TNB Tech Guidebook For The Connection of Generation To The Distn Network PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 188

Tenaga Nasional Berhad TNB Research

First Edition, March 2005

Technical Guidebook for


the Connection of Generation to
the Distribution Network

Prepared by:

TNB Research Sdn. Bhd.

in Collaboration with:

APS Sdn. Bhd., Malaysia


RWE Npower plc, United Kingdom

-1–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Table of Contents
TABLE OF CONTENTS ........................................................................................ 2
CONTRIBUTORS .............................................................................................. 7
PREFACE
PREFACE....................................................................................................... 8
CHAPTER 1: INTRODUCTION
INTRODUCTION...............................................................................10
1.1 BACKGROUND ....................................................................................................................10
1.2 OBJECTIVES OF THE GUIDEBOOK ............................................................................................11
1.3 DEFINITIONS OF KEY TERMS USED IN THE GUIDEBOOK ..............................................................12
1.4 GUIDEBOOK APPROACH .......................................................................................................13
1.5 STATUTORY ACTS, REGULATIONS, RULES AND CODES ..............................................................14
1.6 SCOPE OF THE GUIDEBOOK ...................................................................................................14
1.7 USING THIS GUIDEBOOK .......................................................................................................15
1.8 CONTENTS OF THE GUIDEBOOK ..............................................................................................15
CHAPTER 2: PROCESS FOR GETTING CONNECTED
CONNECTED.....................................................17
2.1 SUMMARY OF PROCESS .......................................................................................................17
2.2 PROJECT PLANNING ............................................................................................................20
2.3 EXCHANGE OF PLANNING INFORMATION & PRELIMINARY STUDY.................................................21
2.4 PROJECT DESIGN ................................................................................................................22
2.5 PROJECT CONSTRUCTION .....................................................................................................23
2.6 PROJECT TESTING AND COMMISSIONING ................................................................................23
2.7 DG OPERATION ..................................................................................................................23
CHAPTER 3: TECHNICAL ISSUES AND REQUIREMENTS FOR CONNECTION ........................24
3.1 RESPONSIBILITIES OF THE DISTRIBUTORS TO CUSTOMERS AND THE DGS .....................................24
3.2 QUALITY OF SUPPLY REQUIREMENTS .....................................................................................24
3.3 TECHNICAL ISSUES..............................................................................................................28
3.4 VOLTAGE CONTROLS AND REGULATIONS .................................................................................28
3.5 FAULT LEVELS ....................................................................................................................32
3.6 NETWORK/FEEDER CAPACITY AND SECURITY ASSESSMENTS ......................................................34
3.7 SUPPLY QUALITY – RELIABILITY AND POWER QUALITY .............................................................38
3.8 PROTECTION AND CONTROLS ................................................................................................39
3.8.1 General
General.......................................................................................................................39
3.8.2 Short term Occasional Parallel Operation ................................................................40
3.8.3 Loss of Mains
Mains.............................................................................................................40
3.8.4 Auto-reclosing
Auto-reclosing............................................................................................................42
3.8.5 Islanded Operation
Operation.....................................................................................................42
3.9 LOSSES .............................................................................................................................44
3.10 EARTHING AND USE OF INTERFACE TRANSFORMERS ...................................................................46
3.11 STABILITY .........................................................................................................................47
3.12 OVER VOLTAGES AND RESONANT OVER-VOLTAGE ......................................................................47
3.13 DATA REQUIREMENTS..........................................................................................................48
3.14 SAFETY .............................................................................................................................48

-2–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

CHAPTER 4: PLANNING, CONNECTION AND OPERATION OF THE DGS


DGS..............................50
4.1 INTRODUCTION ...................................................................................................................50
4.2 PRELIMINARY PLANNING STUDY ...........................................................................................50
4.2.1 Objective ....................................................................................................................50
4.2.2 Connection Facilities Under the Distributor’s Responsibility...................................51
4.2.3 Basic Connection Issues Issues............................................................................................54
4.2.4 Preliminary System Study Procedure Procedure........................................................................55
4.2.5 Basic Protection, Control, Metering and Monitoring Requirements ........................56
4.2.6 Preliminary System Study Report .............................................................................56
4.3 POWER SYSTEM STUDY .......................................................................................................57
4.3.1 Objectives: .................................................................................................................57
4.3.2 Data Requirements ....................................................................................................57
4.3.3 Power System Study Methods and Analyses.............................................................58
4.3.4 Additional Analysis in Power System Study..............................................................59
4.3.5 Power System Study Report and Liaison ..................................................................62
4.4 CONNECTION OF THE DG PLANT TO THE DISTRIBUTION NETWORK ...............................................62
4.4.1 Connection Point and Connection Process................................................................62
4.4.2 Protection Coordination Study...................................................................................62
4.4.3 Protective Equipment Tests and Settings Settings..................................................................64
4.4.4 Inspection and Pre-Commissioning Tests Tests.................................................................65
4.4.5 Commissioning Procedure
Procedure.........................................................................................66
4.4.6 Plant Commissioning and Tests Tests................................................................................67
4.4.7 Establishment of ‘Connection Operation Manual’ Manual’.....................................................68
4.5 OPERATION OF THE DG PLANT WITH THE DISTRIBUTION NETWORK .............................................70
4.5.1 Control Operation.......................................................................................................70
4.5.2 DG Operating Modes..................................................................................................70
4.5.3 Distribution Operation Planning ................................................................................72
4.5.4 Exchange of Operational Information........................................................................72
4.5.5 Operating and Safety Requirements .........................................................................74
CHAPTER 5: INTERFACE DESIGN REQUIREMENTS AND NETWORK REINFORCEMENTS
REINFORCEMENTS..........75
5.1 INTRODUCTION ...................................................................................................................75
5.2 BASIC CONNECTION INTERFACE REQUIREMENTS .......................................................................76
5.2.1 Isolation .....................................................................................................................76
5.2.2 Connection through Star-Delta Transformer .............................................................77
5.3 UTILITY ACCESS .................................................................................................................78
5.4 SYNCHRONISATION .............................................................................................................79
5.5 PROTECTION AND CONTROL ..................................................................................................80
5.5.1 Protection
Protection...................................................................................................................80
5.5.2 Controls
Controls......................................................................................................................82
5.6 INTERLOCKING....................................................................................................................84
5.8 SCADA AND AUTOMATION ...................................................................................................86
5.9 COMMUNICATIONS ..............................................................................................................87
CHAPTER 6: GLOSSARY ....................................................................................89
6.1 GENERAL TERMS ................................................................................................................89
6.2 OTHER TERMS .................................................................................................................101

-3–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

7. APPENDIX A: SUMMARY OF TNB POWER SYSTEMS


SYSTEMS........................................... 108
7.1 INDUSTRY STRUCTURE ......................................................................................................108
7.1.1 A Brief History of Electricity Industry in Malaysia...................................................108
7.1.2 Electricity Industry Reform ......................................................................................108
7.1.3 Renewable Energy (RE) and The Small Renewable Energy Programme (SREP) ..108
7.1.4 Current structure of electricity industry...................................................................108
7.1.5 Regulation and Licensing ........................................................................................110
7.2 POWER GENERATION .........................................................................................................111
7.2.1 Generation Entities ..................................................................................................111
7.2.2 Generation Mix.........................................................................................................111
7.2.3 Self Generation and Co-generation .........................................................................112
7.3 TRANSMISSION AND POWER SYSTEM OPERATION ..................................................................112
7.3.1 Transmission System...............................................................................................112
7.3.2 Power System Operation .........................................................................................114
7.3.2.1 Load forecasting ...............................................................................................114
7.3.2.2 Planning & Investment......................................................................................114
7.3.2.3 Operational planning .........................................................................................115
7.3.2.4 Control operation (NLDC) .................................................................................115
7.3.3 Control of System Frequency...................................................................................115
7.3.4 Control of System Voltage .......................................................................................115
7.4 DISTRIBUTION ..................................................................................................................116
7.4.1 Distribution Organisations.......................................................................................116
7.4.2 Voltages ...................................................................................................................116
7.4.3 Protection in Distribution Networks.........................................................................116
7.4.3.1 Fault and fault current .......................................................................................116
7.4.3.2 Protection system .............................................................................................117
7.4.3.3 Fault level and equipment rating .......................................................................117
7.4.4 Distribution Network Planning.................................................................................118
7.4.5 Control and Operation of Distribution Network .......................................................118
8. APPENDIX B: TYPES OF DGS ...................................................................... 120
8.1 INTRODUCTION .................................................................................................................120
8.1.1 Energy Source ..........................................................................................................120
8.2 HYDROPOWER ..................................................................................................................120
8.3 FUEL CELLS .....................................................................................................................122
8.4 LANDFILL GAS ..................................................................................................................123
8.5 WIND POWER ..................................................................................................................123
8.6 MICROTURBINES...............................................................................................................125
8.7 GEOTHERMAL ...................................................................................................................125
8.8 PHOTOVOLTAIC .................................................................................................................126
8.9 COGENERATION ................................................................................................................126
8.9.1 Definitions of Cogeneration.....................................................................................126
8.9.2 Cogeneration plants in Malaysia.............................................................................128
8.9.3 Description of Cogeneration Technologies .............................................................130
8.9.3.1 Back-pressure steam turbine ................................................................................130
8.9.3.2 Pass-out condensing steam turbine......................................................................131
8.9.3.3 Gas Turbine...........................................................................................................131

-4–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

9. APPENDIX C: DATA AVAILABLE AND TO BE SUBMITTED ...................................... 133


9.1 DATA AVAILABLE FROM TNB AT THE INITIAL STAGE ................................................................133
9.2 DATA TO BE SUBMITTED BY DG DEVELOPER FOR ‘PRELIMINARY SYSTEM STUDY’ – ES.08.01 ......134
9.3 DATA TO BE SUBMITTED FOR ‘POWER SYSTEM STUDY’ – ES.08.03..........................................135
10. APPENDIX D: TNB DISTRIBUTION PLANNING CRITERIA
CRITERIA.................................... 139
10.1 INTRODUCTION .................................................................................................................139
10.2 DISTRIBUTION NETWORK DESIGN PHILOSOPHY .....................................................................139
10.3 NETWORK CAPACITY AND REINFORCEMENT NEEDS .................................................................139
10.4 DISTRIBUTION SYSTEM PLANNING/DESIGN CRITERIA ..............................................................140
10.4.1 Steady State Criteria............................................................................................140
10.4.2 Steady State Voltage limits .................................................................................140
10.4.3 Thermal Ratings Limits .......................................................................................141
10.4.4 Fault Level Ratings Limits (Short-circuit Rating) ...............................................141
10.4.5 Frequency Limits .................................................................................................141
10.4.6 Security of Supply Criteria under Contingency Situation....................................141
10.4.6.1 Network Reliability ............................................................................................141
10.4.6.2 Urban/Sub-Urban Medium Voltage Distribution Feeders ..................................141
10.4.6.3 Rural Medium Voltage Distribution Feeders (<1 MVA)......................................142
10.4.6.4 Low Voltage Distribution Networks...................................................................142
10.4.7 Power Quality Criteria .........................................................................................142
10.4.7.1 Power quality under steady-state conditions ....................................................142
10.4.7.2 Power quality during transient disturbance conditions .....................................142
10.4.7.3 System Frequency.............................................................................................142
10.4.7.4 TNB Power Quality Compatibility Limits............................................................143
TABLE 10.1 - TNB POWER QUALITY COMPATIBILITY STANDARDS AND GUIDELINES ................................143
10.4.8 Conductor Selection Criteria................................................................................144
11. APPENDIX E: SYSTEM STUDIES ASSOCIATED WITH THE CONNECTION OF THE DG ... 145
11.1 INTRODUCTION .................................................................................................................145
11.2 PRELIMINARY SYSTEM STUDY ............................................................................................146
11.2.1 Generating unit data ............................................................................................146
11.2.2 Review/Update Network Model ...........................................................................149
11.2.3 Connecting DG Plant and Modelling Approach ...................................................150
11.2.4 Network Voltage Profile.......................................................................................152
11.2.4.1 Voltage Profile Without the DG .........................................................................153
11.2.4.2 Voltage Profile DG at the end of feeder .............................................................154
11.2.4.3 Voltage Profile DG at the mid of feeder ...............................................................155
11.2.4.4 Voltage Profile DG at the source of feeder ........................................................156
11.2.4.5 Voltage Profile DG at end of feeder with additional 11kV feeder .........................157
11.2.4.6 Voltage Profile DG at end of feeder with 33kV feeder connection .....................158
11.2.5 System Losses .....................................................................................................160
11.2.5.1 Losses DG at the end of the feeder ...................................................................160
11.2.5.2 Losses DG at the mid of the feeder ...................................................................161
11.2.5.3 Losses DG at the source of the feeder ..............................................................162
11.2.6 Short-Circuit Analysis ..........................................................................................163
11.2.7 System/Feeder Adequacy ....................................................................................165

-5–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

11.3 POWER SYSTEM STUDY .....................................................................................................167


11.3.1 Stability Analysis .................................................................................................167
11.3.1.1 Models for Excitation Control..............................................................................167
11.3.1.2 Models for Speed-Governor................................................................................167
11.3.1.3 PSS/ADEPT Network Model to PSS/E Dynamics.................................................167
11.3.1.4 Stability Analysis.................................................................................................171
11.3.2 Insulation Coordination Analysis.........................................................................172
12. APPENDIX F: PROTECTION AND CONTROL REQUIREMENTS .............................. 173
12.1 INTRODUCTION .................................................................................................................173
12.2 TYPES OF PROTECTION REQUIREMENTS ................................................................................173
12.3 DISTRIBUTED GENERATOR PROTECTION SCHEME ...................................................................177
12.4 SUMMARY OF TNB’S DISTRIBUTION PROTECTION PRACTICES ..................................................178
12.4.1 General Requirement...........................................................................................178
12.4.1.1 Maximum Fault Clearing Time, Operating and Reset Time................................178
12.4.1.2 Protection Relays
Relays..............................................................................................178
12.4.2 Protection Scheme Policy....................................................................................179
12.4.2.1 Overhead Line Feeder Protection ......................................................................179
12.4.2.2 Underground Cable Feeder Protection ..............................................................179
12.4.2.3 Transformer Protection
Protection.....................................................................................180
12.4.2.4 Busbar Protection ...............................................................................................181
12.5 COORDINATION BETWEEN DG AND DISTRIBUTION PROTECTION .................................................181
12.6 SCADA/DA REQUIREMENTS ..............................................................................................182
12.6.1 Basic SCADA ........................................................................................................182
12.6.2 SCADA Practices in TNB and Requirements .......................................................182
12.6.3 Master System .....................................................................................................183
12.6.3.1 Master Station.
Station.....................................................................................................184
13. APPENDIX G: CONNECTION AGREEMENT ..................................................... 185
13.1 GENERAL .........................................................................................................................185
13.2 CONNECTION AGREEMENT ..................................................................................................185
13.2.1 Description of Facility and Site. ..........................................................................185
13.2.2 Design & Operations Standard ............................................................................186
13.2.3 Energy Accounting and Metering Equipment. .....................................................186
13.2.4 Interconnection Facilities....................................................................................186
13.5.2 Communication Facilities....................................................................................187
13.5.3 Electricity Characteristics....................................................................................187
13.3 CONNECTION OPERATION MANUAL............................................................................................188

-6–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Contributors
Many individuals have made contributions to the Guidebook. However, the following
persons have made major contributions and deserve to be recorded here:

No Name Organisation
1 Halim Osman TNB Distribution
2 Dr. Fadzil Mohd Siam TNB Research
3 Dr. Sallehhudin Yusof APS Sdn. Bhd.
4 Hamzah Ngah RWE Npower, plc
5 Abu Hanifah Azit TNB IT
6 Abdul Aziz Majid TNB Distribution
7 Loo Chin Koon TNB Distribution
8 Asnawi TNB Research

-7–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Preface

This “Technical Guidebook for the Connection of Generation to the Distribution


Network” published by Tenaga Nasional Berhad (TNB) is intended to be used by DG
(Distributed Generation) Developers, Plant Managers/Engineers, Consultants and Utility
Engineers as guidelines for the planning of the connection of a distributed generation to
the distribution network. This Guidebook will be applicable from March 2005.

The focus of this Guidebook is on connection planning of DG Plants to the distribution


network. However, a good plan always takes into consideration other related issues
particularly DG plant operation. Therefore, if other ancillary subjects apart from
planning of connections are discussed, the intention is complementary thus may not be
dealt with in full.

In this Guidebook, Distributed Generation (DG) Plant is defined as a plant comprising of


one or more generating units that is connected to the distribution network at the
medium voltage level and whose total power output will be scheduled at all times to be
totally consumed by loads in that distribution network (see chapter 1). The types of
generating units addressed in this Guidebook include both synchronous and
asynchronous.

The Guidebook first discusses typical steps involved in connecting DG plant to the
distribution network (see chapter 2). The process starts with the DG Developer
contacting TNB district or regional offices right up to testing and commissioning as well
as identifying list of requirements for successful operation of the plant.

Before discussing the requirements for connection of the DG plant to the distribution
network, technical issues are discussed so that their understanding will lead to an
appreciation on how each of the issues is resolved (in chapter 3).

Not all technical issues are required to be resolved unless they cause problems to the
distribution network and its customers. The Guidebook in chapter 4 discusses how
planning and design studies are carried out and how each of the technical issues is
identified, assessed and resolved. The chapter also discusses how connection is
established and the operation of the DG with the distribution network.

The Guidebook summarises interface requirements and possible distribution network


reinforcements in chapter 5. Chapter 6 defines all the terms used in the Guidebook.
Appendices A through G are provided to support main chapters of the Guidebook.
These appendices contain detailed technical contents of the subjects discussed
including case studies and worked examples.

Although, the Guidebook is comprehensive in its contents, it is not intended to present


total solutions to all design and connection issues. It is also not intended to be
prescriptive, thus Distributors, Developers and Consultants have still to work on
mutually acceptable, safe and optimal solution for every case.

-8–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Chapter 1 – Introduction
Objectives, basic definitions, scope, summary of
contents

Chapter 2 – Procedures for Getting Connected


Describes steps involved in process of getting
connected from initial contact with TNB to
testing/commissioning and operation

Chapter 3 – Technical Issues Associated with


Connections of Distributed Generation
Describes all possible technical issues that may
arise with the connection of DG to the distribution
network

Chapter 4 – Planning, Connection and Operation


of the DGs
Describes planning and design approaches to
identify issues and resolve them. Discusses how
issues are tackled during connection and operation.

Chapter 5 – Interface Design Requirements and


Network Reinforcements
Summarises interface requirements including typical
network reinforcements.

Chapter 6 – Glossary
Definition of terms

Appendix A – G
Supporting chapters, detailed methods/procedures
and case studies

Summary of the Contents of the Guidebook

-9–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Chapter 1: Introduction

1 .1 Background

1.1.1 In 1996 Tenaga Nasional Berhad (TNB) published a document entitled


“Technical Guidebook for the Interconnection of Distribution Generators to
TNB’s Medium Voltage Distribution Network”, hereafter referred to as the “1996
Interconnection Guidebook”. Since then rapid development of distributed
generation (DG) coupled with experience gained in planning, design and
operation by both TNB and DG Developers/Operators have compelled the
electricity industry to review the technical guidelines for the connection of the
DGs to ensure some transparencies in the processes and removal of any
foreseeable technical barriers. Furthermore, in the country’s recently revised
Fuel Diversification Policy, the use renewable energy (RE) has been intensified
and incorporated as the fifth fuel that obliges the electricity distribution industry
players to encourage connections of RE-based DGs to the distribution network
to make the policy a success1.

1.1.2 This Guidebook is a complete revision of the “1996 Interconnection Guidebook”


and has incorporated all the important issues to be addressed before connecting
of a DG to the distribution network. The approach to this revised Guidebook is to
have chapters briefly addressing all issues. Where necessary, the appendices
will elaborate on the subject matter supplemented with case studies. Prior to
the launching of this review work, DG stakeholders have participated in two
workshops and one meeting that resulted in a list of technical and commercial
issues that need to be addressed further. Many of the technical issues and
selected commercial concerns are addressed in this Guidebook.

1.1.3 This “Technical Guidebook for the Connection of Generation to the Distribution
Network” (“the DG Guidebook” or ”the DG Connection Guidebook”) is intended
for use mainly by DG Developers and Distribution Utility engineers for planning,
design and operation of the DGs. Since the Guidebook will also cover all
possible types of synchronous/asynchronous generator connections to the
distribution network, either directly or indirectly, it is also a useful reference to
consulting engineers, factory engineers and plant operators.

1.1.4 There are many tasks to be carried out and issues to be addressed in order to
successfully implement a DG Plant project. This Guidebook focuses only on
connection of DG Plant to the distribution network. Technical matters associated
with energy conversion, mechanical design of DG plant, environmental
protection, etc. is beyond the scope of this Guidebook. However, in order to
make clear some issues, other supplementary subjects not explicitly related to
connection may also be discussed.
1. Refer “Guidelines on Small Renewable Energy Programme (SREP)”, Suruhanjaya Tenaga, Malaysia, not
dated.

- 10 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

1.1.5 The DG Guidebook has been written based on the prevalent electricity industry
structure in Peninsular Malaysia, its regulatory framework and utility industry
practices. The industry structure, regulation and practices may change from time
to time and when necessary relevant parts of this Guidebook will be revised
accordingly.

1 .2 Objectives of the Guidebook

1.2.1 The main objective of this DG Connection Guidebook is to provide guidance on


the step-by-step process and procedures involved from DG Developers initiation
of distributed generation to its connection to the distribution network as well as
its commissioning and operation. The Guidebook is designed to give guidance
on all technical aspects of the DG connection and may therefore have different
objectives from the perspectives of DG Developers or Utility Engineers.

1.2.2 DG Developers/Operators may use this Guidebook for several purposes,


including:

a) To understand how electricity distribution system works;


b) To identify what information and their details that can be obtained from TNB
with respect to connecting a DG plant;
c) To find out what types of schemes and equipment required for connecting
the DG to distribution network and why they are necessary;
d) To understand what supply quality standards are imposed by the Regulator
on a utility like TNB and how a DG could contribute either positively or
negatively to supply quality and security;
e) To understand how a utility like TNB carries out planning studies to
dimension the interface connection and why reinforcements in the
distribution network may become necessary; and
f) To understand how a DG is operated with the distribution network and how
operational planning is carried out.

1.2.3 Utility planning, design and operation engineers could refer to the DG
Guidebook for several purposes but not limited to the following:

a) To find out what information could be requested from DG Developers;


b) To check compliance of the DG interface design with the standard
requirements;
c) To find out what typical parameters could be used to model the DG plant for
the purposes of studies when first proposed by the Developer;
d) To identify the proper steps and methods to be used in conducting system
studies and the timescales involved;
e) To establish cost estimates of connection to be provided to the DG
Developer; and
f) To find out what options could be used to resolve technical problems
identified during planning and design analysis.

- 11 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

1 .3 Definitions of Key Terms Used in the Guidebook

1.3.1 Distributed Generation (DG) or Embedded Generation (EG) is defined as the


production of electrical power by converting another form of energy in a
generating unit that is connected to a distribution system. In this Guidebook, a
DG Plant is defined “as a generating plant comprising of one or more generating
units that is connected to the distribution network at the medium voltage level
and whose total power output will be scheduled at all times to be totally
consumed by loads in that distribution network”. As illustrated in Figure 1.1, the
output power of the DG is scheduled not to spill over to the transmission
network to avoid reverse power flow at the interface of transmission and
distribution networks.

Distribution Network

Power Flow

Transmission
Network

Power Flow

G
Load
Distributed
Generation

Figure 1.1: Distributed generation

1.3.2 In practice the total capacity of a DG Plant connected to the medium voltage
network could vary from hundreds of kW to 20MW as long as the generated
power does not at any time spill over to the transmission network. However, any
generating plant intended to be connected to the Transmission Grid (Grid
System) must be referred to the Grid System Operator (currently assumed by the
System Planning Department of TNB).

1.3.3 Distributed or Embedded Generating Unit is a generating unit connected within a


distribution network and not having direct access to the transmission network.
This includes an Embedded Generator connected to its own network whose
network is interconnected with the Distribution network either directly or through
an interface transformer.

- 12 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

1.3.4 A Distribution Network is defined as a system comprising of electrically


connected equipment or elements that produce, transport, transform, control,
and consume electrical power at medium and low voltage levels not greater than
33kV nominal.

1.3.5 A Distribution System is defined as a system consisting (wholly or mainly) of


electrical lines which are owned and operated by a Distributor and used for the
distribution of electricity from Grid Supply points or Generating Units or other
entry points to the point of delivery to Customers or Other Distributors.

1.3.6 A Distribution System Operator or Distributor is a person or organisation who is


responsible for the management of any portion of a distribution system or for
directing its operations during normal or emergency conditions.

1.3.7 A Distributed Generation Developer (DG Developer) is a person or organisation


who develops or owns a generating plant that is intended to be connected to the
distribution network.

1.3.8 A Distributed Generation Operator (DG Operator) is a person or organisation who


is responsible for the management, operation, maintenance and safety of a
generating plant and its associated network connected to the distribution
network.

1.3.9 A Renewable Energy Plant (RE Plant)1 is a DG Plant that is categorized under the
Small Renewable Energy Programme (SREP) that is being coordinated by a
Special Committee on Renewable Energy (SCORE).

1.3.10 Medium Voltage or MV is any voltage equal to or exceeding 1kV but not
exceeding nominal 33 kV. Low Voltage or LV is any voltage level less than 1000
volts or 1 kV.

1.3.11 Grid System or the Grid is the system consisting (wholly or mainly) of high
voltage, namely nominal 500kV, 275kV, 132kV, and 66kV transmission lines
owned and operated by Tenaga Nasional Berhad (TNB) and used for the
transmission of electricity from one power station to a substation or to another
power station or between substations or to or from any external interconnection,
and includes any Plant and Apparatus and meters owned or operated by TNB in
connection with the transmission of electricity.

1 .4 Guidebook Approach

1.4.1 The Guidebook is written to address all possible technical issues associated
with the connection of the DGs to the distribution network. All these technical
issues will at least be discussed in one of the five chapters of this Guidebook
and the details of which would be provided in the appendices, if necessary. In
other words, the first five chapters contain pointers to more detail account of the
subjects related to connections of the DGs.

- 13 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

1.4.2 The Guidebook is structured to allow for any amendment to the detailed
technical contents and the case studies be updated separately and
independently through the additions or amendments of the appendices.

1 .5 Statutory Acts, Regulations, Rules and Codes

1.5.1 This Guidebook may also refer to relevant legal documents that exist in Malaysia
including acts, regulations, codes, rules and guidelines. Since these documents
are subject to revision and amendments by the appropriate authority, readers
should always ensure that they consult the latest versions.

1.5.2 The relevant safety, electricity production, transmission, distribution and supply
licensing, legal and regulatory requirement are mandatory and nothing in the
Guidebook shall be taken to relieve these legal or regulatory obligations in the
provisions of:
1) The Electricity Supply Act 1990;
2) The Occupational Safety and Health Act 1994;
3) The Electricity Regulations 1994;
4) The Environmental Quality Act 1974;
5) Factories and Machinery (Noise Exposure) Regulation 1989;
6) Licence issued by the Suruhanjaya Tenaga to industry players;
7) The Malaysian Grid Codes;
8) TNB's Safety Regulation;
9) The Malaysian Distribution Code (when available).
With respect to the "The Environmental Quality Act 1974", only relevant
provision shall be applied to DG Plant such as effluent discharge (under
Environment Quality (Prescribe Premises - Crude palm Oil) Regulation 1977),
Emission (under Environmental Quality (Clean Air) Regulation 1978) addressing
issues such as open burning.

1.5.3 There are also guidelines published by authorities including the Ministries and
the Energy Commission that are complementary to this Guidebook and therefore
DG Developers and Utility Engineers are encouraged to refer to those
documents.

1.5.4 A DG plant that is to be connected to the distribution network must be designed


to be compatible with the particular distribution network to which it is to be
connected and the Grid System.

1 .6 Scope of the Guidebook

1.6.1 This Guidebook addresses technical issues associated with the connection of a
DG to the distribution network. Therefore, commercial issues are not addressed
except those necessary without which the subject cannot be fully dealt with.

1.6.2 There are many other issues that will not be addressed by this Guidebook
because they are only the concern of either the Developer or the Distributor and

- 14 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

not with the connection. Issues such as: identifying and obtaining fuel supplies,
project financing, power sales and purchase negotiations, DG plant design,
getting approval of local authorities, land matters etc. are some of the subjects
not covered by this Guidebook.

1 .7 Using this Guidebook

1.7.1 If you have reached this point of the book you should by now have basic
understanding of the background to the Guidebook and its objectives. Chapter 2
outlines the general procedures for getting connected and therefore is referred
to as the root of the Guidebook from which all other chapters and appendices
are referred to.

1.7.2 After understanding the basic procedures for getting connected, a reader may
then refer directly to the relevant chapters and appendices for details. To scan
through all technical issues related to connection of a DG plant one can refer to
chapter 3. Each of the technical issue is discussed in a brief and concise manner
in a section in chapter 3 and the details of which would be found in an appendix
or appendices of the Guidebook.

1.7.3 Technical issues related to the connection of DG plants are usually addressed at
the planning stage. Two main activities carried out during planning are system
and design studies and these activities are discussed in chapter 4. A reader who
is interested to find out how TNB performs preliminary planning study or design
studies should first refer to the relevant sections in chapter 4 and the associated
appendices.

1.7.4 If a reader intends to find out typical requirements of interface designs,


equipment and possible distribution network reinforcements one can refer to
chapter 5 where all interface requirements are summarized.

1 .8 Contents of the Guidebook

1.8.1 This Guidebook comprises of 6 chapters and 12 appendices. The chapters are:

1) Chapter 1: Introduction, provides background to the Guidebook including


objectives, basic definitions of terms, list of legal documents and description
of the scope.

2) Chapter 2: Process of Getting Connected, discusses the steps involved


from DG plant inception to its operation focusing on activities or procedures
for getting connected to the distribution network.

3) Chapter 3: Technical Issues and Requirements for Connection, identifies


and discusses technical issues associated with the connection of a DG plant
to the distribution network. For each of the issue discussed, requirements for
connection are elaborated.

- 15 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4) Chapter 4: Planning, Connection and Operation of the DGs, describes


planning process involving studies to identify relevant technical issues and
their resolutions. The chapter also discusses connection process and its
typical operation after successful tests and commissioning.

5) Chapter 5: Interface Design Requirements and Network Reinforcements,


summarises typical interface design requirements and equipment DG plant
connection to the distribution network. This chapter also describes typical
requirements for distribution network reinforcements.

6) Chapter 6: Glossary, contains definitions of key terms used throughout the


Guidebook.

1.8.2 The appendices are intended to provide useful information and data as well as
details of technical issues mentioned in the chapters including case studies and
examples. The appendices are:

1) Appendix A: Summary of TNB Power Systems, provides basic information


on the power systems managed and operated by TNB focusing on its
distribution network.

2) Appendix B: Types of DGs, describes several type of distributed generation


available particularly those that have been installed in Malaysia.

3) Appendix C: Data Available and to be Submitted, identifies information


available from TNB at different stages of getting connected and list of data
that the Developer should make available to TNB for various purposes of
planning the connection.

4) Appendix D: Quality of Supply and Network Performance Standards,


specifies performance standards that TNB has to comply with during
planning and operation of the distribution network. The chapter also
describes TNB distribution planning and design practices.

5) Appendix E: System Studies Associated with the Connection of DGs,


discusses in detail planning and design studies carried out by TNB to identify
technical issues and their resolutions.

6) Appendix F: Protection, Controls and Interlocking Requirements,


provides list of typical protection, controls and interlocking requirements for
the DGs including their details.

7) Appendix G: Connection Agreements, provides list of items that should be


included in a typical connection agreement between the DG Developer and
the Distributor.

- 16 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Chapter 2: Process for Getting Connected

2 .1 Summary of Process

2.1.1 A general process involved for connecting of a DG plant to the distribution


network is shown in Figure 2.1 that comprises of the several phases:
1) Project planning;
2) Exchange of planning information;
3) Project design;
4) Project construction;
5) Project testing and commissioning; and
6) Project Operation.
In parallel to the above process, both the Developer and the Distributor would
also enter into several negotiations on commercial arrangements including tariff
for power exchange and connection charges.

2.1.2 Opportunity for implementing a DG Plant at a particular location usually stems


out from the availability of long-term indigenous fuel or energy resources. The
energy resources include biomass from palm oil waste, hydro power and biogas
from old waste dumping ground or landfill (see Appendix B). These may include
existing captive generation or a co-generation plant within a factory or host site
that produces heat and power considering connecting to the local distribution
network. There are several reasons for a DG plant or an installation with
Embedded Generation (EG) may want to be connected to the local distribution
network, including:
1) To sell electricity as an Independent Power Producer (IPP);
2) To sell excess generation, for example, by a cogeneration plant and at the
same time improving overall efficiency;
3) To top-up supply;
4) To use utility supply as standby;
5) A combination of the above purposes.
The above purposes are illustrated in Figure 2.2(a) through 2.2(d). Standby
supply from the utility on normally open switch is also another possible reason
for connection.

2.1.3 After identifying opportunity for generation, the DG Developer should contact the
nearest local or regional TNB offices to enquire on the possibilities for
connection to the distribution network. To obtain detailed requirements and cost
estimates for connection, the Developer should write to the Distributor by
providing basic information (see Appendix C) of the proposed DG plant to
enable the Distributor to perform a preliminary system study (see Appendix E) to
identify technical requirements for network extensions and its associated
estimated costs.

- 17 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

2.1.4 Given cost estimates for connection to the distribution network, the DG
Developer could then negotiate and enter into a commercial agreement with the
Distributor before carrying out detailed design. The Developer would need to
provide detailed information of the DG plant and interface facilities to the
Distributor (see Appendix C) for the power system study of the connection (see
Appendix E). This will then form the basis for the connection agreement (see
Appendix G). At the same time the Developer would in parallel be carrying out
detailed design of the DG plant.

1 - Project Planning
Developer making commercial & technical
assessments and initial contacts with Distributor on
connection possibilities.

2 – Exchange of Information & Preliminary Plan


Developer & Distributor exchange information so
Commercial Agreement
that Preliminary System Studies on connection can – purchase, standby,
be conducted to determine connection cost. top-up

3 – Project Design
Developer submit formal application for connection Connection agreement
with detailed information on the plant for utility to – technical &
carry out Power System Studies, detailed commercial
connection requirements & then Developer carrying
detailed design of plant and its connection.

4 – Project Construction
Developer construct plant and Distributor constructs
its connection/reinforcement portions

Connection Operation
4 – Project Testing & Commissioning Manual
Developer & Distributor perform tests and
commissioning of the plant and connection

5 – Operation
Developer & Distributor coordinate operation of the
plant with the distribution network

Figure 2.1: Basic process involved for DG connection to the distribution


network

- 18 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Pt,Qt Pt,Qt

Transmi ssion
Transmi ssion
Grid
Di stribution Grid
Di stribution
Network
Network
Pg,Qg
Pg,Qg

DG Load
DG Load

Pl,Ql
Heat
(b) Sell excess generation of
(a) Sell all generation Cogen plant

Pt,Qt Pt,Qt

Transmi ssion Transmi ssion


Grid Grid
Di stribution Di stribution
Network Network
Pd,Qd 0,0

DG Load DG Load

Pl,Ql Pl,Ql
(c) Top up supply from
Distribution network (d) Standby supply
Figure 2.2(a) – 2.2(d): Various power exchange modes for connection

2.1.5 Once commercial agreements including connection agreement are executed, the
DG Developer and the Distributor would enter project construction phase. Prior
to operation of the connection, both the DG Developer and Distributor would
arrange for testing and commissioning to be carried out. The ‘Connection
Operation Manual’ must be established by the DG Developer in consultation with
the Distributor as the reference document during the operation of the DG plant.

2.1.6 In the following sections, we will describe in more detail the activities involved in
each step/phase of the process in figure 2.1. The steps for getting connected as
described in this Guidebook are generally applied for all DG Plants. In the case
of RE Plant, the steps are slightly different because of the commercial
arrangements and the DG Developer should refer to TNB for the correct
procedure. However, technical requirements for connections for RE Plant are the
same as described in this Guidebook.

- 19 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

2 .2 Project Planning

2.2.1 ‘Project Planning’ is a phase initiated by the DG Developer who recognizes the
potential business opportunities of connecting the proposed plant to the
distribution network. At this stage, the DG Developer would have identified
potential site for the DG plant, energy resources and their long term supplies,
types of generating plants (see Appendix B), and cost estimates of the plant. It
is also important at this point in time for the DG Developer to understand some
basic parameters of the local distribution network including possible connection
points, voltage levels and organization of the local utility (see Appendix A).

2.2.2 A DG Developer who intends to sell power to the local utility as an IPP would
first carry out initial assessment of the availability of energy resources for the DG
plant and makes preliminary commercial assessment of the DG. At this stage of
the feasibility study, the Developer may not know exactly how the DG plant
would be connected to the distribution network and this is when the first contact
with the utility on the possibility of connection should be initiated. This first
contact may discuss both technical and commercial issues.

2.2.3 A cogeneration plant is usually established to provide both heat and power to an
industrial plant or large commercial complex. Such plant or complex may not
necessarily be connected to the local distribution network. But since a
cogeneration plant consumes fuel efficiently, excess electricity could be sold to
the local utility at an attractive tariff. Contact with the district or regional offices
of TNB should be the first step to find out on the possibility of connection.

2.2.4 A factory or manufacturing plant having its own captive load may find that the
on-site generation capacity is insufficient to cater for demand requirements due
to production growth. The plant owner may find that it is not economical to
increase on-site generation capacity instead a more sensible option is to buy
top-up power from the local Distributor. In this case an initial enquiry with the
local Distributor would enable assessment be made on adequacy of the
distribution network for providing the top-up supply.

2.2.5 An installation with on-site generation may find that the available generation
capacity is not sufficient to cater for emergency situations such as loss of
generating units. In most cases where there is local distribution network it is
more economical to connect the plant to the distribution network that acts as
standby rather than adding new generation capacities. Since the Distributor
needs to ensure that the network has the required capacity to reserve for the
plant emergency requirements, it is important that an enquiry be made with the
local distribution offices on possible limitations for standby purposes.

2.2.6 When meeting representatives of the Distributor or TNB District or Regional


officers, it is useful for the DG Developer to prepare basic information of the
proposed plant and its possible connection points. The main objective for the
DG Developer at this stage would be to:
1) Identify possible connection points; and

- 20 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

2) To obtain and confirm the basic parameters – voltage, circuit capacities,


distance to transmission sources, loads in the areas etc. - of the local
distribution network.
Distribution engineers at the district or the regional offices must recognize that at
this point, the DG Developer requires the above information so that a letter could
be submitted to request for estimate of connection cost (see Appendix C).

2 .3 Exchange of Planning Information & Preliminary Study

2.3.1 A DG Developer should enter into the next phase of the connection process after
confirming with the utility that connection would be technically feasible and that
the next important information required is the cost estimates for the connection.
Such cost estimate could only be obtained from the Distributor after a
preliminary system study is carried out.

2.3.2 To request TNB for the cost estimate of connection, the DG Developer should
officially submit a request letter giving some basic information for the Distributor
to carry out preliminary system study (see Appendix C). After receiving the
request letter and basic information on the proposed DG, the Distributor would
be in a position to carry out a preliminary system study in accordance with
procedures as described in Appendix E.

2.3.3 At this preliminary stage, it is sufficient for DG Developer to provide the following
basic data to the Distributor with the request letter:
1) Number of generating units proposed and capacities in kVA;
2) Fuel resource; and
3) Physical location of the plant.
A location map indicating the plant site and nearest existing distribution medium
voltage network facilities should also be submitted with the request letter.

2.3.4 On receipt of the request letter, the Distributor should carry out a preliminary
system study so that major equipment to be added to the network could be
identified and their costs estimated. Typically the Distributor would carry out a
preliminary system study by assuming certain parameters for the plant and
applying procedures as described in Appendix E. The analysis carried out
include:
1) Voltage performance;
2) Network adequacy;
3) Short-circuit calculations; and
4) Losses.

2.3.5 The results of the preliminary system study would enable the following questions
be answered:
a) The feasibility of connection;
b) Point of connection;
c) Major equipment required for connection; and
d) Estimated cost of connection.
The preliminary system study would also identify technical issues that may need
to be addressed further if the DG plant connection is to proceed to next stage. In

- 21 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

particular the Distributor would inform the DG Developer of issues that may need
to be addressed during the plant design stage.

2.3.6 To ensure transparency in the preliminary planning process, the Distributor is


obliged to provide a summary of the preliminary study report to the DG
Developer.

2 .4 Project Design

2.4.1 With the cost estimate for connection provided by the Distributor, the DG
Developer would be able make further assessment on the commercial viability of
the DG plant and its connection to the distribution network. If the DG Developer
decides to proceed with the DG plant development, the Project Design phase
should begin. In parallel to the project design, it is usual for the DG Developer to
also start negotiations on commercial terms and agreements with the
Distributor.

2.4.2 The DG Developer at the project design phase would normally employ services
of consultants to carry out detailed design and establish specifications for
procurements and installation. As soon as details of plant design and equipment
are available, the DG Developer should submit a formal application for
connection to the Distributor making reference to the earlier preliminary system
study and highlighting major changes to plant basic parameters. Formal
application form for connection and details of the data to be submitted to the
Distributor are given in Appendix C.

2.4.3 On receipt of formal application for connection, the Distributor should examine
the information submitted by the DG Developer and should ensure sufficient
data are provided to perform detailed power system study. At this stage, both
the DG Developer and the Distributor may organize several meetings and
discussions to exchange and confirm information.

2.4.4 The main objective of the power system study to be carried out by the
Distributor at this stage is to ensure that the connection of the DG Plant will not
deteriorate the quality of supply and power that is being provided to the existing
customers in the vicinity of the DG plant. If the connection affects the quality of
supply, the Distributor is required in accordance with the prevailing codes and
regulations to apply mitigation measures and the cost of which would have to be
borne by the DG Developer. It is therefore vital that the Distributor performs the
power system study by taking into consideration all factors with valid
assumptions and that the full study report should be made available to all
stakeholders including the DG Developer.

2.4.5 Study report of the power system study should contain sufficient information on
connection requirements to be used by the DG Developer to establish
specifications for procurement and implementation of the connection. It is
important that the study report provide a list of connection interface
requirements with sufficient details of parameters to be applied.

- 22 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

2.4.6 Based on the recommendations of the study report, the DG Developer should
proceed with the specifications and procurements of the DG plant and the
associated interface requirements.

2 .5 Project Construction

2.5.1 Project construction phase would normally comprise of the following activities:
a) Detailed design;
b) Preparation of specifications;
c) Bidding;
d) Procurement; and
e) Construction.
The construction of the DG plant can be divided into two parts: plant installation;
and interface and connection to the distribution network. Construction of the
plant is completely the responsibility of the DG Developer.

2.5.2 With respect to the construction of the interface and connection to the
distribution network, two options can normally used:
1) Constructed by the DG Developer under the supervision of the Distributor; or
2) Constructed by the Distributor.
This part of the network would be operated and maintained by the Distributor.

2 .6 Project Testing and Commissioning

2.6.1 Prior to the commissioning of the DG Plant and its parallel operation with the
distribution network, the DG Developer would coordinate with the Distributor to
identify and list of tests and performance criteria, test procedure and approval.

2.6.2 The ‘Connection Operation Manual’ to be established by the DG Developer in


consultation with the Distributor must be updated based on the findings and
results of the commissioning tests.

2 .7 DG Operation

2.7.1 When a DG Plant begins commercial operation and in parallel with the
distribution network, the provisions of electricity rules and associated codes and
guidelines govern the operational obligations of both the DG Operator and the
Distributor. The details of the operation procedure will be spelled out in the
‘Connection Operation Manual’ (see Appendix G).

2.7.2 Among others, the ‘Connection Operation Manual’ includes the following items:
a) Data to be exchanged between DG Operator and Distributor;
b) Operational planning and scheduling procedure;
c) Dispatching and control procedure;
d) Fault and defect reporting;
e) Loss of mains and restoration procedure; and
f) Joint operation committee.

- 23 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Chapter 3: Technical Issues and Requirements for


Connection

3 .1 Responsibilities of the Distributors to Customers and the DGs

3.1.1 TNB and Other Distributors regulated businesses are obliged under their
licences issued by the Energy Commission (EC) to maintain a standard of supply
and services to their customers. These requirements are usually specified in the
conditions of the licence issued by the regulator to the utility. Based on the
provisions of the licence conditions and to ensure that the requirements are
complied with, TNB has established ‘Quality of Supply Standards’ as given in
Appendix D.

3.1.2 TNB is responsible for ensuring that the requirements or provisions of the Quality
of Supply Standards are complied with at all times. TNB would require imposing
some minimum requirements for any User connections such as a DG to ensure
that the Quality of Supply Standards is maintained.

3.1.3 The objectives of this chapter are:


ƒ To summarise the quality of supply standards that TNB has to comply with;
ƒ To discuss all possible technical issues that may arise with the connection of
a DG to a distribution network that could affect quality of supply; and
ƒ Where appropriate, to suggest mitigations to alleviate the issues.

3 .2 Quality of Supply Requirements

3.2.1 The quality of supply that a Distributor like TNB must comply with comprises of
several aspects whose requirements are summarized in the following
paragraphs.

3.2.2 Under normal operating condition, the steady-state voltage at a customer’s


connection/interface points must remain within the following ranges (see table
3.1).

Table 3.1: Steady-state voltage limit, normal condition


No Nominal Limits
voltage (kV)
1 33 ±5%
2 22 ±5%
3 11 ±5%
4 0.415 + 5% and − 10%

- 24 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

3.2.3 Under contingency operating condition, the voltage at a customer’s


connection/interface points should remain within the following ranges (see table
3.2).

Table 3.2: Steady-state voltage limit, contingency condition


No Nominal Limits
voltage (kV)
1 33 ± 10 %
2 22 ± 10 %
3 11 ± 10 %
4 0.415 ± 10 %

3.2.4 For a distribution network, a normal operating condition is when all major
elements including lines, cables and transformers are operating. However, the
network is said to be in contingency operating condition when any one or more
of the major elements are not operating due to forced or scheduled outages.

3.2.5 With respect to thermal capacity limits of transformers, switchgears, overhead


lines and cables, TNB has set a criterion that under both normal and
contingency operating condition these equipments must not operate beyond
their thermal limits.

3.2.6 The maximum three-phase short-circuit current allowed in TNB network are
given in table 3.3. When the short-circuit level at any point in the network
exceeds 90% of the limits in table 3.3, actions must taken to circumvent the
situation.

Table 3.3: Maximum 3-phase fault currents


No Nominal Maximum 3-phase Fault Current
Voltage (kV) (kA), duration (s)
1 33 25, 3s
2 22 25, 3s
3 11 20, 3s
4 0.415 31.5, 3s

3.2.7 The system frequency is maintained by TNB at 50Hz ±1%. Under emergency
situation and when the frequency drops below 49.5Hz, TNB may shed some
loads through the under-frequency load-shedding scheme.

- 25 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

3.2.8 With respect to supply reliability, TNB is required to plan and design the medium
voltage network that will minimize the System Average Interruption Duration
Index (SAIDI). For actual network planning and design TNB applies Supply
Security Criteria or Contingency Criteria as given in table 3.4.

Table 3.4: Security of supply criteria for medium and low voltage networks
No Type of network Supply security requirements
1 Urban/Sub-Urban • In the event of a feeder outage, the load of
Medium Voltage the feeder can be transferred to adjacent
Distribution feeders by manual or supervisory network
Feeders reconfiguration.
• In the event of a failure of a main intake sub-
station (PPU or PMU) transformer in the
supply zone:
ƒ all of the loads can be transferred to the
other transformer in the main-intake sub-
station; or
ƒ All of the loads can be transferred to
other main intake sub-station
transformers within the supply zone or
other nearby adjacent supply zones.
2 Rural Medium Voltage For rural areas of total loads less than 1 MVA,
Distribution Feeders (<1 the contingency criteria for these feeders are
MVA) not applicable. However, where reasonably
(economically) applicable, interconnections
between feeders shall be provided.
3 Low Voltage Distribution Low voltage distribution service cables to users
Networks are planned and operated as radial circuits.

- 26 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

3.2.9 TNB also specifies power quality compatibility requirements and guidelines to be
complied with as given in table 3.5.

Table 3.5 - TNB Power Quality Compatibility Standards and Guidelines


No Quality of Measurement Maximum permissible value Standards/
power for all sources Guidelines
variation
1 Distortion Total ƒ 5% at 415/240 Volts Engineering
Harmonic ƒ 4% at 11 and 22 kV Recommendation
Distortion ƒ 3 % at 33 kV G5/4
Voltage
(THDV) %
2 Flicker Pst, ƒ Pst, 1.0, Plt 0.8 (at 132 kV Engineering
Plt and below) Recommendation
ƒ Pst, 0.8, Plt 0.6 (Above 132 P28
kV)
3 Momentary V % ƒ 1 % - series voltage Engineering
Voltage change that may lead to Recommendation
Change flickering problems P28
Limits ƒ 3%- single voltage change
due to switching ON or
OFF of any loads
4 Voltage Negative ƒ 2 % for 1 minute duration Engineering
Unbalance Phase Recommendation
Sequence P24-1984
Voltage % P29-1990
5 Voltage % Remaining ƒ 50 % Sag (up to 200 ms) SEMI F47
sag Voltage ƒ 70 % Sag (up to 500 ms)
ƒ 80 % Sag (up to 1000 ms)

3.2.9 Details of the quality of supply standards are discussed in Appendix D.

- 27 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

3 .3 Technical Issues

3.3.1 Distribution systems in Peninsular Malaysia have traditionally been designed


with a single source from a transmission substation. Although the distribution
network may be connected to another transmission source, the two sources are
not normally operated in parallel. At the transmission substation, voltage
transformation from transmission to distribution is established (e.g. 132/11kV,
132/33kV, 275/33kV etc.). Voltage control is achieved using on-load tap
changer with the voltage on the distribution bus being regulated (using
automatic voltage regulator or AVR) to a specified range. Only the voltage at the
busbar connected to the transformer LV winding at the transmission substation
is maintained more or less to a constant value by the transformer AVR. The AVR
is not capable of maintaining the voltages of other nodes or substations.
Therefore, to provide further voltage regulation, reactive sources such as shunt
capacitors are located at strategic points in the system.

3.3.2 Distribution systems, being generally passive in nature, are not normally
designed to accommodate generators. The connection of a DG unit to the
distribution system would seem to provide benefits because it serves the loads
from local source and thereby reducing transmission, substation and feeder
loading. However, there are several technical issues that must be recognized
and addressed before a DG could be connected to the distribution network.

3.3.3 The technical issues are discussed in details in the following sections. Where
necessary more detail treatment of the subjects will be referred to the relevant
appendices.

3 .4 Voltage Controls and Regulations

3.4.1 Other than the obligations to control voltage within limits, voltage control
provided by the DG do bring some advantages such as:
ƒ improving voltage profile across the distribution network;
ƒ improving system losses;
ƒ improving system load flows;
ƒ avoiding potential system collapse; and
ƒ in certain circumstances, voltage control can aid starting of large motors.

3.4.2 The power factor at the main intake substations (PMU/PPU) is typically
maintained at 0.9. The Distributor is under an obligation to maintain PMU/PPU’s
power factor to not less than 0.9.

3.4.3 Normally, voltage control in a distribution system is provided by on-load tap


changing transformers (in-service transformers tap-changing) at the transmission
substations or large distribution substations. In addition to this, switched and
fixed capacitor banks are employed at strategic locations within the distribution
system. Boosters are seldom used now because of their high costs but have
been employed on the medium voltage level. In the LV system, voltage

- 28 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

regulators are employed but now being replaced by switched and fixed
capacitors. Figure 3.1 illustrates different types of voltage control devices
employed in the distribution network.

3.4.4 More expensive means of voltage control is possible with modern FACTS
(Flexible AC Transmission Systems) devices. One example of such a device is
Static VAr Compensators (SVC). These devices are often used within
transmission systems but costs of these devices are high.

Transmission
Network

132kV

OLTC Fixed
Shunt
33kV Cap
33kV

MV OLTC Switched
Network Shunt
11kV Cap

0.415kV
LV
Network
NLTC 11kV
Booster
Pole-top
Shunt
Cap

Figure 3.1: Voltage control devices in a distribution network

3.4.5 A synchronous generator embedded in the distribution network would normally


be equipped with an automatic voltage regulator (AVR) capable of controlling the
voltage or the VAr output at the generator terminal. This is performed by the
AVR through regulating DC excitation current to the generator field circuit.

3.4.6 Although the AVR is usually available, it has been the DG and the Distribution
System Operator operational practice to keep the generating unit on ‘power
factor control’. Power factor control means that the reactive power output of the
generating unit is maintained in proportion to the MW output such that the
power factor would remain constant regardless of the terminal voltage (see
Figure 3.2). When on power factor control, the generating unit does not regulate
voltage, unless it is above the AVR set limits for voltage. The reasons for running
a generating unit on power factor control are:

- 29 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

1) Commercially the DG is treated as a negative load and penalties can be


imposed for poor power factors or leading power factors in relative to real
power export.
2) It is sometime advantageous for a Distribution System Operator to match the
generating unit’s power factor to the demand power factor. This is normally
in the region of 0.95. Operating the unit this way would ensure that the power
factor of the flow from the Grid to the distribution system is kept more or less
constant.
3) Where the DG whose output is not constant is connected close to a Grid
Transformer it would have less interaction with the Transformer Automatic
Voltage Control if the unit is operated on power factor control.
However, using power factor control may result in system voltages breaching
the limits particularly during light load condition.

Example of power factor


control line
MW

0.95 pf

Example of voltage
control line
S

Terminal
Voltage

MVAR

Example of MVAR
control line

Figure 3.2: Generator reactive capability limit and controls.

3.4.7 To ensure proper voltage and VAr control within the distribution system, DGs will
be required to have the capability of both voltage control and power factor
control. Figure 3.2 also shows examples of typical reactive power controls for a
DG. The reactive capability of typical generator is normally between 0.85 lagging
to 0.95 leading at full load.

3.4.8 The choice of control modes will be subject to the ‘Preliminary System Study’ to
be carried out by TNB. It is useful to note that the advantages and
disadvantages of the various controls as in table 3.6.

3.4.9 The discussions on Voltage Control above have been focussed on the
Generation Unit because a majority of Generating Units are directly connected to

- 30 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

the Distribution System. There are a number of Generating Units that are
embedded within their site network, such as a Co-Generation plant. In these
cases, the power factor or voltage control requirements will refer to the
Connection Point to the Distributor’s network.

Table 3,6: Advantages and disadvantages of three VAr controls


Controls Advantages Disadvantages
Power Factor 1) Fix and forget similar to 1) May cause large voltage
Control demand variations between the
2) Prevents commercial extremes of light load to
penalty for ‘poor’ power peak load conditions
factors
3) Less interaction with
Transformer voltage
controllers
4) Can be used if more
that one generator is
connected to the same
bus-bar.
Voltage Control 1) Can control voltage 1) May cause large voltage
variations up to the variations between
limit of generator extremes of generating
capability. full load to generator
tripping
2) Can cause excitation
system hunting if more
than one generator
controls the same busbar
voltage
VAr Control 1) Normally used in large 1) VAr contributions can only
distribution systems, be relied on for reliable
e.g. where voltage generation.
control is ineffective. 2) Excitation droop settings
2) Useful if the Var control would need to be set for
is dispatched. Var sharing between
multiple generators.

- 31 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

3 .5 Fault Levels

3.5.1 Synchronous generators contribute fault currents in response to network faults.


Fault currents are necessary to operate protection systems especially when
discriminating between normal operating current and currents produced as a
result of a fault. Fault currents are also required to enable system voltages to
recover following a fault clearance. Similarly, fault current contributions are
essential to reduce transient voltage drops, for example during starting of large
motors

3.5.2 When a generator is connected to the distribution network, the prospective short
circuit or fault level of the network will increase because of the potential fault
current contribution. This rise of prospective fault level will be limited by the
system capability to withstand a potential fault current. This limit is the
equipment capability such as switchgear and cables. If the fault level at a node
in the network increases to more than 90% of the equipment short circuit rating
than measures must be taken to mitigate the situation. The safety margin of 10%
takes into account the tolerance allowed for the network data accuracy
especially the existence of induction motors in the system. Under no
circumstances should the prospective short circuit current be allowed to exceed
the equipment rating

3.5.3 The common utility practice is to determine short circuit currents in the network
on two types of faults, namely:
1) 3-phase fault; and
2) 1-phase to ground (or earth) fault.
Figure 3.3 shows the common terms used in defining a typical generator fault
current contribution.

Fault Peak Phase current


Make
Current
DC offset
kA Peak
Break

Time (ms)

50 100 150 200

Protection time Contact separation

Fault
Clearance

Figure 3.3: Fault currents contribution from a generator

- 32 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

3.5.4 Generator fault current contributions are calculated using parameters supplied
for the generator. The calculated fault currents on both types of faults must then
be checked against the following fault duties of ratings of circuit breakers:
1) Breaking Capacity (MVA/kA) - The capacity that a circuit-breaker is capable
of breaking at a stated recovery voltage and re-striking voltage. Recovery
voltage is the normal frequency voltage that appears across the breaker
poles after final arc extinction and re-striking voltage is the voltage that
appears across the contacts at the instant of arc extinction. This is normally
measured as an RMS value at the time when the circuit breaker contacts are
required to open as indicated in Figure 3.3.
2) Making Capacity (MVA) (normally 2.5 times the Breaking Capacity, defined as
the asymmetrical peak at 10ms) - The capability of the circuit-breaker when
closing on a standing fault.
3) Short-Time Rating (kA, rated time) - The capability of the circuit-breaker or
cables to carry the specified maximum fault current for a given period of time
normally 3 seconds.

3.5.5 The limit on equipment fault level capability is normally the main reason for
difficulties in connecting a generator. Equipment may need to be replaced to
enable generators to be connected. Replacing equipment in order to raise fault
level capabilities can be extensive over the network and the cost of replacing
equipment can be very high. However, there are a number of alternative
mitigations to reduce the generator contribution to the system possible namely:
1) Increase generator impedance – The generator impedance is normally limited
by the generator design. Changing generator impedance could mean a non-
standard design which is normally more expensive than a standard
generator.
2) Use of in-line reactors – Reactors introduce impedance between the
generator and the network, thus assist in reducing the generator fault current
contribution. However, the disadvantages of using reactors are that losses
are increased and may also cause undesirable voltage reduction at the
connection point. The overall VAr capability of the generator is also
decreased because of the VAr consumed by the reactor. Generator stability
may be affected by too high impedance.
3) Use of in-line transformers – Using a transformer reduces the disadvantages
compared to the use of a reactor, however, the cost of a transformer is much
higher that the cost of a reactor. Transformers are also used for power quality
reasons.
4) Network Splitting – Network splitting involves keeping certain parts of the
circuits normally open to reduce fault levels. Although very effective, but it
may mean less system security and increased operational effort. Installing
automatic switching systems, such as active management system, could
make this option viable.
5) Fault limiters – Is limiters are available in the market. Although effective, it
does have safety concerns mainly because it is an explosive device and
concern about repeatability of operation. Research is still being carried out
using super-conductor technologies which would address these concerns.

- 33 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

6) Connection to a higher voltage - Higher voltage system have a higher fault


level capability. However, equipment costs would be much higher.
7) Generation constraints – Some fault levels problems may be only evident
during certain network configuration, for example during an outage. It may
be acceptable for generation to be prevented from running during these
periods. This option should only be considered if the periods of constraints
are very short.

3 .6 Network/Feeder Capacity and Security Assessments

3.6.1 Security assessment will be carried out for any demand or DG connections to
the distribution network in accordance with security requirement in table 3.4.
This is based on (N-1) contingency.

3.6.2 There is a distinct difference on how network capacity and security is assessed
when connecting demand or generator. Where a firm connection for demand
cannot be guaranteed, then the network would be reinforced accordingly.
However, for generation connections, the developer may have a choice of a firm
or non-firm connection depending on the reinforcement costs needed to
accommodate the generator capacity (see Figure 3.4).

Demand Connection Generator Connection

10MVA 10MVA 10MVA 10MVA

5MVA 5MVA 2MVA


DG DG

12MVA 10MVA

Choice of firm or non-firm connection.


2MVA load cannot be added 12MVA DG connected but
without reinforcement 2MVA is non-firm

Figure 3.4: Demand and generator connections – firm and non-firm

3.6.3 For both demand and generator connections, normal and contingency
conditions will be considered. Demand Connections are assessed using (N-1)
contingency criteria. This is a deterministic contingency criterion. As shown in

- 34 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Figure 3.4, if the future total demand is greater than 10MVA, the network will
need to be reinforced to ensure that firm demand is guaranteed on the outage of
one circuit. Network reinforcements for demand needs to take into account both
current and future demand growth.

3.6.4 Generation connections are treated differently. Any reinforcement considered


will only be for the generator capacity to be connected without any
consideration for future generator connections. As illustrated in Figure 3.4, a
10MVA DG will be guaranteed access based on (N-1) criteria. However, if a
12MVA generator is to be connected using the same network only 10MVA will be
guaranteed, i.e. firm. For the remaining 2MVA, the developer could have a
number of options.

3.6.5 If a firm 12MVA connection is preferred, then network reinforcements will be


required. In the above example either a third 10MVA transformer is installed or
the two 10MVA transformers are replaced by two 12MVA transformers to fulfil
the (N-1) criteria.

3.6.6 Another option is not to carry out any reinforcements, in which case, 12MVA can
be exported during normal network conditions, i.e. no circuit outages. However,
during one circuit planned outage, the generator would need to be constrained
to 10MVA. This means that 10MVA will be firm whilst the remaining 2MVA will be
a non-firm output.

3.6.7 The planning criteria could also allow for short term overload rating over the
equipment continuous rating. Using this short term rating of 120% for example
and allowing for a (N-1) contingency, a generator rated up to 12MVA could be
allowed to be connected. For an unplanned outage of one circuit, this particular
generator would need to reduce its output from 12MVA to 10MVA over the
period allowed for short time overload rating of the circuit. This could be from
milliseconds to minutes depending on the plant item being overloaded.

3.6.8 If reinforcements are not carried out, the Developer will take the risk of the
generator output being constrained during both planned and unplanned
outages. TNB would co-operate with the developer in understanding these risks.
To reduce these risks, the developer could schedule his plant outages to
coincide with TNB’s planned network outages.

3.6.9 There are two main options available for constraining generation given a non-
firm connection. Generally, if there is an allowable period before the generator is
needed to be constrained, then a dispatch instruction is used. This type of
constraint instruction is used for planned outages or short time rating constraint
as described above. However, if an immediate constraint is required, an
automatic intertripping and/or fast generator de-loading system would be
required. This is normally used for unplanned network outages. It should be
noted that the complexity of intertripping systems depends on the complexity of
the network to be protected.

3.6.10 The above is based on a very simplistic configuration. In an actual distribution


network, there are many more parameters to be considered such as network

- 35 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

operational conditions, level of demand in the area, overload capability of


network components and other generation outputs in the area. Demands and
generating capacities can often be used to optimise on the re-enforcements
needed.

3.6.11 For example, where practicable, circuit capability for firm generation output
should be assessed in conjunction with demand. In the example above in Figure
3.5. A generator of up to 12MVA capacity could be considered for a firm
connection whereas if demand is not taken into consideration, a generator of
only 10MVA would be considered as firm. When considering reinforcements for
future demand increase, local generator outputs should also be considered if
appropriate. The methodology of assessing generator contribution is being used
in the UK in the P2/6 Planning standards. This standard is still undergoing public
consultation.

10MVA 10MVA

2MVA
DG

12MVA

Figure 3.5: Taking consideration of load and firm generation

3.6.12 Active network on-line monitoring and automatic control will reduce the risk of
generators being constrained. Reinforcements could be deferred through
knowledge of minute-to-minute demand loadings and generator outputs.

3.6.13 A generator will tend to unload the feeder between it and the main intake
substation, and will have no effect between the generator and the end of the
feeder. This will depend on the generator output in relation to the existing
demand power flow. Generator output higher than the existing demand current
flow and the use of shunt reactor may overload segments of the feeder between
the generator and the main intake substation as illustrated in Figures 3.6a) and
(b). Feeder loading situation must also be assessed to cover future years.

- 36 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

3.6.14 Also in the future, network assessment could adopt a more probabilistic
methodology which should result in reduction in reinforcements.

Feeder 1
Main Intake

Feeder 2

Feeder 3
DG

Feeder 3

Feeder 3

Figure 3.6(a): Feeder without DG

Feeder 1
Main Intake

Feeder 2

S DG Plant

2.2MW
Feeder 3
DG

Reactor
Feeder 3

Feeder 3

Figure 3.6(b): Feeder segments overload with DG

3.6.15 Distribution system would normally have interconnecting feeders with open
points. Under contingency or maintenance when one section is on outage
switching operation would be carried out to restore supply. Adequacy of circuit

- 37 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

capacities must then be assessed under both normal and contingency


situations.

3 .7 Supply Quality – Reliability and Power Quality

3.7.1 Supply quality covers two aspects:


1) Reliability of supply – customers expect continuity of electricity supply
2) Power quality – the shape of voltage waveform remains sinusoidal and
without distortion.
Supply reliability is measured by indices like SAIFI (System Average Interruption
Frequency Index) and SAIDI (System Average Interruption Duration Index).
Power quality is measured using criteria as shown in table 3.5.

3.7.2 A DG can improve the reliability of supply to the distribution network customers
by providing network support. For example, if the DG is allowed islanding
operation rather than being isolated on loss of mains.

3.7.3 If the DG is to be isolated on loss of mains, the DG does not have impact on
reliability and figures for SAIDI and SAIFI remain the same as without the DG. It
could however make it worst since new components are added to the network
including lines, switches and transformers that may fail and disconnect the
feeder. If the DG is allowed to operate on islanded mode to supply total or some
of the feeder loads, then reliability would improve since sustained failure of
components between the feeder source and the DG would enable the DG to
supply some loads that otherwise have to wait until repair is done.

3.7.4 The issues on power quality such as voltage sags, over voltages are discussed
elsewhere in this Chapter. Voltage sags are discussed in Section 3.4 – Voltage
Controls and Regulation and Section 3.5 – Fault Levels. Over voltages are
discussed in Section 3.12.

3.7.5 Harmonics can generally be a problem when using semiconductor devices such
as converters within the network. Very high harmonic levels are associated with
the use of converters in smelting works. Careful monitoring of harmonic level
necessary where a number of these devices are used in the network. Generators
and transformers can dissipate harmonics currents; however, it will cause over-
heating. Information on Total Harmonic Distortions (THD) is available from the
Distributor on request.

3.7.6 Flicker is not currently a problem with the levels of generation connected to
distribution system. However, with increasing generation connections and
different generation technology, interactions between generation and incorrect
control settings could cause flicker. Power System Stabilizers (PSS) installed in
Generator excitation systems can be used to control flicker. It should be noted
that studies will be required to obtain the correct settings for the PSS.

- 38 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

3 .8 Protection and Controls


3.8.1 General

3.8.1.1 Protection systems are essential for both the network and the generator to
ensure safe operation. Network and generator protection systems do interact
and will need to be designed to co-ordinate with each other. TNB is responsible
for design and operation of the network systems, whilst the Developer is
responsible for design and operation of the Generator systems. At a stage in the
generation project, an interchange of information between the developer and the
Distribution Operator is essential to enable each system is designed to be
coordinated.

3.8.1.2 The design of the network protection systems is based on TNB’s Protection
and Control Code of Practice. All equipment used in TNB’s is approved by TNB.
The use of approvals and Code of Practice is needed to ensure design and plant
consistency across the network.

3.8.1.3 Generator connections and generator protection systems should be designed


to a prudent utility practice and conform to current safety and regulatory
standards. The following should also be taken into account when designing
generator protection systems.
ƒ Technical specifications for interface equipment – Protection systems that
interface with the network systems, such as any differential protection
systems, will need to use approved TNB specification to ensure compatibility
and consistency of performance.
ƒ Fault clearance time for generator faults – There are a number of faults within
the generator systems that could affect the stability of Distribution Networks.
It may then be necessary for the network operator to define certain
protection operation performance. Normally, this is limited to protection
operation and fault clearance times.
ƒ Unit protection for connection cables – It has been the practice of the
Distribution Network Operator to equip the connection cable with unit
protection. This was found to be necessary to protect the network against
incorrect co-ordination afforded by slow over-current feeder protection.
Where appropriate and economical, the Distribution Network operator will
consider directional current protection.
ƒ Generator Protection System Minimum requirements - Appendix 5 include a
typical protection system diagram and the minimum requirements for a
generator protection system.
ƒ Connection point minimum requirements – Similarly Appendix 5 shows a
typical connection minimum requirements including loss-of-mains protection.
Specific minimum requirements may include single generator connection and
top-up/standby type connections.
ƒ Other requirements - Pole slipping protection could self-protected generators
from system instability and may be required as identified by stability studies.
ƒ NVD protections – Subject to safety and regulatory considerations, NVD
protection could be used on systems where it could be inadvertently un-
earthed for a very short time.

- 39 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

ƒ Distribution Network Back-up fault clearance - Network backup fault


clearance can take up to a maximum of 1.2 seconds at the source.
Developers will need to take this into account when designing protection
systems.

3.8.2 Short term Occasional Parallel Operation

3.8.2.1 Consideration for reduction in requirements will be given for generators


requiring short time parallel operation. These are generator systems which are
normally operated in islands with their demand, but require standby supplies
from the Distribution Network during generator outages.

3.8.2.2 The islanded system is only synchronized to the Distribution Network before
the generator supporting the island is taken out of service. Provided that the
generator is taken off-line as soon as the system is synchronized, certain
protection requirements such as loss-of-mains may be exempted. The following
systems may be required to be implemented:
ƒ Automatic change over between generator circuit breaker and Network
connection circuit breaker such as make before break systems.
ƒ Controlled short-term paralleling for test and commissioning
ƒ Complete protection system may not be required
ƒ Use of timers to limit time for parallel operation
ƒ Site protection systems will need to be configured when connected to the
Distribution Network due to the change in fault levels for example.

3.8.3 Loss of Mains

3.8.3.1 Occasionally, due to network faults, parts of networks containing embedded


generation or DG may be inadvertently islanded. Depending on the demand
requirements and the generator performance, the DG could remain in operation,
thus supporting the island.

3.8.3.2 Distributors are obliged to maintain a safe system and may be liable for
damages if generator without proper control is allowed to supply the regulated
network and breach the regulatory frequency and voltage limits. Protection
systems and earthing systems are also not designed for inadvertent generator
island systems. For these reasons, it is essential that generator that could
potentially support islanded systems is tripped when the condition arise using
loss-of-mains protection systems.

3.8.3.3 The use of auto-reclosers also makes it necessary for the loss-of-mains
protection to trip the relevant generators before the auto-reclose recloses. Loss-
of-mains protection is usually installed at the point of connection to the
Distribution Network. This arrangement would allow a generator to be islanded
within its own private network if required. A number of loss-of-mains systems
are possible depending on required operation time, network configuration,
demand and generator output.

- 40 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

3.8.3.4 ROCOF/Vector Shift -The system works on the principle of fast frequency
change and waveform shift characterised at the instant when systems are
islanded. However, these systems are prone to nuisance tripping because the
relay can detect overall Grid system disturbance. Generally it will trip more that
necessary, depending on the settings. It is the more cost effective system
compared to other systems. A number of issues have historically been identified
with these systems namely:
ƒ Settings - finding suitable settings may be difficult. It may be necessary to
estimate initial settings and monitor its behaviour. Simulating credible system
disturbances can assist be used to estimate settings.
ƒ Demand to Generation balance – There may be cases where demand almost
equals generation output and the rate of change of frequency or vector shift
is not sufficient to cause operation.
ƒ Testing - On site operational testing will be a problem. System monitoring is
an option.

3.8.3.5 Intertripping - Intertripping is an alternative to ROCOF/Vector Shift relays. The


system is more reliable but can be expensive for an extensive Distribution
Network system. To limit the complexity of the system, the assessment is based
on monitoring circuit breakers up to the point where generator will not be able to
sustain system load. In the example shown in Figure 3.7, the intertrip is set
between the two breakers where the generator can just sustain the network
demand. The principle depends on the generator tripping on the generator over-
current whenever systems islanded contain more demand than the generator
capability. The use of intertripping in conjunction with auto-reclosers is
described in detail below.

DG
2MW

2MW
A B C D

2MW 2MW

Intertripping may only


be required between
breakers C and D

Figure 3.7: Example intertripping on loss of mains

- 41 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

3.8.3.6 Generator overload in combination with Over/Under Voltage and


Over/Under Frequency - As described above, if the potential islanding
configuration has demand greater than the generator overload setting, an over-
current protection relay could be an effective loss-of-mains protection. However,
in the assessment, consideration must be taken during light load conditions
where the condition may not be true and other loss-of-mains of protection as
described above needs to be installed.

3.8.3.7 Over/Under Voltage and Over/Under frequency - Over/Under Voltage and


Over and Under Frequency protection systems is the minimum requirement at
the connection point. These protection relays normally take longer to operate
than those described above and thus may not be suitable for use with auto-
reclosers

3.8.4 Auto-reclosing

3.8.4.1 Auto-reclosing are used on overhead lines within Distribution Networks. The
system is used to reclose lines that are tripped by self-clearing faults, such as
tree branches touching the lines.

3.8.4.2 Auto reclosing lines that have generators connected within the system could
result in out of phase closing. The impact of connecting out-of-phase systems
could be destructive and could lead to:
ƒ Extensive Generator Damage;
ƒ Network Circuit Breaker Damage; and
ƒ Network Voltage Sag due to the high currents caused when connecting out-
of-phase systems. Depending on the phase angle at connection, twice fault
currents can potentially be generated if the voltage at synchronization is
totally opposite in phase and amplitude.

3.8.4.3 Reliable and fast loss-of-mains tripping will be required where reclosers are
used in systems that can be potentially islanded for a short period. Normally, the
use of intertripping for loss-of-mains would provide the reliability and speed of
operation. The use of over-current relays for loss-of-mains may also be suitable,
provided the speed of over-current operation is faster than the auto-reclosing
time.

3.8.5 Islanded Operation

3.8.5.1 Islanding within the Distribution system has not been implemented generally.
However, there are isolated areas which are supplied by systems which are
islanded or capable of being islanded. Generally these would be remote systems
where interconnection to the main distribution system is prohibitively expensive.
Generator capabilities and its performance within these islanded systems are
crucial and need to be controlled. Two main control systems required are
voltage and frequency control.

- 42 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

3.8.5.2 Note that it is Distributor’s responsibility within the Electricity Regulations to


maintain a safe system, thus the need for the Distributor to be responsible for
generator control. As such, the technical and performance requirements will
need to be specified. This will be an additional cost to the DG Developer. An
incentive within the DG ancillary service could provide the needed financial
support to provide the capabilities.

3.8.5.3 The performance requirements will require sophisticated generator and


network control to match generation with demand. Some of the capabilities for
generators and the Distribution System would include:
1) Isochronous operation
This type of operation is normally suitable for smaller machines or a single
machine supplying a system where the demand is less than the generator
output. Isochronous control used in the generator will maintain frequency by
increasing or reducing its output. There is a need to maintain a margin
between the generator output and the demand. The frequency control can be
coarse and may exceed regulatory limits transiently. Load shedding schemes
can be used to supplement the frequency control.
2) Governor droop control
This is the principle used in Transmission Grid system for controlling
frequency. Governor droop control is used for larger systems containing
multiple generators. Droop control will allow generators to share their outputs
proportionally when maintaining frequency. Some form of fast frequency
response systems may be required depending on the nature of the demand
are required for fine control. Droop settings will be dependent on the system
and its demand.
3) Demand load shedding/frequency tripping systems
To supplement generator control, demand load shedding can be used for
controlling frequency. This system is normally used as an emergency
measure. Demand will need to be prioritised for tripping based on acceptable
levels of frequency deviation.
4) Network voltage control
Voltage profiles can be controlled by the generator excitation systems and
Transformer AVRs. Where multiple generators are present within the same
system; care is needed in setting the excitation controls to prevent system
interactions. Voltage profiles do change when systems are running islanded
due to the changing system flows. Transformer AVR controls and generator
excitation system controls would need to be switched to enable them to
operate within an islanded system. Transformer AVRs operation in particular
will be affected by reverse power flows.
5) Seamless Islanding/Black Start
Seamless Islanding would mean that a customer would not see any supply
interruptions. In order to facilitate seamless islanding, all generators required
to support the island would need to automatically switch to its islanding
capabilities described above. These systems may be complex and could be
unnecessarily expensive. A manual system could be implemented where
generators would need to be equipped with Black Start capabilities. The
Islanded Distribution systems are initially allowed to be de-energised and the
systems are then re-energized by matching generator output with demand at

- 43 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

all stages of restoration. The length of supply interruptions would depend on


the speed of restoration of Black Start cells.
6) Network re-synchronising control and locations
Restoration of sub-islanded systems to the main networks will require
synchronizing points to be identified within the system. Voltage and
frequency control between multiple generators would need to be coordinated
so that voltage and phase angles could be matched to allow synchronizing.
7) Loss-of-mains protection
This protection is described in Section 3.8.3. Islanded systems will need to
be separated from the main Distribution System by loss-of-mains protection.
Selection of points of separation is critical to ensure correct islanded
operation, for example when matching demand to generation available.
8) Earthing Arrangement
It is essential that systems are adequately earthed when operating separated
from the main Distribution System. System containing generators operating
in parallel with the Distribution System are normally earthed through the
Distribution network. It is important that earthing systems are designed to
take into account an islanding operation for example lower fault levels and
different load flows, potential multiple grounding points. Earthing islanded
systems consisting of more than one generator can also be complex and
may require switched earths. Protection systems should take into account
the earth switching and its complexities.
9) Protection systems
A number of parameters will affect the operation of protection systems when
a system is islanded from a Distribution System namely; lower fault levels
and different (such as reverse load flows or increased or lowered load flows).
Protection systems would need to be capable of switching from a paralleled
system to an islanded system.

3.8.5.4 Islanding system could make a difference in costs of supply failure during
forced or planned outages. Where appropriate, case studies should be carried
out using real systems to discover benefits, and also costs of realizing the
benefits.

3 .9 Losses

3.9.1 Generators do have a significant effect on network losses; it can lower or


increase losses depending on its location and the network configuration. In
principle, when a generator is connected to a distribution system, there should
not be any increase in losses in comparison to the system without the generator.
As an example, Figure 3.8 illustrates a variation of losses under different load
levels and generating unit outputs. This example case illustrates the possible
increase in losses when a DG unit is connected at the end of a long line. Using
the principle of limiting loss level (loss limit line) as indicated in Figure 3.8, the
generation output, for this example, could be limited to between 2500kW and
3000kW during light and peak load respectively. However for minimum loss
operation, the DG output is limited between 700kW and 1400kW.

- 44 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

500
Peak
450 Intermediate

Feeder Losses (kW ) 400 Light

350

300

250 Loss limit line


200

150

100

50

0
0 1000 2000 2500 3000 4000
700 1400
DG Output (kW)

Figure 3.8: An example of loss variation on different load level and unit
outputs

3.9.2 Connecting generators at a higher voltage and/or at a different location can


normally reduce losses. Location can be important because losses can only be
reduced if the generator can back-off demand. Essentially, losses are reduced
by connecting a generator in high demand areas.

3.9.3 When designing a generator connection, the effect on losses needs to be taken
into consideration. In most cases, there will be an opportunity to reduce system
losses and maximize the benefits brought about by the generator and can only
be analysed through examination of various network operating conditions.

3.9.4 Losses are calculated by carrying out load flow studies on the system.
Procedures for carrying out the studies are described elsewhere in this
Guidebook. Where practical, the methodology for carrying out the studies and
assumptions should be made transparent to the DG Developer.

3.9.5 The procedure for calculating losses needs to take into consideration the
following:
1) Demand Profiles – Demand varies throughout the day and also throughout
the year. A number of permutations are possible and accuracy of the results
will depend on the number scenarios used throughout the year. In general,
the wider the range of demand over the day or year, the more scenarios will
be required.

- 45 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

2) Generator output profiles – Similarly, generator outputs profiles can vary.


Most DGs will run at constant outputs, depending on the availability of fuel.
However, as discussed in chapter 4, there may be occasions that the DG unit
is operated to follow a load profile. Any potential long term constraints on
generators due to network restrictions should also be taken into account
3) Network Configuration – Generally, changes in network configurations
would be less than demand variations. However, any planned network
improvements or long term network outages would need to be taken into
considerations, especially when it involves transformers. Losses due to
transformers would normally be more significant than losses through lines.
4) Voltage profiles - Voltage changes will also significantly affect network
losses. Care should be taken when carrying out studies that credible voltage
profiles are maintained when varying system demands and generator
outputs. This will assist in maintaining consistency across the results.

3.9.6 Methodologies for calculating losses will depend on how the cost of losses is to
be applied. Losses can be capitalized over the project life or ‘loss adjustment
factors’ could be applied to generator outputs. Whichever methodology used
would need regular reviews to take into account changes within the system.

3.10 Earthing and use of interface transformers

3.10.1 Earthing arrangements are discussed in Chapter 4. To ensure robustness of


system earths, it is recommended that generation systems are interconnected to
the distribution network using interface transformers as detailed in Chapter 4.
There are a number of advantages of using interface transformers, namely;
1) Ensuring that the earthing systems of the generating unit and the distribution
system are adequately and independently earthed.
2) In certain cases, the generator will experience less voltage dips originating
from the Distribution Network. This could reduce the number of generator
trippings due to under/over voltage protection.
3) As described elsewhere in this Chapter, it could be a means of reducing the
fault level infeed into the Distribution Network.

- 46 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

3.11 Stability

3.11.1 Generator transient instability is not normally an issue with generators connected
to a distribution system. However, generators connected to very long lines
subject to long protection clearance times could experience transient instability.
Multiple generator installations could be particularly prone to instability. Stability
studies would be carried out to determine the need for additional system and
generator protection such as pole slipping protection.

3.11.2 Pole slipping protection system is used to protect the generator from instability
and the damage it could cause. However, this is a non-standard protection and
will be an additional cost to the DG Developer.

3.11.3 Studies would also need to identify the pole slipping protection settings
required. The settings would need to take into account instability within the
generator and also within the distribution network caused by other generators in
the system.

3.11.4 At the onset of a project, it is unlikely that precise data required for stability
studies will be available. It is essential that sensitivity assessments are carried
out on estimated generator data in order to identify potential stability problems.
Detailed studies may be required once actual data are available, usually when
machines are being ordered.

3.12 Over voltages and resonant over-voltage

3.12.1 Distribution systems can be prone to over-voltages and resonant over-voltages.


Over-voltages are common and normally caused by:
1) Lightning Strikes – Lightning strikes are common in systems having a high
proportion of overhead lines. Mitigations include installing suitable surge
arresters.
2) Switching Surges – These are caused by switching long cables due to their
capacitive effects. Similar to the above, installing surge arresters would offer
protection.
3) Ineffective Grounding of DG – Voltages can rise in the Generator neutrals
and also phase terminal could experience up to twice the phase voltages if
generators or systems are incorrectly earthed. The primary protection against
this phenomenon would be through the earthing system. Earthing design
does need take into account the over-voltage capabilities of the system
including generators, especially system insulation levels. NVD (Neutral
Voltage Displacement) can be used for protection against these ‘unbalanced’
voltage conditions.
4) Line to Ground Faults – Similar to the above, certain line-to-ground faults in
combination with ineffective earthing as described above could give rise to
unbalanced voltage conditions.
5) Load rejections – Disproportionate load rejection can cause generators to
transiently over-excite and cause over-voltages at the generator terminals. It

- 47 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

is essential that generator excitation systems are designed and tested to


ensure correct response of the voltage control during transient conditions.

3.12.2 Resonant over-voltages are caused by resonant conditions brought about by the
presence of capacitance and inductance in the system. These conditions can be
difficult to detect or calculate because the event may only be triggered by
certain network configuration for example during an outage condition. Once
detected, the system can be ‘detuned’.

3.13 Data Requirements

3.13.1 As identified in the various sections of this chapter, availability and accuracy of
data is a major concern when carrying out studies to determine costs of
connections. The reliability of generator data increases throughout the project.
At the onset of the project, only estimated data would be available. It should also
be noted that manufacturer’s schedules have a tolerance of at least +/-10% on
the impedance data as allowed by the IEC standards. Developers would need to
ensure that data submitted to TNB are reliable and checked by the Developer’s
consultant.

3.13.2 Where data tolerances are given, worst case scenarios should be examined in
the studies. It is also important to understand the sensitivities of the tolerances
to the study results. This will identify the level of data accuracy required. The
following are some of the issues related to data requirements.
1) Initial Load Flow Studies: Generally, as identified in the Appendices C and
E, data for load flow studies will be very basic. Based on the generator
estimated ratings, various impedances can be estimated.
2) Fault Level Studies: TNB’s procedure includes a 10% margin when
calculating fault level within the network. This is to allow both network data
tolerances and generator data tolerances. When using manufacturer’s data,
calculation should be based on the worst case, for example using lower end
of the tolerance range of generator impedances.
3) Stability studies: Contrary to the Fault Level Studies, the worst case
scenario may need to use the higher end of the tolerance.
4) Protection Studies: In order for the Distribution Network co-ordination
studies to be carried out, the Distributor will require protection settings from
the DG Developer. The DG Developer will need to ensure that the protection
co-ordination studies within the Developer’s site have been completed before
submitting data. The timing of the data submission will be detailed in the
PPA.

3.14 Safety

3.14.1 Safety must be a priority when designing Distribution Systems and Generation
systems. Some of the issues that concern safety are discussed in the various
sections of this Chapter. Two issues in particular need particular attention.

- 48 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

1) Earthing Arrangements – The design of earthing arrangements also need to


take into account safe touch voltages and safe transfer voltages. Particular
attention should be taken systems remote to the main Distribution system
and areas of high soil resistivities.
2) Protection systems – Protection system issues have been described
elsewhere in this Chapter. Similarly, particular attention should be taken
when designing remote generator connections due to the vulnerability of
connecting lines and access to equipment.

3.15.2 References should include the following when designing systems:; BS


7671:2001 Requirements for electrical installations. IEE Wiring Regulations.
Sixteenth edition. The relevant clauses mentioned include:
ƒ “Clause 413-02-04: The characteristics of each protective device for
automatic disconnection, the earthing arrangement for the installation and the
relevant impedance of the circuit concerned shall be co-coordinated so that
during an earth fault the voltages between simultaneous accessible exposed
and extraneous-conductive-parts occurring anywhere in the installation shall
be of such magnitude and duration as not to cause danger.”
ƒ “Conventional means of compliance with this regulation are given in
regulations 413-02-06 to 413-02-26 according to the type of system earthing,
but equally effective means shall not be excluded.”

The relevant Malaysian Standard to conform to is the MS IEC 60364.

The UK’s ESQRC (The Electricity Safety, Quality and Continuity Regulations
2002) and EA Engineering Recommendations give further guidance of step,
transfer and voltage gradients for industrial, distribution network and power
stations.

- 49 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Chapter 4: Planning, Connection and Operation of


the DGs

4 .1 Introduction

4.1.1 Development of a DG Plant undergoes several phases as described in chapter 2.


The three main phases are planning, connection and operation. Planning are
carried out for two main purposes:
1) For the establishment of the DG Plant itself; and
2) For the establishment of the connection to the distribution network.
Planning for establishing the DG Plant is carried out by the DG Developer while
that associated with the connection is by the Distributor.

4.1.2 When all facilities for connection to the distribution network have been
constructed, inspections and tests have to be carried out prior to the
commissioning of the connection. Before protection and control equipment are
tested, protection setting and coordination studies have to be performed using
the data of the installed protective equipment. The results of the coordination
studies would be referred to by relay test engineers for setting the protection
devices. Another important activity prior to commercial operation is the
establishment ‘Connection Operation Manual (COM)’ that must be developed
and agreed upon by the DG Developer and the Distributor.

4.1.3 The objective of this chapter is to outline the activities involved in the planning,
connection and operation of the DG Plant. Planning of the connection is
performed almost entirely by the Distributor and therefore, it is vital that the DG
Developer understands the tasks and types of analysis carried out during the
main phases of planning studies namely; preliminary and power system. With
respect to connection, the focus is to describe the requirements for protection
study and commissioning tests. The chapter will also cover several aspects of
DG plant operation particularly on modes of operation and requirements for
exchange of operational data and liaisons.

4 .2 Preliminary Planning Study


4.2.1 Objective

4.2.1.1 On a written request by the DG Developer for cost estimates of connection,


TNB Area/State planning engineers are required to carry out ‘a Preliminary
System Study’ so that major equipment and facilities for connecting the DG
Plant to the distribution network could be identified and its costs estimated.
Such request may also come from within TNB such as the Small Energy Unit
(Unit Tenaga Kecil) of TNB Distribution Division for renewable energy projects.

- 50 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4.2.1.2 The main objectives of the preliminary system study are:


1) To determine network capability to accommodate the proposed DG; and
2) To establish cost estimate of the connection of the DG Plant to the
distribution network of the part of the circuit facilities that will come under the
operational responsibility of the Distributor.

4.2.2 Connection Facilities Under the Distributor’s Responsibility

4.2.2.1 At this preliminary stage, connection facilities that will become the operational
responsibility of the Distributor must be indicated. These facilities could vary
depending on the configuration of the connection as shown in Figures 4.1(a),
4.1(b), 4.1(c) and 4.1(d). The configurations must be designed based on the
principle of ‘clear system boundaries and responsibilities’.

DG Plant DG Plant

Utility Utility

Feeder Feeder
House
load
G G

Dual-breaker scheme Three-breaker scheme


Figure 4.1 (a): Connection configuration

Feeder

DG Plant

Utility
Utility

Feeder Feeder

G G
DG Plant

Three-breaker scheme Three-breaker scheme


With bus-coupler With bus-coupler & two feeders
Figure 4.1 (b): Connection configuration

- 51 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

DG Plant

Utility

Feeder

Remote connection point with


Dual-breaker scheme

Figure 4.1 (c): Connection configuration

Utility

DG Plant &
Network
Feeder

Interfacing
Facilities

M M M

M M M

Figure 4.1 (d): Connection configuration

- 52 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4.2.2.2 Figures 4.1(a) and 4.1(b) illustrate connection configurations when the points of
interface are located in same premises as the DG Plant. Figure 4.1(c) illustrates
the dual-breaker scheme with the interface point remotely located near the utility
existing network and this is a typical case of connecting a mini-hydro DG Plant
with a long connecting line to the distribution network. In the case of connection
configuration in Figure 4.1(c), the DG Operator is also responsible to manage
and operate the interconnection line up to the interface point.

4.2.2.3 From distribution network design and operation point of view, the basic
requirements for major DG Plant and interface/connection facilities must include
the following facilities:
1) Interface-transformer;
2) Interface-transformer star-grounded through NER;
3) Synchronisation facilities as part of the plant; and
4) Circuit breaker(s).
The above facilities could be arranged in several ways as shown in Figure 4.2.

4.2.2.4 The Preliminary System Study report must also indicate the connection and
interface facilities that should be provided by the DG Developer including their
basic requirements. This information must then be provided by the Distributor to
the DG Developer.

NER
One LV Breaker

NER
One HV Breaker

NER
LV and HV Breakers

Synchronising

Figure 4.2(a): Basic requirements at the plant for connection to the


Distribution network – generator transformers.

- 53 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

NER

M
DG Plant &
Network
M

Synchronising

Figure 4.2(b): Basic requirements at the plant for connection to the


Distribution network – interface transformer.

4.2.3 Basic Connection Issues

4.2.3.1 Connection technical issues (see chapter 3) of importance during the


preliminary study are listed below in accordance with the type of DG plant:
1) Hydro: The location of hydro DG in the network is normally remote and
connected through long lines or cables. The main issues are:
ƒ Voltage and its controls; and
ƒ Losses
2) Biomass: Biomass plant can be located near existing feeders in rural areas
as well as near industrial areas. The main issues are therefore:
ƒ Voltage and its controls;
ƒ Losses; and
ƒ Fault Level
3) Co-generation plant: Co-generation plant is usually located near Grid
substations and main issue is:
ƒ Fault level.

- 54 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4.2.4 Preliminary System Study Procedure

4.2.4.1 The ‘Preliminary System Study’ starts by developing load flow and short-circuit
model for typical generating units of the DG Plant based on the following basic
information provided by the DG Developer:
1) Number of generating units proposed and their capacities;
2) Quantum of power to be sent to the distribution network;
3) Fuel resource; and
4) Physical location of the plant including location map.
Based on the fuel resource, the distribution planning engineer could use any of
the following typical models available in the simulation software employed by
TNB – Shaw PTI’s PSS/ADEPT:
a) Steam turbine (small) – biomass units, cogeneration steam units
b) Hydro without damper – mini hydro units
c) Combustion turbine – gas turbine units

4.2.4.2 The load flow model of the distribution network to which the DG Plant will be
connected to must also be updated with the latest available information
including:
1) Feeder and PMU/PPU loadings – peak, intermediate and light or minimum;
2) Fault levels at PMU/PPU transmission voltage level.
The distribution planning engineer should then identify options for connection
that will be evaluated.

4.2.4.3 For each of the connection options identified, the following


analysis/assessments should be carried out after the simulation models are
carefully checked:
ƒ Network voltage profile under different loading condition and network
contingencies:
o Peak, intermediate and light loads
o Normal and contingency situations
Any option that violates voltage criteria must be eliminated
ƒ System Adequacy:
For system adequacy assessment, any branch overload due to introduction
of the DG Plant is to be identified for upgrading or reinforcement.
ƒ System Losses:
Increase or decrease in system losses must be noted and estimated into the
future for purposes of related commercial calculations
ƒ Short-Circuit Studies:
Evaluate fault level – values of above 90% equipment short-circuit rating
must be noted
During the study, continuous interactions between the area/state planning
engineers and the DG Developer are encouraged to confirm data and
assumptions.

4.2.3.4 The cost of each option that satisfy all planning criteria are to be estimated by
taking into consideration the following:
1) Investment costs:
ƒ Cost of new asset from DG Plant to the existing network; and

- 55 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

ƒ Cost of new internal network reinforcement assets.


2) Operating cost not including losses:
ƒ Cost of operating the new asset from DG Plant to the existing network;
and
ƒ Cost of operating the new internal network reinforcement assets.

4.2.3.5 Losses (increase or decrease) due to the connection of the DG Plant must be
calculated and included in the ‘Preliminary Study Report’. Information on system
losses will be used by the Commercial Department of TNB Distribution for tariff
calculations. However, the principle to be used with respect to system losses is
that ‘the connection of the DG Plant should not result in system losses to be
more than when the system is without the DG Plant’.

4.2.5 Basic Protection, Control, Metering and Monitoring Requirements

4.2.5.1 Amongst others, the preliminary study report should indicate the following
basic requirements for connection:
1) Automatic Disconnection
ƒ On loss of mains
2) Synchronization Point and Procedure
ƒ On DG terminal
ƒ Re-synchronizing only proceed once the system is restored to it’s normal
state and sanction given by TNB.
3) Protection at Network Interface
ƒ The proposed protection scheme and setting from the DG plant to TNB
substations shall be reviewed and approved by TNB.
ƒ The purpose of the protection scheme is to ensure proper coordination
and integrity of the overall protection system at the interface points.
4) Monitoring of DG Network Operations
ƒ TNB needs to monitor the status, voltage and flows at interface
ƒ Monitoring using RTU to be provided DG developer.
5) Metering Point and Systems
ƒ The metering scheme to be reviewed by TNB.
ƒ Under Metering Code

4.2.6 Preliminary System Study Report

4.2.6.1 ‘Preliminary System Study Report’ is not normally provided to the DG


Developer. However, TNB is obliged to make presentation of the report to the
DG Developer. From experience, the duration required to conduct the
‘preliminary system study’ is about 2 months.

4.2.6.2 TNB is only obliged to provide summary of the results and connection
requirements of the Preliminary System Study Report and connection cost
estimates. The DG Developer may then use the results of the Preliminary Study
Report to decide whether or not to proceed with the DG project.

- 56 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4 .3 Power System Study


4.3.1 Objectives:

4.3.1.1 Following confirmation by the DG Developer to proceed, the DG plant project


then enters the design phase. It is assumed that at this point in time the DG
Developer would have more detailed information on the DG plant and submits a
formal application for connection to TNB (see Appendix C). While basic
connection requirements have been identified in the ‘Preliminary System Study’,
the objective of the ‘Power System Study’ are:
1) To identify additional controls and protection and operating strategies for the
DG plant when connected to the distribution network.
2) To be used by DG Developer to establish relevant specifications for DG plant
and its interface with the distribution network.

4.3.1.2 Power System Study is currently performed by TNB Distribution Division,


Engineering Services and Logistics Department based in Petaling Jaya. This
study is only carried out when all data as required in connection application form
have been provided and the study fee is paid to TNB by the DG Developer.

4.3.2 Data Requirements

4.3.2.1 It is important that when the DG Developer submits the application for
connection, data for the following major equipment of the DG unit(s) are
provided based on estimates or typical values to be provided as far as possible
by the intended manufacturers. The major manufacturer’s data are for:
a) Generator electrical
b) Generator transformer and grounding
c) Generator mechanical
d) Generator excitation control
e) Generator turbine-control
f) Generator other supplementary controls

4.3.2.2 As a follow up to the requirements of the ‘Preliminary System Study’, the DG


Developer must also submit the followings preliminary designs with the
application for connections:
1) Protection and control schemes;
2) Synchronisation scheme;
3) Control of equipment and their operation; and
4) Layout scheme of the plant and circuits.

- 57 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4.3.3 Power System Study Methods and Analyses

4.3.3.1 Since the data provided by the DG Developer can be assumed to be more
representative of the DG Plant to be established, it is therefore important for the
‘Power System Study’ to revisit the analysis carried out during the ‘Preliminary
System Study’, The analysis include:
1) Network voltage profile;
2) System/network Adequacy;
3) System Losses; and
4) Short-Circuit Studies.
However, at this stage more detailed analysis is required to identify possible
control measures including equipment that would be installed in the DG Plant
and interface specifications.

4.3.3.2 When evaluating voltage profile and controls the following inputs on the DG
units must be included:
1) Reactive capability curve;
2) Voltage control capability;
3) Power factor control capability;
Voltage profile under at least three load conditions of peak, intermediate and
light must be studied for the purpose of identifying the most suitable control
method – either voltage or power factor. The evaluation must also take into
consideration response of major voltage control equipment in the network such
as the main intake transformer in-service tap-changers.

4.3.3.3 Aspects of system/network adequacy should have been evaluated during the
‘Preliminary System Study’ to identify interface and reinforcement requirements
and no particular control is associated with this aspect. However, any
compensation equipment proposed by the DG Developer (based on the results
of the ‘Preliminary System Study’) could impact on the capacity of the network
and the interface and therefore this aspect should also be evaluated and
reported.

4.3.3.4 Impact on system losses with the connection of the DG is an important aspect
that must be thoroughly examined and cost estimated. This aspect must be
evaluated during the ‘Preliminary System Study’. However, there is a need to re-
evaluate the losses since compensation and parameters of equipment (including
transformer losses) would normally be different from what have been assumed
during the ‘Preliminary System Study’.

4.3.3.5 One most important purpose of the ‘Power System Study’ is to identify
measures or controls to limit impacts of increased fault level with the connection
of the generating unit. At this stage, it is vital that generator impedance and time
constant parameters provided by the DG Developer would represent the values
of the DG units to be installed. Any increase in fault of more than 90% of existing
equipment rating must be re-evaluated with fault level containment measures –
methods are discussed in chapter 3. It is also important to note that apart from
fault levels, the analysis must include evaluation of making and breaking

- 58 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

capabilities of switching equipment in the network particularly those closed to


the DG Plant installation.

4.3.4 Additional Analysis in Power System Study

4.3.4.1 Apart from the steady-state analysis described previously and where
appropriate, the Power System Study are to include two major additional
analysis, namely:
1) Stability; and
2) Insulation coordination.

4.3.4.2 It must be emphasized that the main purpose of the stability analysis is to
examine and analyse electromechanical transient responses of the DG unit
under various system faults and contingency situations so that necessary
measures could be specified to avoid potential damaging effects on the DG
units. For purposes of dynamic analysis, all generating units in the distribution
network must be modelled in detail. The transmission main intake source(s)
could be modelled as an infinite bus, that is, a classical generator with inertia
constant (H) of zero.

4.3.4.3 The DG Developer when submitting the application for connection must pay
particular attention to the data required for dynamic modelling of the generating
units. It is essential that the DG Developer obtains the services of experienced
consultant who would be able to provide accurate information for the dynamic
modelling of the DG Plant. Responsibility of estimating dynamic models of the
DG Plant should not be relegated to the Distributor who is carrying out the
Power System Study.

4.3.4.4 In carrying out stability analysis of the DG Plant connected to the distribution
network, the following factors that can affect generator stability must be noted
and taken into consideration when necessary:
a) Generator loading – the more the generator is loaded, the more advanced is
the rotor angle;
b) Generator output during the fault which depends on the fault location, type,
and severity;
c) Fault clearing time - in distribution system, long clearing time of protective
device following fault could result in loss of synchronism;
d) Post fault system reactance - loss of lines/ cables would change reactance;
e) Generator reactance - a lower reactance increases peak power and reduces
initial rotor angle;
f) Generator inertia - the higher the inertia, the slower the rate of change of
rotor angle and reduces the kinetic energy gained during fault;
g) Generator internal voltage magnitude - this depends on the field excitation;
and
h) Transmission source voltage magnitudes.

- 59 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4.3.4.5 As a minimum, response of the generating unit(s) to the following


contingencies must be evaluated and analysed:
1) Determine critical fault clearing time for 3-phase-to-ground fault on the star
side of the generator transformer (see Figure 4.3);
2) 3-phase fault for 500 ms at the main intake transformer secondary side
followed by loss of the feeder to the DG Plant (see Figure 4.4).
3) 3-phase fault for 500 ms on a bus in the feeder followed by loss of a spur
line/section supply large load.
Other contingencies to be applied must be considered depending on the
network configurations, including:
ƒ Presence of other generating units in the distribution network;
ƒ Presence of large motors where its starting behaviour need to be examined;

4.3.4.6 Where appropriate the following contingencies should also be analysed:


1) Determine critical fault clearing time for 1-phase-to-ground fault on the star
side of the generator transformer (see Figure 4.3);
2) 1-phase-to-ground fault for 3 seconds at the main intake transformer
secondary side followed by loss of one main intake transformer;

NER Fault

Figure 4.3: Fault for determining critical fault clearing time

- 60 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Feeder 1
Main Intake

Feeder 2

S DG Plant
2. Breaker
Opened

Feeder 3
DG

1. Fault

Reactor
Feeder 3

Feeder 3

Figure 4.4: Fault at main intake transformer secondary and loss of feeder to
DG Plant

4.3.4.7 In addition to transient stability analysis, the Power System Study, where
appropriate, may also include an ‘insulation coordination’ analysis to examine
the following two aspects of the DG connection:
1) Lightning over-voltages and arrester requirements at the interface point for
overhead line feeder;
2) Switching over-voltages under fault and load rejection conditions as well as
possible self-excitation (may also be examined using transient stability
analysis)
The transient over-voltages must be compared with the standard BIL and LIL of
the distribution equipment normally employed by TNB.

4.3.4.8 Control measures that could be applied to mitigate stability problems include:
1) Power system stabiliser (PSS);
2) Generator tripping scheme;
3) Generator intertripping scheme;
4) Dynamic brake; and
5) Pole slip protection.

- 61 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4.3.5 Power System Study Report and Liaison

4.3.5.1 Power System Study report must be submitted to the DG Developer upon
completion and the study must be completed within 4 months from the receipt
of application for connection with the complete data.

4.3.5.2 During the duration of the study, continuous interactions and communications
between DG Developer and Distributor are encouraged to clarify data and
assumptions used for the studies.

4 .4 Connection of the DG Plant to the Distribution Network


4.4.1 Connection Point and Connection Process

4.4.1.1 The connection point is a site in the distribution network at which the DG Plant
network connects the Distributor’s MV distribution network. Identification of the
connection point is not meant to imply ownership of apparatus adjacent to the
connection point. For practical purposes, a connection point is designated as
the MV circuit breaker that is under the operational responsibility of the
Distributor located at the interface. These connection points are also indicated in
Figures 4.1(a) through 4.1(c).

4.4.1.2 Connection process comprises of activities to be carried out when all


interfacing equipment are installed and before electrically connecting the DG
Plant to the distribution network. These activities are:
1) Protection coordination study;
2) Protective equipment tests and settings;
3) Inspections and pre-commissioning tests;
4) Commissioning procedure; and
5) Plant commissioning and tests.
The above activities are described in the following sections. Protection systems
drawings must be submitted to the Distributor for approval prior to any
Commissioning.

4.4.2 Protection Coordination Study

4.4.2.1 In order for a distribution network having a DG Plant to operate safely and
reliably, the protection devices in both the DG Plant and the distribution
networks must be properly coordinated. Coordinated operation of the protection
devices ensures that no damage to equipment could result due to flow of fault
currents and that only selected components of the network would be isolated to
remove the fault.

4.4.2.2 With the connection of a generator to the distribution network, the fault current
contribution would normally increase and if the generator is connected near to
the main intake substation, the fault level could exceed the short-time rating of
nearby equipment in the network. With the changes in the value of the fault
current and to ensure proper operation of protective devices, resetting and

- 62 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

coordinating of the affected protective devices are required and this is


performed through ‘Protection Coordination Study’.

4.4.2.3 Protection coordination study is carried out in two Phases:


1) Phase 1: DG Plant relay setting and data exchange
2) Phase 2: Distributor relay coordination study

4.4.2.4 In Phase 1, the following procedures are to be carried out by the DG


Developer:
a. Request TNB for short-circuit levels – 3-phase fault and 1-phase-to-ground
fault – at the point of interface with TNB;
b. Calculate settings of all relays in the DG Plant. In this case, the DG Developer
should propose settings for the protection of the DG Plant equipment
disregarding any coordination with the utility distribution protection;
c. DG Developer to submit a ‘DG Plant Protection Setting Report’ to TNB
addressing the following aspects:
• Protection philosophies adopted;
• Short-circuit limits including making and breaking capacities of
equipment - breakers, cables, lines etc.
• Generator limits - reactive, active power, field current and voltage
limits, over-speed and under-speed;
• Documents or references on characteristics of the relays and fuses
employed;
• Breaker operating time – time taken from receipt of tripping signal
from relays to full opening of breaker contacts;
• Proposed settings/coordination curves (if applicable) of relays in the
DG Plant and the reasons for the chosen setting; and
• Other important limits on the DG Plant equipment that the Distributor
should know.

4.4.2.5 Upon receipt of the ‘DG Plant Protection Coordination and Setting Report’, the
Distributor must examine the report particularly the protection philosophies and
data on protection relays. In Phase 2, the Distributor must carry out a ‘Protection
Coordination Study’ with the assumption that the DG Plant is connected to the
distribution network. The ‘Protection Coordination Study’ Report should address
the following aspects:
ƒ The proposed relay settings and their coordination; and
ƒ Changes required, if any, on the DG plant relay settings and the reason for
the changes.

- 63 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4.4.3 Protective Equipment Tests and Settings

4.4.3.1 Protective equipment including relays must be tested in accordance with


prudent utility practices to confirm that they are in good working condition after
installation. When all tests are satisfactory, the relays could then be finally set to
the approved setting values.

4.4.3.2 Secondary injection tests are usually carried out to ensure that protective
relays, meters and other control equipment are installed and wired properly and
in good condition for service. For each protective relay, its approved operating
settings (see 4.4.2 on protection coordination study) will be set following
completion of the tests. It is the responsibility of DG Developer to carry out the
tests for protective and control equipment within the DG Plant.

4.4.3.3 Tests and setting of protective relays at the interface/connection points and its
associated equipment (current and voltage transformers) should normally be
carried out by the DG Developer using services of licensed test engineers
approved by the Distributor. The tests and settings programme must be
coordinated with the Distributor to ensure that all safety switching requirements
are met and that the Distributor representatives are available for witnessing the
tests.

4.4.3.4 Prior to carrying out protective equipment tests and settings at the
interface/connection points, the DG Developer should submit the following to
TNB:
1) Test programme;
2) List of equipment to be tested;
3) Test methods/procedures;
4) Access requirements to TNB’s sites or part of the network.
Tests of protective equipment at the interface should only be carried out with the
approval of TNB of the test programme.

4.4.3.5 In addition to testing of protective equipment, check and tests must be carried
out on DC equipment and control circuits. Test of the DC equipment is of main
interest of the utility since in many cases, this facility is shared with the DG Plant.

4.4.3.6 On completion of protection and control tests, the DG Developer must submit
the test reports to the Distributor for approval prior to commissioning and
energising of the connection.

- 64 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4.4.4 Inspection and Pre-Commissioning Tests

4.4.4.1 Prior to commissioning of the connection and thus parallel operation of the DG
Plant to the distribution network, inspections and pre-commissioning tests
should be carried out. It is the responsibility of the DG Developer to perform
inspection and pre-commissioning tests for the DG Plant and its network.
However, for the interface/connection equipment, it is the responsibility of the
Distributor. The inspection and pre-commissioning tests should be initiated by
the DG Developer and coordinated with the Distributor. At this point in the
connection process, all protective devices are set and test reports are submitted
and approved by the Distributor.

4.4.4.2 Inspections that need to be carried prior to commissioning and energisation


are visual examinations of the following conditions or equipment:
a) General inspection of connection equipment & facilities;
b) Site conditions – should be free from leftover construction debris particularly
that may pose safety hazards;
c) Grounding – all electrical equipment must be adequately grounded;
d) Nameplate information – ensure that approved nameplate information are
sufficiently clear and installed in accessible locations;
e) Labelling – equipment and safety labels must be clearly visible and
noticeable;
f) Clearances – ensure that clearances to live parts are within safety
requirements;
g) DC system – final tests should be carried out on tripping of circuit breakers
and functioning of control circuits supplied from the DC supply;
h) Control wiring – visible inspection of control wiring to ensure that they
properly segregated and bunched;
i) Switches – tests of all switches to ensure that they are working properly
including full closing and opening and operation of motorized mechanism, if
any;
j) Breakers – ensure that circuit breaker auxiliary tools are in place and the
truck racking in and out operations are tested;
k) Surge arresters – visual inspection to ensure that arresters are installed and
connected to the lines and it's grounding is properly connected with no sign
of damage to the arrester housing; and
l) Transformers – inspection of the physical conditions of transformers
including signs of oil leaks, colour of silica gel, connections and grounding.
It is a normal practice for the DG Developer to prepare a check list of particulars
to be inspected and verified for each of the above items.

4.4.4.3 Pre-commissioning tests that are normally carried out include:


a) Earthing resistance measurements;
b) Discharge and recharge tests of DC batteries;
c) Test circuit breakers for electric trip and close, manual trip and close, breaker
operation time, insulation level, interlocks and status indicators, heaters; and
d) Transformer test include; oil dielectric tests, winding configuration and phase
check, turns ratio, insulation tests of windings etc.

- 65 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4.4.5 Commissioning Procedure

4.4.5.1 Prior to commissioning of the DG Plant and the interface/connection, the DG


Developer in consultation with the Distributor should identify step-by-step
energisation of equipment before synchronization. If there is doubt as to the
impacts on system performance during the energisation, simulation of the
energisation sequence may need to be performed to ensure network conditions
will remain within criteria limits. This is particularly important when energizing DG
Plant involving long lines with reactive compensation. Energisation procedure
document should include:
ƒ List of precautions to be taken during energisation;
ƒ Ensure that other tests (see section 4.4.3 and 4.4.4) are completed and
approved;
ƒ Identify steps for connecting

4.4.5.2 As an example, steps for connecting the DG Plant in Figure 4.5 to the
distribution network could comprise of the following steps:
1) Ensure that breaker BR3 is opened and line BR4 – BR3 ready to be energized
and all safety earthing removed;
2) Close switch BR4;
3) Live test incoming voltage at BR3;
4) Rack-in breaker BR3;
5) Close SW4 of shunt reactor;
6) Close breaker BR3;
7) Record voltage at DG Plant busbar;
8) Energise auxiliary transformer through SF2;
9) Open generator turbine control valve and run generator to full speed;
10) Excitation controller on manual until terminal voltage magnitude is reached;
11) Set AVR on automatic control;
12) Set governor on speed control;
13) Close breaker BR1 and this energises the generator transformer;
14) Ensure the synchronisation parameters are within limits and synchronise
through closing of breaker BR2.

- 66 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

SW4
AVR

BR1
G
BR2
BR3

SF2

Governor

From source SW1 BR4 SW2

SF1

Figure 4.4: Example system for energisation procedure

4.4.6 Plant Commissioning and Tests

4.4.6.1 As described in an example in 4.4.5.1, typical energisation steps are:


1) Energize circuits from utility side
2) Auxiliary transformer
3) Generator
4) Generator transformer
5) Synchronisation

4.4.6.2 In the case of the synchronization point being located on the generator
breaker, it is usual to energise generator-transformer from the utility side.
Otherwise as in Figure 4.5, the generator transformer is energized from the
generator and this is to be done after the generator has reached full speed and
attained full terminal voltage.

4.4.6.3 When energizing the synchronous generator, the generator will initially be in
open position. The turbine is first operated manually to full speed. Excitation
should only be applied when the speed is more than 90% of rated speed. Both
turbine and excitation controls are manually adjusted until full speed and the
terminal voltage is reached.

- 67 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4.4.6.4 Before synchronization is performed, ensure the followings are verified:


ƒ Generator phase voltages are well balanced – line-neutral voltage difference
should not exceed 1%;
ƒ Line-to-line and line-neutral voltage are related by factor of /3; and
ƒ Phase rotation of generator voltage to be compared with utility side voltage.
Synchronisation is carried using synchroscope where all parameters are satisfied
before the synchronising breaker is closed.

4.4.6.5 Following successful synchronisation and parallel operation of the DG Plant


with the distribution network, the following tests and checks are normally carried
out:
a) Load rejection tests;
ƒ To verify dynamic response of generators
b) Loss of mains test or anti-islanding test; and
c) Final site checks.

4.4.6.6 Before load rejection tests are carried out, recording equipment that will not
only measure electrical quantities (AC and DC) but also mechanical quantities
such as speed and valve positions should be installed. Real and reactive power
load rejection tests are carried out to record and verify dynamic response of the
unit. Opportunity must be taken to perform load rejection tests whose results
could be used to verify and derive generator parameters including excitation and
governor controllers. The tests comprise of staged test at several active and
reactive power output with excitation controllers in manual and automatic
modes. The procedure for load rejection tests would be discussed with
Distributor and normally the Distributor would absorb the generator output
power during the tests.

4.4.6.7 Loss of mains tests should be carried out to ensure that the generating plant is
isolated from the distribution network when any of the utility-side circuit breaker
is opened. An agreed test procedure should be developed between the DG
Developer and the Distributor. The DG Plant Operator should note that loss of
mains protection may not operate at times and should take reasonable
precautions. It may be appropriate that ROCOF type relays be monitored and
studied for its performance.

4.4.6.8 Final site checks should then be carried out before leaving the plant operating
in parallel with the distribution network. These checks are visual inspection of all
major equipment in the plant including, light indicators, transformer noise level,
corona noise, oil leaks, temperature etc.

4.4.7 Establishment of ‘Connection Operation Manual’

4.4.7.1 ‘Connection Operation Manual’ is a document to be jointly prepared by the DG


Developer and Distributor outlining procedure to be followed for operation of the
connection of the DG Plant to the distribution network. This document is
technical and procedural in nature. One important element that must be included
in all operating procedures is the safety aspect.

- 68 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4.4.7.2 Typical contents of the COM include but not limited to the followings:
1) Objectives of the COM – could be slightly different from the perspective of
each party;
2) Description of the connection/interface facilities and responsibility of each
party:
ƒ Circuit breakers, isolators
ƒ Synchronizing equipment
ƒ Interlocking system
ƒ Grounding/earthing facilities
ƒ Protection and controls
ƒ Metering
3) Liaison and Communication – communication methods and procedures, and
contact persons;
4) Switching and isolation procedure – a step-by-step switching procedure for
all major equipment at the interface/connection point as well as the DG Plant;
5) Procedure for Reporting/Notifications of Events/Outages/Faults;
6) General outline of DG Plant maintenance requirements;
7) Emergency Operation Procedures

- 69 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4 .5 Operation of the DG Plant with the Distribution Network


4.5.1 Control Operation

4.5.1.1 Normally the day to day operation of the DG Plant is the responsibility of
the DG Operator. However, the Distributor may need to exercise control under
the following circumstances:
ƒ When the DG plant is operating on varying output mode;
ƒ For safety reasons;
ƒ For reasons associated with supply reliability; and
ƒ For reasons associated with power quality.

4.5.1.2 Control needs for reasons as listed above or any additional reasonable
basis must be included in the ‘Connection Operation Manual’.

4.5.2 DG Operating Modes

4.5.2.1 In terms of power output into the distribution network, a DG Plant could be
operating in any of the following modes:
1) Constant MW output for the whole day
2) MW output following load demand – load following
3) MW output depending fuel supply variations
4) Zero MW output
The first two operating modes are illustrated in Figure 4.5.

MW Distribution
MW profile
Load
following

Constant
MW

Time 24-hours

Figure 4.5: DG Operating Modes

4.5.2.2 For a DG Plant with constant MW output, it is a practice to ensure that the DG
output will remain 15% below the minimum load of the distribution network as
illustrated in Figure 4.6.

- 70 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Transmission
Distribution Network
Network

Load Profile
MW

Lpk

15%
DG Lmin

DG Output to remain
15% below minimum load or
less Hours

Figure 4.6: Constant MW output to remain 15% below minimum daily load

4.5.2.3 ‘Load following’ operating mode allows the DG plant output to be varied over
the 24-hour period so that its output would remain 15% below the total system
demand as illustrated in Figure 4.7.

Transmission
Distribution Network
Network

Load Profile
MW

Lpk

DG Lmin

DG Output to remain
15% below load or
less Hours

Figure 4.7: Load following mode with MW output to remain 15% below load
profile

- 71 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4.5.2.4 The MW output of a DG Plant could vary depending on availability of fuel and
this is typical of biomass DG Plant. In this case of operating mode, the maximum
MW output of the DG plant must remain 15% below load profile.

4.5.2.5 For all operating modes, the Distributor must be notified of the scheduled
output of generator on weekly and daily basis and this procedure is carried out
under the operation planning process discussed below.

4.5.3 Distribution Operation Planning

4.5.3.1 Distribution Operation Planning is a task carried out by the Distributor to


establish Operation Plan that contains strategies on how the distribution network
should be operated under normal and abnormal conditions following
contingencies after taking into consideration several items including scheduled
output of DG Plants. The main objective of the Operation Plan is to ensure that
security supply is maintained to all customers inline with the requirements of
operation criteria. It is usual for the Distributor to establish an ‘Annual Operation
Plan’ that is reviewed on monthly basis and be used on daily basis for a day a
head operation.

4.5.3.2 Two major inputs to the ‘Annual Operation Plan’ are scheduled weekly profile
of DG Plant outputs in MW and MVAR and scheduled maintenance outages of
the DG Plant. Using these two inputs together with other network information,
the Distributor would establish plans for network operation. One important
results of the Operation Plan that of interest to the DG Operator is the scheduled
output of DG Plant particularly those that have to be limited due to network and
demand constraints.

4.5.3.3 The ‘Annual Operation Plan’ should also contain liaison and communication
information between Distributor and the DG Operator.

4.5.4 Exchange of Operational Information

4.5.4.1 Distribution network operation is usually organized with control responsibility


being assumed by a control centre and/or a supply management centre. The
control centre monitors, controls and operates the distribution network and have
direct communication with the Transmission Network Operator as well as DG
Operators.

4.5.4.2 To coordinate the operation of the distribution system, the Distributor and all
other connected entities including the DG Operator must maintain
communication and exchange information on operations and events. There are
four major occasions where operational information are to be provided by the
DG Operator to the Distributor:
ƒ Information for Annual Operation Plan and monthly review;
ƒ Notification of operations;
ƒ Notification of events; and
ƒ Reporting of faults and/or outages.

- 72 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Exchange of the above information and other relevant information must be


included in the Connection Operation Manual (COM). Typical information for
Annual Operation Plan to be provided by the DG Operator to the Distributor are
discussed in 4.5.3

4.5.4.3 DG Operators must notify the Distributor of any operation that will have or may
have an effect on the distribution network including but not limited to the
following :
a) implementation of scheduled outages of plants and / or equipment which has
been reported and arranged previously;
b) switching operation that will result in temporary disconnection at the point of
interface to the Distributor’s distribution system;
c) switching operation for paralleling of system;
d) generating unit synchronizing; and
e) changes in voltage controls.

4.5.4.4 The notification to the Distributor must contain sufficient detail describing the
operations, and locations of equipment and must be provided before the
implementation of the operations. Likewise, in case of any operation in the
distribution system, which to the opinion of the Distributor, will have or may have
effects on the DG Plant, the Distributor should inform the DG Operator of such
operations.

4.5.4.5 DG Operators must also notify the Distributor of any event in their system
which has had or may have had an effect on the distribution network including
but not limited to the following:
a) the activation of any alarm or indication of any abnormal operating
conditions;
b) breakdown of or faults on, forced or partial outages of plant and/or apparatus
including protection and controls;
c) increased risk of inadvertent protection operation;
d) operation of plant and / or apparatus either manually or automatically; and
e) occurrence of voltage levels outside the required limits;

4.5.4.6 The notification to the Distributor must be given in sufficient detail to describe
the event and locations of equipment immediately by phone after the event has
occurred to allow for the Distributor to make the necessary assessment on the
implications of the event and if necessary to make adjustment to the distribution
system. This is normally followed by a detailed written report submitted to the
Distributor. Similarly, in case of any event that has occurred in the distribution
system that has had or may have had effects on DG Plant, the Distributor should
inform the DG Operator.

4.5.4.7 When forced outages or any significant event has occurred in the DG Plant
which have or may have resulted in interruption of supplies to Customers in the
Distributor’s distribution system, the DG Operator must verbally inform the
Distributor of the event providing the details of sequence of events known at that
time leading to the supply interruption. Both DG Operator and Distributor shall
coordinate actions to restore supplies to Customers according to the required
security levels.

- 73 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

4.5.5 Operating and Safety Requirements

4.5.5.1 It is important that for the safety of operating staff and public, both the
Distributor and the DG Operator must coordinate, establish and maintain the
necessary isolation and earthing when work and/or tests are to be carried out at
the interface/connection point. The safety coordination applies to when work
and/or tests that are to be carried out involving the interface between the
distribution network and the DG Plant and it is the responsibility of the
Distributor and DG Operator to comply with the requirements of statutory acts,
regulations, sub – regulations, individual license conditions, Standardized
Distributor’s Safety Rules and the Malaysian Grid Code.

4.5.5.2 For purposes of safety coordination procedure, the following requirements are
prerequisites:
a) at each point of interface/connection between the distribution network and
the DG Plant, the boundary of ownership is clearly defined;
b) the Distributor and the DG Operator provide each other with the operating
diagrams of their respective side of the point of interface/connection;
c) the Distributor and the DG Operator must exchange information on safety
rules and / or instruction as practiced in their respective system.
The above information must be included in the Connection Operation Manual.

4.5.5.3 All switching operations shall be carried our according to the procedures as
defined in the Standardized Distributor’s Safety Rules (TNB Safety Rules), which
shall include but not limited to the following:
a) Coordination;
b) Isolation;
c) Earthing;
d) Recording;
e) Testing;
f) Commissioning;
g) Cancellation; and
h) Reenergizing.

- 74 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Chapter 5: Interface Design Requirements and


Network Reinforcements

5 .1 Introduction

5.1.1 An interface between a DG plant and the distribution network comprises of the
following set of equipment:
ƒ protection and control of the connection;
ƒ metering facilities for measurements of power and energy; and
ƒ SCADA facilities for remote monitoring and controls.
A connection interface in relation to the distribution network and operation
centre as well as the DG Plant is illustrated in Figure 5.1.

Pt, Qt
Distribution
System

Transmission
System

DG Plant
Distribution
Connection Operation/
Interface Control
Centre
CB CB

Sync
M

Communication/Data exchange

Figure 5.1: Connection interface

5.1.2 Many technical issues identified in chapter 3 and its analysis as described in
chapter 4 can be resolved and addressed by having a proper interface design.
However, there are technical issues that cannot be addressed at the interface
but may have to be incorporated in the DG plant at the design stage.

- 75 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

5.1.3 The main objective of this chapter is to summarise the requirements of typical
interface design and equipment. In addition to this, the chapter will also discuss
the types of reinforcements in the distribution network that may become
necessary with the connection of the DG Plant. This chapter will also indicate
how connection costs are calculated including the aspects on losses. The topics
covered in the chapter are:
1) Basic Connection Interface Requirements
2) Utility Access
3) Synchronisation
4) Protection and Control
5) Interlocking
6) Metering
7) SCADA and Automation
8) Communications
9) Network Reinforcements
10) Cost estimation

5 .2 Basic Connection Interface Requirements


5.2.1 Isolation

5.2.1.1 The designated connection point of a DG Plant to TNB network must include a
means of isolation the two systems (DG Plant/Network and TNB Distribution
Network). The following are requirements for the isolation point:
a) It must be suitably labelled;
b) It must be capable of safety isolating the whole of the DG output from the
TNB’s Network.;
c) It must have facilities to permit work to be undertaken on the TNB network
without danger to staff;
d) Isolation must be lockable in the isolated position in accordance to TNB’s
standard safety locking procedures;
The above requirements are illustrated in Figures 5.2(a) and 5.2(b).

Interlocked
Isolation point:
•Isolate from TNB network
DG Plant
•Suitably labeled
•Safely isolating DG output
•When opened cannot
synchronise (interlocked with
synchronising switch)
•To permit work
•Grounding requirement
Feeder •Lockable
G

Figure 5.2(a): Basic interface/connection point requirements – 3-breaker


scheme

- 76 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Isolation point:
DG Plant •Isolate from TNB network
•Suitably labeled
•Safely isolating DG output
•When opened cannot
synchronise (interlocked with
synchronising switch)
•To permit work
Feeder •Grounding requirement
•Lockable
G
Interlocked
Figure 5.2(b): Basic interface/connection point requirements – two breaker
scheme

5.2.2 Connection through Star-Delta Transformer

5.2.2.1 Although the design and configuration of a new DG Plant is the responsibility
of the DG Developer, there are basic requirements to be met for ensuring safe
and secure operation of the integrated systems. These basic requirements
applicable to the DG Plants are:
1) The Generator star shall be earthed or grounded.
2) The choice of generator neutral grounding is up to the DG Developer.
However, the followings should be noted:
ƒ normally DG units are designed to withstand maximum 3-phase fault
current but not necessary unrestricted phase-to-ground fault current; and
ƒ use resistor to limit earth-fault current to 300A irrespective of size is a
common practice with step touch voltage within the criteria limits.
3) Two-or three winding transformer with star winding on the Distributor’s side.
4) The star side of the transformer which connects to the Distributor’s network
shall be grounded through an NER designed to limit earth fault current of
150A to flow from the generator side on a single-line to ground fault on the
star side of the generator transformer (see Figure 5.3).
5) An earth fault relay must be installed to detect earth faults on the Distributor’s
network fed from the Generator and to disconnect the DG network from
TNB’s network.

5.2.2.2 Where a DG Plant that has its own network and comprising of more than one
generating units, an interface transformer as illustrated in Figure 5.4 shall be
required. For this case the star-side of the interface shall be grounded as
described above. It is recognised that existing installation may not currently be
connected through interface transformers. For these existing installations,
including generating plant upgrades, may not require interface transformers.

- 77 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

DG Plant Distribution
Network

EF Relay
NER

1-phase to
ground fault

150A

Figure 5.3: Earthing/grounding at the interface

Pt, Qt
DG Plant/Network

Transmission
System
G
M

Interface through
Delta-star transformer
Distribution network

Figure 5.4: DG Plant/network interface through delta-star transformer

5 .3 Utility Access

5.3.1 To enable TNB's operational staff a 24-hour access to the switchgear and
equipment that TNB has operational responsibility for, consideration should be
given to the location of the interface or connection point to permit such access.
Access off an all weather road surface is preferred where this is practicable,
otherwise delays will be experienced.

- 78 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

5.3.2 It is acceptable that the interface/connection control panel under TNB’s


responsibility be located in the same premises or building as the DG Operator
control panels. However, visible and clear indication must be provided to
distinguish TNB’s control panels from those under the operational control of the
DG Operator. Access procedure to the interface/connection point must be
stipulated in the Connection Operation Manual (COM). The COM must address
access to the following equipment:
ƒ Control and relay panels;
ƒ Circuit breakers;
ƒ Metering;
ƒ Interlocking control;
ƒ Locking devices.

5 .4 Synchronisation

5.4.1 DG unit control system must include synchronization facilities to enable the
generator to be connected to the distribution network, Control facilities and
methods to be employed for synchronization will need to be approved by TNB.
An automatic synchronizing panel from a recognized manufacturer, designed for
the type of machine proposed, will normally be acceptable.

5.4.2 Synchronisation point is usually a breaker under the operational responsibility of


the DG Operator. This synchronization point and the breaker must be adjacent
to the breaker under the operational responsibility of TNB. Locations of
synchronizing facilities for various connection configurations are illustrated in
Figures 5.5 and 5.6.

DG Plant DG Plant

Utility Utility

Feeder Feeder
House
G load G

Interlock
Synchronisation
point

Dual-breaker scheme Three-breaker scheme


Figure 5.5: Synchronisation points and interlocks (1)

- 79 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Feeder

DG Plant

Utility
Utility

Feeder Feeder

G G
DG Plant
Interlock
Synchronisation
point
Three-breaker scheme Three-breaker scheme
With bus-coupler With bus-coupler

Figure 5.6: Synchronisation points and interlocks (2)

5.4.1 For synchronising synchronous generator to the distribution system the


synchroscope should be able to detect that the following limits be satisfied
before closing of the breaker is allowed:
a) Frequency difference: < 0.2 Hz;
b) Voltage magnitude difference: < 10%;
c) Voltage angle difference: < 10 degrees; and
d) Interlocking logics are satisfied.
Frequency/speed is adjusted for the generator by the governor control and the
voltage magnitude by the excitation control. The voltage angle is used to
indicate that there is no gross mistake in vector groups of the two systems and
therefore the limits on voltage angle difference may have to be relaxed
depending on the system.

5 .5 Protection and Control


5.5.1 Protection

5.5.1.1 The protective scheme must be based on the need to detect system faults and
malfunctions both within the DG installation as well as the distribution feeder. On
detection of fault or malfunction, the relays must trip appropriate circuit breakers
to isolate the faulty section:
ƒ to minimise equipment damage and safety hazards during the faults; and
ƒ to maintain power supply continuity on healthy parts of the system.
Although the design and types of protection for the DG installation is the
responsibility of the DG Developer, the Distributor must ensure that these
protections are properly coordinated for reliable and safe operation of the
distribution feeder (see section 4.4). See also Appendix F for details on
protection practices in TNB

- 80 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

5.5.1.2 The basic requirements for the types and design of the protection schemes are
that:
1) For any internal fault within the DG installation, the DG must not cause
problems to the utility system and the utility customers; and
2) For any distribution network fault outside the DG Plant, the generator must
be protected from any damaging effects.

5.5.1.3 For generating units directly connected to the distribution network, the
following protections are required:
a) Under Voltage (UV);
b) Over Voltage (OV);
c) Under Frequency (UF);
d) Reverse Active Power (RP);
e) Overcurrent (OC);
f) Earth fault (EF);
g) Step up transformer protection; (above 5 MVA transformer size
recommended to include transformer unit protection);
h) Loss of system synchronisation / Field failure relay (FF);
The following paragraphs describe the reasons for the requirements of the above
protection. For generating units, embedded within its own network, items a, b
and c are required at the connection point. For these generating units, items e, f
and g will be required for the connecting cables and the interface transformers.
These minimum requirements are detailed in Appendix F, Section F.3.

5.5.1.4 UV and UF relays are designed to trip the generator when the distribution
feeder is taken off (loss-of-mains). When the feeder is supplying load greater
than the capacity of the generator, under-frequency and under-voltage are
expected to occur to trip the generator. The setting of the under-frequency trip
(Hz) must be based on the recommendation of the manufacturer. If the feeder
load to be supplied by the generator is less than the generation, over-frequency
will occur and therefore OF relay is required. The setting of the OF relay must
also be based on the recommendation of the generator manufacturer. However,
when the feeder load is sufficient to be supplied from the generator under
islanded operation, UV, UF or OF relays may not operate and special relays such
as ROCOF and Vector Shift will be required (see section 3.8).

5.5.1.5 If the resulting feeder load could be totally supplied by the generator under
islanded operation, this may present a hazard to personnel. Generator damage
would be likely when the feeder breaker is reclosed. In distribution systems,
feeder breakers are not equipped with dead line check to prevent reclosing on
live feeder. An alternative to dead line check relays is an automatic transfer trip
that upon opening of the utility feeder breaker, a signal is provided to trip the
generator. Any islanded operation required later must be performed based on
operation and safety procedures agreed by both the generator and the utility.

5.5.1.6 OV relays are installed on the DG side to protect against over voltages
resulting from a sudden loss of load. However, the generator voltage regulator
will take care of the over voltage by reducing excitation. Therefore, the over-
voltage relay would be useful if when the voltage regulator is defective or limited
that it would result in sustained over-voltage. Transient over-voltages due to

- 81 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

switching or lightning should be catered for by the design of the distribution


network and DG system insulation level and coordination.

5.5.1.7 To prevent damage on the prime mover (turbine system) due to motoring of the
generator during reversal of power, RP or directional relays are installed. Time
delay must be incorporated to prevent nuisance tripping during synchronization
of the generator.

5.5.1.8 Combined over-current and earth-fault (OCEF) relays are employed for
protection of over-current and earth-fault in both directions. IDMT relays
equipped with instantaneous trip are used in this case. For large generators
provided with its own unit protection, the OCEF relays are used as backup for
the generator internal fault. During distribution system fault, both generator
OCEF and feeder OCEF would see these fault currents. Coordination of the
generator OCEF relays with that of feeders would become more difficult due
flow of fault currents from both sources into fault. It is normal practice that on a
distribution fault on the feeder, the feeder OCEF is allowed to trip first followed
by the generator. If the fault is cleared and the generator operates in isolation
then frequency and voltage relays would likely to operate depending on the
generation-demand balance. However, if inter-trip is provided, the generator
would also be tripped out.

5.5.1.9 Loss of synchronism manifested into generator over-speed or under-speed


that would be detected by the generator mechanical speed relays.

5.5.1.10 Field failure (FF) relays are employed to detect malfunction of the generator
excitation field. Upon loss of excitation, the generator rotor accelerates to
above synchronous speed where it continues to generate power as an
induction generator. Loss of field is normally detected by an undercurrent
relay connected to a shunt in the field circuit.

5.5.1.11 Negative phase sequence relays are employed to detect excessive unbalanced
loading of the generator.

5.5.2 Controls

5.5.2.1 To provide for safe and flexible operation of the DG Plant and its
interconnection, the followings controls are required:
1) Breaker controls;
2) Turbine-governor controls;
3) Excitation controls;
4) Synchronising controls; and
5) Emergency trip controls.

5.5.2.2 Basic breaker controls functions are ‘trip’ and ‘close’ both at local and remote
locations. Typical features for breaker controls must include:

- 82 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

a) For synchronizing breaker, the ‘close’ control must be operated through


synchronizing control and close only when conditions listed in 5.3 are
satisfied.
b) Interlocking control logic.

5.5.2.3 DG unit connected to MV network must be equipped with automatic turbine-


governor control for several purposes:
ƒ For load following;
ƒ For control of generator speed during load rejection and loss of mains.
For small DG unit with constant output power mode, it may not be required to
have automatic governor control provided that the generator will not be
susceptible to damages following protracted over- or under-speed conditions.
However, all units must have means to control turbine output manually for
starting and shutting down.

5.5.2.4 DG unit must be capable of both voltage and power factor controls. Both of
these controls are discussed in chapter 3. These controls are achieved through
excitation system. Voltage control is achieved through automatic voltage
regulator (AVR) that regulates the reactive power output and absorption by the
generating unit to maintain the desired terminal voltage. If the generator is
required to be on power factor control, the AVR will adjust reactive power output
to maintain to the desired power factor disregarding the resulting terminal
voltage level. These controls refer to exporting sites only. Importing sites are
subject to the demand power factor requirements.

5.5.2.5 Synchronisation requirements are discussed in section 5.3. Apart from the
requirements in 5.3.3, the synchronizing control must also ensure that excitation
current could only be applied when the generator speed has reached at least
85% of nominal value.

5.5.2.6 Emergency trip control should also be provided for isolating the DG Plant from
the distribution network (breaker at the interface). This ‘push-button’ type control
should be located at convenient place for access by TNB operator particularly
for emergency purposes.

- 83 –
Tenaga Nasional Berhad TNB Research

5 .6 Interlocking

5.6.1 Operating interlocks are required to prevent undesired operation that could
present safety hazard to operating staff or public. Operating interlocks are
categorized into two purposes:
ƒ Preventive
ƒ Corrective

5.6.2 Preventive interlock inhibits operation until all required conditions are satisfied.
Examples of preventive interlocks are:
ƒ Inhibit breaker closing for parallel operation until synchronizing criteria are
met (see 5.6).
ƒ Remote and local control of circuit breakers – remote control inoperable
when local control is selected
ƒ Utility and synchronizing breakers as shown in Figures 5.5 and 5.6:
- Synchronizing breaker cannot be closed if utility breaker is opened.
- Utility breaker cannot be closed if synchronizing breaker is closed;

5.6.3 Corrective interlocks do not inhibit breaker operation but initiate the additional
remedial operations to enable the desired operation. An example of corrective
interlock is illustrated in Figure 5.7. If BR3 is opened then BR2 automatically
opened. Loss of Mains intertripping is another example of corrective interlock.

SW4 (No Load Break


Switch)

Bus
BR1 Reactor
G
BR2
BR3

SF2

From source SW1 BR4 SW2

Figure 5.7: Example of corrective interlock

- 84 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

5.6.4 All necessary interlocks must be clearly described in the interface/connection


design for the approval of the Distributor.

5.7 Metering

5.7.1 Each connection/interface point to the distribution network must have metering
installations unless other arrangements are made with the Distributor. There are
two types of metering normally required at the connection/interface point:
1) Revenue metering; and
2) Operational metering.
This section provides only general guidelines on metering requirements. For
detailed requirements, the Metering Code adopted by the Distributor should be
referred to.

5.7.2 For the purposes of revenue metering, the following quantities are to measured:
ƒ Active power delivered to the Distributor (kW or MW);
ƒ Reactive power delivered to the Distributor (kVAR or MVAR); and
ƒ Energy delivered to the Distributor (kWh or MWh).
Where there is a possibility of power being supplied from the distribution system
to the DG Plant the following revenue metering are also required:
ƒ Active power consumed by the DG Plant (kW or MW);
ƒ Reactive power consumed by the DG Plant (kVAR or MVAR); and
ƒ Energy consumed by the DG Plant (kWh or MWh).

5.7.3 In the case of DG Plant, it is usual for the DG Developer to install all the meters
and associated current transformers, voltage transformers, panel and wiring at
the connection/interface point in accordance with the requirements of the
Distributor. The Distributor shall later maintain the metering installation including
any required meter accuracy instrument transformers.

5.7.4 Check meters will normally be used on connection/interface point where the
monthly active energy passing through is above 50,000 kWh or where a
maximum demand exceeds 7.5 MW and with reactive check meters being
installed where reactive energy passing through exceeds 250,000 kWh or as
otherwise determined by the Distributor. Check meters are to be used to provide
metering data validation, substitution or estimation when the main revenue
meters are suspected to have malfunctioned.

5.7.5 The metering installation may consist of combinations of voltage transformers,


current transformers, secure and protected interconnecting wiring, meter, data
logger, communication interface equipment, alarm circuit, test links, and other
appurtenances as determined by an Agreement or the Distributor’s Standard.

5.7.6 The followings are requirements for metering accuracies of active energy ( kWh )
meters for different range of active energy passing through interface/connection
point:
1) Between 50,000kWh and 250,000kWh:
ƒ Main and check meters of class 2.0 with ±2% accuracy and allowable
error of ±4%

- 85 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

2) Between 250,000kWh and 5,000,000 kWh:


ƒ Main and check meters of class 0.5 with ±0.5% accuracy and allowable
error of ±1%.
3) More than 5,000,000 kWh or having maximum demand exceeding 7.5 MW:
ƒ Main and check meters of class 0.2 with ±0.2% accuracy and allowable
error of ±1%.
5.7.7 The followings are requirements for metering accuracies of reactive energy (
kWh ) meters for different range of reactive energy passing through
interface/connection point:
4) Between 50,000kWh and 250,000kWh:
ƒ Main meters of class 3.0 with ±3% accuracy and allowable error of ±6%.
5) More than 250,000 kWh or having maximum demand exceeding 7.5 MW:
ƒ Main and check meters of class 3.0 with ±3% accuracy and allowable
error of ±6%.

5.7.8 The Distributor should routinely test and calibrate revenue meters in accordance
with current prudent utility practices. This would normally include periodic
random audits of metering installations to confirm compliance with adopted
metering standards.

5.7.9 Operational metering at the interface/connection points include the following:


1) Current reading in ampere (A) for each phase;
2) Voltage reading in kV for each phase-to-phase;
3) Frequency in Hz; and
4) Real and reactive power flows.

5 .8 SCADA and Automation

5.8.1 All DG Plant interface/connection point must be equipped with the following
SCADA facilities:
ƒ Remote Terminal Units (RTU) c/w Marshalling cubicle; and
ƒ Communication system from DG plant to TNB control centre.

5.8.2 The RTU shall monitor the following:


ƒ Frequency (Hz);
ƒ Voltage (Volts);
ƒ Current (Amps);
ƒ Real Power Energy flow (kW or MW);
ƒ Reactive Power Energy flow (kVAR or MVAr); and
ƒ Energy meters.
ƒ Breaker Status
ƒ Relay indications, where appropriate.
Where appropriate, derived values, for example real power from voltage and
current phasors would be acceptable.

5.8.3 If remote control of switches that are in the jurisdiction/area of responsibility of


TNB are required to be installed at TNB’s control centre, this shall be able to be
executed via the RTUs. RTU installed must be able to communicate with TNB

- 86 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Master System using IEC 60870-5-101 TNB’s matrix or protocol determines by


TNB.

5 .9 Communications

5.9.1 The communication system between the DG Plant interface/connection point


where the RTU is located and TNB control centre should be dedicated and
reliable communication network. The mode of communication to be used should
depend on the location of the DG Plant, capacity of the generating units and/or
distance of the DG Plant to the nearest TNB main intake substation (PMU or
PPU).

5.10 Network Reinforcements

5.10.1 The connection of the DG Plant to the distribution network may require network
reinforcement to be carried out. During the ‘Preliminary System Study’ stage, the
Distributor must ensure that the connection of the DG Plant and its proposed
quantum of power injection to the distribution would not result in violation of the
design criteria as discussed in chapter 3. The followings are typical criteria
applied by the Distributor at the ‘Preliminary Planning Study’:
1) Normal steady-state voltage limits;
2) Contingency voltage limits;
3) Thermal overload limits of network element;
In addition to the above, the following criteria are also applied:
4) Voltage step limit;
5) Fault level 90% limit;
6) Losses to be below without DG Plant; and
7) SAIDI Reliability index is not worst of without DG Plant.
In carrying out the above assessments, current practice is to assume that the
DG unit is operating at unity power factor and that three load levels are used for
assessments, namely: peak, intermediate and light loads.

5.10.2 If any of the above criteria is not met or too restrictive, three options could be
applied:
1) Use of voltage and or turbine controls;
2) Reduced active power generation from the DG Plant, that is, lower than what
is proposed by the DG Developer; or
3) Network reinforcements which may include any of the following or their
combinations:
ƒ Additional feeders
ƒ Additional switches/breakers
ƒ Shunt capacitors
ƒ Series capacitors
ƒ Shunt reactors
ƒ Series reactors
ƒ Different voltage levels.

- 87 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

5.10.3 The cost of connection should comprise of two components:


ƒ Circuit from interface/connection point to a point in the Distributor’s existing
network; and
ƒ Any of the network reinforcements as listed above.

5.10.4 With respect to network losses, the current practice is to use the following
options to ensure that losses due to the connection of the DG will not be greater
than losses without the DG:
ƒ Network reinforcement; or/and
ƒ Reduce DG Plant export to the distribution network.

- 88 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Chapter 6: Glossary

6 .1 General Terms

6.1.1 In this guidebook, the following general terms, words and expressions shall bear
the following meanings:

A.C., a.c., AC or ac Alternating current.

Act The Electricity Supply Act 1990 (Act 447) including


any modification, extension, or re-enactment the of
and any subordinate legislation made there under.

Active Energy The electric energy produced, flowing, or supplied by


an electric circuit during a time interval, being the
integral with respect to time of the instantaneous
power, measured in units of watt-hours (wh) and
multiples thereof.

Active Power The product of voltage and the in-phase component


of alternating current measured in units of watts and
multiples thereof.

Adequate / Adequacy The ability of the distribution system to provide


acceptable and continuous supply of electricity while
remaining within component ratings during normal or
contingency conditions.

Apparatus All items of equipment in which electrical conductors


are used, supported, or which may form a part.

Apparent Power The product of voltage and alternating current


measured in units of volt amperes. Is also the square
root of the sum of the squares of the active power
and the reactive power.

Automatic Reclose Equipment In relation to a transmission line or distribution line,


the equipment which automatically recloses the
relevant line’s circuit breaker(s) following their
opening as a result of the detection of a fault in the
transmission line or the distribution line (as the case
may be).

Automatic Voltage Regulator A system for controlling generating unit or


transformer voltage within set limits.

- 89 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Black Start The procedures necessary for a recovery from a Total


Shutdown or Partial Shutdown.

Black Start Capability The ability of Embedded generation to start-up from a


stopped or cold state, without a source of external
power, and to energize part of the Distribution
network upon instruction from the Distributor.

Busbar A common connection point in a power station


switchyard or a transmission/distribution network
substation.

Capacitor Bank Electrical equipment used to generate reactive power


and support voltage levels on distribution lines in
periods of high load.

Capacity The net MW and MVAr capacity of generating unit, or


any other transmission/distribution apparatus at a
particular time, to supply electrical energy.

Caution Notice A notice conveying a warning against interference.

Central Dispatch The process of Scheduling and issuing direct


operating instructions by the Grid System Operator.

Centrally Dispatched Generator A Genset of a capacity of 10 MW and above


subject to Central Dispatch under the Grid Code.

Check Meter A meter, other than a revenue meter, used as a


source of metering information.

Check Metering Installation A metering installation used as the source of metering


information for validation in the settlements process.

Connect, Connected, Connection To form a physical link to or through a


transmission or distribution network.

Connection Agreement An agreement between a Distributor and Other Entity


or other person by which the Other Entity or other
person is connected to the transmission or
distribution network and/or receives transmission or
distribution services.

Connection point The agreed point of supply between a Distributor and


other Entity.

Consumer See Customer.

- 90 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Contingency In respect of a transmission or distribution network, a


sequence of related events which result in outages of
one or more transmission or distribution elements.

Control Center A location used for the purpose of control and


operation of the Grid System or a Distributor’s
distribution network.

Control System Means of monitoring and controlling the operation of


the power system or equipment including generating
units connected to a transmission or distribution
network.

Current Harmonics Distortion Is the measure of the departure of the a.c. current
waveform from sinusoidal shape, i.e., caused by the
addition of one or more harmonics to the fundamental
component.

Current Transformer (CT) A transformer for use with meters and/or protection
devices in which the current in the secondary winding
is, within prescribed error limits, proportional to and
in phase with the current in the primary winding.

Customer A person who engages in the activity of purchasing


energy supplied through a transmission or distribution
system; and the final and user of energy.

Data Collection System All equipment and arrangements that lie between the
metering database and the point where the metering
data enters the public telecommunications network
and used for calculations of payments due to or from
Other Entities.

Data Logger A device that collects energy data, packages it into


30 minute intervals (or sub-multiples), holds a
minimum of 35 days at data, and is capable of being
accessed electronically via the data collection
system. This device may be a separate item of
equipment, or combined with the energy measuring
components within one physical device.

Demand The demand of MW and MVAr of electricity (i.e., both


Active and Reactive Power ), unless otherwise stated,
at a particular time or during a time period.

Demand Control Any or all of the following methods of achieving a


Demand reduction; (a) Customer Demand
Management initiated by Distributors; (b) Customer
voltage reduction initiated by Distributor (other than
following an instruction from the Independent Grid

- 91 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

System Operator); (c) Customer Demand reduction by


Disconnection initiated by Distributors (other than
following an instruction from the Independent Grid
System Operator); (d) Customer Demand reduction
instructed by the Independent Grid System Operator;
(e) Automatic Low Frequency Demand Disconnection;
(f) emergency Manual Demand Disconnection.

Dispatch The issue by the Independent Grid System Operator


of instructions for Generating plant to achieve specific
Active Power ( and in relation to Generating plant,
reactive Power, or target voltage ) levels within their
Generation Scheduling and Dispatch parameters and
by stated times.

Disconnection, Disconnect The operation of switching equipment or other action


so as to prevent the flow of electricity at a connection
point.

Discrimination The quality where a relay or protective system is


enable to pick out and cause to be disconnected only
the faulty Apparatus.

Distribution Line A power line, including underground cables, that is


part of a distribution network.

Distribution Losses Electrical energy losses incurred in distributing


electricity over a distribution network.

Distribution Network A system comprising of electrically connected


equipment or elements that produce, transport,
transform, control, and consume electrical power at
medium and low voltage levels.

Distribution System The system consisting ( wholly or mainly ) of electric


lines which are owned and operated by Distributor
and used for the distribution of electricity from Grid
Supply points or Generating Units or other entry
points to the point of delivery to Customers or Other
Distributors.

Distribution System Control Center


The facility used by a Distribution System Operator
for directing the minute to minute operation of the
relevant distribution system.

Distribution System Operator A person who is responsible for the management of


any portion of a distribution system or for directing its
operations.

- 92 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Distributor A person who is licensed Under Section 9 of the Act


and is connected to the Grid System and distributes
electricity for the purpose of enabling a supply to be
given to any premises.
Disturbance Any perturbation to the electric system caused by the
sudden loss of generation or interruption of load.

Earthed Means connected to the general mass of earth by


means of a suitable buried metal pipe or plate or
other means approved by the Director General.

Earthing A way of providing a connection between conductors


and earth by an Earthing Device which is either: (a)
immobilized and locked in the earthing position.
Where the Earthing Device is locked with a Safety
key, the Safety Key must be secured in a key Safe
and the Key safe key must be retained in safe
custody, or (b) maintained and/or secured in position
by such other method which must be in accordance
with the Local Safety instructions of the independent
Grid System Operator or that Distributor, as the case
may be.

Earthing Device A means of providing a connection between a


conductor and earth being of adequate strength and
capability.

Embedded Generating Unit A generating unit connected within a distribution


network and not having direct access to the
transmission network. This includes an Embedded
Generator connected to its own Network which
Network is interconnected with the Distributor’s
network either directly or through a step up
transformer.

Embedded Generation The production of electrical power by converting


another form of energy in a generating unit that is
connected to the distribution system.

Embedded Generator A Generator or Customer who owns, operates, or


controls an embedded generating unit.

Energy ( Active and Reactive ) Active energy is the electrical energy produced,
flowing or supplied during a time interval measured in
units of watt-hours (Wh) or standard multiples thereof.
Reactive energy is the energy produced, flowing or
supplied during a time interval measured in units of
volt-ampere-hours reactive, (varh) or standard
multiples thereof.

- 93 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Energy Data The information that results from the measurement of


the flow of electricity in a power conductor. The
measurement is carried out at a metering point.

Event An unscheduled or unplanned occurrence on or


relating to a system including faults, incidents, and
breakdown.

Forced Outage An outage caused by emergency condition directly


associated with a component that requires to be
taken out of service immediately, either automatically
or as soon as switching operation can be performed,
or an outage caused by improper operation of
equipment or human error.

Frequency the number of alternating current cycles per second


(expressed in hertz (Hz)) at which alternating current
electricity is operating.

Generation the production of electrical power by converting


another form of energy in a generating unit.

Generating Plant See generating system.

Generating System A system comprising one or more generating units.

Generating units Any apparatus which produces electricity.

Generator A person who is licensed Under Section 9 of the Act


and is connected to the Grid System and generates
electricity for the purpose of enabling a supply to be
given to any premises. Also, any apparatus which
generates or produces AC electrical power, including
Active and/or Reactive Power.

Grid Code The Malaysian Grid Code, as from time to time,


revised in accordance with the License by the
Malaysian Grid Code Committee.

Grid Entry Point A point at which a Generating Unit, as the case may
be, which is directly connected to the Grid System.

Grid Supply point A point of supply from the Grid System.

Grid System The system consisting (wholly or mainly ) of high


voltage, namely 500kV, 275kV, 132kV, and 66kV
transmission lines owned by a Transmittor and
operated by the Grid System Oerator and used for
the transmission of electricity from one power station
to a substation or to another power station or

- 94 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

between substations or to or from any External


Interconnection, and includes any Plant and
Apparatus and meters owned or operated by the
Transmittor in connection with the transmission of
electricity.

Interruption The loss of service to one or more customers or other


facilities and is the result of one or more component
outages, depending on the system configuration.

High Voltage (HV) A voltage equal to or greater than 50kV.

Insulated Means covered or protected by insulating material.

Interconnection, Interconnector, Interconnect, Interconnected


A transmission or distribution line or group of
transmission or distribution lines that connects the
transmission or distribution networks in adjacent
regions.

Isolating Device A device for achieving Isolation by adequate physical


separation or sufficient gap for voltage level involved.

License Any license granted by the Energy Commission of


Malaysia.

Licensee Any person, who is granted a license for generation,


transmission, distribution, or combination thereof to
supply electricity to any premises, by the Director
General of the Department of Electricity and gas
Supply.

Load To Active, Reactive, or Apparent Power, as the


context requires, generated, transmitted, distributed
or consumed.

Loading The apparent power level at which each element of


the network is operated.

Load Forecast Estimate of future consumption or generation of


electricity in MW, MVAr, MWh, MVARh.

Load-shedding Reducing or disconnecting load from the power


system.

Low Frequency Relay Has the same meaning as Under Frequency Relay.

Low Voltage or LV A voltage level less than 1000 volts or 1 kV.

- 95 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Medium Voltage or MV A voltage equal to or exceeding 1kV but not


exceeding 50 kV.

Meter A device complying with Standards which measures


and records the production or consumption of
electrical energy and/or demand.

Metering Recording the production or consumption of


electrical energy.

Metering Data. The data obtained from a metering installation, the


processed data or substituted data.

Metering Point The point of physical connection of the device


measuring the current in the power conductor.

Metering System The collection of all components and arrangements


installed or existing between each metering point and
the metering database.

MV Distribution Network The various circuit and Apparatus owned by the


Distributor operating at primary phase to phase
voltages above 1kV and less than 50kV.

Momentary Interruption An interruption having a duration limited to the period


to restore service by automatic or supervisor-
controlled switching where an operator is immediately
available.

Nominal Frequency Means 50Hz frequency on Grid System or Distribution


System.

Non-Scheduled outage See forced outage.

Operating Criteria Refers to a set of measures for assessing the


performance of the distribution system during the
operation stage.

Operation A scheduled or planned action relating to the


operation of a System.

Operation Criteria see operating criteria

Out of Synchronism The condition where a System or generating unit


cannot meet the requirements to enable it to be
synchronized.

Outage Describes the state of the component when it is not


available to perform the intended function due to

- 96 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

some event associated with that equipment. Duration


will count toward computation of SAIDI.

Planning Criteria See planning and design criteria

Planning and Design Criteria Refers to a set of measures for assessing the
performance of the distribution system during the
planning stage.

Planned Outage See scheduled outage.

Point of Interface A designated boundary of owner ship between the


Distributor and the Other Entities.

Power Factor The ratio of Active Power to Apparent Power.

Power Quality It is the measure of the purity of supply voltage and


current waveforms.

Power Quality Characteristics In this guidebook the term refers to the measures
used for determining the purity of the a.c. voltage of
current waveforms.

Power Station An installation comprising one or more Generating


Units (even where sited separately) owned and/or
controlled by the same Generator which may
reasonably be considered as being managed as one
Power Station.

Power System The electricity power system of Malaysia including


associated generation and transmission and
distribution networks for the supply of electricity,
operated as an integrated arrangement.

Protection The provisions for detecting abnormal conditions on a


system and initiating fault clearance or actuating
signals or indications.

Protection Apparatus A group of one or more Protection relays and/or logic


elements designated to perform a specified
protection function.

Protection System A system, which includes equipment, used to protect


facilities from damage due to an electrical or
mechanical fault or due to certain conditions of the
power system.

Prudent Utility practices With respect to the Distributor, means the exercise of
that degree of skills, diligence, prudence and
foresight consistent with the applicable acts,

- 97 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

regulations, condition of license, standards, codes


and the Distributor’s owned standards and practices.

Reactive Energy A measure, in var hours (varh) of the alternating


exchange of stored energy in inductors and
capacitors, which is the time-integral of the product
of voltage and the out-of-phase component of current
flow across a connection point.

Reactive Power The product of voltage and current and the sine of the
phase angle between them measured in units of volt
amperes reactive. The rate at which reactive energy is
transferred.

Reliability In the context of a distribution system is a measure of


availability of adequate and secure supply to the
Customers

Revenue Meter The meter that is used for obtaining the primary
source of metering data for billing purposes.

Revenue Metering Installation A metering installation used as the primary source of


metering data.

Safety Precautions Isolation and/or Earthing

Safety Rules The rules of a Generator or Distributor that seek to


ensure that persons working on Plant and/or
apparatus to which the rules apply are safeguarded
from hazards arising from the System.

SAIDI System Average Interruption Duration Index for all


types of interruptions. This distribution reliability index
sometimes referred to as customer Minutes or
Customer Hours is designed to provide information
about the average time the customers are interrupted.

SAIFI System Average Interruption Frequency Index for


sustained interruption. The objective of this
distribution reliability index is to provide information
about the average frequency of sustained
interruptions per customer over a predefined area.

Schedule Outage An outage that results when a component is


deliberately taken out of service at a selected time,
usually for the purpose of construction, preventive
maintenance or repair.

Security Means security of supply

- 98 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Security of Supply The ability of the distribution system restore supply to


Customers following momentary or temporary
interruptions.
Single Contingency In respect of a transmission or distribution network, a
sequence of related events which result in the
removal from service of one transmission or
distribution line, or transformer. The sequence of
events may include the applications and clearance of
a fault of defined severity.

Substation A facility at which two or more lines are switched for


operational purposes. May include one or more
transformers so that some connected lines operate at
different nominal voltages to others.

Supply Characteristics In this Guidebook the term refers to power quality


characteristics, that is, the measure of the purity of
the voltage or current waveforms.

Supply Performance Refers to each of the performance measures


contained in the planning or operating criteria.

Sustained Interruption It is any supply interruption to one or more customers


not classified as momentary or temporary.

Supply Security See Security of Supply

Synchronized The condition where an incoming Generating Unit or


System is connected to the bus bars of another
System so that the Frequencies and phase
relationships of that Generating Unit or System, as
the case may be, and the System to which it is
connected are identical.

System Any distributor or Generator’s System or the Grid


System, as the case may be.

System Constraint A limitation on the use of System due to lack of


distribution capacity or other System conditions.

System Operator A person whom a Distributor has appointed as its


agent to carry out some or all of its rights and
obligations.

Tap-changing Transformer A transformer with the capability to allow internal


adjustment of output voltages which can be
automatically or manually initiated and which is used
as a major component in the control of the voltage of
the transmission and distribution networks.

- 99 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Tariff Metering Meters, associated CTs and VTs, metering protection


equipment, data collection, wiring and other devices
or part thereof which are part of the Active Energy or
Reactive Energy measuring equipment at a specific
Connection Point.

Temporary Interruption An interruption having a duration limited to the period


required to restore service by manual switching at
locations where operators are not immediately
available.

Total Harmonic Distortion The departure of a wave form from sinusoidal shape,
that is caused by the addition of one or more
harmonics to the fundamental, and is the squares of
all harmonics expressed as a percentage of the
magnitude of the fundamental frequency.

Transformer A plant or device that reduces or increases the


voltage of alternating current.

Transformer Tap Position Where a tap changer is fitted to a transformer, each


tap position represents a change in voltage ratio of
the transformer which can be manually or
automatically adjusted to change the transformer
output voltage. The tap position is used as a
reference for the output voltage of the transformer.

Transmission Grid A network operating at nominal voltages of 50 kV and


above.

Transmission or Distribution system


A transmission or distribution system that : (1) is used
to convey, and control the conveyance of, electricity
to Customers (whether wholesale or retail); and (2) is
connected to another such system.

Transmission Plant Apparatus or equipment associated with the function


or operation of a transmission lone or an associated
substation or switchyard, which may include
transformers, circuit breakers, reactive plant and
monitoring equipment and control equipment.

Tripping The opening of a circuit breaker as a direct and


normally immediate consequence of the operation of
a protection relay or advice.

Unbalanced Load The situation where the Load on each phase is not
equal.

- 100 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Under Frequency Relay An electrical measuring relay intended to operate


when its characteristic quantity (Frequency) reaches
the relay settings by decrease in Frequency.
Voltage Dip Transient reduction in voltage magnitude measured
as the percentage or per unit reduction of the voltage
magnitude to the nominal voltage magnitude.

Voltage Harmonic Distortion It is the measure of the departure of the a.c. voltage
waveform fro, sinusoidal shape, that is caused by the
addition of one or more harmonics to the
fundamental.

Voltage Sag Transient reduction in voltage magnitude measured


as the percentage or per unit remaining voltage
magnitude to nominal voltage magnitude.

Voltage Sensitive Load A load that will mal-operate on transient distortion of


supply voltage sinusoidal waveform.

Voltage transformer (VT) A transformer for use with meters and/or protection
devices in which the voltage across the secondary
terminals is proportional to and in phase with the
voltage across the primary terminals.

6 .2 Other Terms

6.2.1 The following additional or alternative terms are mainly used in TNB’s
connection and commercial agreements and may be used as reference.

“Agreement” This Renewable Energy Power Purchase Agreement and the


appendices, schedules and exhibits hereto as may be
amended, deleted and/or changed from time to time by prior
written consent of both Parties;

“Billing Period” The period (i) commencing on the Commercial Operation


Date of the Facility and ending on the last calendar day of
that month and thereafter (ii) between the first calendar day
and the last calendar day of every calendar month throughout
the Term for the Facility; and (iii) the period beginning on the
first day of the month in which the Term expires and ending
on the day the Term expires;

“Business Day” Any day on which commercial banks are authorized or


required to be opened in Kuala Lumpur, Malaysia;

“Change-in-Law” Any of the following events occurring after the Effective Date
as a result of, or in connection with, any action by any

- 101 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Governmental Entity, court or tribunal :

(a) A change in or repeal of an existing Law;

(b) An enactment or making of a new Law.

(c ) A change in the manner in which a Law is applied or


in the interpretation thereof.

(d) The imposition of a requirement for a new


Governmental Authorization ; or

(e) A change in the terms and conditions of a


Governmental Authorization.

“Commencement The date on which construction work on the Facility is to


Date” begin and written notice of such date shall be given, being
not less than thirty (30) days prior to actual commencement
of construction at Site, by The Seller to TNB;

“Commercial The date on which (i) all of the conditions precedent set forth
Operation Date” in Clause 4 shall have been satisfied or waived by TNB and
(COD) (ii) shall have established its export capacity of XXX MW;
“Communication Means all of the facilities described under Appendix E as
Facilities” determined by TNB under Clause 12.6 to be necessary, in
accordance with Prudent Utility Practices, to enable the
Control Centre to communicate and Despatch the Facility;

“Control Centre” The Control Centre of TNB as designated in writing by TNB


from time to time (but not more than one at any one time) as
being the sole TNB control centre, for the Facility;

“Default Rate” A rate equal to two per centum (2%) above the base lending
rate then in effect at the principal office of MayBank Berhad,
or its successors in title.

“Delivered Power” For the purpose of this Agreement shall mean the rate at
which electrical energy is delivered by the Facility to TNB at
the Interconnection Point and is measured in Kilowatts;

“Despatch” Means the issuance of an oral or written instruction

communicated to The Seller by the Control Centre directing

the Facility to commence, increase, decrease or cease the

- 102 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

generation and delivery of electrical energy into the TNB

System, in accordance with the provisions of this Agreement;

“EC” The Energy Commission, a statutory body established under

the Energy Commission Act 2001 and any successors

thereof;

“Effective Date” The date of the execution and delivery of this Agreement by
The Seller and TNB and that all corporate authorisations
which are required to have been obtained by the Parties in
connection with the execution and delivery of this Agreement
have been obtained and are in full force and effect and a
statement in writing to that effect has been submitted to each
Party;

“Emergency A condition or situation that, in TNB’s reasonable judgment,


Condition” based on Prudent Utility Practices (i) presents an imminent
physical threat of danger to life, health or property, or (ii)
threatens the safety, reliability or security of the TNB System,
or (iii) could reasonably be expected to cause a significant
disruption on the TNB System or (iv) could reasonably be
expected to adversely affect TNB’s ability to meet its
obligations to provide safe, adequate and reliable electricity
service to its customers, including other utilities with which
TNB System is interconnected;

“Energy Payment” For each Billing Period, the payment to be made by TNB to
The Seller for electrical energy delivered to the
Interconnection Point and received by TNB during such
Billing Period;

“Event of Default” The occurrence of any of the events described in Clause 18


hereof;

“Facility” The whole of the plant installation with the nominal capacity
of YYY MW as stipulated in Recital A, with all necessary
plant, buildings and land in connection therewith, electricity
connection and consuming apparatus, if any as per Appendix
A of this Agreement;

“Force Majeure Any event, condition or circumstance described in Clause 17


Event”

- 103 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

hereof;

“Forced Outage” Any interruption (excluding an interruption due to a Force


Majeure Event) of the Facility then in effect that is not the
result of (i) a Scheduled Outage, Maintenance Outage or
Major Overhaul Outage, or (ii) a condition caused by TNB or
the TNB System;

“Fossil Fuel” A hydrocarbon deposit that consists of remains of animal or

vegetable life from past geologic ages that is now in a

combustible form which is suitable for use as fuel; for

example, oil, coal, or natural gas;

“Government Any authorization, consent, licence, concession, permit,


Authorization” waiver, privilege, exemption and/or approval from, or filing
with, or notice to any Government Entity;

“Government Any national, state or local legislature of the government of


Entity” Malaysia and any ministry, department, instrumentality,
agency, authority or commission of the government of
Malaysia or any other similar entity, including Energy
Commission;

“Grid Code” Means the Malaysian Grid Code, as amended from time to
time in accordance with applicable Law;

“Independent Shall mean the reputable consulting engineering firm or


Engineer” professional engineer retained by The Seller and approved by
The Seller’s financiers as the Independent Engineer of The
Seller in connection with the design and construction of the
Facility and Interconnection Facilities;

“Initial Operation The first date on which electrical energy is generated and
Date” (IOD) delivered from the Facility to the Interconnection Point;

“Interconnection All of the facilities, as specifically described in Appendix D, to


Facilities” be necessary, in accordance with Prudent Utility Practices, to
enable TNB to receive electrical energy from the Facility and
to maintain the stability of the TNB System, including the
sub-station and/or switching station, all transmission lines,
transformers and associated equipment, communications
equipment, relay and switching equipment, circuit breakers
and other protective devices and safety equipment,
telecommunications equipment and the metering equipment,
wherever located;

- 104 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

“Interconnection The physical points where the Facility and the TNB System
Point” are connected, as shown in Appendix D, or such other point
or points as the Parties may agree;

“KTAK” Ministry of Energy, Water and Communication (formerly


known as Ministry of Energy, Communications and
Multimedia);

“kW” Kilowatt;

“kWh” Kilowatt-hour;

“Law” Any (i) law, legislation, statute, act, rule, order, treaty, code or
regulation, or (ii) legally binding announcement, directive or
published practice or any interpretation thereof, enacted,
issued or promulgated by any Governmental Entity or court
or tribunal;

“Licence” The licence granted to The Seller under the Electricity Supply
Act, 1990 to enable The Seller to own and operate the Facility
and to operate electricity generating capacity and supply
electric energy to TNB therefrom;

“Maintenance A planned interruption or reduction of the electricity


Outage” generating capability of the Facility that (i) is not a Forced
Outage, Scheduled Outage or a Major Overhaul Outage, (ii)
has been co-ordinated with TNB in accordance with Clause
12 and (iii) is for the purpose of performing work on the
Facility, which work could be postponed by at least seventy
two (72) hours, but in the opinion of The Seller should not be
postponed until the next Scheduled Outage;

“Major Overhaul A planned interruption or reduction of the electricity


Outage” generating capability of the Facility that is needed for a major
overhaul of any generating unit or any associated equipment
of the Facility that has been co-ordinated with TNB in
accordance with Clause 12, and is in accordance with
Prudent Utility Practices and manufacturer’s
recommendations;

“The Seller” The Seller Sdn. Bhd., a company incorporated under the laws
of Malaysia, including its successors in title and permitted
assigns;

“MW” Megawatt;

“Off-Peak Hours” Shall mean the periods between 0000 hours to 0900 hours

- 105 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

and between 1700 hours to 2400 hours of each day;

“Operations Shall mean the operations committee described in Clause


Committee” 11.2 hereof;

“Peak Hours” Shall mean the period between 0900 hours to 1700 hours of
each day;

“Parties” TNB and The Seller and a reference to a “Party” means either
TNB or The Seller as the case may be;

“Person” Means any individual, corporation, partnership, joint venture,


trust, unincorporated organisation or Government Entity;

“Power System Impact assessment study of the operations of The Seller’s


Study” (PSS) Facility on the TNB System based on TNB requirements as
stipulated in the TNBD MV Technical Guidebook;

“Project” The development, design, financing, insurance, procurement,


construction, installation, testing, commissioning, ownership,
operation, management and maintenance of the Facility
including ancillary buildings and associated activities related
to this project, as more specifically described in Appendix A,
and any modification thereof;

“Prudent Utility Means the practices, methods and standards generally


Practices” followed by the electricity supply industry in Malaysia, during
the applicable period, with respect to the design,
construction, testing, operation and maintenance of the
electricity generating, transmission and distribution
equipment of the type used by the Facility and the TNB
System, which practices, methods and standards generally
conform to applicable Laws, the operation and maintenance
standards recommended by the equipment suppliers and
manufacturers of the Facility and the TNB System, the
International Electricity Commission standards, the Grid Code
and any other applicable electricity code approved by EC;

“Renewable Any means of fuelling or driving the Facility as permitted


Energy Fuel”
under the Small Renewable Energy Power (SREP)

Programme guidelines, being in each case a non-fossil fuel;

“Ringgit” (“RM”) The lawful currency of Malaysia;

“Scheduled The scheduled date for the commencement of commercial

- 106 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Commercial operation of the Facility as specified in Clause 5.4;


Operation
Date”(SCOD)

“Scheduled A planned interruption of the electricity generating capability


Outage” of the Facility that (i) is not a Maintenance Outage or Major
Overhaul Outage, (ii) has been co-ordinated in advance with
TNB with a mutually agreed start date and duration pursuant
to Clause 12 and (iii) that is required for the inspection,
preventive maintenance or corrective maintenance, repair or
improvement of the Facility;

“Sen” The lawful currency of Malaysia;

“Site” The parcels of land upon which the Facility is to be


constructed and located, and as more specifically described
in Appendix A hereto;

“Small Renewable A programme initiated by KTAK on 11.5.2001 which is aimed


Energy Power at supporting the Government’s desire to develop Renewable
Programme” Energy (RE) as an alternative fuel resource;

“Term” The period of this Agreement as specified in Clause 3.1


hereof;

“Test Energy” The electrical energy associated with the start-up and
commissioning of the Facility prior to the relevant
Commercial Operation Date, and metered at the
Interconnection Point;

“TNB” Tenaga Nasional Berhad, a company incorporated under the


laws of Malaysia, including its successors in title and
permitted assigns;

“TNB Licence” Means the licence required and obtained by TNB or any
extension thereof pursuant to Section 9 of the Electricity
Supply Act 1990;

“TNB MV Means the latest edition of the guidebook for other users to
Interconnection be interconnected to the TNB Medium Voltage (MV)
Guidebook” Distribution network titled “A Guidebook of the Technical
Requirements for the Interconnection of A User’s Network to
TNB’s MV Distribution Network”;

The bulk power network controlled or used by TNB for the


“TNB System” purpose of generating electricity, and transmitting and
distributing electricity to TNB’s customers.

- 107 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

7. Appendix A: Summary of TNB Power Systems

7.1 Industry Structure


7.1.1 A Brief History of Electricity Industry in Malaysia
Prior to 1950’s, the electricity supply industry in Malaysia was dominated by privately
owned companies operating in their respective franchise areas and regulations were
minimal. As the demand of electricity grew, a government utility, the Central Electricity
Board (CEB) was established in 1949 to acquire many small privately owned companies
while the major companies continued to operate and being regulated by the Government. In
1965, the CEB is renamed as the National Electricity Board (NEB, well-known in Malay as
LLN) with added responsibility to ‘nationalise’ the private suppliers. Nationalisation policy
resulted in acquisition of privately owned utilities. In 1987, the privatisation of the electricity
supply industry was initiated and in 1990 the NEB was corporatised as Tenaga Nasional
Berhad (TNB).

7.1.2 Electricity Industry Reform


In late 1980’s the Government’s privatization policy marked the beginning of electricity
industry reforms of 1990’s that is still undergoing at the present. The government has
created competition, to a certain extent, in generation by licensing private sector to build,
own and operate power generating plants as independent power producers (IPPs) and
supply electricity through negotiated power purchase agreements (PPA). Since 1997, TNB
has also been gradually divesting their interests in thermal power plants to private investors
and until 2004, there are 23 IPPs have been given licenses to operate in Peninsular
Malaysia.

7.1.3 Renewable Energy (RE) and The Small Renewable Energy


Programme (SREP)
The Government of Malaysia has embarked on programmes to promote efficient use of
energy as well as to increase the use of renewable energy (RE), particularly biomass from
the agricultural sector for power generation in line with the launch of the revised Energy
Policy in 2001. This is known as ‘RE As 5th Fuel’. The aim of the RE Programme is to
generate 5% of the country’s electricity from renewable energy resources by year 2005. In
addition, The Small Renewable Energy program (SREP) was launched in 2001, aiming at
encouraging private sector to use renewable energy resources, especially oil palm waste
from the palm oil industry, to generate electricity to the local distribution network.

7.1.4 Current structure of electricity industry


In the current structure, there are three main electricity utilities in Malaysia: TNB in
Peninsular Malaysia; Sabah Electricity Sdn Bhd (SESB) in the State of Sabah; and, SESCo in
the State of Sarawak. The Government and related government-owned companies/entities
own approximately 75% of TNB. SESB is owned 80% by TNB and 20% the Sabah State
Government. The major shareholder of SESCo is the Sarawak State Government. The three

- 108 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

main utilities are vertically integrated entities undertaking generation, transmission,


distribution and supply of electricity in the Peninsular Malaysia, Sabah and Sarawak
respectively. Until recently, besides the three main utilities, twenty-three IPP licenses, one
transmission licenses and a number of merchant co-generations licenses have been
granted. Besides these, about two thousands self-generation licenses have been issued to
industrial and commercial entities that generate electricity for their own use. In addition,
three mini utilities have been established to provide high quality supply for high-tech
semiconductor and petro-chemical industrial entities. The current structure of electricity
supply industry in Peninsular Malaysia and Sabah and Sarawak are illustrated in figures
7.1(a) and 7.1(b) respectively.

Figure 7.1(a): The Structure of Electricity Supply Industry in Peninsular Malaysia

- 109 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Figure 7.1(b): The Structure of Electricity Supply Industry in Sabah and Sarawak

7.1.5 Regulation and Licensing


Malaysia has successfully privatized the electricity supply industry since early 1990s.
However, after in depth studies, Malaysia did not join the other countries in the ‘dash for
deregulation’. The power sector of Malaysia remains as regulated industry with vertically
integrated utilities. In 1990, The Department of Electricity Supply (DES) was formed under
the Electricity Supply act 1990 as the industry and safety regulator of the electricity supply
in Peninsular Malaysia and Sabah. However, in Sarawak the State Electricity Ordinance is in
force providing the State Electrical Inspectorate with the legal power for electricity supply
regulatory functions. In 2001, the DES was known as the Energy Commission (EC) of
Malaysia - established under the Energy Commission Act 2001 - whose functions include:
ƒ To promote competition in the electricity industry
ƒ To issue and enforce licenses
ƒ To undertake economic, technical and safety regulations
ƒ To enforce consumer protection codes
ƒ To ensure compliance with industry codes
The EC reports directly to the Minister and has ‘promotion of competition’ being one of the
most important function. Electricity pricing is an item handled Electricity Commission. A
balance is required between the market price and the price affordable by majority of the
population. Currently, tariff is approved by the highest decision making body in the country
where political and socio-economic considerations are of prime importance. Currently,
electricity tariff is fixed but varies according to customer groups and voltage level. Energy

- 110 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Laws and Regulation that are regulating the electricity industry in Peninsular Malaysia and
Sabah are:
ƒ Energy Commissioning Act 2001
ƒ Electricity Supply Act 1990
ƒ Electricity Supply Regulation 1994
Figure A.2 illustrates the current structure of institutional and regulatory structure of the
industry in Peninsular Malaysia and Sabah

Figure 7.2: Institutional and Regulatory Structure of Electricity Supply Industry in


Peninsular Malaysia and Sabah

7.2 Power Generation


7.2.1 Generation Entities
Power generation in Malaysia is mainly provided by three main electricity utilities: TNB in
Peninsular Malaysia; SESB in the State of Sabah; and, SESCo in the State of Sarawak. There
are also a number of IPPs operating in the Peninsular Malaysia, Sarawak and Sabah. As in
2002, there are 23 licensed IPPs operating throughout the country.

7.2.2 Generation Mix


In 2002, generation mix fuel of TNB and IPP was 75.0% gas, 11.0% coal, 7.1% hydro,
4.5% oil and the remaining others. The total installed generating capacity in Malaysia, as at
April 2003, was 15,838MW: 14,221MW in Peninsular Malaysia; 819MW in Sarawak, and;
798MW in Sabah. In Peninsular Malaysia, TNB Generation Division (formerly known as TNB

- 111 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Generation and TNB Hidro ), provide approximately 60% of the installed generating
capacity. Five IPPs provide the remaining 40%. In Sabah, SESB provides 493MW (62%) of
installed capacity with five IPPs providing the remaining 305MW of capacity (38%). In
Sarawak, SESCo provides 499MW (61%) of the installed capacity with the other 320MW
(39%) being provided by two IPPs. Within the total installed capacity in Malaysia, there is
an approximate 30% to 35% reserve margin.

7.2.3 Self Generation and Co-generation


In addition to the grid connected generating capacity, there are also a considerable number
of self-generation and co-generation power plants in operation Malaysia. The agriculture
and timber processing industries in the remote areas of Malaysia operate self-generation
power plants to supply their own needs. Large portions of these facilities are using biomass
or agricultural waste as fuel. A number of industrial and commercial complexes also
operate co-generation power plants to supply both their heat or chilled water requirements
and electricity by using natural gas as fuel. There are also several industrial complexes,
especially in the petro-chemical sector, using industrial waste heat for generation.

7.3 Transmission and Power System Operation


7.3.1 Transmission System
TNB Transmission Division (known as TNBT) is the transmission network service provider
for Peninsular Malaysia and has a monopoly on the transmission of electricity in Peninsular
Malaysia. Similarly, SESCo and SESB have monopolies on transmission in Sarawak and
Sabah respectively. TNB Transmission Division manages and operates the 132kV, 275kV
and 500kV transmission systems that form an integrated network - the National Grid as
illustrated in figure 7.3. The Grid can be considered as the backbone of the electricity
industry in Peninsular Malaysia. TNB’s National Grid system spans the whole of Peninsular
Malaysia, connecting power stations owned by TNB and IPPs to customers. The grid is
interconnected in the North to Thailand’s transmission system (operated by the Electricity
Generating Authority of Thailand, EGAT) via a HVDC interconnection with a transmission
capacity of 300MW and a 132kV AC overhead line with maximum capacity of 80MW. In the
South, the National Grid is connected to Singapore’s transmission system at Senoko via 2
X 230kV submarine cables with a firm transmission capacity of 200MW. Standard nominal
voltages for transmission system are 500kV, 275kV and 132kVas illustrated in figures 7.4
and 7.5. Sub-transmission voltage system used to interface between bulk power
transmission system and distribution system. In TNB system, the 132kV network is used to
deliver power from National Grid to distribution substations.

- 112 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Figure 7.3: TNB Power System Configuration

Figure 7.4: TNB System Voltage Configuration

- 113 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Figure 7.5: Typical Supply Scheme

7.3.2 Power System Operation


Operation of Grid is a process and procedure of coordinating the supply and demand of
electricity through the Grid, which is inherently complex. In order to ensure reliable
operation of the power Grid, several activities involving load forecasting, planning and
investment, operational planning and control operation of The National Load Dispatch
Centre (NLDC) must be carried out accurately and efficiently.

7.3.2.1 Load forecasting


In power system operation, short-term load forecasting is a starting point of maintaining
the balance between generation and demand. In TNB, both long-term and short-term load
forecasting are carried out by a group of specialists in the system planning unit. The
forecast would then be used by the Production Planning unit to schedule and commit
generating units in the system.

7.3.2.2 Planning & Investment


Apart from operating the existing system economically and securely, power system
operation function may from time to time be involved in planning of the network involving
investment of capital to enhance system reliability. As the system changes and/or different
contingencies applied, operation engineers may find that the network may not be able to
operate securely and that can only be corrected through installation of additional equipment
or facilities. In such cases, the investment requirements are determined by operation
function as opposed to usual cases by the network system planning function. In TNB,

- 114 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

operation function cooperates and coordinates closely with the planning function to identify
short- to medium term plans to improve system reliability. Otherwise most network
investment plans including improvement of reliability are carried out by the network
planning group.

7.3.2.3 Operational planning


Operational planning comprises of activities carried out for the purposes of preparing
system operators, power plant operators and other users of the network including
maintenance crew on how to operate the network – its components and controls - in the
most economical manner while keeping security as the top priority. Demand forecast is the
fundamental input for operational planning – both medium terms and short terms.
Activities of operational planning include; plant availability forecasting, coordination of
generation and transmission outages, fuel transport and storage requirements plans, and to
advice control operators on real-time control particularly on responses to contingency
situations. In TNB, Operational Planning Unit comprises of several teams of engineers that
coordinate their functions to provide three main inputs to the NLDC for the next day
operation. These inputs are; generation unit commitment and schedule, list of planned
transmission outages, list of precautions and control/operation strategies for network
operations.

7.3.2.4 Control operation (NLDC)


The National Load Dispatch Centre (NLDC) is nerve centre of the Peninsular Malaysia Grid.
Team of Control Engineers and Technicians are manning the centre on a 24-hour basis to
ensure that sufficient generation is scheduled to meet load demand and that the system will
remain in secure situation following any disturbance. The NLDC communicates directly on
real time basis to all power plants in the network and all major substations and load
centres. Statuses, outputs and voltage levels of major equipment at power plants and
substations are monitored closely and reporting system including alarms will alert
operators in case of abnormal operating conditions.

7.3.3 Control of System Frequency


In Malaysia, the electricity system operates at 50 Hz. This operational power frequency is
kept very close to this level by all electricity users and generators. This is achieved by
scheduling generation to match demand and by means of deliberate control actions on the
part of some generators.

7.3.4 Control of System Voltage


The control of voltage levels especially in distribution network is an important issue, due to
its significance to the end users. The supply voltage needs to be kept within a given range
for the correct operation of customer’s appliances. Although TNB tries to keep system
voltages close to their nominal levels, the actual voltage varies as the load on the system
changes. Voltages tend to fall when people are using a lot of electricity and they are often
lower at the end of long distribution lines. The voltage at the customer’s terminal shall not
vary from system terminal voltage of 6.6/11/22/33kV by more than ±5%, while for system

- 115 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

voltage of 415/240V by more than +5% to –10%. Distribution networks are designed to
provide electricity to users at reasonably constant voltage levels. Normally, voltage control
in distribution system is provided by on-load tap changing transformer. The transformers
that transfer power from the higher to the lower voltage system are fitted with automatic
voltage control that compensate voltage changes on the high voltage side. In addition to
this, switched and fixed capacitor banks are employed at strategic locations in the
distribution system. Boosters are seldom used now because of their high costs. In the LV
system, voltage regulators are employed but now being replaced by switched and fixed
capacitors. The presence of distributed generation can assist in improved voltage profiles,
but often makes the process of voltage control more complex. Conversely, power in-feeds
from distributed generators tend to increase the voltage levels.

7.4 Distribution
7.4.1 Distribution Organisations
TNB Distribution Division (known as TNBD), SESCo and SESB are the main distributors of
electricity throughout the Peninsular, Sarawak and Sabah respectively. Until 2002, The
Government has issued licenses to 26 companies who are allowed to operate as local
distributors or suppliers of electricity in certain designated locations, such as shopping
complexes and industrial parks. Some of these companies also operate their own co-
generation plants to supply part of their demand.

7.4.2 Voltages
In TNB distribution system, the network system voltage can be categorized into two:
1) Medium voltage (MV), which are 33kV, 22kV, 11kV, 6.6kV
2) Low voltage (LV) which are 415V and 240V
In some areas in State of Perak and Johor, the 22kV networks are being converted to 33kV
and 11kV. The sub-transmission feeding points into distribution systems are via HV/MV
substations of 132/33 kV, 132/22kV and 132/11kV – normally called PMUs. MV network
predominantly made up of underground cable while LV feeders are predominantly overhead
lines with underground cable for selected commercial and housing areas.

7.4.3 Protection in Distribution Networks


7.4.3.1 Fault and fault current
It is not possible to eliminate the electrical faults in distribution network due to it being
exposed to environmental influence and the large geographical area that the network may
cover. These faults may be caused by events such as overhead lines touched by trees, or
the accidental excavation of underground cables. When these things happen, very high
current can occur at the fault and in the parts of the network that feed current into the fault.
If they are not quickly detected and stopped, these fault currents are a risk to life and can
cause extensive damage to transformers, cables and other equipment, as well as affecting
the electricity supply to customers.

- 116 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

7.4.3.2 Protection system


Circuit breakers and fuses are installed at strategic points in the network, together with
protective relays and sensing devices such as current transformers. On detection of
unusually high currents or other abnormal conditions by these sensing devices, the
measured electricity basic quantities of voltage, current or frequency is then sent to relays,
which are the decision makers. Depending on the magnitude of the measured quantity, the
relay is set to do nothing or to trip the circuit breakers to interrupt the flow of current.
These tripping devices and their respective functions are known as protection systems.

A properly coordinated protection system in distribution network is vital to ensure safety of


public and to minimize the interruption to customers and the damage of equipment from
the effect of faults. In typical utility practices, a protection system must satisfy the following
requirements:
ƒ Disconnection of equipment is restricted to the minimum necessary to isolate the fault.
ƒ Sensitive enough to operate under minimum fault condition.
ƒ Stable and remain inoperative under certain specified condition (such as through faults
and transients)
ƒ Fast operation in order to clear the fault from the system to minimize damage to
affected system components.
The typical types of distribution protection system are Over-current and Earth Fault (OCEF)
and unit protection for feeders. OCEF relays are used to detect over-current and earth faults
on underground cables and overhead lines, as well as transformers and capacitors. Pilot
wire protections and directional over-current/earth fault relays are the two methods
available for distribution feeders from 6.6kV up to 33kV.

The majority of faults occurring on overhead lines are transient faults due to lightning,
swinging of wires, tree branch falling on the lines or because of animals. The advantage
derived from auto reclosing is to reduce interruption time to the customers due to transient
fault as well as to support fault isolation management. Auto reclosers and sectionalisers are
installed on 33kV overhead lines system. These devices re-close the circuit breakers a few
seconds after it is tripped. If the fault has not cleared by this stage, the protection will be
activated and the circuit breaker will trip again. However, if the fault has cleared, the line
will then remain reconnected to the supply.

Automatic re-closers are usually set to operate up to three or four times after a fault. If the
fault does not clear after this number of operations, the circuit breaker remains tripped and
must be re-set manually. The dead time between each successive reclosure is important
information for DG in order that generator protections can be designed to avoid the auto-
reclosure closing with the generator and the grid out of synchronism.

7.4.3.3 Fault level and equipment rating


It is vital to have accurate information on fault level in the distribution system in order to
decide the fault rating of equipment forming part of the network and to specify the
parameters of the protection scheme. The system components must be rated such that
during short circuit the resultant heat can be dissipated and mechanical forces will stood
under maximum fault. The fault level must not exceed the short circuit rating of the circuit

- 117 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

breaker interrupting the fault. The maximum fault level allowed in the distribution system
are as follows:

Nominal System Rated Voltage (kV) Fault Current (kA)


Voltage (kV)
33 36 25
22 24 20
11 12 20
0.415 0.415 31.5

The equipment shall be rated to withstand the rated fault current for duration of 3seconds.

7.4.4 Distribution Network Planning


Distribution network extension, modification and reinforcement are required to meet
changing patterns of demand for electricity. Existing network infrastructure sometimes has
to be upgraded to support growing demand for electricity. New housing developments,
industrial sites and electricity generation schemes all require extension to distribution
network. All of these changes have to be coordinated to maintain standard of safety,
reliability and operation.

Distribution Division of TNB has the responsibility to plan and develop their network, while
maintaining the standards of safety and reliability, as well as maintaining system’s technical
efficiency in line with the basic objective of distribution network planning to provide secure
supply whilst fully meeting customer demand at the most economic overall cost, consistent
with the nature of the load.

Planning for the future in general begins with annual load forecasting followed by
preparation of master plan, execution and evaluation of current system performance. The
key sets of planning criteria involve security level standard, contingency criteria, loading
criteria of network element under normal and emergency, fault level as well as equipment
breaking duty.

7.4.5 Control and Operation of Distribution Network


Variety of operational configuration in distribution network is useful to minimize disruption
due to fault and routine maintenance. In the event of a fault, for example, the network
operator can re-configure the network, selecting the configuration that maintains supplies
to the greatest number of customers while the fault is being rectified. It is also being aided
by the introduction of computer based, Distribution Automation System that enables the
control and operation of distribution networks to be automated. The level of automation of
the distribution system depends on the level of security of supply defined on certain areas
or customers.

Distribution system operations are not entirely controlled and monitored via SCADA.
Existing SCADA comprises of supervision and control at substation level and master station

- 118 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

only while distribution feeder automation is under implementation stage. The number
controlled and monitored distribution substation under the on-going SCADA program is
only 10% of total number in the whole of TNB system by end of 2007. In addition, a
program of wider placement of EFI and LFI is to be implemented in 2004 to improve
operational flexibility and system efficiency in general. The EFI will be placed at incomer
and outgoing feeder at every distribution substation and be later integrated with planned
SCADA.

- 119 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

8. Appendix B: Types of DGs

8.1 Introduction
8.1.1 Energy Source
Mechanical energy to turn the generator rotor is supplied by the prime mover. This involves
energy conversion from mechanical energy to electrical energy. Some of the most common
type of energy sources for DGs are:
• Hydropower
• Fuel Cells
• Landfill Gas
• Biomass
• Wind Power
• Geothermal
• Photovoltaic
If the installed capacity of DG Plants is taken into account by the utility in its energy and
capacity planning, the reliability of the energy source must be considered. The availability of
power from wind turbines is highly unpredictable. Landfill gas turbines, Geothermal and
reciprocating engines are more reliable source of energy, with long outages to shutdowns
for maintenance, which can be planned in advance. The reliability of hydropower turbines is
also inherently very high but energy availability depends greatly on the pattern of water
flow. For back pressure steam turbines, where the steam from the DG turbines is used for
processes, the amount of generation is often dictated by the steam requirements of the
plant at different times of the day.

The Government of Malaysia is signatory to the 1992 Rio Earth Summit and participated in
the Berlin Summit. This requires the reduction of the greenhouse gases and thus renewable
energy (RE) such as run of river hydro, solar, biomass and wind energy generation meets
these objectives. Consequently any project using the RE sources should be given every
assistance and prioroty to connect to TNB’s medium voltage (MV) network.

8.2 Hydropower
Hydropower is a valuable source of energy. Unlike other sources of energy, water retains its
value even after it is used as a medium to generate electricity. Hydroelectric station uses
water that is stored in a reservoir behind a dam or from run-of-river to drive the turbine. As
the water rushes through the turbine, it spins the turbine shaft which produces mechanical
power as shown in Figure 8.1. The mechanical power is then converted to electrical power
through the generator, which is connected to the turbine.

- 120 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Figure 8.1: Pondage hydro-power scheme

There are generally three types of hydropower scheme namely:


ƒ run-of-river;
ƒ peaking or pumped storage; and
ƒ impoundment.
Run-of-river uses natural flow of river without causing an appreciable change in river flow and
the surrounding environment. Normally such system is built on small dam that impound little
water. An example of this type of hydro is the Kenerong Hydro Scheme located in Ulu Kelantan

A peaking or pumped storage station impounds and releases water when the energy is needed.
In this method, excess energy is used to pump water from lower reservoir to an upper
reservoir. During period of high electricity demand, the water is released to the lower reservoir
to generate electricity.

An impounded facility, typically a large hydropower station, uses dam to store river water in a
reservoir – also termed as pondage hydro. This method allows water to be released constantly
to generate electricity. Example of impounded facility is the Kenyir Hydro Station in
Terengganu.

The main advantage of hydropower is that it does not produce or emit any pollutant as by-
product. In addition, its operating cost is very low and hydropower can respond quickly to
utility load demand when it is required. On the other hand, high initial capital cost and potential
environmental impact, especially for big hydropower plant are the main disadvantages. The

- 121 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

environmental impact, however, can be avoided or reduced with proper planning in the initial
stage of implementation.

8.3 Fuel Cells


Fuel cells produced power electrochemically by passing a hydrogen-rich fuel over anode
and air over a cathode and separated by an electrolyte. The by-products of the process are
water, heat and carbon dioxide. Fuel cells was first discovered in 1839 by Sir William Grove
who utilized four large cells, each containing hydrogen and oxygen to produce electricity
which then used to split the water in the upper cell into hydrogen and oxygen. In 1959, the
first practical application for fuel cell was developed, capable of powering welding machine.
In the 1960s, NASA used fuel cell to power on-board electronics for space vehicles Gemini
and Apollo. Fuel cell can be categorized into five different groups, distinguished by the
types of electrodes used. The features of these fuel cells are summarised in Table 8.1.

Fuel cell offers high efficiency and environmental advantage in comparison to some other
technologies mainly due to the electrochemical process which does not require any moving
parts. Phosphoric acid fuel cell can achieve up to 40 percent efficiency while molten
carbonate and Solid oxide fuel cells have an efficiency of nearly 60 percent. In addition, fuel
cells are virtually soundless, making it suitable to be used in premises where noise is a
problem.

Table 8.1: Fuel Cell Characteristics


Type Operating Temperature Status and Application
Alkaline 50-100° C Mostly for space market, but is available for
land vehicle.
Solid 50-100° C Potential use for cars and buses.
Polymer

Phosphoric 200° C Used for medium scale cogeneration


application.
Acid

Molten 600° C Used for medium and large scale


cogeneration plant
carbonate

Solid Oxide 500-1000° C Can be utilized for all sizes of cogeneration


application.

- 122 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

8.4 Landfill Gas


Landfill gas occurs naturally wherever household and commercial waste is disposed off in
engineered rubbish sites. As the organic matter in the buried waste decomposes it creates
a methane-rich biogas. This is made up of about 55% methane and 45% carbon dioxide. It
is the methane which is valuable as a source of energy for both heat and power. At a
modern disposal site, excavated areas are progressively lined with an impervious material
before being filled with waste and then capped over again. The lining and the capping help
to prevent gas from escaping. Landfill gas is produced within about a year of the first
tipping. It can continue to be exploited for up to decades afterwards.

To utilize the biogases produced from the waste landfill, gas wells are drilled at few places
on the disposal site as shown in Figure 8.2. The gas would first be filtered before being sent
through gas collector line to drive the turbine that generates electricity.

Figure 8.2: Landfill generation

8.5 Wind Power


Wind energy conversion systems are designed to convert the kinetic energy of wind
movement into mechanical power, which is the movement of a machine. The mechanical
power is then converted to electricity by the generator. The electricity generated can either
be stored in batteries or used directly by connecting through utility distribution network.
Wind turbine comprises of four basic components; the rotor, electrical generator, speed
control system and the tower as depicted in Figure 8.3. Wind power fall into two broad
categories:

- 123 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

1) Horizontal axis with propeller type design


2) Vertical axis, Darrieus or ‘egg-beater’ design.
The horizontal axis turbines are generally gear boxes and startup through the action without
the need for an external motor vertical axis turbines are generally not equipped with gear
boxes but are coupled directly to the most vertical axis turbines are not self starting. Both
types of turbines normally employ induction generators which are well suited to the wide
range of operating speeds possible.

Figure 8.3: Components of wind turbine

The startup time for a vertical axis turbine’ is less than one minute. Smaller machine started
by connecting directly across the line larger machines reduced voltage starters may be
employed to reduce inrush currents. System disturbances which cause such units to trip
off line require a complete and restart of the machine. Wind power typically have no speed
control or at best have relatively crude speed control such as varying blade pitch. It is
therefore difficult to bring the slip speed of the induction generator to zero because closing
the connecting switch to the utility system and voltage fluctuations are likely at the instant
connection. The main factor affecting rate of load change is the inertia constant and its
relation to wind speed changes.

Despite being considered as environmental friendly, wind turbine has several


disadvantages. Wind turbines are normally situated off shore and represent negative visual

- 124 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

impacts. In addition, wind turbines produce acoustics noise and electrical interference
which would be unpleasant to the surrounding environments.

8.6 Microturbines
Microturbines are small combustion turbines with output ranging from 25kW to 1000kW.
Microturbines evolved from automotives and trucks turbocharge auxiliary power units from
airplanes and small jet engines used on pilotless military aircrafts. Most microturbines are
typically single-shaft machines, with the compressor and turbine mounted on the same
shaft as the electrical generator. It consists of only one rotating part, eliminating the need
for gear-box and associated moving parts thus reducing maintenance and increasing
reliability. Microturbine rotates at speed of 6,000 to 10,000 rpm driving either a two or four
pole permanent magnet generator. The shaft is mounted on either oil lubricated bearings or
air bearings. A key component of the microturbine is the recuperator, which transfers heat
from exhaust gas to air that is sent to the combustor. Pre-heating combustion air reduces
the fuel consumption and increases its overall efficiency to 25 to 30 percent. Further
utilization can be gained by utilizing the waste heat from the turbine and incorporating heat
recovery system to the unit.

Performance of microturbine is better as compared to bigger turbine where it’s combustion


process is quieter and cleaner. Microturbines can achieve fuel to electricity efficiency up to
40 percent and produce less than 7 parts per million of NOX gas emission. Microturbines
can burn a variety of fuels including natural gas, diesel, gasoline and methane. Microturbine
provides an abundance of usable heat for hot water, absorption chilling, and distilling and
direct heat applications. This supply of heat makes microturbine, when used in a combined
heat and power application, highly efficient with its efficiency in the range of 70 to 80
percent. With maintenance cost forecast to be one third of the traditional reciprocating
equipment and very high efficiency, microturbine is an attractive option.

8.7 Geothermal
Geothermal energy is heat energy originating deep from the earth molten area. It is this
heat which is responsible for volcanoes and earthquakes. The temperature in the earth’s
interior is as high as 7000’C. There are four types of geothermal resources namely
hydrothermal, geo-pressured, hot dry rock and magma. Of the four types, only the
hydrothermal resource is currently commercially available. Hydrothermal resource comes
in the form of either steam or hot water depending on the temperature and pressures
involved. High grade resource is normally used for electricity generation and lower grade
resource is used in direct heating applications. A typical geothermal plant is shown in
Figure 8.4.

- 125 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Figure 8.4: Geothermal Power Plant

8.8 Photovoltaic
Photovoltaic system uses semiconductors-based cells to directly convert sunlight to
electricity. The semiconductor cells use thin film and crystalline silicon materials. The
greater the intensity of the light, the more power it will generate. Photovoltaic system can
be used to generate electricity at almost any scale, depending on how many modules are
connected together. The cost of photovoltaic cell has been reduced by almost 50 percent
since 1980 and the sales have been increasing steadily particularly in the remote power
operation. PV cell was initially developed in the 1950s for use on satellites and space
program and has been used widely as the source for satellites orbiting earth since 1960s.
With technology advancement in the 1980s and 1990s, many applications of PV cell have
been commercialized. The applications in use today include health care system,
communications, security system, electricity supply and transport aids.

8.9 Cogeneration
8.9.1 Definitions of Cogeneration
Cogeneration or more popularly known as combine heat and power (CHP) refers to the
sequential generation of two different forms of useful energy (e.g. thermal and electrical)
from the same amount of primary fuel input within a manufacturing process. This form of
generation enhances the utilization of energy efficiently and is highly promoted by the
Malaysian Government. Energy efficiency can be increased from 35% to 75 – 80% using

- 126 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

this mode of generation. Figure 8.5(a) and 8.5(b) illustrate this approach of generation and
its increased efficiency when compared to conventional generation.

Figure 8.5(a): Concept of Cogeneration – conventional generation

Figure 8.5(b): Concept of Cogeneration – cogeneration

- 127 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

8.9.2 Cogeneration plants in Malaysia


Since 1993, Jabatan Bekalan Elektrik dan Gas (JBEG, now Energy Commission (EC)) had
issued more than 26 licenses to major developers in the petrochemical, chemical, steel,
refinery, pulp and paper, district cooling industries to generate electricity as part of their
manufacturing processes. The list of developers and the amount of generating capacity for
each project is shown in Table 8.2. The total generating capacity is 645.8 MW, which
represents less than 6% of the maximum demand of Peninsular Malaysia. Most of this
cogeneration plants uses either natural gas or process waste gas as the main source of
fuel. Amongst these plants that are connected and operated in parallel to the distribution
networks are summarized in Table 8.2.

Table 8.2: List of Co-generation plants in Malaysia


Inter-
Installed Top
Standby connection
No Developer and plant address Fuel Capacity Up/Export
(MW) Voltage
(MW) (MW)
(kV)
See Sen Chemical Bhd.
Process
Kawasan Perindustrian Telok
1 Waste 6 - 2.4 11
Kalong, Kemaman,
Gas
Terengganu
TCL Industries (M) Sdn. Bhd.
Process
Kawasan Perindustrian Telok
2 Waste 7 2.4 Export - 11
Kalong, Kemaman,
Gas
Terengganu
Gas District Cooling (M) Sdn.
Natural
3 Bhd. 8.4 - 0.5 11
Gas
Universiti Petronas, Tronoh
Tractors Malaysia Sdn. Bhd. Natural 11 (not
4 1.2 0.9 -
Kampong Puchong, Selangor Gas parallel)
Gas District Cooling (M) Sdn.
Natural
5 Bhd. 26 20 Export - 33
Gas
Kuala Lumpur City Center
Gas District Cooling (M) Sdn.
Bhd. Natural
6 60 - - 33
Kuala Lumpur International Gas
Airport
Gas District Cooling (M) Sdn.
Natural
7 Bhd. 10.8 - 0.5 33
Gas
Putrajaya Precinct 2
Titan Petrochemicals (M) Sdn,
Bhd. Process
8 Tanjung Langsat Industrial Waste 25 6 10 132
Estate Gas
Pasir Gudang, Johor
Shell Refining Company Bhd. Process
9 Batu 1, Jalan pantai Waste 35 - 17.5 132
Port Dickson, Negeri Sembilan Gas

- 128 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

The developments of cogeneration are essentially driven by the following key factors:
ƒ Advancement in the technology for small-scale power generation e.g. efficient lesser
capacity generators.
ƒ Energy efficiency or rational use of energy
ƒ Deregulation or competition policy
ƒ Environmental awareness – reduction in Green-House-Gas (GHG) emission.
Table 8.4 lists the various technologies used in Co-Generation or CHP plants.

Table 8.4: Cogeneration technologies


Average heat/power
Main Prime Mover
ratio
Back-pressure steam turbine 6.9:1
Pass-out condensing steam turbine 6.7:1
Gas Turbine 3.6:1
Combine Cycle 1.8:1
Reciprocating Engine 1.8:1

- 129 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

8.9.3 Description of Cogeneration Technologies


8.9.3.1 Back-pressure steam turbine
Back-pressure steam turbines exhaust steam at greater than atmospheric pressure either
directly to an industrial process or to a heat exchanger. The higher the back pressure the
more energy there is in the exhausted steam and so less electrical power is produced. The
back-pressure steam turbines have an average heat to power ration of 7:1 and so, once the
site electrical load has been met, any export of electrical power will be small. Figure 8.6 is
a simplified diagram of a CHP scheme using a back-pressure steam turbine. All the steam
passes through the turbine, which drives a synchronous generator, usually operating at
3000 rpm. After the turbine, the steam, at a pressure typically in the range 0.12 – 4 MPa
and a temperature of between 200 and 300 °C depending on its use, is passed to industrial
process or through a heat exchanger fou use in space heating.

Figure 8.6: Co-Generation scheme using a back pressure steam turbine

- 130 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

8.9.3.2 Pass-out condensing steam turbine


In a pass out (or extraction) condensing steam turbine (see Figure 8.7) some steam is
extracted at an intermediate pressure for the supply of useful heat with the remainder being
fully condensed. This arrangement allows a wide range of heat/power ratios.

Figure 8.7: Co-Generation scheme using a pass-out steam turbine

8.9.3.3 Gas Turbine


Figure 8.8 shows how the waste heat of a gas turbine may be used. Gas turbines using
either natural gas or distillate oil liquid fuel are available in ratings from less than 1 MW to
more than 100 MW.

- 131 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Figure 8.8: Co-Generation scheme using a gas turbine with waste heat recovery

- 132 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

9. Appendix C: Data available and to be submitted

9.1 Data Available from TNB at the Initial Stage


A DG Developer upon recognizing the potential for connection of the DG plant to the local
distribution network should make the necessary appointment to meet representatives of the
local Distributor. At the initial meeting it will be useful for the DG Developer to brief the
Distributor on the DG plant with the following basic information:
1) Location of plant
2) Type of generation and fuel
3) Capacity of plant

Basic information that can immediately be obtained from the Distributor includes the
followings:
1) Nearest substation, distribution lines or cables to the DG plant and their capacities;
2) The distance to the nearest connection point;
3) Three-phase short-circuit level at nearby substations;
4) Source transmission substation and loading profile (24-hour MW, MVAR for working
days and weekends) of the feeder where the plant would be connected;
5) Development of the network in the area; and
6) Any special problems that the Distributor faces with respect to power supply in the
area.
It is important at this point for the Distributor to indicate to the DG Developer how the
proposed DG plant should have its power output scheduled to ensure no spill-over of
power to the transmission network (operation regime).

- 133 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

9.2 Data to be Submitted by DG Developer for ‘Preliminary


System Study’ – ES.08.01
After a preliminary assessment of a possible development of DG plant and contacts with the
local Distributor, the Developer needs to know the cost estimate for connection to the local
distribution network. The local Distributor in order to provide the cost estimates would
need to carry out a ‘Preliminary System Study’ so that requirements for additional network
components and reinforcements could be identified.

For purpose of a preliminary system study, the Developer is required to submit a letter to
local TNB offices. The letter should also describe basic parameters of the proposed DG
plant.

Date:

To: District/Regional Officer


Tenaga Nasional Berhad

Request for Cost Estimates of DG Connection


DG Plant units & Capacity: 2 x 3MW
Fuel Type: Hydro
Location of Plant: Batu 4 Sg. Ping

We refer to the above basic information on the proposed DG plant


that we intend to connect to your distribution network.

Enclosed herewith is the location map indicating the site of the


DG plant and the nearest point to your distribution network
facilities.

We would be very glad to receive from you as soon as possible


indications on the following items:

1) Cost estimates for connection;


2) Estimate of duration for implementation of connection; and
3) Operation regime of the DG plant.

Thank you.

Yours Sincerely,

(signed)
DG Plant Developer

- 134 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

9.3 Data to be Submitted for ‘Power System Study’ –


ES.08.03
Based on the preliminary cost estimates of the DG plant implementation including
connection costs, the Developer with the knowledge of possible operating regime of the
plant would be in a good position to make assessment of the commercial viability of the
project. In proceeding with the project, the DG Developer would enter the design stage
where consultants would normally be appointed for the design and specifications of the
plant. When details of the proposed plant are available, the DG Developer should now
submit official application for connection to the local Distributor.

The official application should be submitted in Form DG001 (see next page). This
application form must be accompanied by details of the plant.

- 135 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

FORM DG 001

APPLICATION FORM FOR CONNECTION OF DISTRIBUTED GENERATION/RE PLANT TO TNB


DISTRIBUTION NETWORK

SECTION A: DEVELOPER INFORMATION


Company

Address

Contact Information Telephone Fax


Email
Web site
Contact Person
Name/Contact
Information Telephone Handphone
Email

SECTION B: FACILITY/PLANT INFORMATON


Plant/Facility Address

Type of Plant

(Hydro, Biomass, Landfilled Gas, Cogen)


Electrical Consultant
Name & Contact
Information

Telephone Handphone
Email

- 136 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

SECTION C: DETAIL EQUIPMENT INFORMATION


Part 1 – General Information
NO ITEMS DATA
1 Generator type 9 - synchronous
9 - asynchronous (induction type)
2 Rotor Construction
3 Generator rating (kVA)
4 Generator power factor
5 Rated terminal voltage (kV)
6 Frequency (Hz)
7 Rated speed (r.p.m)
8 Minimum power factor lagging
9 Minimum power factor leading
10 Type of prime mover
11 Generator voltage control
12 Generator Sub-Transient Reactance (p.u)
13 Generator Transient Reactance (p.u)
14 Excitation System Controls
15 Governor Controls
16 Leakage Reactance (p.u)
17 Inertia Constant (MW.sec/MVA)

Part 2 - For Generator > 3 MW


NO ITEMS DATA
1 Direct Axis Sub-Transient Reactance (p.u)
2 Direct Axis Transient Reactance (p.u)
3 Direct Axis Synchronous Reactance (p.u)
4 Quadrature-Axis Sub-Transient O/Cct Time Constant (p.u)
5 Quadrature- Axis Transient O/Cct Time Constant (p.u)
6 Quadrature- Axis Synchronous O/Cct Time Constant (p.u)
7 Direct Axis Sub-Transient O/Cct Time Constant (sec)
8 Direct Axis Transient O/Cct Time Constant (sec)
9 Direct Axis Transient O/Cct Time Constant (sec)
10 Quadrature Axis Sub-Transient O/Cct Time Constant (sec)
11 Quadratura Axis Transient O/Cct Time Constant (sec)
12 Zero Sequence Resistance (p.u)
13 Negative Sequence Resistance (p.u)
14 Zero Sequence Reactance (p.u)
15 Negative Sequence Reactance (p.u)

- 137 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Part 3 – Generator Transformer (if applicable)


NO ITEMS DATA
1 Rated Capacity (MVA)
2 Voltage Ratio (HV/LV)
3 Tap Range: Max
Min
4 Vector Group (HV/LV)
5 Tap Step
6 Impedance (%)
7 Method of Earthing
8 Resistance Value (p.u)

Part 4 – Short Circuit


NO ITEMS DATA
1 Maximum 3-N Symmetrical S/Cct
Infeed into TNB Network (kA)
2 Maximum Zero Sequence Impedance
of the User’s Network at the Point of
Common Coupling with TNB’s Network
(kA)
3 Breaker Rating (at point of interconnection)
(1) Continuous (A)
(2) Short-time rating (kA rated time)
(3) Making Capacity (MVA)
(4) Breaking Capacity (MVA/kA)

Part 5 – Diagram/Plan to be Submitted


NO Diagram/Plan (Tick (•) in relevant box) Tick
1 Site Plan
2 Single Line Diagram of any Existing or Proposed Arrangements of the
interface connection between TNB and Generator.
3 Generator Reactive Capability Chart
4 Protection System Data and Setting (Generator,Tx,CB,CT,PT)
5 Plant Single Line Diagram
6 Plant Load Profile
7 Open Circuit Saturation Characteristics
8 Block Diagram of Excitation System and Parameters

- 138 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

10. Appendix D: TNB Distribution Planning Criteria

10.1 Introduction
This appendix outlines the planning/design criteria as applied by TNB to ensure that the
distribution networks meet the following requirements:
ƒ Secure electricity supply;
ƒ Reliable electricity supply;
ƒ High quality electricity supply;
ƒ Optimal equipment utilization;
ƒ Optimal network losses; and
ƒ Safety of staff and public.
The purpose of the distribution system planning/design criteria is to provide the balance
between the customer’s need for a safe, secure, reliability, high quality electricity supply
and costs by TNB.

10.2 Distribution Network Design Philosophy


TNB designs its distribution networks to operate as radial systems and under normal
circumstances, the loss of a component of the network will result in the loss of supply to a
number of customers connected to the sub-system. The duration of loss of supply is
minimized through the use of fault indicators which improves fault location and hence
isolation of the faulty sections. In certain designated supply load centres, SCADA is used to
further minimize loss of supply duration.

In urban, sub-urban and town areas, the distribution networks are configured an open
meshed/ring network that is run radially with open points. By operating the network with
open points, fault levels are reduced (as compared to closed rings or meshed) and simply
technical and operational requirements. Open meshed/ring network arrangement allows
improvements in supply restoration times following an outage.

In rural areas where the total feeder maximum demand is less than 1MVA, the network
operates in radial configuration without alternative supply.

The distribution system is not designed for islanded operation with distributed generation.
DG must be designed to be disconnected from the distribution network if the feeder that the
generator is connected to is separated from the remainder of the distribution system.

10.3 Network Capacity and Reinforcement Needs


Network capacity and the need for network reinforcements are assessed by comparing the
planning criteria with network planned performance level due to increase in load or addition
of generation like DG Plant. To meet the planned performance levels in terms of security,

- 139 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

reliability and quality, the least cost option is normally chosen. The extent of network
reinforcement works is dependent on the following:
ƒ Load forecast projections;
ƒ The anticipated max demand of the customers or generation output; and
ƒ Age and condition of the existing assets.
Economic analysis is applied in assessing network reinforcement requirements for the
following purposes:
ƒ To indicate returns of proposed capital investments;
ƒ To choose the best options - least cost being the method used; and
ƒ To minimise losses.

10.4 Distribution System Planning/Design Criteria


The planning/design criteria applied are a set of standards/requirements applied to ensure
that the distribution network would be operated to the desired security, reliability and power
quality. These criteria are used as planning and design limits/requirements to serve the
interests of the customers connected to the network in terms of quality of supply and at
minimum overall costs.

10.4.1Steady State Criteria


The steady state criteria define the adequacy of the network to supply the electricity/energy
requirements of the customers within the component ratings, frequency and voltage limits.
The steady state criteria apply to the normal continuous operating condition of the network
and also include post supply interruption/post disturbance condition (or contingency
condition) once the network has been normalized.

10.4.2Steady State Voltage limits


The distribution network must be designed to achieve a continuous network steady state
voltages at the customer’s connection/interface during normal operating conditions are to
be within the following limits:
1) ± 5 % at 33 kV
2) ± 5 % at 11 kV
3) + 5% and − 10% at .415 kV

Under contingency operating conditions the steady state voltages are to be within the
following limits:
1) ± 10 % at 33 kV
2) ± 10 % at 11 kV
3) ± 10% at 0.415 kV
It must be emphasized that the steady-state voltage limits are measured at metering points
or defined connection/interface and the voltage measured is phase to neutral.

- 140 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

10.4.3Thermal Ratings Limits


The thermal ratings of any network components must not be exceeded under normal or
contingency conditions and those thermal limits are as follows:
1) Transformers: Specified by TNB / manufacturer name plate rating
2) Switchgears: Specified TNB / manufacturer name plate rating
3) Overhead Lines: Rating as specified by TNB
4) Underground Cables: Rating in accordance with IEC 60502-02 or as specified by
TNB
5) Overhead Cables: Rating as specified by TNB

10.4.4 Fault Level Ratings Limits (Short-circuit Rating)


For safety reasons, the fault rating of any equipment must not be less than the fault level in
the network at any time and for any normal network configuration. For system planning
study purposes, the fault level calculated is not to exceed 90% of the fault rating of the
existing equipment installed in the network. If fault level studies indicate that the calculated
fault level is to be beyond 90% of the fault rating of the existing network beyond a certain
specified year, provision has to be made by reconfiguring the network and steps be taken to
have a higher fault rating for new equipment in the foreseeable future. The maximum fault
levels permitted on TNB distribution network are currently as follows:
1) 11 kV – 20 kA
2) 22 kV – 20 kA
3) 33 kV - 25 kA
Equipment owned and operated by TNB and connected to the network is designed to
withstand these fault levels for 3 seconds (short time withstand current of 3 seconds).

10.4.5Frequency Limits
Under normal conditions, the transmission and distribution network frequency is
maintained at 50 Hz ± 1%. Under emergency conditions that caused the frequency to drop
below 49.5 Hz, under frequency load shedding scheme will operate to reduce load on the
network so as to prevent total failure of the electricity system operated by TNB.

10.4.6Security of Supply Criteria under Contingency Situation


Security of supply under contingency relates to the ability of the network to be reconfigured
after an outage of a network element and supply to the healthy portions of the network
restored.

10.4.6.1 Network Reliability


TNB will plan and design its networks so that the System Average Interruption Duration
Index (SAIDI) is minimized.

10.4.6.2 Urban/Sub-Urban Medium Voltage Distribution Feeders


Medium voltage distribution feeders in urban areas must be planned and designed so that,
in the event of an outage of any network element, the load of the feeder can be transferred
to adjacent feeders by manual or supervisory (when planned for) network reconfiguration.

- 141 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

The network shall be planned and designed so that in the event of a failure of a main intake
sub-station transformer in the supply zone:
ƒ all of the loads can be transferred to the other transformer in the main-intake sub-
station; or
ƒ all the loads can be transferred to other main intake sub-station transformers within
the supply zone or other nearby adjacent supply zones.
In essence, the deterministic criteria of single network element contingency i.e. (N-1)
criterion is applied for medium voltage network planning for urban/sub-urban areas
resulting in no loss of loss load during repair time.

10.4.6.3 Rural Medium Voltage Distribution Feeders (<1 MVA)


For rural areas of total feeder load less than 1 MVA, the security of supply under
contingency as in urban/sub-urban areas are not applicable. However, where economically
feasible and reasonable, open point connections between feeders should be provided.

10.4.6.4 Low Voltage Distribution Networks


Low voltage distribution service cables to users are planned as radial circuits. Where
practical and safe, for urban areas, low voltage distribution networks are connected as
open rings to provide an alternative supply in the event of circuit outages.

10.4.7 Power Quality Criteria


Power quality criteria define the shape and limits on the deviations of supply voltage
sinusoidal waveform in the distribution network. This is also referred to as the quality of
voltage provided by TNB at the point of common coupling or interface with
customers/generators. The following criteria have been established:
1) Power quality under steady-state conditions;
2) Power quality during transient disturbance conditions;
3) System frequency limits

10.4.7.1 Power quality under steady-state conditions


Power quality under steady-state conditions refers to the quality of the normal voltage
being supplied to the customer at the point of common coupling. It refers to voltage
fluctuation or regulation, and limits for flickers, harmonics, as well as voltage unbalance.

10.4.7.2 Power quality during transient disturbance conditions


Power quality under transient disturbance conditions refers to limits of variations of voltage
quality during disturbances. The disturbances include outages, momentary interruptions,
voltage sags and other transients.

10.4.7.3 System Frequency


Limits of frequency must comply with the requirements of clause 10.4.5.

- 142 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

10.4.7.4 TNB Power Quality Compatibility Limits


The distribution networks as well as the transmission network are analyzed to ensure
satisfactory performance, in accordance with TNB’s Power Quality Criteria, whenever a new
customer is to be connected to TNB distribution network at the point of common coupling,
or when a complaint is received from an existing customer. Harmonic Voltage, Voltage
Unbalance and Flicker Limits will be analyzed depending on the nature of load of the new
customer being connected to TNB. In summary, the compatibility limits currently being
adopted TNB are summarized as in Table 10.1.

Table 10.1 - TNB Power Quality Compatibility Standards and Guidelines


Quality of Measurement Maximum permissible value for Standards/ Guidelines
supply all sources
variation
Distortion Total Harmonic Distortion 5% at 415/240 Volts Engineering
Voltage (THDV) % 4% at 11 and 22 kV Recommendation
3% at 33 kV G5/4

Flicker Pst, Pst, 1.0, Plt 0.8 (at 132 kV and Engineering
Plt below) Recommendation P28

Pst, 0.8, Plt 0.6 (Above 132 kV)

Momentary V% 1 % - series voltage change that Engineering


Voltage may lead to flickering problems Recommendation
Change P28
Limits 3%- single voltage change due to
switching ON or OFF of any loads.

Voltage Negative Phase Sequence 2 % for 1 minute duration Engineering


Unbalance Voltage % Recommendation P24-
1984
P29-1990

Voltage sag % Remaining Voltage 50 % Sag (up to 200 ms) SEMI F47
70 % Sag (up to 500 ms)
80 % Sag (up to 1000 ms)

- 143 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

10.4.8 Conductor Selection Criteria


TNB uses both underground cables and overhead lines in its distribution network. In
designing extensions or network reinforcements, demand forecasts over a planning horizon
is used to establish the network concept plan and the initial installations shall conform to
the concept plans and TNB will use conductors that are appropriately sized.

To achieve cost efficiencies, standard overhead conductors and underground cable sizes
have been designed.

System Planning, Engineering Services


Engineering Services & Logistics Dept.
Distribution Division
TNB
July 2004

- 144 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

11. Appendix E: System studies associated with the


connection of the DG

11.1 Introduction
Distribution networks are primarily designed to distribute power from central generation via
transmission system to customer loads. In this configuration the power from the source i.e.
central generation will flow through transmission system and distribution system and
finally absorbed by customer loads. It is a straight forward one way power flow. But when
distributed generation is introduced in distribution system the power flow becomes more
complex and may flow both ways.

In such a configuration the normal conventional way of planning, designing and operating
the distribution system need to be reviewed. The present of local generation will alter the
behaviour of the distribution system either at steady state or transient state. This will
obviously affect the protection strategy and operation, the network design and operation
and restoration operation after fault. Failure of either one of these will affect the safety of
the operating personnel as well as the equipment.

There are two stages of studies carried out by TNB for connection of a DG Plant to the
distribution network:
1) Preliminary system study; and
2) Power system study.

The ‘preliminary system study’ has two main objectives:


a) To determine the feasibility of connecting the DG Plant to the distribution network; and
b) To determine estimation of cost for connecting the DG Plant to the distribution network.

The ‘power system study’ is carried out after DG Developer has submitted formal
application for connection and the study has the following main objectives:
1) To confirm the findings of the ‘preliminary system study’
2) To determine additional control measures; and
3) To be used as guidelines for relevant technical specifications for the DG Plant.

In this appendix methods and approaches to both preliminary and power system studies
are elaborated to be as guidelines for TNB planning and design engineers.

- 145 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

11.2 Preliminary System Study


11.2.1Generating unit data
When the DG Developer requests for feasibility and cost estimates of connections, the only
information available to the distribution planning engineers are:
1) Number of generating units proposed and their capacities;
2) Quantum of power to be sent to the distribution network;
3) Fuel resource; and
4) Physical location of the plant including location map.
Based on the fuel resource, the distribution planning engineer could use any of the
following typical models available in the simulation software employed by TNB – PTI’s
PSS/ADEPT (see figure 11.1):
a) Steam turbine (small) – biomass units, cogeneration steam units
b) Hydro without damper – mini hydro units
c) Combustion turbine – gas turbine units

Figure 11.1: PSS/ADEPT generator model

- 146 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Tables 11.1 through 11.3 provide guidelines on typical data for synchronous machines that
could be used for studies.

Table 11.1: Typical data for HV synchronous machines


Type of Machine Turbo Salient pole generator Salient pole generator
/ Parameters Generators with damper winding without damper winding
High Speed Low Speed High Speed Low Speed
2p < 16 2p > 16 2p < 16 2p > 16
Subtransient reactance 9-32 14-32 15-25 22-35 25-40
(saturated) X”d (%)
Transient reactance 14-45 20-32 22-36 22-35 25-40
(saturated) X”d (%)
Synchronous reactance 120-300 80-140 75-125 80-140 75-125
(saturated) Xd (%)
No-load/Short-circuit 0.33-0.8 0.7-1.6 0.8-1.2 0.7-1.6 0.8-1.2
Ratio
Negative sequence 9-32 14-25 15-27 36-63 36-60
Reactance X2 (%)
Zero sequence 2 - 20 3 - 20 3 - 22 4 - 24 4 - 30
Reactance X0 (%)
Subtransient time- 0.02-0.05 0.02-0.05 0.02-0.05 - -
Constant T”d (s)
Transient time- 0.4-1.8 0.7-2.5 0.7-2.5 0.7-2.5 0.7-2.5
Constant T’d (s)
Time constant of d.c. 0.07-1.0 0.1-0.4 0.1-0.4 0.15-0.5 0.2-0.5
Component Tg (s)
Note: Generator resistance, Rg = 0.07X”d for Sng < 100MVA, Rg = 0.05X”d for Sng > 100MVA

Table 11.2: Typical data for LV synchronous machines


Turbo Generator Pole Salient pole Pole
Number generator Number
Rated apparent power (kVA) 40 - 1400 1600-3600
Subtransient reactance 10 - 12 2
10 - 15
(saturated) X”d (%) 11 - 13 4
Transient reactance 13 - 17 2
20 - 40
(saturated) Xd (%) 26 - 36 4
Synchronous reactance 170 - 220 2
150 - 300
(saturated) Xd (%) 260 - 300 4
No-load/Short-circuit 0.6 - 0.7 2
0.4 - 0.8
Ratio 0.4 - 0.5 4
Negative sequence 4 - 14 2-4
=X”d =X”d
Reactance X2 (%)
Zero sequence 2–4
(0.4 - 0.8)X”d (0.4 - 0.8)X”d
Reactance X0 (%)
Subtransient time- 2–4
0.002 - 0.03 0.02 - 0.05
Constant T”d (s)
Transient time- 2–4
0.006 - 1.0 0.5 - 1.2
Constant T’d (s)
Time constant of d.c. 2–4
0.008 - 0.1 0.03 - 0.15
Component Tg (s)
Note: Generator resistance, Rg = 0.15X”d

- 147 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Table 11.3: Typical range of generator data


Parameters Hydraulic Units Thermal Units
Direct-axis synchrounous reactance, Xd 0.6-1.5 1.0-2.3
Quadrature-axis synchrounous reactance Xq 0.4-1.0 1.0-2.3
Direct-axis transient reactance, X’d 0.2-0.5 0.15-0.8
Quadrature-axis transient reactance X’q - 0.3-1.0
Direct-axis subtransient reactance, X’’d 0.15-0.35 0.12-0.25
Quadrature-axis subtransient reactance X’’q 0.2-0.45 0.12-0.25
Direct-axis transient open circuit time-constant T’do 1.5-9.0 3.0-10.0
Quadrature-axis transient open circuit time-constant T’qo - 0.5-2.0
Direct-axis subtransient open circuit time-constant T’’do 0.01-0.05 0.02-0.05
Quadrature-axis subtransient open circuit time-constant T’’qo 0.01-0.09 0.02-0.05
Stator leakage inductance Xl 0.1-0.2 0.1-0.2
Stator resistance Ra 0.002-0.02 0.0015-0.005
Reactances are based on machine MVA in p.u.
Time-constants in seconds

If only the d-axis parameters are known, the q-axis parameters can be estimated as:
1) Xq = 0.9 * Xd (0.65 * Xd for hydro)
2) X’q = 2.0 * X"d (can be 3 to 4 times higher)
In some cases, only the transient d-axis reactance X’d is known. In that case, the other
reactances can be estimated using X’d. The relationships can also be used to fill in where
one or two data items are missing. For Round Rotor Machines:
1) Xq = 5.33 X’d
2) Xd = 1.1 Xq
3) X’q = 0.3 Xq
4) X"d = 0.66 X’d
5) Xl = 0.66 X"d
6) T’do = 6.0
7) T"do= 0.035
8) T’qo = 0.6
9) T"qo= 0.07
10) s(1.0)= 0.13
11) s(1.2)= 0.4

For Salient Pole Machines:


1) Xq = 2.23 X’d
2) Xd = 1.57 Xq
3) X"d = 0.66 X’d
4) Xl = 0.66 X"d
5) T’do = 8.0
6) T"do = 0.05
7) T"qo = 0.1
8) s(1.0) = 0.11
9) s(1.2) = 0.5

- 148 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

If only saturated values of the reactances are known, it is possible to estimate the
unsaturated reactances needed for input stability simulations. The standard method for
labeling reactances is:
1) Reactance at rated voltage (saturated) = X"dv
2) Reactance at rated current (unsaturated) = X"di
Similar terminology is used for the transient reactances. An estimate of the relationship
between the two is:
1) X’di = 1.35 X’dv
2) X"di = 1.35 X"dv
The relationship varies significantly among machines; the range of the factor is about 1.1 to
1.45. There is usually little or no effect of saturation on the steady-state reactances and also
no effect on X’q.

In all applications, the reactances must conform to the ratios:


a) Xd > X’d > X"d > Xl
b) Xq >X’q > X"q > Xl
Note that subtransient saliency (i.e., where X"d • X"q) has negligible effect on transient
stability calculation and is normally ignored. Thus, X"q is assumed equal to X"d.

11.2.2Review/Update Network Model


It is assumed that existing network model has already been established for all distribution
networks in TNB. Before the DG Plant model is included in the network data, the existing
data must be reviewed and updated to reflect the condition when the DG Plant will be
connected. In particular the following updates must be included:
1) All new network additions – substations and circuits
2) Feeder loads must be updated in accordance to the latest load forecast
In PSS/ADEPT network model, only the ‘Base Case’ load should be scaled. Load could be
scaled by selecting all loads in the network or by categories of load.

After the loads have been updated, at least 2 additional load snapshots should be prepared,
namely:
1) Intermediate; and
2) Light load.
Figure 11.2 illustrates an example of selecting load snapshots from a 24-hour load profile
given in p.u. Since we require 3 load levels, the load levels from light to peak (0.4 to 1.0
respectively) are divided into three equal sections – in the case of figure E.2, having four
pints at 0.4, 0.6, 0.8 and 1.0. Peak load level should be chosen as 1.0 p.u. and light load
level 0.4 p.u. However, for intermediate load the load level should chosen at the middle of
intermediate load duration, about 0.7. The duration of each load levels are then determined
from the intersections of the four load level points with the load duration curve. These
values are to be for defining the load snapshots of network model in PSS/ADEPT.

- 149 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

1.2

Peak Load
1
Load
Load (p.u.) 0.8
Intermediate Load Level

0.6
Load duration Load
Duration
0.4 Light Load

0.2

0
1 6 11 16 21
Time (hours)

Base/Peak Intermediate Light

Figure 11.2: An example of calculating load snapshots

After the network model without the DG Plant has been established and checked, the DG
Plant could then be included in the model.

11.2.3Connecting DG Plant and Modelling Approach


Generally there are four possible ways of connecting a DG Plant to the distribution network:
i) Isolated with no grid connection – operate independently of the distribution
network;
ii) Isolated with automatic/manual transfer – under normal condition operates
independently from distribution network and automatically/manually connected to
the distribution network on loss of DG Plant generation sources;
iii) Connected to the distribution network and operates parallel without export of
power;
iv) Connected to the distribution network and operates parallel with import/export (bi-
directional power flow) possibilities.
Case (i) is the least complex and case (iv) is the most in term of system studies, planning
and design.

Before a DG Plant is connected to a network bus, the voltage level at that bus must be
within the criteria range (see Appendix D). A planning/design approach that ignores the
reactive power contribution (sending and absorbing) of the DG Plant is normally used. This
approach ensures that the voltage in the distribution network would be maintained within
criteria limit on loss of the DG Plant. If there is one generating unit, it can be set as

- 150 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

‘constant power’ unit with zero reactive power output (power factor 1.0) as illustrated in
figure 11.3.

Figure 11.3: Constant power unit on power factor = 1.0

If there are several generating units in the DG Plant with its own loads, the generators must
also be set to constant power factor with reactive power output to match the DG Plant
loads. The objective is to have negligible reactive power flow through the interface.
Normally, there may be more than one option of connecting the DG Plant to the network.
Where the DG Plant has its own distribution network, the network together with generating
units and interface transformer(s) must be modelled.

- 151 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

The interface transformer has major influence on the short-circuit contribution of the DG
Plant to the distribution network and therefore its parameters particular positive and zero
sequence impedances must be reasonably modelled. Table 11.4 shows minimum
impedance values for different size transformers in accordance with the requirements of
IEC 76. In PSS/ADEPT, the zero sequence impedance of the transformer would be assumed
to be the same with the positive sequence. What will influence the zero sequence current
contribution is the grounding of the star point of the interface transformer. The minimum
impedance value should be used in the ‘preliminary system study’ for maximum
contribution of fault current from the DG Plant.

Table 11.4: Minimum transformer impedance (IEC 76)


No kVA Range Minimum +Ve sequence
impedance (%)
1 Up to 630 4
2 631 – 1,250 5
3 1,251 – 3,150 6.25
4 3,151 – 6,300 7.15
5 6,301 – 12,500 8.35
6 12501 – 25,000 10
7 25,001 – 200,000 12.5

11.2.4Network Voltage Profile


Clearly, with DG connected to the distribution network the voltage profiles will be altered.
The load flow analysis could be used to determine the voltage profiles in the network
particularly the feeder where DG is connected. The analysis should be carried out under at
least the three load conditions of peak (base), intermediate and light. For voltage profile
analysis, the generating unit must be set to power factor of 1.0. With DG connected to the
distribution network, it must not cause the network voltages to stray outside any statutory
limits and the limits defined by the planning criteria. As the power is forced through the
feeder towards the source, the voltage will rise in the direction of the generator terminals.
Since distribution transformer uses fixed tap, such voltage rise will reflect directly through
to LV customers. This aspect will tend to be the significant limiting factor in dictating the
maximum size of generator that can be accommodated at a specific voltage level.

Clearly, the potential for greatest voltage rise will occur when the distribution network is
during light load since this condition hinders the local absorption of the exported power.
The degree of voltage rise will be related to:
1) Type of generator and its associated control systems – assume power factor of 1.0;
2) The location of the DG Plant in the feeder;
3) The level of export relative to the minimum load condition;
4) The distribution of load on the feeder; and
5) The size of the feeder conductors and its connections to the DG Plant.
To illustrate voltage profile analysis a distribution network as shown in figure 11.4 is
modeled in PSS/ADEPT. An existing 11kV feeder with uniformly distributed load is where
the DG Plant is to be connected. To illustrate the effects on voltage profile, the DG will also

- 152 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

be connected to the middle and beginning of the feeder. Effects of additional 11kV feeder
and distribution at higher voltage level of 33kV would also be demonstrated.

33kV

33kV connection
alternative 33kV

Additional 11kV Feeder

11kV

DG Plant

Feeder with uniformly


distributed load

Figure 11.4: Example uniformly distributed load feeder for voltage profile
analysis

11.2.4.1 Voltage Profile Without the DG


Without the DG Plant, the voltage profile along the feeder is shown in figure 11.5. In this
example, the voltage at the end of the feeder is slightly below the criteria limit of 0.95 p.u.
during peak load.

1.1 Peak
Intermediate
Voltage (p.u.)

1.05 Light

0.95

0.9
0 5 10 15 20 25 30 35 40 45 50

Distance (km)

Figure 11.5: Feeder voltage profile without DG Plant

- 153 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

11.2.4.2 Voltage Profile DG at the end of feeder


The voltage profiles with the DG located at the end of the feeder with generator export of
500kW and 1000kW are shown in figures 11.6 and 11.7 respectively. With 500kW output
voltages remain within criteria for all nodes throughout the load levels – peak, intermediate
and light. It must be noted that the DG contributes to significantly to increase and flatten
the voltage profile along the feeder. When the power export to distribution network is
increased to 1000kW, voltage profile along the feeder is raised to significant level beyond
the criteria limits particularly during light load.

1.1 Peak
Intermediate
Voltage (p.u.)

1.05 Light

0.95

0.9
0 5 10 15 20 25 30 35 40 45 50

Distance (km)

Figure 11.6: Voltage profile, DG at end of feeder, 500kW export

1.1 Peak
Intermediate
Light
Voltage (p.u.)

1.05

0.95

0.9
0 5 10 15 20 25 30 35 40 45 50

Distance (km)

Figure 11.7: Voltage profile, DG at end of feeder, 1000kW export

When a DG is connected at the end of a feeder, voltage profile analysis would indicate the
limit on power export to the distribution network and thus the total size or capacity of the
DG Plant units.

Since the approach is for the DG Plant not to contribute reactive power regulation (constant
power factor at 1.0), a sudden loss of the unit would not result in voltage limit violation.

- 154 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

11.2.4.3 Voltage Profile DG at the mid of feeder


Figures 11.8 through 11.10 show voltage profiles at the three load levels for various DG
Plant power export when it is located in the mid of the feeder. An export of 1000kW would
result in voltage to be slightly out of the criteria range near the generator bus.

1.1 Peak
Intermediate
Voltage (p.u.)

1.05 Light
1

0.95

0.9
0 10 20 30 40 50
Distance (km)

Figure 11.8: Voltage profile, DG at mid of feeder, 500kW export

1.1 Peak
Intermediate
Voltage (p.u.)

1.05 Light
1

0.95

0.9
0 10 20 30 40 50
Distance (km)

Figure 11.9: Voltage profile, DG at mid of feeder, 1000kW export

1.1 Peak
Intermediate
Voltage (p.u.)

1.05 Light
1

0.95

0.9
0 10 20 30 40 50
Distance (km)

Figure 11.10: Voltage profile, DG at mid of feeder, 2100kW export

When located at the mid of the feeder, amount of export could be increased but voltage
remains the limiting factor.

- 155 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

11.2.4.4 Voltage Profile DG at the source of feeder


When the DG Plant is located near the source of the feeder, the amount of export to the
distribution network could be increase further with respect to voltage limits as indicated in
figure 11.11 through 11.13. In this case a maximum export of 2000kW would result in
voltage to slightly outside the criteria range (see figure 11.12).

1.1 Peak
Intermediate
Voltage (p.u.)

1.05 Light

0.95

0.9
0 5 10 15 20 25 30 35 40 45 50

Distance (km)

Figure 11.11: Voltage profile, DG at the source of feeder, 500kW export

1.1 Peak
Intermediate
Voltage (p.u.)

1.05 Light

0.95

0.9
0 10 20 30 40 50
Distance (km)

Figure 11.12: Voltage profile, DG at the source of feeder, 2000kW export

1.1 Peak
Intermediate
Voltage (p.u.)

1.05 Light

0.95

0.9
0 10 20 30 40 50
Distance (km)

Figure 11.13: Voltage profile, DG at the source of feeder, 5000kW export

- 156 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

11.2.4.5 Voltage Profile DG at end of feeder with additional 11kV feeder


As an example, we investigate the impact on voltage profile of a reinforcement comprising
of an additional 11kV circuit operating in parallel with the existing feeder as shown in figure
11.14.

11kV Parallel
Feeder

Figure 11.14: Reinforcement with parallel 11kV feeder

We examine the impacts of voltage profile with the additional 11kV parallel feeder. Without
any DG output, the cable capacitance results in slight increase in voltage at the end of the
feeder as shown in figure 11.15.

1.1 Peak
Intermediate
Voltage (p.u.)

1.05 Light

0.95

0.9
0 5 10 15 20 25 30 35 40 45 50

Distance (km)

Figure 11.15: Voltage profile, with parallel 11kV feeder DG output = 0.0 kW

- 157 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

The addition of the long 11kV feeder cause voltage rise to appear at lower DG output as
compared with the one without the additional feeder (see figure 11.16).

1.1 Peak
Intermediate
Voltage (p.u.) 1.05 Light

0.95

0.9
0 5 10 15 20 25 30 35 40 45 50

Distance (km)

Figure 11.16: Voltage rise at 500kW output with parallel 11kV feeder

The above result shows that a feeder reinforcing the network may not serve to eliminated or
reduce the voltage rise problem. Therefore, voltage profile must again be examined when
reinforcement particularly using long circuits is attempted.

11.2.4.6 Voltage Profile DG at end of feeder with 33kV feeder connection


Another possible reinforcement is to have circuit at the next voltage level as shown in figure
11.17 using 33kV line. In this example, DG output is transferred using the 33kV circuit.

33kV
Feeder

Figure 11.17: Use of 33kV feeder for power transfer

- 158 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

The 33kV circuit significantly improves voltage profile performance even with high DG kW
export as indicated in figures 11.18 through 11.20.

1.1 Peak
Intermediate
Voltage (p.u.) 1.05 Light
1

0.95

0.9
0 10 20 30 40 50
Distance (km)

Figure 11.18: 33kV feeder, 500kW export

1.1 Peak
Intermediate
Voltage (p.u.)

1.05 Light
1

0.95

0.9
0 10 20 30 40 50
Distance (km)

Figure 11.19: 33kV feeder, 2000kW export

1.1 Peak
Intermediate
Voltage (p.u.)

1.05 Light

0.95

0.9
0 10 20 30 40 50
Distance (km)

Figure 11.20: 33kV feeder, 9000kW export

In the example of using 33kV feeder, the limiting factor is overload of circuits.

- 159 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

11.2.5 System Losses


Losses must be treated as an important attribute of the DG Plant. Therefore, in planning the
main principle to be followed is that ‘the connection of the DG must not result in increase in
system losses’. It must never be assumed that a DG Plant connection will contribute to
reduce losses. The following results using network of figure 11.4 indicate the behaviour of
system losses.

11.2.5.1 Losses DG at the end of the feeder


Figure 11.21 shows losses and voltage profiles with different DG kW outputs. If loss at
peak without DG is used as the limit, the DG output with respect to loss limit can be as high
as 3000kW. However, the limiting criterion is the voltage where the maximum export at
peak is limited to less than 1500kW. If the output is limited to the voltage limit of 1.05
(maximum of about 1300kW), this corresponds to minimum (reduced) loss for the feeder.

500
Peak
450 Intermediate

400 Light
Feeder Losses (kW)

350

300

250 Loss limit


200 (use peak)
150

100

50

0
0 1000 2000 3000 4000

DG Output (kW)

1.2
Peak
Intermediate
1.15 Light
Voltage (p.u.)

1.1

1.05

Voltage limit
1
Range

0.95

0.9
0 1000 2000 3000 4000

DG Output (kW)

Figure 11.21: Loss variation with DG connected at the end of the feeder

When a DG is connected to the end of the feeder, voltage limit may be the limiting factor for
export as compared to loss limit.

- 160 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

11.2.5.2 Losses DG at the mid of the feeder


When the DG is located at the middle of the feeder, losses are reduced significantly with DG
Plant maximum export of slightly less than 5000kW (see figure 11.22). However, voltage
criterion requirement results in limiting the DG Plant output to less than 2500kW

500
Peak
450 Intermediate

400 Light
Feeder Losses (kW)

350

300

250 Loss limit


200 (use peak)
150

100

50

0
0 1000 2000 3000 4000 5000

DG Output (kW)

1.2
Peak
Intermediate
1.15 Light
Voltage (p.u.)

1.1

1.05

Voltage limit
1
Range

0.95

0.9
0 1000 2000 3000 4000 5000

DG Output (kW)

Figure 11.22: Loss variation with DG connected at the mid of the feeder

When a DG is connected to the mid of the feeder, voltage limit may also be the limiting
factor for export as compared to loss limit.

- 161 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

11.2.5.3 Losses DG at the source of the feeder


When the DG is located at the source of the feeder, the amount of export could increased
significant from both the perspective of losses and voltage (see figure 11.23). However,
voltage criterion requirement results in limiting the DG Plant output to less than 3500kW

500
Peak
450 Intermediate
Light
400
Feeder Losses (kW)

350

300

250 Loss limit


200 (use peak)
150

100

50

0
0 1000 2000 3000 4000 5000 6000

DG Output (kW)

1.2
Peak
Intermediate
1.15 Light
Voltage (p.u.)

1.1

1.05

1
Voltage limit
Range
0.95

0.9
0 1000 2000 3000 4000 5000 6000

DG Output (kW)

Figure 11.23: Loss variation with DG connected at the source of the feeder

Based on the above analysis, the output (the quantum of export) of the DG when connected
to existing feeder would significantly limited by voltage limit criteria.

- 162 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

11.2.6 Short-Circuit Analysis


The connection of DG will contribute to the local system fault level. All of the associated
switchgears must be able to withstand the stress to which they are subjected. Fault level
study has to be carried out and it shall not exceed 90% of the rating of the associated
switchgears or TNB design fault level. Network protection will cause a delay in tripping, as a
result fault breaking will be a less onerous condition since fault current have been reduced.
Detail knowledge on the protection operating time and the time constant of a particular
generator are required to assess this situation. Therefore, particular attention must be paid
to:
1) Increase in 3-phase fault MVA (90% limit)
2) Making capacity
For calculating of making duty, a multiplying factor of 1.8 should be used on the 3-phase
fault MVA level.

To illustrate the analysis of DG Plant contribution to fault level, a network in figure 11.24 is
used.

25kA, 3-phase

Tx with NER

Tx with min
IEC impedance

Tx with NER
150A, min.
IEC imped.

Figure 11.24: Network for fault level analysis

The following modelling assumptions are to be used:


1) Source must be modelled with maximum value of fault kA – for 33kV, 25kA for 3-phase
is used;
2) Step-down transformer (at Main Intake S/S) impedance must be based on the actual. If
however, the values not available, minimum IEC impedance should be used;
3) Step-down transformer (at Main Intake S/S) NER must be modelled;
4) DG interface transformer minimum IEC impedance should be used; and

- 163 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

5) DG interface transformer NER must be modelled for 150A contribution the distribution
network.
When evaluating the impact of DG Plant on fault level, it is important to look at the 415V
busbar after the LV step-down transformer. This is because the fault rating of 31.5kA for LV
equipment may be exceeded with increase fault level due to DG Plant contribution. For fault
level evaluation the LV transformer tap should be set to the maximum, that is, with highest
possible voltage.

The fault current contribution of the DG Plant is most critical when it is located near the
source bus as illustrated in figure 11.25. In this example, the LV bus has exceeded the 90%
limit. The making duty of the 415V and 11kV breakers are 51.6kA and 28.0kA respectively
and these should be checked against the actual make rating.

51.6kA

28.0kA
91.1%

77.9%

Figure 11.25: 3-phase fault level assessment

- 164 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

11.2.7 System/Feeder Adequacy


Based on previous analysis, feeder capacity is not normally the limiting parameter in terms
of DG Plant output to the distribution network. As an example, feeder overload occurs when
the DG output is 4MW (see figure 11.26). However, at this power export overvoltage of
1.22 p.u. has already occurred.

4MW
Output
Overload

Figure 11.26: Feeder overload is not limiting export when DG Plant at the end of the
feeder.

If the DG Plant is located in the middle of the feeder, overload would occur at higher MW
output. In this case 5.5MW as shown in figure 11.27. However, as in the previous case, the
limiting factor remains voltage and not circuit capacity.

When the DG is located closed to the source, overload/circuit capacity and voltage issue are
limiting DG output as indicated in figure 11.28.

- 165 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Overload

5.5MW
Output

Figure 11.27: Feeder overload is not limiting export when DG Plant at the end of the
feeder.

6MW
Output

Figure 11.28: Feeder overload and voltage are not limiting export when DG Plant at the
source.

- 166 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

11.3 Power System Study


Power system study is carried following formal submission of application for connection of
the DG Plant to the distribution network and confirmation of all input data and parameters.
As stated earlier the main objectives of the ‘power system study’ are:
1) To review the results/findings of the ‘preliminary system study’ with revised input data;
2) To examine additional control requirements to mitigate possible problems; and
3) To establish functional specifications of the interface and associated equipment for use
by the DG Developer.
Apart from reviewing the ‘preliminary system study’, the ‘power system study’ has to
include two new studies:
1) Stability; and
2) Insulation coordination.

11.3.1Stability Analysis
Study on local distribution network stability and security need to carried out for every DG
installation especially for DG with a capacity of more than 5 MW. For DG installation that is
less than 1 MW the study might be waived.

In this study the frequency and the voltage stability need to be confirmed under fault
condition. Frequency stability is analysed by tracking the frequency at each substation as it
evolves over time. If the frequency values either remain constant (at the nominal value of
50Hz) or converge to a different equilibrium value then the system is stable. On the other
hand if a small disturbance at one substation in the system causes the frequency at one or
more substations do diverge from equilibrium then the system is said to be unstable.

The scenarios for this study are both at peak load and base load conditions with
disturbance introduce at various selected critical points in the network. It is important also
to study the stability and the security of the network that has been detached (if any) from
the grid due to loss of mains -islanded network. This would determine how DG should react
under such a condition.

11.3.1.1 Models for Excitation Control


If model and parameters for excitation controllers are not provided, typical models as found
in PSS/E and PSS/VIPER manuals could be used.

11.3.1.2 Models for Speed-Governor


If model and parameters for speed-governor controls are not provided, typical models as
found in PSS/E and PSS/VIPER manuals could be used.

11.3.1.3 PSS/ADEPT Network Model to PSS/E Dynamics


TNB currently employs PSS/ADEPT for distribution network analysis. This tool will be used
in most of the analysis required in the ‘preliminary system study’ and the first part of

- 167 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

‘power system study’. TNB also uses PSS/VIPER for dynamic analysis. This way requires
that PSS/ADEPT network model for steady-state analysis be reentered into PSS/VIPER.
However, a new approach is being developed that the PSS/ADEPT network model can be
translated for use with PSS/E for dynamic simulations.

As an example, a distribution network in figure 11.29 is to be examined in terms of


transient stability.

Figure 11.29: Sample network for stability analysis in PSS/ADEPT

In PSS/ADEPT, the network data can be saved into a HUB format and this format could read
in PSS/ADEPT Utility as shown in figure 11.30. PSS/ADEPT Utility is a program that
converts PSS/ADEPT file to PSS/E and thus ready for stability simulations.

- 168 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Figure 11.30: Reading PSS/ADEPT HUB File into PSS/ADEPT Utility

Currently the Utility converts PSS/ADEPT generator data to corresponding PSS/E dynamic
data but without excitation and speed-governor controls. The two controls will have to be
added separately to the dynamic data file.

In PSS/ADEPT Utility, stability simulation with PSS/E in the background can be carried out
as shown in figure 11.31 and 11.32.

- 169 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Figure 11.31: Stability simulation setup

Figure 11.32: Stability run

- 170 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Figure 11.33: Specifying disturbance

11.3.1.4 Stability Analysis


Analysis of stability simulations is based examination of the system responses to
disturbances. As an example, rotor angle response as shown in figure 11.34 would indicate
whether or not out of synchronism had occurred.

Figure 11.34: Response of states and controls following system disturbances

- 171 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

11.3.2Insulation Coordination Analysis


Insulation coordination study is particularly important when overhead lines are involved.
The objective of the study is to examine possible overvoltage conditions following
contingencies and to ensure that sufficient insulation and protection are provided.

Insulation coordination study is not yet carried out by TNB. In this guidebook, insulation
coordination study has been proposed to be carried out and therefore TNB is encourage to
explore further.

- 172 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

12. Appendix F: Protection and Control


Requirements

12.1 Introduction
The protective requirement must be based on the need to detect system faults and
malfunctions both within the DG installation as well as the TNB distribution feeder. On
detection of fault or malfunction, the relays must trip appropriate circuit breakers to isolate
the faulty section to minimize equipment damage and safety hazards during the faults
whilst maintaining power supply continuity on healthy parts of the system.

Although the design and types of protection for the DG installation including its generating
units is the responsibility of the DG Developer, TNB must ensure that these protections are
properly coordinated for reliable and safe operation of the distribution feeder to protect TNB
equipment and safety of other TNB customers. The basic philosophies for the types and
design of the protection schemes are that:
a) For any internal fault within the DG installation, the DG must not cause problems to the
utility system and the customers.
b) For any distribution fault, the generator must be protected from any damaging effects.

12.2 Types of Protection Requirements


The following paragraphs describe the various functions of the required protections under
various types of faults and conditions.

Under voltage (UV) and Under Frequency (UF) relays are designed to trip the generator
when the distribution feeder is taken off. When the feeder is supplying load greater than
the capacity of the generator, under frequency and under voltage are expected to occur and
UV and UF relays will operate to trip the generator (see figure 12.1). The setting of the
under frequency trip (Hz) must be based on the recommendation of the manufacturer.

- 173 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Feeder 1
1. BR3 open
Main Intake 2. DG to supply 5MW with 3MW turbine power limit then:
BR1 • Underfrequency trip; or/and
Feeder 2
• Undervoltage trip.

BR2
S DG Plant

2MW 3MW UF
UV

BR3

DG

Feeder 4

BR4
Total load
5MW
Feeder 5

BR5

Figure 11.1: Illustration of UV and UF relays operation

When the feeder load is sufficient to be supplied from the generator under islanded
operation, UV and UF relays may not operate. Therefore, under the current operational
practice, this condition where flow to the feeder at the source will result in sustained
islanded operation of the DG Plant with feeder must be avoided by rescheduling the DG
export to the distribution network.

If the resulting feeder load could be totally supplied by the generator under islanded
operation, this may present a hazard to personnel. Generator damage would be likely when
the feeder breaker is reclosed. In distribution systems, feeder breakers are not equipped
with dead line check to prevent reclosing on live feeder. An alternative to dead line check
relays is an automatic transfer trip that upon opening of the utility feeder breaker, a signal
is provided to trip the generator. Any islanded operation required later must be performed
based on operation and safety procedures agreed by both the generator and the utility.

If the feeder load to be supplied by the generator is less than the generation, over-
frequency will occur and therefore OF relay is required as illustrated in figure 12.2. The
setting of the OF relay must also be based on the recommendation of the generator
manufacturer.

- 174 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Feeder 1
1. BR3 open
Main Intake 2. DG to supply only 1MW with 3MW turbine power:
BR1 • Overfrequency trip.
Feeder 2

BR2
S DG Plant

2MW 3MW
OF

BR3

DG

Feeder 4

BR4
Total load
1MW
Feeder 5

BR5

Figure 12.2: Illustration of OF relay operation

OV relays are installed on the DG side to protect against over-voltage resulting from a
sudden loss of load. However, the generator voltage regulator will take care of the over-
voltage by reducing excitation. Therefore, the over-voltage relay would be useful when the
voltage regulator is defective or limited that it would result in sustained over-voltage.
Transient over-voltages due to switching or lightning should be catered for by the design of
the distribution and DG systems insulation.

To prevent damage on the prime mover due to motoring of the generator during reversal of
power, RP or directional relays are installed. Time delay must be incorporated to prevent
nuisance tripping during synchronization of the generator.

Combined over current and earthfault (OCEF) relays are employed for protection of over-
current and earthfault in both directions. IDMT relays equipped with instantaneous trip are
used in this case. For large generators provided with its own unit protection, the OCEF
relays are used as backup for the generator internal fault. On distribution system fault,
both generator OCEF and feeder OCEF would see these fault currents. Coordination of the
generator OCEF relays with that of feeders would become more difficult due flow of fault
currents from both sources into fault. It is normal practice that on a distribution fault on
the feeder, the feeder OCEF is allowed to trip first followed by the generator. If the fault is
cleared and the generator operates in isolation then frequency and voltage relays would
likely to operate depending on the generation-demand balance. However, if inter-trip is
provided, the generator would also be tripped out.

Loss of synchronism manifested into generator over-speed or under-speed that would be


detected by the generator mechanical speed relays.

- 175 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Field failure (FF) relays is employed to detect malfunction of the generator excitation field.
Upon loss of excitation, the generator rotor accelerates to above synchronous speed where
it continues to generate power as an induction generator. Loss of field is normally detected
by an undercurrent relay connected to a shunt in the field circuit.

Negative phase sequence relays are employed to detect excessive unbalanced loading of
the generator.

To summarise, the requirements of protection are as follows:


i) Undervoltage (UV)
ii) Over-voltage (OV)
iii) Under Frequency (UF)
iv) Reverse Power (RP)
v) Over-current (OC)
vi) Earthfault (EF)
vii) Step-up transformer differential protection - above 5MVA requires unit protection
(TD)
viii) Loss of system synchronization/Field failure relay (FF)

- 176 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

12.3 Distributed Generator Protection Scheme


Figure 12.3 shows the functional details of the required DG protection scheme. All the
relaying code used follows the TNB protective device code.

Figure 12.3: Distributed Generator protection schemes

- 177 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

12.4 Summary of TNB’s Distribution Protection Practices


“The Protection and Control: Code of Practice (2nd Edition)” was launched in May 2003 as a
main guidebook to standardize the policies, schemes and practices on the protection,
control and their supporting equipment for all TNB core business, Generation,
Transmission and Distribution Divisions.

All TNB primary equipment shall be protected against damages from any type of faults. For
all external parties such as IPPs, co-generators and bulk customers, their primary
equipment shall also be protected against damage from any type of faults and shall follow
the setup and schemes specified as in the guidebook.

12.4.1General Requirement
12.4.1.1 Maximum Fault Clearing Time, Operating and Reset Time
The maximum fault clearing time is defined as the maximum time interval between the fault
inception and the fault clearance of the faulty element from the power system.

For substation and transformer faults, the fault clearing time must not exceed 150ms, while
for cable and overhead lines the maximum fault clearing time allowed is 600ms. These
requirements applied for 33kV, 22kV and 11kV systems for the Main protection relaying
scheme,

For the Backup protection relaying scheme, the maximum fault clearing time shall not
exceed the short-circuit rating of the primary equipment.

Maximum Pickup time, maximum operating time and maximum reset time shall be
standardized not to exceed 50ms.

12.4.1.2 Protection Relays


The general requirements for protection relays to be used in TNB system are as follows:
1) Relays shall be suitable for operation on D.C system in the range of 80% to 120% of
the nominal 110V DC or 30 V D.C without the use of voltage dropping devices. The
condition also applies for D.C/D.C converter.
2) All protective relays shall be stable and not be affected by a slow decay, surges, dips,
ripples, spikes and chattering of the D.C supply.
3) The protective relays shall not give a trip output signal when D.C supply is lost and
during restoration.
4) The Relays shall be housed in dust and moisture proof cases according to IEC 60529
and shall be suitable for duty under tropical climate.
5) The relays shall be insensitive to the capacitive effect of control cable.
6) All relays shall be correctly rated to the current transformer secondary rating and
voltage transformer secondary rating.
7) Reset facilities shall be made available, either electrically or mechanically and all
indicators shall be clearly visible without opening of relay front cover or relay panel
door.

- 178 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

8) The relays contacts shall be suitably rated for tripping, control and indication purposes
and sufficient number of contacts shall be provided separately for tripping, control and
alarm functions.
9) The relays, whether mounted in panels or not, shall b provided with clearly inscribed
labels describing their rating and application, including at least the following :
a) Function, e.g., Over-current, Under-voltage
b) Model and version, e.g., REL561 V1.2, 7VK512 V1.0
c) Serial number
d) Nominal input ratings of D.C voltage, A.C current and A.C frequency

12.4.2Protection Scheme Policy


All Main, Backup, Control and auxiliary relays shall be limited to the TNB Accepted Relay
List. All the relaying code shall follow the protective device codes.

12.4.2.1 Overhead Line Feeder Protection


The overhead line shall be protected against faults and equipped with appropriate auto-
reclosing facilities to reduce the outage period. The overhead lines shall be protected as
tabulated in the following Table 12.1.

Table 12.1: Distribution overhead line feeder protection requirements


Voltage Route length Scheme
33kV and > 2 downstream 1. Main unit protection [87CC or 87CD]
below substation 2. Backup Over-current and Earthfault protection [50OC
(outgoing + 50EF + 51OC + 51EF]
feeder)
< 2 downstream 1. Main Over-current and Earthfault protection [50OC +
substation 50EF]
2. Backup Over-current and Earthfault protection [51OC
+ 51EF]

All Main protection relays shall be able to initiate auto-reclose cycle. For distribution
network, auto-reclose shall also be initiated by Backup protections. A scheme for live line
maintenance purposes shall be also incorporated. In addition, for 33kV system and below,
direct optical fiber connections shall be applied.

12.4.2.2 Underground Cable Feeder Protection


The underground cable shall be protected against severe damage caused by faults and
insulation breakdown. The functional scheme for underground cable feeder protection is
tabulated as in Table 12.2.

- 179 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

Table 12.2: Distribution underground cable feeder protection requirements


Voltage Scheme
33kV and below 1. Main unit protection [87CC or 87CD]
(outgoing feeder)
2. Backup Over-current and Earthfault
protection [51OC + 51EF]

Unit protection relays shall have sufficient contacts to initiate the Breaker failure protection
and other protection, control and signaling function and optical fiber shall be used for new
installation.
For Aerial Bundle Cable (ABC) installation, it shall be treated as underground cable feeder.
In addition, direct optical fiber shall be used for tele-protection, while no auto-reclose
scheme shall be applied for underground cable feeder protection.

12.4.2.3 Transformer Protection


Transformer protection is required to prevent any damage to transformer and all associated
equipment for all internal electrical and mechanical faults, and to minimize the loss of life
due to over-excitation. Types of transformer protection and its associated protection can be
categorized as tabulated in Table 12.3.

Table 12.3: Transformer protection requirements


Type Protection scheme Control scheme
Power 1. Main Unit protection [87TBD] Automatic
Transformer 2. Mains Transformer Guard protection Voltage controller
(33- [26OT + 26WT + 63BT + 63 TCBT +
22)/11kV 63PRD]
[26OA + 26WA + 63BA +71OLL]
3. Main Restricted Earthfault protection
[64REF/LV]
4. Backup Over-current and Earthfault
protection
[50OC + 51OC] HV side
[51OC + 51EF] LV side
5. Backup Standby Earthfault protection
[64SBEF2]
Earthing Automatic Voltage
Transformer 1. Main Transformer Guard Protection Controller, where
[63BT] required
[63BA + 63PRD + 71OLL]
2. Backup Standby Earthfault protection
[64SBEF2]
Local Automatic Voltage
Transformer 1. Backup Over-current and Earthfault Controller, where
protection required
[51OC + 51EF]

- 180 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

All other interconnecting equipment such as power cable etc, to the transformer shall be
protected by their relevant protection scheme. All Main protection relays shall be dedicated,
independent from any other relays except for over-excitation protection relay. In addition,
alarm and tripping indications for all types of transformers shall be separated. The LV side
of earthing and local transformers shall be protected by suitable rated fuses.

12.4.2.4 Busbar Protection


Busbars shall be adequately protected and the Busbar zone of protection shall be provided
for each busbar section in any busbar configuration system. Table 12.4 describes the
functional details of the required Busbar protection scheme.

Table 12.4: Busbar protection requirements


Voltage Level Functional scheme Busbar Type

Reverse blocking scheme or 87BBHI Gas Insulated


33kV, 22kV Substation (GIS)
and 11kV.
Reverse blocking scheme or Arc protection Air Insulated
relay Substation (AIS)

Intertripping scheme to the remote end shall be provided for complete clearing of faults,
where it is required. In addition, the D.C supply for the Busbar protection scheme at the
busbar protection panel shall be separated from other protection schemes.

12.5 Coordination between DG and Distribution Protection


For the distribution system with the DG to operate safely and reliably, the protection
devices in both systems must be properly coordinated. With the connection of a generator,
the fault current contribution and distribution would change significantly requiring detailed
analysis and resetting/coordinating the protection devices.

It is only proper that coordination study be carried out to verify the proper operation of the
protective equipment. The following general procedure should be followed:

Initially, the DG should submit proposed setting of all relays given the interface short-circuit
contribution from the utility. The DG should set all the protective relays for the protection
of their installation disregarding any coordination with the utility system. The report to the
utility should include:
a) Protection philosophies adopted;
b) Short-circuit limits including making and breaking capacities of equipment - breakers,
cables, lines etc..
c) Transformer heat withstands capability;
d) Generator limits - reactive, active power, field current and voltage limits, over-speed
and under-speed; etc..
e) Documents on characteristics of the relays and fuses employed;

- 181 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

f) Information on breaker operating time;


g) Proposed settings/coordination curves (if applicable) and the reasons for the chosen
setting; and
h) Other important limits required of the utility.

The utility perform coordination with the generator interconnected and the report should
include:
a) The proposed setting and their coordination; and
b) Changes required on the DG plant relay settings and the reason for the changes.

12.6 SCADA/DA Requirements


12.6.1 Basic SCADA
Supervisory Control and Data Acquisition (SCADA)
SCADA systems consist of one or more computers with appropriate applications software
(Master Stations) connected by a communications system (wire, radio, power line carrier
or fiberoptics) to a number of remote terminal units (RTUs) placed at various locations to
collect data, remote control, and more recently perform intelligent autonomous (local)
control of electrical systems and report results back to the remote master(s). SCADA
systems are used for fault identification, isolation and service restoration, breaker control,
recloser blocking, generator control, feeder switching and reconfiguration, line switching,
voltage control, load management, automated meter reading (AMR), archiving processes,
automatic generation control (AGC), dispatch accuracy feedback, economic dispatch,
energy purchased and sold, system load, system emulation, capacitor bank switching,
monitoring voltage regulators, transformer temperature, as well as metering power
functions. (For additional discussion, see also Chapter 25 in the Standard Handbook,
“Computer Applications in the Electric Power Industry”).

Remote Terminal Units (RTU)


RTUs are special purpose computers which contain analog to digital converters (ADC),
digital to analog converters (DAC), digital inputs (status) and outputs (control). RTUs are
ruggedly constructed; inputs and outputs are fully protected against spurious electrical
transients per the surge withstand capability (SWC) test specified by IEEE Std. 472 and
ANSI Std. C37.90a. RTUs are designed for an extended temperature environment (-40 to
+85°C) expected of the electric utility environment. RTUs are designed to be powered by
120/240 Vac or 24/125 Vdc substation battery. An RTU may have multiple communications
ports so that more than one master station can share the RTU.

12.6.2 SCADA Practices in TNB and Requirements


TNB distribution system will be SCADA ready by 2007. All the control centers will be
equipped with SCADA facilities for supervisory control. Recognizing that the operation of
any DG Plant would become an important feature of distribution operation, all DG Plants
interface/connection are to be equipped with SCADA facilities, that is, SCADA-ready prior to
commissioning of the plant. The SCADA facilities required are as follows:-
ƒ Remote Terminal Units (RTU) c/w Marshalling cubicle;

- 182 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

ƒ Communication system from the DG Plant to TNB designated control centre.


1 nos. of RTU complete with marshalling cubicle is required to be placed at the point of
connection/interface. All necessary interface modules to the RTU used for measurement
purposes such as transducers shall be fixed. The RTU shall be provided by the DG
Developer. TNB will provide the necessary functional and detailed specifications as well as
the approved models/make. The RTU will be commissioned during commissioning of the
DG Plant interface connection. The RTU shall be maintained by the DG Plant Operator.

The RTU shall measure / record the following :-


1) Frequency (Hz)
2) Voltage ( Volts)
3) Current (Amps)
4) Power factor
5) Real Power Energy flow (MW)
6) Reactive Power Energy flow (MVAr)
and any other measurements deemed necessary by TNB. If required, remote control shall
be able to be executed via the RTU on all switches that are in TNB’s jurisdiction/area of
responsibility

The communication system between the generator plant where the RTU is located and TNB
could be via wire or wireless configuration. Wire configuration shall include lease lines or
telephone lines. Wireless configuration shall include via microwave, satellite or GSM. The
mode of communication to be used shall depend on the siting of the generator plant,
capacity of the generator plant and/or distance of the generator plant to the nearest TNB
main substation (PMU or PPU). Lease line is the preferred option by TNB. Nevertheless,
TNB will advice the generator plant of the mode of communication to be used.

12.6.3 Master System


The following data shall be required to be submitted to TNB for the purpose of TNB
Network Application installed in the Master System:

For each interface Transformer:


• Rated voltage (kV) for every winding
• Rated Apparent power (MVA)
• Impedance voltage drop (%)
• Short circuit (Copper) loss (kW)
• No load loss (kW)
• No load current loss (%)
• Earth possibility
• Short circuit resistance (ohm)
• Short circuit reactance (ohm)
• No load resistance (ohm)
• No load reactance (ohm)
• Vector group

For each generating unit:


• Nominal voltage

- 183 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

• Bus type (PV or PQ)


• Rated Voltage (kV)
• Rated apparent power (kW)
• Ratio delta P /delta f for equivalent governor model (kW/Hz)
• Rated power factor
• Sub-transient reactance (%)
• Stator resistance (%)
• Zero sequence reactance

In the case that TNB has to control the generator, the master system installed does not
cater for AGC (automatic generator controller). Therefore, if TNB has to develop this
function and any other associated function in order to meet the requirement, TNB requires
that 10% of the development cost to be charged to the plant generators

12.6.3.1 Master Station.


The SCADA Master Station, which monitors and controls RTUs and their attached electric
apparatus, is no longer a turn-key custom product. The graphics capabilities of the modern
workstations (and to a limited extent PCs) generally results in a man/machine interface
(MMI) that makes it possible for the operator to easily deal with a variety of systems
without sensory overload. The Master Station has a core program which is called the
operating system. Running on the operating system are the applications programs written
by the utility or the SCADA vendor. Dynamic data exchange (DDE) mechanisms in the
operating systems allow the computer to link automated mapping/facilities management
(AM/FM) databases to the SCADA system. The Master Station can not only monitor and
control RTUs but can call up customer records from a networked billing computer, a map
of the affected area from an AM/FM database on the mapping system. Artificial intelligence
programs will be able to filter alarms and perform corrective actions without operator
intervention. The ability to call up multiple databases in conjunction with SCADA alarms
allows for more efficient maintenance crew callouts when trouble occurs. PC Based
Systems. The most common Master Station today is the ubiquitous IBM PC compatible
microcomputer with either Microsoft or IBM DOS, IBM OS-2 or Microsoft Windows disk
operating system. PCs can be networked so the processing and displays can be distributed
either for multiple users or to share tasks. True multi-tasking (running several independent
programs in parallel) on a single PC is only possible with OS-2. There are also several
variants of Unix that are PC compatible but their use in SCADA is minimal. The PC VGA
display screen (the highest standard available for the PC) is considered a medium
resolution device. While there are special drivers and video boards to enable non-standard
higher resolution modes, such components require special software drivers. Mouse or
trackball cursor pointer support is optional as is a LAN system such as Ethernet.

- 184 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

13. Appendix G: Connection agreement

13.1 General
This appendix outlines the possible technical contents of ‘Connection Agreement’ or
‘Connection Operation Manual’ to be established and agreed by both the DG Operator and
TNB.

The connection agreement will contain both commercial and technical sections and
information related to the connection of the DG plant. This appendix contains a list of
possible technical information on the DG plant and the network that the DG is connected to.
Generally, this information should describe the ‘as installed’ plant.

13.2 Connection Agreement


Examples of data required for the connection agreement include:

13.2.1 Description of Facility and Site.

13.2.1.1 This section describes the DG plant and its auxiliaries and may include the following:

13.2.1.2 Electrical system diagram – The electrical system diagram should be a high level diagram
showing the electrical system at the connection point, such as a single line diagram.

13.2.1.3 Machine Data – This should include all the relevant machine capability and data such as:
ƒ Data on the turbine
ƒ Manufacturers and test data of generator impedances and time constants, mechanical.
ƒ Block diagrams of all controls and model parameters
ƒ Excitation capability
ƒ Protection settings and grounding
ƒ Settings of each protective device
ƒ Grounding types and values
ƒ Generator Transformer data including tap changing facilities

13.2.1.4 Fault level contribution – The fault level infeed into the network should include
contribution from generators and any induction motors.

13.2.1.5 Auxiliary system data – Data on large items of equipment should be included such as
large motors, switchgear capability, auxiliary transformers and interconnecting cables.

13.2.1.6 Control settings – control settings such as interlocking systems, synchronizing systems
should be described and where necessary details provided.

- 185 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

13.2.1.7 Operating regime - The DG plant operating regime should be described and may include
description of:
• Short term Parallel to network
• Intermittent operation
• Continuous operation
• Standby generation

13.2.2 Design & Operations Standard

13.2.2.1 List of standards used in the design of the facility and network. It is important that the
current revisions of the standards at the time of design and installation are stated.

13.2.3 Energy Accounting and Metering Equipment.

13.2.3.1 The metering system should be described. Metering locations and a single line diagram
should be included. The description should include:
- Main and Check Meters
- MW and Mvar meters
- Operational and Tariff Metering

13.2.4 Interconnection Facilities.

13.2.4.1 This section should list out the technical conditions and any agreed requirements for the
connection. Items include:

13.2.4.2 Permitted Max Export


ƒ Maximum MW
ƒ Maximum Mvar

13.2.4.3 Excitation Controls – The agreed control regime including agreed settings where
appropriate such as
ƒ Power Factor
ƒ Voltage control
ƒ Var Control

13.2.4.4 Constraints – Agreed constraints and description of the conditions for constraints should
be included here. If the connection has firm and/or non firm offers, the conditions of each
should be described.

13.2.4.5 Max Import – If necessary, the agreed levels of imports, such as Standby and Top Up
supplies should be included. Where necessary, the conditions for the agreed levels may be
included. The levels should include Maximum MW and Maximum Mvar.

- 186 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

13.5.2Communication Facilities

13.5.2.1 This section should describe all the communication facilities and the list of available
indications and control points. It should also include any voice communication equipment.
Items may include:
• SCADA control points
• Remote indications
• Output dispatch controls if any

13.5.3Electricity Characteristics.

13.5.3.1 This section describes the Distribution network characteristics and should include items
such as:

13.5.3.2 System limits


ƒ Operating Voltage
ƒ Operating frequency
ƒ Harmonics

13.5.3.3 Maximum Network Design System fault levels – This is normally the designed capability
of the Distribution network at the point of connection.
ƒ Normal configuration
ƒ Outage configuration

13.5.3.4 Current System Fault Levels – This is the normal fault level at the connection point. It
should be made clear whether this fault level includes the DG plant.
ƒ Normal Configuration
ƒ Outage Configuration

13.5.3.5 System Drawing – a system drawing such as a single line diagram at the connection point
should be included. It should have sufficient details as necessary, including protection
system details relevant to the DG plant.

13.5.3.6 Interface protection system – The network protection system relevant to the connection
point should be described. It should include any interlocking facilities implemented.

13.5.3.7 Operating limits – Any other agreed operating limitations should be described. This may
include description of operation such as short term paralleling operation.

13.5.3.8 Auto-reclosing facilities – Any auto reclosing facility that may affect the DG plant should
be described.

- 187 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research

13.3 Connection Operation Manual.


The operation agreements should include section such as:
• Brief description of how network maintenance and DG plant maintenance is to be communicated.
• Any interim operational arrangements.
• Supply restoration following a network disturbance.
• Communicating daily dispatch.
• Safety procedures.

- 188 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005

You might also like