fo
sources Level Qty
labour skilled 8
un skilled 5
a.aster 8.1
materials b.color 9
Actual rate
15% conctractor overhead
Rate per 100m2 Rs. 24387.59 Total (Rs.)
Rate per 1m2 Rs. 243.8759
Rate per sq. ft Rs. 22.66842
1016
Roofing with 0.5mm Corrugated CG
sources Level
labour skilled
un skilled
a. Sheet
materials d.38mm Bol
1020
CI Pipe Truss with metal Primer a
sources Level
Fabricatio CI Pipe Tru
n
CI Pipe
Truss and
colour In
Intallation local
S.N. Descripitio
(A) Labours
Semi Skill
Skilled
(B) Material
Cement
Sand
Aggregate
Aggregate
water
Diesel
Petrol
Mixture
Viberator
S.N. Descripitio
(A) Labours
Semi Skill
Skilled
(B) Material
Sand
Cement
Ceramic til
White Cem
S.N. Descripitio
(A) Labours
Semi Skill
Skilled
(B) Material
Cement
Sand
Water pro
12 m2 475.59 5707.07
33 m3 5.46 180.02 5887.08
Actual rate 7187.08
15% conctractor overhead 1078.06
Total (Rs.) 8265.145
Pipe Truss with metal Primer and Enamel Colour;analysis for 1kg
Qty Unit Rate/unit cost Total Cost
1 kg 150.00 150.00
150.00
CC in Proportion1:1:2