TNB Tech Guidebook For The Connection of Generation To The Distn Network PDF
TNB Tech Guidebook For The Connection of Generation To The Distn Network PDF
TNB Tech Guidebook For The Connection of Generation To The Distn Network PDF
Prepared by:
in Collaboration with:
-1–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Table of Contents
TABLE OF CONTENTS ........................................................................................ 2
CONTRIBUTORS .............................................................................................. 7
PREFACE
PREFACE....................................................................................................... 8
CHAPTER 1: INTRODUCTION
INTRODUCTION...............................................................................10
1.1 BACKGROUND ....................................................................................................................10
1.2 OBJECTIVES OF THE GUIDEBOOK ............................................................................................11
1.3 DEFINITIONS OF KEY TERMS USED IN THE GUIDEBOOK ..............................................................12
1.4 GUIDEBOOK APPROACH .......................................................................................................13
1.5 STATUTORY ACTS, REGULATIONS, RULES AND CODES ..............................................................14
1.6 SCOPE OF THE GUIDEBOOK ...................................................................................................14
1.7 USING THIS GUIDEBOOK .......................................................................................................15
1.8 CONTENTS OF THE GUIDEBOOK ..............................................................................................15
CHAPTER 2: PROCESS FOR GETTING CONNECTED
CONNECTED.....................................................17
2.1 SUMMARY OF PROCESS .......................................................................................................17
2.2 PROJECT PLANNING ............................................................................................................20
2.3 EXCHANGE OF PLANNING INFORMATION & PRELIMINARY STUDY.................................................21
2.4 PROJECT DESIGN ................................................................................................................22
2.5 PROJECT CONSTRUCTION .....................................................................................................23
2.6 PROJECT TESTING AND COMMISSIONING ................................................................................23
2.7 DG OPERATION ..................................................................................................................23
CHAPTER 3: TECHNICAL ISSUES AND REQUIREMENTS FOR CONNECTION ........................24
3.1 RESPONSIBILITIES OF THE DISTRIBUTORS TO CUSTOMERS AND THE DGS .....................................24
3.2 QUALITY OF SUPPLY REQUIREMENTS .....................................................................................24
3.3 TECHNICAL ISSUES..............................................................................................................28
3.4 VOLTAGE CONTROLS AND REGULATIONS .................................................................................28
3.5 FAULT LEVELS ....................................................................................................................32
3.6 NETWORK/FEEDER CAPACITY AND SECURITY ASSESSMENTS ......................................................34
3.7 SUPPLY QUALITY – RELIABILITY AND POWER QUALITY .............................................................38
3.8 PROTECTION AND CONTROLS ................................................................................................39
3.8.1 General
General.......................................................................................................................39
3.8.2 Short term Occasional Parallel Operation ................................................................40
3.8.3 Loss of Mains
Mains.............................................................................................................40
3.8.4 Auto-reclosing
Auto-reclosing............................................................................................................42
3.8.5 Islanded Operation
Operation.....................................................................................................42
3.9 LOSSES .............................................................................................................................44
3.10 EARTHING AND USE OF INTERFACE TRANSFORMERS ...................................................................46
3.11 STABILITY .........................................................................................................................47
3.12 OVER VOLTAGES AND RESONANT OVER-VOLTAGE ......................................................................47
3.13 DATA REQUIREMENTS..........................................................................................................48
3.14 SAFETY .............................................................................................................................48
-2–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
-3–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
-4–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
-5–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
-6–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Contributors
Many individuals have made contributions to the Guidebook. However, the following
persons have made major contributions and deserve to be recorded here:
No Name Organisation
1 Halim Osman TNB Distribution
2 Dr. Fadzil Mohd Siam TNB Research
3 Dr. Sallehhudin Yusof APS Sdn. Bhd.
4 Hamzah Ngah RWE Npower, plc
5 Abu Hanifah Azit TNB IT
6 Abdul Aziz Majid TNB Distribution
7 Loo Chin Koon TNB Distribution
8 Asnawi TNB Research
-7–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Preface
The Guidebook first discusses typical steps involved in connecting DG plant to the
distribution network (see chapter 2). The process starts with the DG Developer
contacting TNB district or regional offices right up to testing and commissioning as well
as identifying list of requirements for successful operation of the plant.
Before discussing the requirements for connection of the DG plant to the distribution
network, technical issues are discussed so that their understanding will lead to an
appreciation on how each of the issues is resolved (in chapter 3).
Not all technical issues are required to be resolved unless they cause problems to the
distribution network and its customers. The Guidebook in chapter 4 discusses how
planning and design studies are carried out and how each of the technical issues is
identified, assessed and resolved. The chapter also discusses how connection is
established and the operation of the DG with the distribution network.
-8–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Chapter 1 – Introduction
Objectives, basic definitions, scope, summary of
contents
Chapter 6 – Glossary
Definition of terms
Appendix A – G
Supporting chapters, detailed methods/procedures
and case studies
-9–
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Chapter 1: Introduction
1 .1 Background
1.1.3 This “Technical Guidebook for the Connection of Generation to the Distribution
Network” (“the DG Guidebook” or ”the DG Connection Guidebook”) is intended
for use mainly by DG Developers and Distribution Utility engineers for planning,
design and operation of the DGs. Since the Guidebook will also cover all
possible types of synchronous/asynchronous generator connections to the
distribution network, either directly or indirectly, it is also a useful reference to
consulting engineers, factory engineers and plant operators.
1.1.4 There are many tasks to be carried out and issues to be addressed in order to
successfully implement a DG Plant project. This Guidebook focuses only on
connection of DG Plant to the distribution network. Technical matters associated
with energy conversion, mechanical design of DG plant, environmental
protection, etc. is beyond the scope of this Guidebook. However, in order to
make clear some issues, other supplementary subjects not explicitly related to
connection may also be discussed.
1. Refer “Guidelines on Small Renewable Energy Programme (SREP)”, Suruhanjaya Tenaga, Malaysia, not
dated.
- 10 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
1.1.5 The DG Guidebook has been written based on the prevalent electricity industry
structure in Peninsular Malaysia, its regulatory framework and utility industry
practices. The industry structure, regulation and practices may change from time
to time and when necessary relevant parts of this Guidebook will be revised
accordingly.
1.2.3 Utility planning, design and operation engineers could refer to the DG
Guidebook for several purposes but not limited to the following:
- 11 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Distribution Network
Power Flow
Transmission
Network
Power Flow
G
Load
Distributed
Generation
1.3.2 In practice the total capacity of a DG Plant connected to the medium voltage
network could vary from hundreds of kW to 20MW as long as the generated
power does not at any time spill over to the transmission network. However, any
generating plant intended to be connected to the Transmission Grid (Grid
System) must be referred to the Grid System Operator (currently assumed by the
System Planning Department of TNB).
- 12 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
1.3.9 A Renewable Energy Plant (RE Plant)1 is a DG Plant that is categorized under the
Small Renewable Energy Programme (SREP) that is being coordinated by a
Special Committee on Renewable Energy (SCORE).
1.3.10 Medium Voltage or MV is any voltage equal to or exceeding 1kV but not
exceeding nominal 33 kV. Low Voltage or LV is any voltage level less than 1000
volts or 1 kV.
1.3.11 Grid System or the Grid is the system consisting (wholly or mainly) of high
voltage, namely nominal 500kV, 275kV, 132kV, and 66kV transmission lines
owned and operated by Tenaga Nasional Berhad (TNB) and used for the
transmission of electricity from one power station to a substation or to another
power station or between substations or to or from any external interconnection,
and includes any Plant and Apparatus and meters owned or operated by TNB in
connection with the transmission of electricity.
1 .4 Guidebook Approach
1.4.1 The Guidebook is written to address all possible technical issues associated
with the connection of the DGs to the distribution network. All these technical
issues will at least be discussed in one of the five chapters of this Guidebook
and the details of which would be provided in the appendices, if necessary. In
other words, the first five chapters contain pointers to more detail account of the
subjects related to connections of the DGs.
- 13 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
1.4.2 The Guidebook is structured to allow for any amendment to the detailed
technical contents and the case studies be updated separately and
independently through the additions or amendments of the appendices.
1.5.1 This Guidebook may also refer to relevant legal documents that exist in Malaysia
including acts, regulations, codes, rules and guidelines. Since these documents
are subject to revision and amendments by the appropriate authority, readers
should always ensure that they consult the latest versions.
1.5.2 The relevant safety, electricity production, transmission, distribution and supply
licensing, legal and regulatory requirement are mandatory and nothing in the
Guidebook shall be taken to relieve these legal or regulatory obligations in the
provisions of:
1) The Electricity Supply Act 1990;
2) The Occupational Safety and Health Act 1994;
3) The Electricity Regulations 1994;
4) The Environmental Quality Act 1974;
5) Factories and Machinery (Noise Exposure) Regulation 1989;
6) Licence issued by the Suruhanjaya Tenaga to industry players;
7) The Malaysian Grid Codes;
8) TNB's Safety Regulation;
9) The Malaysian Distribution Code (when available).
With respect to the "The Environmental Quality Act 1974", only relevant
provision shall be applied to DG Plant such as effluent discharge (under
Environment Quality (Prescribe Premises - Crude palm Oil) Regulation 1977),
Emission (under Environmental Quality (Clean Air) Regulation 1978) addressing
issues such as open burning.
1.5.3 There are also guidelines published by authorities including the Ministries and
the Energy Commission that are complementary to this Guidebook and therefore
DG Developers and Utility Engineers are encouraged to refer to those
documents.
1.6.1 This Guidebook addresses technical issues associated with the connection of a
DG to the distribution network. Therefore, commercial issues are not addressed
except those necessary without which the subject cannot be fully dealt with.
1.6.2 There are many other issues that will not be addressed by this Guidebook
because they are only the concern of either the Developer or the Distributor and
- 14 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
not with the connection. Issues such as: identifying and obtaining fuel supplies,
project financing, power sales and purchase negotiations, DG plant design,
getting approval of local authorities, land matters etc. are some of the subjects
not covered by this Guidebook.
1.7.1 If you have reached this point of the book you should by now have basic
understanding of the background to the Guidebook and its objectives. Chapter 2
outlines the general procedures for getting connected and therefore is referred
to as the root of the Guidebook from which all other chapters and appendices
are referred to.
1.7.2 After understanding the basic procedures for getting connected, a reader may
then refer directly to the relevant chapters and appendices for details. To scan
through all technical issues related to connection of a DG plant one can refer to
chapter 3. Each of the technical issue is discussed in a brief and concise manner
in a section in chapter 3 and the details of which would be found in an appendix
or appendices of the Guidebook.
1.7.3 Technical issues related to the connection of DG plants are usually addressed at
the planning stage. Two main activities carried out during planning are system
and design studies and these activities are discussed in chapter 4. A reader who
is interested to find out how TNB performs preliminary planning study or design
studies should first refer to the relevant sections in chapter 4 and the associated
appendices.
1.8.1 This Guidebook comprises of 6 chapters and 12 appendices. The chapters are:
- 15 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
1.8.2 The appendices are intended to provide useful information and data as well as
details of technical issues mentioned in the chapters including case studies and
examples. The appendices are:
- 16 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
2 .1 Summary of Process
2.1.3 After identifying opportunity for generation, the DG Developer should contact the
nearest local or regional TNB offices to enquire on the possibilities for
connection to the distribution network. To obtain detailed requirements and cost
estimates for connection, the Developer should write to the Distributor by
providing basic information (see Appendix C) of the proposed DG plant to
enable the Distributor to perform a preliminary system study (see Appendix E) to
identify technical requirements for network extensions and its associated
estimated costs.
- 17 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
2.1.4 Given cost estimates for connection to the distribution network, the DG
Developer could then negotiate and enter into a commercial agreement with the
Distributor before carrying out detailed design. The Developer would need to
provide detailed information of the DG plant and interface facilities to the
Distributor (see Appendix C) for the power system study of the connection (see
Appendix E). This will then form the basis for the connection agreement (see
Appendix G). At the same time the Developer would in parallel be carrying out
detailed design of the DG plant.
1 - Project Planning
Developer making commercial & technical
assessments and initial contacts with Distributor on
connection possibilities.
3 – Project Design
Developer submit formal application for connection Connection agreement
with detailed information on the plant for utility to – technical &
carry out Power System Studies, detailed commercial
connection requirements & then Developer carrying
detailed design of plant and its connection.
4 – Project Construction
Developer construct plant and Distributor constructs
its connection/reinforcement portions
Connection Operation
4 – Project Testing & Commissioning Manual
Developer & Distributor perform tests and
commissioning of the plant and connection
5 – Operation
Developer & Distributor coordinate operation of the
plant with the distribution network
- 18 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Pt,Qt Pt,Qt
Transmi ssion
Transmi ssion
Grid
Di stribution Grid
Di stribution
Network
Network
Pg,Qg
Pg,Qg
DG Load
DG Load
Pl,Ql
Heat
(b) Sell excess generation of
(a) Sell all generation Cogen plant
Pt,Qt Pt,Qt
DG Load DG Load
Pl,Ql Pl,Ql
(c) Top up supply from
Distribution network (d) Standby supply
Figure 2.2(a) – 2.2(d): Various power exchange modes for connection
2.1.5 Once commercial agreements including connection agreement are executed, the
DG Developer and the Distributor would enter project construction phase. Prior
to operation of the connection, both the DG Developer and Distributor would
arrange for testing and commissioning to be carried out. The ‘Connection
Operation Manual’ must be established by the DG Developer in consultation with
the Distributor as the reference document during the operation of the DG plant.
2.1.6 In the following sections, we will describe in more detail the activities involved in
each step/phase of the process in figure 2.1. The steps for getting connected as
described in this Guidebook are generally applied for all DG Plants. In the case
of RE Plant, the steps are slightly different because of the commercial
arrangements and the DG Developer should refer to TNB for the correct
procedure. However, technical requirements for connections for RE Plant are the
same as described in this Guidebook.
- 19 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
2 .2 Project Planning
2.2.1 ‘Project Planning’ is a phase initiated by the DG Developer who recognizes the
potential business opportunities of connecting the proposed plant to the
distribution network. At this stage, the DG Developer would have identified
potential site for the DG plant, energy resources and their long term supplies,
types of generating plants (see Appendix B), and cost estimates of the plant. It
is also important at this point in time for the DG Developer to understand some
basic parameters of the local distribution network including possible connection
points, voltage levels and organization of the local utility (see Appendix A).
2.2.2 A DG Developer who intends to sell power to the local utility as an IPP would
first carry out initial assessment of the availability of energy resources for the DG
plant and makes preliminary commercial assessment of the DG. At this stage of
the feasibility study, the Developer may not know exactly how the DG plant
would be connected to the distribution network and this is when the first contact
with the utility on the possibility of connection should be initiated. This first
contact may discuss both technical and commercial issues.
2.2.3 A cogeneration plant is usually established to provide both heat and power to an
industrial plant or large commercial complex. Such plant or complex may not
necessarily be connected to the local distribution network. But since a
cogeneration plant consumes fuel efficiently, excess electricity could be sold to
the local utility at an attractive tariff. Contact with the district or regional offices
of TNB should be the first step to find out on the possibility of connection.
2.2.4 A factory or manufacturing plant having its own captive load may find that the
on-site generation capacity is insufficient to cater for demand requirements due
to production growth. The plant owner may find that it is not economical to
increase on-site generation capacity instead a more sensible option is to buy
top-up power from the local Distributor. In this case an initial enquiry with the
local Distributor would enable assessment be made on adequacy of the
distribution network for providing the top-up supply.
2.2.5 An installation with on-site generation may find that the available generation
capacity is not sufficient to cater for emergency situations such as loss of
generating units. In most cases where there is local distribution network it is
more economical to connect the plant to the distribution network that acts as
standby rather than adding new generation capacities. Since the Distributor
needs to ensure that the network has the required capacity to reserve for the
plant emergency requirements, it is important that an enquiry be made with the
local distribution offices on possible limitations for standby purposes.
- 20 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
2.3.1 A DG Developer should enter into the next phase of the connection process after
confirming with the utility that connection would be technically feasible and that
the next important information required is the cost estimates for the connection.
Such cost estimate could only be obtained from the Distributor after a
preliminary system study is carried out.
2.3.2 To request TNB for the cost estimate of connection, the DG Developer should
officially submit a request letter giving some basic information for the Distributor
to carry out preliminary system study (see Appendix C). After receiving the
request letter and basic information on the proposed DG, the Distributor would
be in a position to carry out a preliminary system study in accordance with
procedures as described in Appendix E.
2.3.3 At this preliminary stage, it is sufficient for DG Developer to provide the following
basic data to the Distributor with the request letter:
1) Number of generating units proposed and capacities in kVA;
2) Fuel resource; and
3) Physical location of the plant.
A location map indicating the plant site and nearest existing distribution medium
voltage network facilities should also be submitted with the request letter.
2.3.4 On receipt of the request letter, the Distributor should carry out a preliminary
system study so that major equipment to be added to the network could be
identified and their costs estimated. Typically the Distributor would carry out a
preliminary system study by assuming certain parameters for the plant and
applying procedures as described in Appendix E. The analysis carried out
include:
1) Voltage performance;
2) Network adequacy;
3) Short-circuit calculations; and
4) Losses.
2.3.5 The results of the preliminary system study would enable the following questions
be answered:
a) The feasibility of connection;
b) Point of connection;
c) Major equipment required for connection; and
d) Estimated cost of connection.
The preliminary system study would also identify technical issues that may need
to be addressed further if the DG plant connection is to proceed to next stage. In
- 21 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
particular the Distributor would inform the DG Developer of issues that may need
to be addressed during the plant design stage.
2 .4 Project Design
2.4.1 With the cost estimate for connection provided by the Distributor, the DG
Developer would be able make further assessment on the commercial viability of
the DG plant and its connection to the distribution network. If the DG Developer
decides to proceed with the DG plant development, the Project Design phase
should begin. In parallel to the project design, it is usual for the DG Developer to
also start negotiations on commercial terms and agreements with the
Distributor.
2.4.2 The DG Developer at the project design phase would normally employ services
of consultants to carry out detailed design and establish specifications for
procurements and installation. As soon as details of plant design and equipment
are available, the DG Developer should submit a formal application for
connection to the Distributor making reference to the earlier preliminary system
study and highlighting major changes to plant basic parameters. Formal
application form for connection and details of the data to be submitted to the
Distributor are given in Appendix C.
2.4.3 On receipt of formal application for connection, the Distributor should examine
the information submitted by the DG Developer and should ensure sufficient
data are provided to perform detailed power system study. At this stage, both
the DG Developer and the Distributor may organize several meetings and
discussions to exchange and confirm information.
2.4.4 The main objective of the power system study to be carried out by the
Distributor at this stage is to ensure that the connection of the DG Plant will not
deteriorate the quality of supply and power that is being provided to the existing
customers in the vicinity of the DG plant. If the connection affects the quality of
supply, the Distributor is required in accordance with the prevailing codes and
regulations to apply mitigation measures and the cost of which would have to be
borne by the DG Developer. It is therefore vital that the Distributor performs the
power system study by taking into consideration all factors with valid
assumptions and that the full study report should be made available to all
stakeholders including the DG Developer.
2.4.5 Study report of the power system study should contain sufficient information on
connection requirements to be used by the DG Developer to establish
specifications for procurement and implementation of the connection. It is
important that the study report provide a list of connection interface
requirements with sufficient details of parameters to be applied.
- 22 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
2.4.6 Based on the recommendations of the study report, the DG Developer should
proceed with the specifications and procurements of the DG plant and the
associated interface requirements.
2 .5 Project Construction
2.5.1 Project construction phase would normally comprise of the following activities:
a) Detailed design;
b) Preparation of specifications;
c) Bidding;
d) Procurement; and
e) Construction.
The construction of the DG plant can be divided into two parts: plant installation;
and interface and connection to the distribution network. Construction of the
plant is completely the responsibility of the DG Developer.
2.5.2 With respect to the construction of the interface and connection to the
distribution network, two options can normally used:
1) Constructed by the DG Developer under the supervision of the Distributor; or
2) Constructed by the Distributor.
This part of the network would be operated and maintained by the Distributor.
2.6.1 Prior to the commissioning of the DG Plant and its parallel operation with the
distribution network, the DG Developer would coordinate with the Distributor to
identify and list of tests and performance criteria, test procedure and approval.
2 .7 DG Operation
2.7.1 When a DG Plant begins commercial operation and in parallel with the
distribution network, the provisions of electricity rules and associated codes and
guidelines govern the operational obligations of both the DG Operator and the
Distributor. The details of the operation procedure will be spelled out in the
‘Connection Operation Manual’ (see Appendix G).
2.7.2 Among others, the ‘Connection Operation Manual’ includes the following items:
a) Data to be exchanged between DG Operator and Distributor;
b) Operational planning and scheduling procedure;
c) Dispatching and control procedure;
d) Fault and defect reporting;
e) Loss of mains and restoration procedure; and
f) Joint operation committee.
- 23 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.1.1 TNB and Other Distributors regulated businesses are obliged under their
licences issued by the Energy Commission (EC) to maintain a standard of supply
and services to their customers. These requirements are usually specified in the
conditions of the licence issued by the regulator to the utility. Based on the
provisions of the licence conditions and to ensure that the requirements are
complied with, TNB has established ‘Quality of Supply Standards’ as given in
Appendix D.
3.1.2 TNB is responsible for ensuring that the requirements or provisions of the Quality
of Supply Standards are complied with at all times. TNB would require imposing
some minimum requirements for any User connections such as a DG to ensure
that the Quality of Supply Standards is maintained.
3.2.1 The quality of supply that a Distributor like TNB must comply with comprises of
several aspects whose requirements are summarized in the following
paragraphs.
- 24 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.2.4 For a distribution network, a normal operating condition is when all major
elements including lines, cables and transformers are operating. However, the
network is said to be in contingency operating condition when any one or more
of the major elements are not operating due to forced or scheduled outages.
3.2.6 The maximum three-phase short-circuit current allowed in TNB network are
given in table 3.3. When the short-circuit level at any point in the network
exceeds 90% of the limits in table 3.3, actions must taken to circumvent the
situation.
3.2.7 The system frequency is maintained by TNB at 50Hz ±1%. Under emergency
situation and when the frequency drops below 49.5Hz, TNB may shed some
loads through the under-frequency load-shedding scheme.
- 25 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.2.8 With respect to supply reliability, TNB is required to plan and design the medium
voltage network that will minimize the System Average Interruption Duration
Index (SAIDI). For actual network planning and design TNB applies Supply
Security Criteria or Contingency Criteria as given in table 3.4.
Table 3.4: Security of supply criteria for medium and low voltage networks
No Type of network Supply security requirements
1 Urban/Sub-Urban • In the event of a feeder outage, the load of
Medium Voltage the feeder can be transferred to adjacent
Distribution feeders by manual or supervisory network
Feeders reconfiguration.
• In the event of a failure of a main intake sub-
station (PPU or PMU) transformer in the
supply zone:
all of the loads can be transferred to the
other transformer in the main-intake sub-
station; or
All of the loads can be transferred to
other main intake sub-station
transformers within the supply zone or
other nearby adjacent supply zones.
2 Rural Medium Voltage For rural areas of total loads less than 1 MVA,
Distribution Feeders (<1 the contingency criteria for these feeders are
MVA) not applicable. However, where reasonably
(economically) applicable, interconnections
between feeders shall be provided.
3 Low Voltage Distribution Low voltage distribution service cables to users
Networks are planned and operated as radial circuits.
- 26 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.2.9 TNB also specifies power quality compatibility requirements and guidelines to be
complied with as given in table 3.5.
- 27 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3 .3 Technical Issues
3.3.2 Distribution systems, being generally passive in nature, are not normally
designed to accommodate generators. The connection of a DG unit to the
distribution system would seem to provide benefits because it serves the loads
from local source and thereby reducing transmission, substation and feeder
loading. However, there are several technical issues that must be recognized
and addressed before a DG could be connected to the distribution network.
3.3.3 The technical issues are discussed in details in the following sections. Where
necessary more detail treatment of the subjects will be referred to the relevant
appendices.
3.4.1 Other than the obligations to control voltage within limits, voltage control
provided by the DG do bring some advantages such as:
improving voltage profile across the distribution network;
improving system losses;
improving system load flows;
avoiding potential system collapse; and
in certain circumstances, voltage control can aid starting of large motors.
3.4.2 The power factor at the main intake substations (PMU/PPU) is typically
maintained at 0.9. The Distributor is under an obligation to maintain PMU/PPU’s
power factor to not less than 0.9.
- 28 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
regulators are employed but now being replaced by switched and fixed
capacitors. Figure 3.1 illustrates different types of voltage control devices
employed in the distribution network.
3.4.4 More expensive means of voltage control is possible with modern FACTS
(Flexible AC Transmission Systems) devices. One example of such a device is
Static VAr Compensators (SVC). These devices are often used within
transmission systems but costs of these devices are high.
Transmission
Network
132kV
OLTC Fixed
Shunt
33kV Cap
33kV
MV OLTC Switched
Network Shunt
11kV Cap
0.415kV
LV
Network
NLTC 11kV
Booster
Pole-top
Shunt
Cap
3.4.6 Although the AVR is usually available, it has been the DG and the Distribution
System Operator operational practice to keep the generating unit on ‘power
factor control’. Power factor control means that the reactive power output of the
generating unit is maintained in proportion to the MW output such that the
power factor would remain constant regardless of the terminal voltage (see
Figure 3.2). When on power factor control, the generating unit does not regulate
voltage, unless it is above the AVR set limits for voltage. The reasons for running
a generating unit on power factor control are:
- 29 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
0.95 pf
Example of voltage
control line
S
Terminal
Voltage
MVAR
Example of MVAR
control line
3.4.7 To ensure proper voltage and VAr control within the distribution system, DGs will
be required to have the capability of both voltage control and power factor
control. Figure 3.2 also shows examples of typical reactive power controls for a
DG. The reactive capability of typical generator is normally between 0.85 lagging
to 0.95 leading at full load.
3.4.8 The choice of control modes will be subject to the ‘Preliminary System Study’ to
be carried out by TNB. It is useful to note that the advantages and
disadvantages of the various controls as in table 3.6.
3.4.9 The discussions on Voltage Control above have been focussed on the
Generation Unit because a majority of Generating Units are directly connected to
- 30 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
the Distribution System. There are a number of Generating Units that are
embedded within their site network, such as a Co-Generation plant. In these
cases, the power factor or voltage control requirements will refer to the
Connection Point to the Distributor’s network.
- 31 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3 .5 Fault Levels
3.5.2 When a generator is connected to the distribution network, the prospective short
circuit or fault level of the network will increase because of the potential fault
current contribution. This rise of prospective fault level will be limited by the
system capability to withstand a potential fault current. This limit is the
equipment capability such as switchgear and cables. If the fault level at a node
in the network increases to more than 90% of the equipment short circuit rating
than measures must be taken to mitigate the situation. The safety margin of 10%
takes into account the tolerance allowed for the network data accuracy
especially the existence of induction motors in the system. Under no
circumstances should the prospective short circuit current be allowed to exceed
the equipment rating
3.5.3 The common utility practice is to determine short circuit currents in the network
on two types of faults, namely:
1) 3-phase fault; and
2) 1-phase to ground (or earth) fault.
Figure 3.3 shows the common terms used in defining a typical generator fault
current contribution.
Time (ms)
Fault
Clearance
- 32 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.5.4 Generator fault current contributions are calculated using parameters supplied
for the generator. The calculated fault currents on both types of faults must then
be checked against the following fault duties of ratings of circuit breakers:
1) Breaking Capacity (MVA/kA) - The capacity that a circuit-breaker is capable
of breaking at a stated recovery voltage and re-striking voltage. Recovery
voltage is the normal frequency voltage that appears across the breaker
poles after final arc extinction and re-striking voltage is the voltage that
appears across the contacts at the instant of arc extinction. This is normally
measured as an RMS value at the time when the circuit breaker contacts are
required to open as indicated in Figure 3.3.
2) Making Capacity (MVA) (normally 2.5 times the Breaking Capacity, defined as
the asymmetrical peak at 10ms) - The capability of the circuit-breaker when
closing on a standing fault.
3) Short-Time Rating (kA, rated time) - The capability of the circuit-breaker or
cables to carry the specified maximum fault current for a given period of time
normally 3 seconds.
3.5.5 The limit on equipment fault level capability is normally the main reason for
difficulties in connecting a generator. Equipment may need to be replaced to
enable generators to be connected. Replacing equipment in order to raise fault
level capabilities can be extensive over the network and the cost of replacing
equipment can be very high. However, there are a number of alternative
mitigations to reduce the generator contribution to the system possible namely:
1) Increase generator impedance – The generator impedance is normally limited
by the generator design. Changing generator impedance could mean a non-
standard design which is normally more expensive than a standard
generator.
2) Use of in-line reactors – Reactors introduce impedance between the
generator and the network, thus assist in reducing the generator fault current
contribution. However, the disadvantages of using reactors are that losses
are increased and may also cause undesirable voltage reduction at the
connection point. The overall VAr capability of the generator is also
decreased because of the VAr consumed by the reactor. Generator stability
may be affected by too high impedance.
3) Use of in-line transformers – Using a transformer reduces the disadvantages
compared to the use of a reactor, however, the cost of a transformer is much
higher that the cost of a reactor. Transformers are also used for power quality
reasons.
4) Network Splitting – Network splitting involves keeping certain parts of the
circuits normally open to reduce fault levels. Although very effective, but it
may mean less system security and increased operational effort. Installing
automatic switching systems, such as active management system, could
make this option viable.
5) Fault limiters – Is limiters are available in the market. Although effective, it
does have safety concerns mainly because it is an explosive device and
concern about repeatability of operation. Research is still being carried out
using super-conductor technologies which would address these concerns.
- 33 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.6.1 Security assessment will be carried out for any demand or DG connections to
the distribution network in accordance with security requirement in table 3.4.
This is based on (N-1) contingency.
3.6.2 There is a distinct difference on how network capacity and security is assessed
when connecting demand or generator. Where a firm connection for demand
cannot be guaranteed, then the network would be reinforced accordingly.
However, for generation connections, the developer may have a choice of a firm
or non-firm connection depending on the reinforcement costs needed to
accommodate the generator capacity (see Figure 3.4).
12MVA 10MVA
3.6.3 For both demand and generator connections, normal and contingency
conditions will be considered. Demand Connections are assessed using (N-1)
contingency criteria. This is a deterministic contingency criterion. As shown in
- 34 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Figure 3.4, if the future total demand is greater than 10MVA, the network will
need to be reinforced to ensure that firm demand is guaranteed on the outage of
one circuit. Network reinforcements for demand needs to take into account both
current and future demand growth.
3.6.6 Another option is not to carry out any reinforcements, in which case, 12MVA can
be exported during normal network conditions, i.e. no circuit outages. However,
during one circuit planned outage, the generator would need to be constrained
to 10MVA. This means that 10MVA will be firm whilst the remaining 2MVA will be
a non-firm output.
3.6.7 The planning criteria could also allow for short term overload rating over the
equipment continuous rating. Using this short term rating of 120% for example
and allowing for a (N-1) contingency, a generator rated up to 12MVA could be
allowed to be connected. For an unplanned outage of one circuit, this particular
generator would need to reduce its output from 12MVA to 10MVA over the
period allowed for short time overload rating of the circuit. This could be from
milliseconds to minutes depending on the plant item being overloaded.
3.6.8 If reinforcements are not carried out, the Developer will take the risk of the
generator output being constrained during both planned and unplanned
outages. TNB would co-operate with the developer in understanding these risks.
To reduce these risks, the developer could schedule his plant outages to
coincide with TNB’s planned network outages.
3.6.9 There are two main options available for constraining generation given a non-
firm connection. Generally, if there is an allowable period before the generator is
needed to be constrained, then a dispatch instruction is used. This type of
constraint instruction is used for planned outages or short time rating constraint
as described above. However, if an immediate constraint is required, an
automatic intertripping and/or fast generator de-loading system would be
required. This is normally used for unplanned network outages. It should be
noted that the complexity of intertripping systems depends on the complexity of
the network to be protected.
- 35 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.6.11 For example, where practicable, circuit capability for firm generation output
should be assessed in conjunction with demand. In the example above in Figure
3.5. A generator of up to 12MVA capacity could be considered for a firm
connection whereas if demand is not taken into consideration, a generator of
only 10MVA would be considered as firm. When considering reinforcements for
future demand increase, local generator outputs should also be considered if
appropriate. The methodology of assessing generator contribution is being used
in the UK in the P2/6 Planning standards. This standard is still undergoing public
consultation.
10MVA 10MVA
2MVA
DG
12MVA
3.6.12 Active network on-line monitoring and automatic control will reduce the risk of
generators being constrained. Reinforcements could be deferred through
knowledge of minute-to-minute demand loadings and generator outputs.
3.6.13 A generator will tend to unload the feeder between it and the main intake
substation, and will have no effect between the generator and the end of the
feeder. This will depend on the generator output in relation to the existing
demand power flow. Generator output higher than the existing demand current
flow and the use of shunt reactor may overload segments of the feeder between
the generator and the main intake substation as illustrated in Figures 3.6a) and
(b). Feeder loading situation must also be assessed to cover future years.
- 36 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.6.14 Also in the future, network assessment could adopt a more probabilistic
methodology which should result in reduction in reinforcements.
Feeder 1
Main Intake
Feeder 2
Feeder 3
DG
Feeder 3
Feeder 3
Feeder 1
Main Intake
Feeder 2
S DG Plant
2.2MW
Feeder 3
DG
Reactor
Feeder 3
Feeder 3
3.6.15 Distribution system would normally have interconnecting feeders with open
points. Under contingency or maintenance when one section is on outage
switching operation would be carried out to restore supply. Adequacy of circuit
- 37 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.7.2 A DG can improve the reliability of supply to the distribution network customers
by providing network support. For example, if the DG is allowed islanding
operation rather than being isolated on loss of mains.
3.7.3 If the DG is to be isolated on loss of mains, the DG does not have impact on
reliability and figures for SAIDI and SAIFI remain the same as without the DG. It
could however make it worst since new components are added to the network
including lines, switches and transformers that may fail and disconnect the
feeder. If the DG is allowed to operate on islanded mode to supply total or some
of the feeder loads, then reliability would improve since sustained failure of
components between the feeder source and the DG would enable the DG to
supply some loads that otherwise have to wait until repair is done.
3.7.4 The issues on power quality such as voltage sags, over voltages are discussed
elsewhere in this Chapter. Voltage sags are discussed in Section 3.4 – Voltage
Controls and Regulation and Section 3.5 – Fault Levels. Over voltages are
discussed in Section 3.12.
3.7.5 Harmonics can generally be a problem when using semiconductor devices such
as converters within the network. Very high harmonic levels are associated with
the use of converters in smelting works. Careful monitoring of harmonic level
necessary where a number of these devices are used in the network. Generators
and transformers can dissipate harmonics currents; however, it will cause over-
heating. Information on Total Harmonic Distortions (THD) is available from the
Distributor on request.
3.7.6 Flicker is not currently a problem with the levels of generation connected to
distribution system. However, with increasing generation connections and
different generation technology, interactions between generation and incorrect
control settings could cause flicker. Power System Stabilizers (PSS) installed in
Generator excitation systems can be used to control flicker. It should be noted
that studies will be required to obtain the correct settings for the PSS.
- 38 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.8.1.1 Protection systems are essential for both the network and the generator to
ensure safe operation. Network and generator protection systems do interact
and will need to be designed to co-ordinate with each other. TNB is responsible
for design and operation of the network systems, whilst the Developer is
responsible for design and operation of the Generator systems. At a stage in the
generation project, an interchange of information between the developer and the
Distribution Operator is essential to enable each system is designed to be
coordinated.
3.8.1.2 The design of the network protection systems is based on TNB’s Protection
and Control Code of Practice. All equipment used in TNB’s is approved by TNB.
The use of approvals and Code of Practice is needed to ensure design and plant
consistency across the network.
- 39 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.8.2.2 The islanded system is only synchronized to the Distribution Network before
the generator supporting the island is taken out of service. Provided that the
generator is taken off-line as soon as the system is synchronized, certain
protection requirements such as loss-of-mains may be exempted. The following
systems may be required to be implemented:
Automatic change over between generator circuit breaker and Network
connection circuit breaker such as make before break systems.
Controlled short-term paralleling for test and commissioning
Complete protection system may not be required
Use of timers to limit time for parallel operation
Site protection systems will need to be configured when connected to the
Distribution Network due to the change in fault levels for example.
3.8.3.2 Distributors are obliged to maintain a safe system and may be liable for
damages if generator without proper control is allowed to supply the regulated
network and breach the regulatory frequency and voltage limits. Protection
systems and earthing systems are also not designed for inadvertent generator
island systems. For these reasons, it is essential that generator that could
potentially support islanded systems is tripped when the condition arise using
loss-of-mains protection systems.
3.8.3.3 The use of auto-reclosers also makes it necessary for the loss-of-mains
protection to trip the relevant generators before the auto-reclose recloses. Loss-
of-mains protection is usually installed at the point of connection to the
Distribution Network. This arrangement would allow a generator to be islanded
within its own private network if required. A number of loss-of-mains systems
are possible depending on required operation time, network configuration,
demand and generator output.
- 40 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.8.3.4 ROCOF/Vector Shift -The system works on the principle of fast frequency
change and waveform shift characterised at the instant when systems are
islanded. However, these systems are prone to nuisance tripping because the
relay can detect overall Grid system disturbance. Generally it will trip more that
necessary, depending on the settings. It is the more cost effective system
compared to other systems. A number of issues have historically been identified
with these systems namely:
Settings - finding suitable settings may be difficult. It may be necessary to
estimate initial settings and monitor its behaviour. Simulating credible system
disturbances can assist be used to estimate settings.
Demand to Generation balance – There may be cases where demand almost
equals generation output and the rate of change of frequency or vector shift
is not sufficient to cause operation.
Testing - On site operational testing will be a problem. System monitoring is
an option.
DG
2MW
2MW
A B C D
2MW 2MW
- 41 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.8.4 Auto-reclosing
3.8.4.1 Auto-reclosing are used on overhead lines within Distribution Networks. The
system is used to reclose lines that are tripped by self-clearing faults, such as
tree branches touching the lines.
3.8.4.2 Auto reclosing lines that have generators connected within the system could
result in out of phase closing. The impact of connecting out-of-phase systems
could be destructive and could lead to:
Extensive Generator Damage;
Network Circuit Breaker Damage; and
Network Voltage Sag due to the high currents caused when connecting out-
of-phase systems. Depending on the phase angle at connection, twice fault
currents can potentially be generated if the voltage at synchronization is
totally opposite in phase and amplitude.
3.8.4.3 Reliable and fast loss-of-mains tripping will be required where reclosers are
used in systems that can be potentially islanded for a short period. Normally, the
use of intertripping for loss-of-mains would provide the reliability and speed of
operation. The use of over-current relays for loss-of-mains may also be suitable,
provided the speed of over-current operation is faster than the auto-reclosing
time.
3.8.5.1 Islanding within the Distribution system has not been implemented generally.
However, there are isolated areas which are supplied by systems which are
islanded or capable of being islanded. Generally these would be remote systems
where interconnection to the main distribution system is prohibitively expensive.
Generator capabilities and its performance within these islanded systems are
crucial and need to be controlled. Two main control systems required are
voltage and frequency control.
- 42 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 43 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.8.5.4 Islanding system could make a difference in costs of supply failure during
forced or planned outages. Where appropriate, case studies should be carried
out using real systems to discover benefits, and also costs of realizing the
benefits.
3 .9 Losses
- 44 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
500
Peak
450 Intermediate
350
300
150
100
50
0
0 1000 2000 2500 3000 4000
700 1400
DG Output (kW)
Figure 3.8: An example of loss variation on different load level and unit
outputs
3.9.3 When designing a generator connection, the effect on losses needs to be taken
into consideration. In most cases, there will be an opportunity to reduce system
losses and maximize the benefits brought about by the generator and can only
be analysed through examination of various network operating conditions.
3.9.4 Losses are calculated by carrying out load flow studies on the system.
Procedures for carrying out the studies are described elsewhere in this
Guidebook. Where practical, the methodology for carrying out the studies and
assumptions should be made transparent to the DG Developer.
3.9.5 The procedure for calculating losses needs to take into consideration the
following:
1) Demand Profiles – Demand varies throughout the day and also throughout
the year. A number of permutations are possible and accuracy of the results
will depend on the number scenarios used throughout the year. In general,
the wider the range of demand over the day or year, the more scenarios will
be required.
- 45 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.9.6 Methodologies for calculating losses will depend on how the cost of losses is to
be applied. Losses can be capitalized over the project life or ‘loss adjustment
factors’ could be applied to generator outputs. Whichever methodology used
would need regular reviews to take into account changes within the system.
- 46 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.11 Stability
3.11.1 Generator transient instability is not normally an issue with generators connected
to a distribution system. However, generators connected to very long lines
subject to long protection clearance times could experience transient instability.
Multiple generator installations could be particularly prone to instability. Stability
studies would be carried out to determine the need for additional system and
generator protection such as pole slipping protection.
3.11.2 Pole slipping protection system is used to protect the generator from instability
and the damage it could cause. However, this is a non-standard protection and
will be an additional cost to the DG Developer.
3.11.3 Studies would also need to identify the pole slipping protection settings
required. The settings would need to take into account instability within the
generator and also within the distribution network caused by other generators in
the system.
3.11.4 At the onset of a project, it is unlikely that precise data required for stability
studies will be available. It is essential that sensitivity assessments are carried
out on estimated generator data in order to identify potential stability problems.
Detailed studies may be required once actual data are available, usually when
machines are being ordered.
- 47 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
3.12.2 Resonant over-voltages are caused by resonant conditions brought about by the
presence of capacitance and inductance in the system. These conditions can be
difficult to detect or calculate because the event may only be triggered by
certain network configuration for example during an outage condition. Once
detected, the system can be ‘detuned’.
3.13.1 As identified in the various sections of this chapter, availability and accuracy of
data is a major concern when carrying out studies to determine costs of
connections. The reliability of generator data increases throughout the project.
At the onset of the project, only estimated data would be available. It should also
be noted that manufacturer’s schedules have a tolerance of at least +/-10% on
the impedance data as allowed by the IEC standards. Developers would need to
ensure that data submitted to TNB are reliable and checked by the Developer’s
consultant.
3.13.2 Where data tolerances are given, worst case scenarios should be examined in
the studies. It is also important to understand the sensitivities of the tolerances
to the study results. This will identify the level of data accuracy required. The
following are some of the issues related to data requirements.
1) Initial Load Flow Studies: Generally, as identified in the Appendices C and
E, data for load flow studies will be very basic. Based on the generator
estimated ratings, various impedances can be estimated.
2) Fault Level Studies: TNB’s procedure includes a 10% margin when
calculating fault level within the network. This is to allow both network data
tolerances and generator data tolerances. When using manufacturer’s data,
calculation should be based on the worst case, for example using lower end
of the tolerance range of generator impedances.
3) Stability studies: Contrary to the Fault Level Studies, the worst case
scenario may need to use the higher end of the tolerance.
4) Protection Studies: In order for the Distribution Network co-ordination
studies to be carried out, the Distributor will require protection settings from
the DG Developer. The DG Developer will need to ensure that the protection
co-ordination studies within the Developer’s site have been completed before
submitting data. The timing of the data submission will be detailed in the
PPA.
3.14 Safety
3.14.1 Safety must be a priority when designing Distribution Systems and Generation
systems. Some of the issues that concern safety are discussed in the various
sections of this Chapter. Two issues in particular need particular attention.
- 48 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
The UK’s ESQRC (The Electricity Safety, Quality and Continuity Regulations
2002) and EA Engineering Recommendations give further guidance of step,
transfer and voltage gradients for industrial, distribution network and power
stations.
- 49 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4 .1 Introduction
4.1.2 When all facilities for connection to the distribution network have been
constructed, inspections and tests have to be carried out prior to the
commissioning of the connection. Before protection and control equipment are
tested, protection setting and coordination studies have to be performed using
the data of the installed protective equipment. The results of the coordination
studies would be referred to by relay test engineers for setting the protection
devices. Another important activity prior to commercial operation is the
establishment ‘Connection Operation Manual (COM)’ that must be developed
and agreed upon by the DG Developer and the Distributor.
4.1.3 The objective of this chapter is to outline the activities involved in the planning,
connection and operation of the DG Plant. Planning of the connection is
performed almost entirely by the Distributor and therefore, it is vital that the DG
Developer understands the tasks and types of analysis carried out during the
main phases of planning studies namely; preliminary and power system. With
respect to connection, the focus is to describe the requirements for protection
study and commissioning tests. The chapter will also cover several aspects of
DG plant operation particularly on modes of operation and requirements for
exchange of operational data and liaisons.
- 50 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.2.2.1 At this preliminary stage, connection facilities that will become the operational
responsibility of the Distributor must be indicated. These facilities could vary
depending on the configuration of the connection as shown in Figures 4.1(a),
4.1(b), 4.1(c) and 4.1(d). The configurations must be designed based on the
principle of ‘clear system boundaries and responsibilities’.
DG Plant DG Plant
Utility Utility
Feeder Feeder
House
load
G G
Feeder
DG Plant
Utility
Utility
Feeder Feeder
G G
DG Plant
- 51 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
DG Plant
Utility
Feeder
Utility
DG Plant &
Network
Feeder
Interfacing
Facilities
M M M
M M M
- 52 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.2.2.2 Figures 4.1(a) and 4.1(b) illustrate connection configurations when the points of
interface are located in same premises as the DG Plant. Figure 4.1(c) illustrates
the dual-breaker scheme with the interface point remotely located near the utility
existing network and this is a typical case of connecting a mini-hydro DG Plant
with a long connecting line to the distribution network. In the case of connection
configuration in Figure 4.1(c), the DG Operator is also responsible to manage
and operate the interconnection line up to the interface point.
4.2.2.3 From distribution network design and operation point of view, the basic
requirements for major DG Plant and interface/connection facilities must include
the following facilities:
1) Interface-transformer;
2) Interface-transformer star-grounded through NER;
3) Synchronisation facilities as part of the plant; and
4) Circuit breaker(s).
The above facilities could be arranged in several ways as shown in Figure 4.2.
4.2.2.4 The Preliminary System Study report must also indicate the connection and
interface facilities that should be provided by the DG Developer including their
basic requirements. This information must then be provided by the Distributor to
the DG Developer.
NER
One LV Breaker
NER
One HV Breaker
NER
LV and HV Breakers
Synchronising
- 53 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
NER
M
DG Plant &
Network
M
Synchronising
- 54 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.2.4.1 The ‘Preliminary System Study’ starts by developing load flow and short-circuit
model for typical generating units of the DG Plant based on the following basic
information provided by the DG Developer:
1) Number of generating units proposed and their capacities;
2) Quantum of power to be sent to the distribution network;
3) Fuel resource; and
4) Physical location of the plant including location map.
Based on the fuel resource, the distribution planning engineer could use any of
the following typical models available in the simulation software employed by
TNB – Shaw PTI’s PSS/ADEPT:
a) Steam turbine (small) – biomass units, cogeneration steam units
b) Hydro without damper – mini hydro units
c) Combustion turbine – gas turbine units
4.2.4.2 The load flow model of the distribution network to which the DG Plant will be
connected to must also be updated with the latest available information
including:
1) Feeder and PMU/PPU loadings – peak, intermediate and light or minimum;
2) Fault levels at PMU/PPU transmission voltage level.
The distribution planning engineer should then identify options for connection
that will be evaluated.
4.2.3.4 The cost of each option that satisfy all planning criteria are to be estimated by
taking into consideration the following:
1) Investment costs:
Cost of new asset from DG Plant to the existing network; and
- 55 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.2.3.5 Losses (increase or decrease) due to the connection of the DG Plant must be
calculated and included in the ‘Preliminary Study Report’. Information on system
losses will be used by the Commercial Department of TNB Distribution for tariff
calculations. However, the principle to be used with respect to system losses is
that ‘the connection of the DG Plant should not result in system losses to be
more than when the system is without the DG Plant’.
4.2.5.1 Amongst others, the preliminary study report should indicate the following
basic requirements for connection:
1) Automatic Disconnection
On loss of mains
2) Synchronization Point and Procedure
On DG terminal
Re-synchronizing only proceed once the system is restored to it’s normal
state and sanction given by TNB.
3) Protection at Network Interface
The proposed protection scheme and setting from the DG plant to TNB
substations shall be reviewed and approved by TNB.
The purpose of the protection scheme is to ensure proper coordination
and integrity of the overall protection system at the interface points.
4) Monitoring of DG Network Operations
TNB needs to monitor the status, voltage and flows at interface
Monitoring using RTU to be provided DG developer.
5) Metering Point and Systems
The metering scheme to be reviewed by TNB.
Under Metering Code
4.2.6.2 TNB is only obliged to provide summary of the results and connection
requirements of the Preliminary System Study Report and connection cost
estimates. The DG Developer may then use the results of the Preliminary Study
Report to decide whether or not to proceed with the DG project.
- 56 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.3.2.1 It is important that when the DG Developer submits the application for
connection, data for the following major equipment of the DG unit(s) are
provided based on estimates or typical values to be provided as far as possible
by the intended manufacturers. The major manufacturer’s data are for:
a) Generator electrical
b) Generator transformer and grounding
c) Generator mechanical
d) Generator excitation control
e) Generator turbine-control
f) Generator other supplementary controls
- 57 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.3.3.1 Since the data provided by the DG Developer can be assumed to be more
representative of the DG Plant to be established, it is therefore important for the
‘Power System Study’ to revisit the analysis carried out during the ‘Preliminary
System Study’, The analysis include:
1) Network voltage profile;
2) System/network Adequacy;
3) System Losses; and
4) Short-Circuit Studies.
However, at this stage more detailed analysis is required to identify possible
control measures including equipment that would be installed in the DG Plant
and interface specifications.
4.3.3.2 When evaluating voltage profile and controls the following inputs on the DG
units must be included:
1) Reactive capability curve;
2) Voltage control capability;
3) Power factor control capability;
Voltage profile under at least three load conditions of peak, intermediate and
light must be studied for the purpose of identifying the most suitable control
method – either voltage or power factor. The evaluation must also take into
consideration response of major voltage control equipment in the network such
as the main intake transformer in-service tap-changers.
4.3.3.3 Aspects of system/network adequacy should have been evaluated during the
‘Preliminary System Study’ to identify interface and reinforcement requirements
and no particular control is associated with this aspect. However, any
compensation equipment proposed by the DG Developer (based on the results
of the ‘Preliminary System Study’) could impact on the capacity of the network
and the interface and therefore this aspect should also be evaluated and
reported.
4.3.3.4 Impact on system losses with the connection of the DG is an important aspect
that must be thoroughly examined and cost estimated. This aspect must be
evaluated during the ‘Preliminary System Study’. However, there is a need to re-
evaluate the losses since compensation and parameters of equipment (including
transformer losses) would normally be different from what have been assumed
during the ‘Preliminary System Study’.
4.3.3.5 One most important purpose of the ‘Power System Study’ is to identify
measures or controls to limit impacts of increased fault level with the connection
of the generating unit. At this stage, it is vital that generator impedance and time
constant parameters provided by the DG Developer would represent the values
of the DG units to be installed. Any increase in fault of more than 90% of existing
equipment rating must be re-evaluated with fault level containment measures –
methods are discussed in chapter 3. It is also important to note that apart from
fault levels, the analysis must include evaluation of making and breaking
- 58 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.3.4.1 Apart from the steady-state analysis described previously and where
appropriate, the Power System Study are to include two major additional
analysis, namely:
1) Stability; and
2) Insulation coordination.
4.3.4.2 It must be emphasized that the main purpose of the stability analysis is to
examine and analyse electromechanical transient responses of the DG unit
under various system faults and contingency situations so that necessary
measures could be specified to avoid potential damaging effects on the DG
units. For purposes of dynamic analysis, all generating units in the distribution
network must be modelled in detail. The transmission main intake source(s)
could be modelled as an infinite bus, that is, a classical generator with inertia
constant (H) of zero.
4.3.4.3 The DG Developer when submitting the application for connection must pay
particular attention to the data required for dynamic modelling of the generating
units. It is essential that the DG Developer obtains the services of experienced
consultant who would be able to provide accurate information for the dynamic
modelling of the DG Plant. Responsibility of estimating dynamic models of the
DG Plant should not be relegated to the Distributor who is carrying out the
Power System Study.
4.3.4.4 In carrying out stability analysis of the DG Plant connected to the distribution
network, the following factors that can affect generator stability must be noted
and taken into consideration when necessary:
a) Generator loading – the more the generator is loaded, the more advanced is
the rotor angle;
b) Generator output during the fault which depends on the fault location, type,
and severity;
c) Fault clearing time - in distribution system, long clearing time of protective
device following fault could result in loss of synchronism;
d) Post fault system reactance - loss of lines/ cables would change reactance;
e) Generator reactance - a lower reactance increases peak power and reduces
initial rotor angle;
f) Generator inertia - the higher the inertia, the slower the rate of change of
rotor angle and reduces the kinetic energy gained during fault;
g) Generator internal voltage magnitude - this depends on the field excitation;
and
h) Transmission source voltage magnitudes.
- 59 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
NER Fault
- 60 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Feeder 1
Main Intake
Feeder 2
S DG Plant
2. Breaker
Opened
Feeder 3
DG
1. Fault
Reactor
Feeder 3
Feeder 3
Figure 4.4: Fault at main intake transformer secondary and loss of feeder to
DG Plant
4.3.4.7 In addition to transient stability analysis, the Power System Study, where
appropriate, may also include an ‘insulation coordination’ analysis to examine
the following two aspects of the DG connection:
1) Lightning over-voltages and arrester requirements at the interface point for
overhead line feeder;
2) Switching over-voltages under fault and load rejection conditions as well as
possible self-excitation (may also be examined using transient stability
analysis)
The transient over-voltages must be compared with the standard BIL and LIL of
the distribution equipment normally employed by TNB.
4.3.4.8 Control measures that could be applied to mitigate stability problems include:
1) Power system stabiliser (PSS);
2) Generator tripping scheme;
3) Generator intertripping scheme;
4) Dynamic brake; and
5) Pole slip protection.
- 61 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.3.5.1 Power System Study report must be submitted to the DG Developer upon
completion and the study must be completed within 4 months from the receipt
of application for connection with the complete data.
4.3.5.2 During the duration of the study, continuous interactions and communications
between DG Developer and Distributor are encouraged to clarify data and
assumptions used for the studies.
4.4.1.1 The connection point is a site in the distribution network at which the DG Plant
network connects the Distributor’s MV distribution network. Identification of the
connection point is not meant to imply ownership of apparatus adjacent to the
connection point. For practical purposes, a connection point is designated as
the MV circuit breaker that is under the operational responsibility of the
Distributor located at the interface. These connection points are also indicated in
Figures 4.1(a) through 4.1(c).
4.4.2.1 In order for a distribution network having a DG Plant to operate safely and
reliably, the protection devices in both the DG Plant and the distribution
networks must be properly coordinated. Coordinated operation of the protection
devices ensures that no damage to equipment could result due to flow of fault
currents and that only selected components of the network would be isolated to
remove the fault.
4.4.2.2 With the connection of a generator to the distribution network, the fault current
contribution would normally increase and if the generator is connected near to
the main intake substation, the fault level could exceed the short-time rating of
nearby equipment in the network. With the changes in the value of the fault
current and to ensure proper operation of protective devices, resetting and
- 62 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.4.2.5 Upon receipt of the ‘DG Plant Protection Coordination and Setting Report’, the
Distributor must examine the report particularly the protection philosophies and
data on protection relays. In Phase 2, the Distributor must carry out a ‘Protection
Coordination Study’ with the assumption that the DG Plant is connected to the
distribution network. The ‘Protection Coordination Study’ Report should address
the following aspects:
The proposed relay settings and their coordination; and
Changes required, if any, on the DG plant relay settings and the reason for
the changes.
- 63 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.4.3.2 Secondary injection tests are usually carried out to ensure that protective
relays, meters and other control equipment are installed and wired properly and
in good condition for service. For each protective relay, its approved operating
settings (see 4.4.2 on protection coordination study) will be set following
completion of the tests. It is the responsibility of DG Developer to carry out the
tests for protective and control equipment within the DG Plant.
4.4.3.3 Tests and setting of protective relays at the interface/connection points and its
associated equipment (current and voltage transformers) should normally be
carried out by the DG Developer using services of licensed test engineers
approved by the Distributor. The tests and settings programme must be
coordinated with the Distributor to ensure that all safety switching requirements
are met and that the Distributor representatives are available for witnessing the
tests.
4.4.3.4 Prior to carrying out protective equipment tests and settings at the
interface/connection points, the DG Developer should submit the following to
TNB:
1) Test programme;
2) List of equipment to be tested;
3) Test methods/procedures;
4) Access requirements to TNB’s sites or part of the network.
Tests of protective equipment at the interface should only be carried out with the
approval of TNB of the test programme.
4.4.3.5 In addition to testing of protective equipment, check and tests must be carried
out on DC equipment and control circuits. Test of the DC equipment is of main
interest of the utility since in many cases, this facility is shared with the DG Plant.
4.4.3.6 On completion of protection and control tests, the DG Developer must submit
the test reports to the Distributor for approval prior to commissioning and
energising of the connection.
- 64 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.4.4.1 Prior to commissioning of the connection and thus parallel operation of the DG
Plant to the distribution network, inspections and pre-commissioning tests
should be carried out. It is the responsibility of the DG Developer to perform
inspection and pre-commissioning tests for the DG Plant and its network.
However, for the interface/connection equipment, it is the responsibility of the
Distributor. The inspection and pre-commissioning tests should be initiated by
the DG Developer and coordinated with the Distributor. At this point in the
connection process, all protective devices are set and test reports are submitted
and approved by the Distributor.
- 65 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.4.5.2 As an example, steps for connecting the DG Plant in Figure 4.5 to the
distribution network could comprise of the following steps:
1) Ensure that breaker BR3 is opened and line BR4 – BR3 ready to be energized
and all safety earthing removed;
2) Close switch BR4;
3) Live test incoming voltage at BR3;
4) Rack-in breaker BR3;
5) Close SW4 of shunt reactor;
6) Close breaker BR3;
7) Record voltage at DG Plant busbar;
8) Energise auxiliary transformer through SF2;
9) Open generator turbine control valve and run generator to full speed;
10) Excitation controller on manual until terminal voltage magnitude is reached;
11) Set AVR on automatic control;
12) Set governor on speed control;
13) Close breaker BR1 and this energises the generator transformer;
14) Ensure the synchronisation parameters are within limits and synchronise
through closing of breaker BR2.
- 66 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
SW4
AVR
BR1
G
BR2
BR3
SF2
Governor
SF1
4.4.6.2 In the case of the synchronization point being located on the generator
breaker, it is usual to energise generator-transformer from the utility side.
Otherwise as in Figure 4.5, the generator transformer is energized from the
generator and this is to be done after the generator has reached full speed and
attained full terminal voltage.
4.4.6.3 When energizing the synchronous generator, the generator will initially be in
open position. The turbine is first operated manually to full speed. Excitation
should only be applied when the speed is more than 90% of rated speed. Both
turbine and excitation controls are manually adjusted until full speed and the
terminal voltage is reached.
- 67 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.4.6.6 Before load rejection tests are carried out, recording equipment that will not
only measure electrical quantities (AC and DC) but also mechanical quantities
such as speed and valve positions should be installed. Real and reactive power
load rejection tests are carried out to record and verify dynamic response of the
unit. Opportunity must be taken to perform load rejection tests whose results
could be used to verify and derive generator parameters including excitation and
governor controllers. The tests comprise of staged test at several active and
reactive power output with excitation controllers in manual and automatic
modes. The procedure for load rejection tests would be discussed with
Distributor and normally the Distributor would absorb the generator output
power during the tests.
4.4.6.7 Loss of mains tests should be carried out to ensure that the generating plant is
isolated from the distribution network when any of the utility-side circuit breaker
is opened. An agreed test procedure should be developed between the DG
Developer and the Distributor. The DG Plant Operator should note that loss of
mains protection may not operate at times and should take reasonable
precautions. It may be appropriate that ROCOF type relays be monitored and
studied for its performance.
4.4.6.8 Final site checks should then be carried out before leaving the plant operating
in parallel with the distribution network. These checks are visual inspection of all
major equipment in the plant including, light indicators, transformer noise level,
corona noise, oil leaks, temperature etc.
- 68 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.4.7.2 Typical contents of the COM include but not limited to the followings:
1) Objectives of the COM – could be slightly different from the perspective of
each party;
2) Description of the connection/interface facilities and responsibility of each
party:
Circuit breakers, isolators
Synchronizing equipment
Interlocking system
Grounding/earthing facilities
Protection and controls
Metering
3) Liaison and Communication – communication methods and procedures, and
contact persons;
4) Switching and isolation procedure – a step-by-step switching procedure for
all major equipment at the interface/connection point as well as the DG Plant;
5) Procedure for Reporting/Notifications of Events/Outages/Faults;
6) General outline of DG Plant maintenance requirements;
7) Emergency Operation Procedures
- 69 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.5.1.1 Normally the day to day operation of the DG Plant is the responsibility of
the DG Operator. However, the Distributor may need to exercise control under
the following circumstances:
When the DG plant is operating on varying output mode;
For safety reasons;
For reasons associated with supply reliability; and
For reasons associated with power quality.
4.5.1.2 Control needs for reasons as listed above or any additional reasonable
basis must be included in the ‘Connection Operation Manual’.
4.5.2.1 In terms of power output into the distribution network, a DG Plant could be
operating in any of the following modes:
1) Constant MW output for the whole day
2) MW output following load demand – load following
3) MW output depending fuel supply variations
4) Zero MW output
The first two operating modes are illustrated in Figure 4.5.
MW Distribution
MW profile
Load
following
Constant
MW
Time 24-hours
4.5.2.2 For a DG Plant with constant MW output, it is a practice to ensure that the DG
output will remain 15% below the minimum load of the distribution network as
illustrated in Figure 4.6.
- 70 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Transmission
Distribution Network
Network
Load Profile
MW
Lpk
15%
DG Lmin
DG Output to remain
15% below minimum load or
less Hours
Figure 4.6: Constant MW output to remain 15% below minimum daily load
4.5.2.3 ‘Load following’ operating mode allows the DG plant output to be varied over
the 24-hour period so that its output would remain 15% below the total system
demand as illustrated in Figure 4.7.
Transmission
Distribution Network
Network
Load Profile
MW
Lpk
DG Lmin
DG Output to remain
15% below load or
less Hours
Figure 4.7: Load following mode with MW output to remain 15% below load
profile
- 71 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.5.2.4 The MW output of a DG Plant could vary depending on availability of fuel and
this is typical of biomass DG Plant. In this case of operating mode, the maximum
MW output of the DG plant must remain 15% below load profile.
4.5.2.5 For all operating modes, the Distributor must be notified of the scheduled
output of generator on weekly and daily basis and this procedure is carried out
under the operation planning process discussed below.
4.5.3.2 Two major inputs to the ‘Annual Operation Plan’ are scheduled weekly profile
of DG Plant outputs in MW and MVAR and scheduled maintenance outages of
the DG Plant. Using these two inputs together with other network information,
the Distributor would establish plans for network operation. One important
results of the Operation Plan that of interest to the DG Operator is the scheduled
output of DG Plant particularly those that have to be limited due to network and
demand constraints.
4.5.3.3 The ‘Annual Operation Plan’ should also contain liaison and communication
information between Distributor and the DG Operator.
4.5.4.2 To coordinate the operation of the distribution system, the Distributor and all
other connected entities including the DG Operator must maintain
communication and exchange information on operations and events. There are
four major occasions where operational information are to be provided by the
DG Operator to the Distributor:
Information for Annual Operation Plan and monthly review;
Notification of operations;
Notification of events; and
Reporting of faults and/or outages.
- 72 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.5.4.3 DG Operators must notify the Distributor of any operation that will have or may
have an effect on the distribution network including but not limited to the
following :
a) implementation of scheduled outages of plants and / or equipment which has
been reported and arranged previously;
b) switching operation that will result in temporary disconnection at the point of
interface to the Distributor’s distribution system;
c) switching operation for paralleling of system;
d) generating unit synchronizing; and
e) changes in voltage controls.
4.5.4.4 The notification to the Distributor must contain sufficient detail describing the
operations, and locations of equipment and must be provided before the
implementation of the operations. Likewise, in case of any operation in the
distribution system, which to the opinion of the Distributor, will have or may have
effects on the DG Plant, the Distributor should inform the DG Operator of such
operations.
4.5.4.5 DG Operators must also notify the Distributor of any event in their system
which has had or may have had an effect on the distribution network including
but not limited to the following:
a) the activation of any alarm or indication of any abnormal operating
conditions;
b) breakdown of or faults on, forced or partial outages of plant and/or apparatus
including protection and controls;
c) increased risk of inadvertent protection operation;
d) operation of plant and / or apparatus either manually or automatically; and
e) occurrence of voltage levels outside the required limits;
4.5.4.6 The notification to the Distributor must be given in sufficient detail to describe
the event and locations of equipment immediately by phone after the event has
occurred to allow for the Distributor to make the necessary assessment on the
implications of the event and if necessary to make adjustment to the distribution
system. This is normally followed by a detailed written report submitted to the
Distributor. Similarly, in case of any event that has occurred in the distribution
system that has had or may have had effects on DG Plant, the Distributor should
inform the DG Operator.
4.5.4.7 When forced outages or any significant event has occurred in the DG Plant
which have or may have resulted in interruption of supplies to Customers in the
Distributor’s distribution system, the DG Operator must verbally inform the
Distributor of the event providing the details of sequence of events known at that
time leading to the supply interruption. Both DG Operator and Distributor shall
coordinate actions to restore supplies to Customers according to the required
security levels.
- 73 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4.5.5.1 It is important that for the safety of operating staff and public, both the
Distributor and the DG Operator must coordinate, establish and maintain the
necessary isolation and earthing when work and/or tests are to be carried out at
the interface/connection point. The safety coordination applies to when work
and/or tests that are to be carried out involving the interface between the
distribution network and the DG Plant and it is the responsibility of the
Distributor and DG Operator to comply with the requirements of statutory acts,
regulations, sub – regulations, individual license conditions, Standardized
Distributor’s Safety Rules and the Malaysian Grid Code.
4.5.5.2 For purposes of safety coordination procedure, the following requirements are
prerequisites:
a) at each point of interface/connection between the distribution network and
the DG Plant, the boundary of ownership is clearly defined;
b) the Distributor and the DG Operator provide each other with the operating
diagrams of their respective side of the point of interface/connection;
c) the Distributor and the DG Operator must exchange information on safety
rules and / or instruction as practiced in their respective system.
The above information must be included in the Connection Operation Manual.
4.5.5.3 All switching operations shall be carried our according to the procedures as
defined in the Standardized Distributor’s Safety Rules (TNB Safety Rules), which
shall include but not limited to the following:
a) Coordination;
b) Isolation;
c) Earthing;
d) Recording;
e) Testing;
f) Commissioning;
g) Cancellation; and
h) Reenergizing.
- 74 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
5 .1 Introduction
5.1.1 An interface between a DG plant and the distribution network comprises of the
following set of equipment:
protection and control of the connection;
metering facilities for measurements of power and energy; and
SCADA facilities for remote monitoring and controls.
A connection interface in relation to the distribution network and operation
centre as well as the DG Plant is illustrated in Figure 5.1.
Pt, Qt
Distribution
System
Transmission
System
DG Plant
Distribution
Connection Operation/
Interface Control
Centre
CB CB
Sync
M
Communication/Data exchange
5.1.2 Many technical issues identified in chapter 3 and its analysis as described in
chapter 4 can be resolved and addressed by having a proper interface design.
However, there are technical issues that cannot be addressed at the interface
but may have to be incorporated in the DG plant at the design stage.
- 75 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
5.1.3 The main objective of this chapter is to summarise the requirements of typical
interface design and equipment. In addition to this, the chapter will also discuss
the types of reinforcements in the distribution network that may become
necessary with the connection of the DG Plant. This chapter will also indicate
how connection costs are calculated including the aspects on losses. The topics
covered in the chapter are:
1) Basic Connection Interface Requirements
2) Utility Access
3) Synchronisation
4) Protection and Control
5) Interlocking
6) Metering
7) SCADA and Automation
8) Communications
9) Network Reinforcements
10) Cost estimation
5.2.1.1 The designated connection point of a DG Plant to TNB network must include a
means of isolation the two systems (DG Plant/Network and TNB Distribution
Network). The following are requirements for the isolation point:
a) It must be suitably labelled;
b) It must be capable of safety isolating the whole of the DG output from the
TNB’s Network.;
c) It must have facilities to permit work to be undertaken on the TNB network
without danger to staff;
d) Isolation must be lockable in the isolated position in accordance to TNB’s
standard safety locking procedures;
The above requirements are illustrated in Figures 5.2(a) and 5.2(b).
Interlocked
Isolation point:
•Isolate from TNB network
DG Plant
•Suitably labeled
•Safely isolating DG output
•When opened cannot
synchronise (interlocked with
synchronising switch)
•To permit work
•Grounding requirement
Feeder •Lockable
G
- 76 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Isolation point:
DG Plant •Isolate from TNB network
•Suitably labeled
•Safely isolating DG output
•When opened cannot
synchronise (interlocked with
synchronising switch)
•To permit work
Feeder •Grounding requirement
•Lockable
G
Interlocked
Figure 5.2(b): Basic interface/connection point requirements – two breaker
scheme
5.2.2.1 Although the design and configuration of a new DG Plant is the responsibility
of the DG Developer, there are basic requirements to be met for ensuring safe
and secure operation of the integrated systems. These basic requirements
applicable to the DG Plants are:
1) The Generator star shall be earthed or grounded.
2) The choice of generator neutral grounding is up to the DG Developer.
However, the followings should be noted:
normally DG units are designed to withstand maximum 3-phase fault
current but not necessary unrestricted phase-to-ground fault current; and
use resistor to limit earth-fault current to 300A irrespective of size is a
common practice with step touch voltage within the criteria limits.
3) Two-or three winding transformer with star winding on the Distributor’s side.
4) The star side of the transformer which connects to the Distributor’s network
shall be grounded through an NER designed to limit earth fault current of
150A to flow from the generator side on a single-line to ground fault on the
star side of the generator transformer (see Figure 5.3).
5) An earth fault relay must be installed to detect earth faults on the Distributor’s
network fed from the Generator and to disconnect the DG network from
TNB’s network.
5.2.2.2 Where a DG Plant that has its own network and comprising of more than one
generating units, an interface transformer as illustrated in Figure 5.4 shall be
required. For this case the star-side of the interface shall be grounded as
described above. It is recognised that existing installation may not currently be
connected through interface transformers. For these existing installations,
including generating plant upgrades, may not require interface transformers.
- 77 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
DG Plant Distribution
Network
EF Relay
NER
1-phase to
ground fault
150A
Pt, Qt
DG Plant/Network
Transmission
System
G
M
Interface through
Delta-star transformer
Distribution network
5 .3 Utility Access
5.3.1 To enable TNB's operational staff a 24-hour access to the switchgear and
equipment that TNB has operational responsibility for, consideration should be
given to the location of the interface or connection point to permit such access.
Access off an all weather road surface is preferred where this is practicable,
otherwise delays will be experienced.
- 78 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
5 .4 Synchronisation
5.4.1 DG unit control system must include synchronization facilities to enable the
generator to be connected to the distribution network, Control facilities and
methods to be employed for synchronization will need to be approved by TNB.
An automatic synchronizing panel from a recognized manufacturer, designed for
the type of machine proposed, will normally be acceptable.
DG Plant DG Plant
Utility Utility
Feeder Feeder
House
G load G
Interlock
Synchronisation
point
- 79 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Feeder
DG Plant
Utility
Utility
Feeder Feeder
G G
DG Plant
Interlock
Synchronisation
point
Three-breaker scheme Three-breaker scheme
With bus-coupler With bus-coupler
5.5.1.1 The protective scheme must be based on the need to detect system faults and
malfunctions both within the DG installation as well as the distribution feeder. On
detection of fault or malfunction, the relays must trip appropriate circuit breakers
to isolate the faulty section:
to minimise equipment damage and safety hazards during the faults; and
to maintain power supply continuity on healthy parts of the system.
Although the design and types of protection for the DG installation is the
responsibility of the DG Developer, the Distributor must ensure that these
protections are properly coordinated for reliable and safe operation of the
distribution feeder (see section 4.4). See also Appendix F for details on
protection practices in TNB
- 80 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
5.5.1.2 The basic requirements for the types and design of the protection schemes are
that:
1) For any internal fault within the DG installation, the DG must not cause
problems to the utility system and the utility customers; and
2) For any distribution network fault outside the DG Plant, the generator must
be protected from any damaging effects.
5.5.1.3 For generating units directly connected to the distribution network, the
following protections are required:
a) Under Voltage (UV);
b) Over Voltage (OV);
c) Under Frequency (UF);
d) Reverse Active Power (RP);
e) Overcurrent (OC);
f) Earth fault (EF);
g) Step up transformer protection; (above 5 MVA transformer size
recommended to include transformer unit protection);
h) Loss of system synchronisation / Field failure relay (FF);
The following paragraphs describe the reasons for the requirements of the above
protection. For generating units, embedded within its own network, items a, b
and c are required at the connection point. For these generating units, items e, f
and g will be required for the connecting cables and the interface transformers.
These minimum requirements are detailed in Appendix F, Section F.3.
5.5.1.4 UV and UF relays are designed to trip the generator when the distribution
feeder is taken off (loss-of-mains). When the feeder is supplying load greater
than the capacity of the generator, under-frequency and under-voltage are
expected to occur to trip the generator. The setting of the under-frequency trip
(Hz) must be based on the recommendation of the manufacturer. If the feeder
load to be supplied by the generator is less than the generation, over-frequency
will occur and therefore OF relay is required. The setting of the OF relay must
also be based on the recommendation of the generator manufacturer. However,
when the feeder load is sufficient to be supplied from the generator under
islanded operation, UV, UF or OF relays may not operate and special relays such
as ROCOF and Vector Shift will be required (see section 3.8).
5.5.1.5 If the resulting feeder load could be totally supplied by the generator under
islanded operation, this may present a hazard to personnel. Generator damage
would be likely when the feeder breaker is reclosed. In distribution systems,
feeder breakers are not equipped with dead line check to prevent reclosing on
live feeder. An alternative to dead line check relays is an automatic transfer trip
that upon opening of the utility feeder breaker, a signal is provided to trip the
generator. Any islanded operation required later must be performed based on
operation and safety procedures agreed by both the generator and the utility.
5.5.1.6 OV relays are installed on the DG side to protect against over voltages
resulting from a sudden loss of load. However, the generator voltage regulator
will take care of the over voltage by reducing excitation. Therefore, the over-
voltage relay would be useful if when the voltage regulator is defective or limited
that it would result in sustained over-voltage. Transient over-voltages due to
- 81 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
5.5.1.7 To prevent damage on the prime mover (turbine system) due to motoring of the
generator during reversal of power, RP or directional relays are installed. Time
delay must be incorporated to prevent nuisance tripping during synchronization
of the generator.
5.5.1.8 Combined over-current and earth-fault (OCEF) relays are employed for
protection of over-current and earth-fault in both directions. IDMT relays
equipped with instantaneous trip are used in this case. For large generators
provided with its own unit protection, the OCEF relays are used as backup for
the generator internal fault. During distribution system fault, both generator
OCEF and feeder OCEF would see these fault currents. Coordination of the
generator OCEF relays with that of feeders would become more difficult due
flow of fault currents from both sources into fault. It is normal practice that on a
distribution fault on the feeder, the feeder OCEF is allowed to trip first followed
by the generator. If the fault is cleared and the generator operates in isolation
then frequency and voltage relays would likely to operate depending on the
generation-demand balance. However, if inter-trip is provided, the generator
would also be tripped out.
5.5.1.10 Field failure (FF) relays are employed to detect malfunction of the generator
excitation field. Upon loss of excitation, the generator rotor accelerates to
above synchronous speed where it continues to generate power as an
induction generator. Loss of field is normally detected by an undercurrent
relay connected to a shunt in the field circuit.
5.5.1.11 Negative phase sequence relays are employed to detect excessive unbalanced
loading of the generator.
5.5.2 Controls
5.5.2.1 To provide for safe and flexible operation of the DG Plant and its
interconnection, the followings controls are required:
1) Breaker controls;
2) Turbine-governor controls;
3) Excitation controls;
4) Synchronising controls; and
5) Emergency trip controls.
5.5.2.2 Basic breaker controls functions are ‘trip’ and ‘close’ both at local and remote
locations. Typical features for breaker controls must include:
- 82 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
5.5.2.4 DG unit must be capable of both voltage and power factor controls. Both of
these controls are discussed in chapter 3. These controls are achieved through
excitation system. Voltage control is achieved through automatic voltage
regulator (AVR) that regulates the reactive power output and absorption by the
generating unit to maintain the desired terminal voltage. If the generator is
required to be on power factor control, the AVR will adjust reactive power output
to maintain to the desired power factor disregarding the resulting terminal
voltage level. These controls refer to exporting sites only. Importing sites are
subject to the demand power factor requirements.
5.5.2.5 Synchronisation requirements are discussed in section 5.3. Apart from the
requirements in 5.3.3, the synchronizing control must also ensure that excitation
current could only be applied when the generator speed has reached at least
85% of nominal value.
5.5.2.6 Emergency trip control should also be provided for isolating the DG Plant from
the distribution network (breaker at the interface). This ‘push-button’ type control
should be located at convenient place for access by TNB operator particularly
for emergency purposes.
- 83 –
Tenaga Nasional Berhad TNB Research
5 .6 Interlocking
5.6.1 Operating interlocks are required to prevent undesired operation that could
present safety hazard to operating staff or public. Operating interlocks are
categorized into two purposes:
Preventive
Corrective
5.6.2 Preventive interlock inhibits operation until all required conditions are satisfied.
Examples of preventive interlocks are:
Inhibit breaker closing for parallel operation until synchronizing criteria are
met (see 5.6).
Remote and local control of circuit breakers – remote control inoperable
when local control is selected
Utility and synchronizing breakers as shown in Figures 5.5 and 5.6:
- Synchronizing breaker cannot be closed if utility breaker is opened.
- Utility breaker cannot be closed if synchronizing breaker is closed;
5.6.3 Corrective interlocks do not inhibit breaker operation but initiate the additional
remedial operations to enable the desired operation. An example of corrective
interlock is illustrated in Figure 5.7. If BR3 is opened then BR2 automatically
opened. Loss of Mains intertripping is another example of corrective interlock.
Bus
BR1 Reactor
G
BR2
BR3
SF2
- 84 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
5.7 Metering
5.7.1 Each connection/interface point to the distribution network must have metering
installations unless other arrangements are made with the Distributor. There are
two types of metering normally required at the connection/interface point:
1) Revenue metering; and
2) Operational metering.
This section provides only general guidelines on metering requirements. For
detailed requirements, the Metering Code adopted by the Distributor should be
referred to.
5.7.2 For the purposes of revenue metering, the following quantities are to measured:
Active power delivered to the Distributor (kW or MW);
Reactive power delivered to the Distributor (kVAR or MVAR); and
Energy delivered to the Distributor (kWh or MWh).
Where there is a possibility of power being supplied from the distribution system
to the DG Plant the following revenue metering are also required:
Active power consumed by the DG Plant (kW or MW);
Reactive power consumed by the DG Plant (kVAR or MVAR); and
Energy consumed by the DG Plant (kWh or MWh).
5.7.3 In the case of DG Plant, it is usual for the DG Developer to install all the meters
and associated current transformers, voltage transformers, panel and wiring at
the connection/interface point in accordance with the requirements of the
Distributor. The Distributor shall later maintain the metering installation including
any required meter accuracy instrument transformers.
5.7.4 Check meters will normally be used on connection/interface point where the
monthly active energy passing through is above 50,000 kWh or where a
maximum demand exceeds 7.5 MW and with reactive check meters being
installed where reactive energy passing through exceeds 250,000 kWh or as
otherwise determined by the Distributor. Check meters are to be used to provide
metering data validation, substitution or estimation when the main revenue
meters are suspected to have malfunctioned.
5.7.6 The followings are requirements for metering accuracies of active energy ( kWh )
meters for different range of active energy passing through interface/connection
point:
1) Between 50,000kWh and 250,000kWh:
Main and check meters of class 2.0 with ±2% accuracy and allowable
error of ±4%
- 85 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
5.7.8 The Distributor should routinely test and calibrate revenue meters in accordance
with current prudent utility practices. This would normally include periodic
random audits of metering installations to confirm compliance with adopted
metering standards.
5.8.1 All DG Plant interface/connection point must be equipped with the following
SCADA facilities:
Remote Terminal Units (RTU) c/w Marshalling cubicle; and
Communication system from DG plant to TNB control centre.
- 86 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
5 .9 Communications
5.10.1 The connection of the DG Plant to the distribution network may require network
reinforcement to be carried out. During the ‘Preliminary System Study’ stage, the
Distributor must ensure that the connection of the DG Plant and its proposed
quantum of power injection to the distribution would not result in violation of the
design criteria as discussed in chapter 3. The followings are typical criteria
applied by the Distributor at the ‘Preliminary Planning Study’:
1) Normal steady-state voltage limits;
2) Contingency voltage limits;
3) Thermal overload limits of network element;
In addition to the above, the following criteria are also applied:
4) Voltage step limit;
5) Fault level 90% limit;
6) Losses to be below without DG Plant; and
7) SAIDI Reliability index is not worst of without DG Plant.
In carrying out the above assessments, current practice is to assume that the
DG unit is operating at unity power factor and that three load levels are used for
assessments, namely: peak, intermediate and light loads.
5.10.2 If any of the above criteria is not met or too restrictive, three options could be
applied:
1) Use of voltage and or turbine controls;
2) Reduced active power generation from the DG Plant, that is, lower than what
is proposed by the DG Developer; or
3) Network reinforcements which may include any of the following or their
combinations:
Additional feeders
Additional switches/breakers
Shunt capacitors
Series capacitors
Shunt reactors
Series reactors
Different voltage levels.
- 87 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
5.10.4 With respect to network losses, the current practice is to use the following
options to ensure that losses due to the connection of the DG will not be greater
than losses without the DG:
Network reinforcement; or/and
Reduce DG Plant export to the distribution network.
- 88 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Chapter 6: Glossary
6 .1 General Terms
6.1.1 In this guidebook, the following general terms, words and expressions shall bear
the following meanings:
- 89 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 90 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Current Harmonics Distortion Is the measure of the departure of the a.c. current
waveform from sinusoidal shape, i.e., caused by the
addition of one or more harmonics to the fundamental
component.
Current Transformer (CT) A transformer for use with meters and/or protection
devices in which the current in the secondary winding
is, within prescribed error limits, proportional to and
in phase with the current in the primary winding.
Data Collection System All equipment and arrangements that lie between the
metering database and the point where the metering
data enters the public telecommunications network
and used for calculations of payments due to or from
Other Entities.
- 91 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 92 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Energy ( Active and Reactive ) Active energy is the electrical energy produced,
flowing or supplied during a time interval measured in
units of watt-hours (Wh) or standard multiples thereof.
Reactive energy is the energy produced, flowing or
supplied during a time interval measured in units of
volt-ampere-hours reactive, (varh) or standard
multiples thereof.
- 93 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Grid Entry Point A point at which a Generating Unit, as the case may
be, which is directly connected to the Grid System.
- 94 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Low Frequency Relay Has the same meaning as Under Frequency Relay.
- 95 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 96 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Planning and Design Criteria Refers to a set of measures for assessing the
performance of the distribution system during the
planning stage.
Power Quality Characteristics In this guidebook the term refers to the measures
used for determining the purity of the a.c. voltage of
current waveforms.
Prudent Utility practices With respect to the Distributor, means the exercise of
that degree of skills, diligence, prudence and
foresight consistent with the applicable acts,
- 97 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Reactive Power The product of voltage and current and the sine of the
phase angle between them measured in units of volt
amperes reactive. The rate at which reactive energy is
transferred.
Revenue Meter The meter that is used for obtaining the primary
source of metering data for billing purposes.
- 98 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 99 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Total Harmonic Distortion The departure of a wave form from sinusoidal shape,
that is caused by the addition of one or more
harmonics to the fundamental, and is the squares of
all harmonics expressed as a percentage of the
magnitude of the fundamental frequency.
Unbalanced Load The situation where the Load on each phase is not
equal.
- 100 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Voltage Harmonic Distortion It is the measure of the departure of the a.c. voltage
waveform fro, sinusoidal shape, that is caused by the
addition of one or more harmonics to the
fundamental.
Voltage transformer (VT) A transformer for use with meters and/or protection
devices in which the voltage across the secondary
terminals is proportional to and in phase with the
voltage across the primary terminals.
6 .2 Other Terms
6.2.1 The following additional or alternative terms are mainly used in TNB’s
connection and commercial agreements and may be used as reference.
“Change-in-Law” Any of the following events occurring after the Effective Date
as a result of, or in connection with, any action by any
- 101 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
“Commercial The date on which (i) all of the conditions precedent set forth
Operation Date” in Clause 4 shall have been satisfied or waived by TNB and
(COD) (ii) shall have established its export capacity of XXX MW;
“Communication Means all of the facilities described under Appendix E as
Facilities” determined by TNB under Clause 12.6 to be necessary, in
accordance with Prudent Utility Practices, to enable the
Control Centre to communicate and Despatch the Facility;
“Default Rate” A rate equal to two per centum (2%) above the base lending
rate then in effect at the principal office of MayBank Berhad,
or its successors in title.
“Delivered Power” For the purpose of this Agreement shall mean the rate at
which electrical energy is delivered by the Facility to TNB at
the Interconnection Point and is measured in Kilowatts;
- 102 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
thereof;
“Effective Date” The date of the execution and delivery of this Agreement by
The Seller and TNB and that all corporate authorisations
which are required to have been obtained by the Parties in
connection with the execution and delivery of this Agreement
have been obtained and are in full force and effect and a
statement in writing to that effect has been submitted to each
Party;
“Energy Payment” For each Billing Period, the payment to be made by TNB to
The Seller for electrical energy delivered to the
Interconnection Point and received by TNB during such
Billing Period;
“Facility” The whole of the plant installation with the nominal capacity
of YYY MW as stipulated in Recital A, with all necessary
plant, buildings and land in connection therewith, electricity
connection and consuming apparatus, if any as per Appendix
A of this Agreement;
- 103 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
hereof;
“Grid Code” Means the Malaysian Grid Code, as amended from time to
time in accordance with applicable Law;
“Initial Operation The first date on which electrical energy is generated and
Date” (IOD) delivered from the Facility to the Interconnection Point;
- 104 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
“Interconnection The physical points where the Facility and the TNB System
Point” are connected, as shown in Appendix D, or such other point
or points as the Parties may agree;
“kW” Kilowatt;
“kWh” Kilowatt-hour;
“Law” Any (i) law, legislation, statute, act, rule, order, treaty, code or
regulation, or (ii) legally binding announcement, directive or
published practice or any interpretation thereof, enacted,
issued or promulgated by any Governmental Entity or court
or tribunal;
“Licence” The licence granted to The Seller under the Electricity Supply
Act, 1990 to enable The Seller to own and operate the Facility
and to operate electricity generating capacity and supply
electric energy to TNB therefrom;
“The Seller” The Seller Sdn. Bhd., a company incorporated under the laws
of Malaysia, including its successors in title and permitted
assigns;
“MW” Megawatt;
“Off-Peak Hours” Shall mean the periods between 0000 hours to 0900 hours
- 105 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
“Peak Hours” Shall mean the period between 0900 hours to 1700 hours of
each day;
“Parties” TNB and The Seller and a reference to a “Party” means either
TNB or The Seller as the case may be;
- 106 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
“Test Energy” The electrical energy associated with the start-up and
commissioning of the Facility prior to the relevant
Commercial Operation Date, and metered at the
Interconnection Point;
“TNB Licence” Means the licence required and obtained by TNB or any
extension thereof pursuant to Section 9 of the Electricity
Supply Act 1990;
“TNB MV Means the latest edition of the guidebook for other users to
Interconnection be interconnected to the TNB Medium Voltage (MV)
Guidebook” Distribution network titled “A Guidebook of the Technical
Requirements for the Interconnection of A User’s Network to
TNB’s MV Distribution Network”;
- 107 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 108 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 109 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Figure 7.1(b): The Structure of Electricity Supply Industry in Sabah and Sarawak
- 110 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Laws and Regulation that are regulating the electricity industry in Peninsular Malaysia and
Sabah are:
Energy Commissioning Act 2001
Electricity Supply Act 1990
Electricity Supply Regulation 1994
Figure A.2 illustrates the current structure of institutional and regulatory structure of the
industry in Peninsular Malaysia and Sabah
- 111 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Generation and TNB Hidro ), provide approximately 60% of the installed generating
capacity. Five IPPs provide the remaining 40%. In Sabah, SESB provides 493MW (62%) of
installed capacity with five IPPs providing the remaining 305MW of capacity (38%). In
Sarawak, SESCo provides 499MW (61%) of the installed capacity with the other 320MW
(39%) being provided by two IPPs. Within the total installed capacity in Malaysia, there is
an approximate 30% to 35% reserve margin.
- 112 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 113 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 114 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
operation function cooperates and coordinates closely with the planning function to identify
short- to medium term plans to improve system reliability. Otherwise most network
investment plans including improvement of reliability are carried out by the network
planning group.
- 115 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
voltage of 415/240V by more than +5% to –10%. Distribution networks are designed to
provide electricity to users at reasonably constant voltage levels. Normally, voltage control
in distribution system is provided by on-load tap changing transformer. The transformers
that transfer power from the higher to the lower voltage system are fitted with automatic
voltage control that compensate voltage changes on the high voltage side. In addition to
this, switched and fixed capacitor banks are employed at strategic locations in the
distribution system. Boosters are seldom used now because of their high costs. In the LV
system, voltage regulators are employed but now being replaced by switched and fixed
capacitors. The presence of distributed generation can assist in improved voltage profiles,
but often makes the process of voltage control more complex. Conversely, power in-feeds
from distributed generators tend to increase the voltage levels.
7.4 Distribution
7.4.1 Distribution Organisations
TNB Distribution Division (known as TNBD), SESCo and SESB are the main distributors of
electricity throughout the Peninsular, Sarawak and Sabah respectively. Until 2002, The
Government has issued licenses to 26 companies who are allowed to operate as local
distributors or suppliers of electricity in certain designated locations, such as shopping
complexes and industrial parks. Some of these companies also operate their own co-
generation plants to supply part of their demand.
7.4.2 Voltages
In TNB distribution system, the network system voltage can be categorized into two:
1) Medium voltage (MV), which are 33kV, 22kV, 11kV, 6.6kV
2) Low voltage (LV) which are 415V and 240V
In some areas in State of Perak and Johor, the 22kV networks are being converted to 33kV
and 11kV. The sub-transmission feeding points into distribution systems are via HV/MV
substations of 132/33 kV, 132/22kV and 132/11kV – normally called PMUs. MV network
predominantly made up of underground cable while LV feeders are predominantly overhead
lines with underground cable for selected commercial and housing areas.
- 116 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
The majority of faults occurring on overhead lines are transient faults due to lightning,
swinging of wires, tree branch falling on the lines or because of animals. The advantage
derived from auto reclosing is to reduce interruption time to the customers due to transient
fault as well as to support fault isolation management. Auto reclosers and sectionalisers are
installed on 33kV overhead lines system. These devices re-close the circuit breakers a few
seconds after it is tripped. If the fault has not cleared by this stage, the protection will be
activated and the circuit breaker will trip again. However, if the fault has cleared, the line
will then remain reconnected to the supply.
Automatic re-closers are usually set to operate up to three or four times after a fault. If the
fault does not clear after this number of operations, the circuit breaker remains tripped and
must be re-set manually. The dead time between each successive reclosure is important
information for DG in order that generator protections can be designed to avoid the auto-
reclosure closing with the generator and the grid out of synchronism.
- 117 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
breaker interrupting the fault. The maximum fault level allowed in the distribution system
are as follows:
The equipment shall be rated to withstand the rated fault current for duration of 3seconds.
Distribution Division of TNB has the responsibility to plan and develop their network, while
maintaining the standards of safety and reliability, as well as maintaining system’s technical
efficiency in line with the basic objective of distribution network planning to provide secure
supply whilst fully meeting customer demand at the most economic overall cost, consistent
with the nature of the load.
Planning for the future in general begins with annual load forecasting followed by
preparation of master plan, execution and evaluation of current system performance. The
key sets of planning criteria involve security level standard, contingency criteria, loading
criteria of network element under normal and emergency, fault level as well as equipment
breaking duty.
Distribution system operations are not entirely controlled and monitored via SCADA.
Existing SCADA comprises of supervision and control at substation level and master station
- 118 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
only while distribution feeder automation is under implementation stage. The number
controlled and monitored distribution substation under the on-going SCADA program is
only 10% of total number in the whole of TNB system by end of 2007. In addition, a
program of wider placement of EFI and LFI is to be implemented in 2004 to improve
operational flexibility and system efficiency in general. The EFI will be placed at incomer
and outgoing feeder at every distribution substation and be later integrated with planned
SCADA.
- 119 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
8.1 Introduction
8.1.1 Energy Source
Mechanical energy to turn the generator rotor is supplied by the prime mover. This involves
energy conversion from mechanical energy to electrical energy. Some of the most common
type of energy sources for DGs are:
• Hydropower
• Fuel Cells
• Landfill Gas
• Biomass
• Wind Power
• Geothermal
• Photovoltaic
If the installed capacity of DG Plants is taken into account by the utility in its energy and
capacity planning, the reliability of the energy source must be considered. The availability of
power from wind turbines is highly unpredictable. Landfill gas turbines, Geothermal and
reciprocating engines are more reliable source of energy, with long outages to shutdowns
for maintenance, which can be planned in advance. The reliability of hydropower turbines is
also inherently very high but energy availability depends greatly on the pattern of water
flow. For back pressure steam turbines, where the steam from the DG turbines is used for
processes, the amount of generation is often dictated by the steam requirements of the
plant at different times of the day.
The Government of Malaysia is signatory to the 1992 Rio Earth Summit and participated in
the Berlin Summit. This requires the reduction of the greenhouse gases and thus renewable
energy (RE) such as run of river hydro, solar, biomass and wind energy generation meets
these objectives. Consequently any project using the RE sources should be given every
assistance and prioroty to connect to TNB’s medium voltage (MV) network.
8.2 Hydropower
Hydropower is a valuable source of energy. Unlike other sources of energy, water retains its
value even after it is used as a medium to generate electricity. Hydroelectric station uses
water that is stored in a reservoir behind a dam or from run-of-river to drive the turbine. As
the water rushes through the turbine, it spins the turbine shaft which produces mechanical
power as shown in Figure 8.1. The mechanical power is then converted to electrical power
through the generator, which is connected to the turbine.
- 120 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
A peaking or pumped storage station impounds and releases water when the energy is needed.
In this method, excess energy is used to pump water from lower reservoir to an upper
reservoir. During period of high electricity demand, the water is released to the lower reservoir
to generate electricity.
An impounded facility, typically a large hydropower station, uses dam to store river water in a
reservoir – also termed as pondage hydro. This method allows water to be released constantly
to generate electricity. Example of impounded facility is the Kenyir Hydro Station in
Terengganu.
The main advantage of hydropower is that it does not produce or emit any pollutant as by-
product. In addition, its operating cost is very low and hydropower can respond quickly to
utility load demand when it is required. On the other hand, high initial capital cost and potential
environmental impact, especially for big hydropower plant are the main disadvantages. The
- 121 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
environmental impact, however, can be avoided or reduced with proper planning in the initial
stage of implementation.
Fuel cell offers high efficiency and environmental advantage in comparison to some other
technologies mainly due to the electrochemical process which does not require any moving
parts. Phosphoric acid fuel cell can achieve up to 40 percent efficiency while molten
carbonate and Solid oxide fuel cells have an efficiency of nearly 60 percent. In addition, fuel
cells are virtually soundless, making it suitable to be used in premises where noise is a
problem.
- 122 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
To utilize the biogases produced from the waste landfill, gas wells are drilled at few places
on the disposal site as shown in Figure 8.2. The gas would first be filtered before being sent
through gas collector line to drive the turbine that generates electricity.
- 123 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
The startup time for a vertical axis turbine’ is less than one minute. Smaller machine started
by connecting directly across the line larger machines reduced voltage starters may be
employed to reduce inrush currents. System disturbances which cause such units to trip
off line require a complete and restart of the machine. Wind power typically have no speed
control or at best have relatively crude speed control such as varying blade pitch. It is
therefore difficult to bring the slip speed of the induction generator to zero because closing
the connecting switch to the utility system and voltage fluctuations are likely at the instant
connection. The main factor affecting rate of load change is the inertia constant and its
relation to wind speed changes.
- 124 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
impacts. In addition, wind turbines produce acoustics noise and electrical interference
which would be unpleasant to the surrounding environments.
8.6 Microturbines
Microturbines are small combustion turbines with output ranging from 25kW to 1000kW.
Microturbines evolved from automotives and trucks turbocharge auxiliary power units from
airplanes and small jet engines used on pilotless military aircrafts. Most microturbines are
typically single-shaft machines, with the compressor and turbine mounted on the same
shaft as the electrical generator. It consists of only one rotating part, eliminating the need
for gear-box and associated moving parts thus reducing maintenance and increasing
reliability. Microturbine rotates at speed of 6,000 to 10,000 rpm driving either a two or four
pole permanent magnet generator. The shaft is mounted on either oil lubricated bearings or
air bearings. A key component of the microturbine is the recuperator, which transfers heat
from exhaust gas to air that is sent to the combustor. Pre-heating combustion air reduces
the fuel consumption and increases its overall efficiency to 25 to 30 percent. Further
utilization can be gained by utilizing the waste heat from the turbine and incorporating heat
recovery system to the unit.
8.7 Geothermal
Geothermal energy is heat energy originating deep from the earth molten area. It is this
heat which is responsible for volcanoes and earthquakes. The temperature in the earth’s
interior is as high as 7000’C. There are four types of geothermal resources namely
hydrothermal, geo-pressured, hot dry rock and magma. Of the four types, only the
hydrothermal resource is currently commercially available. Hydrothermal resource comes
in the form of either steam or hot water depending on the temperature and pressures
involved. High grade resource is normally used for electricity generation and lower grade
resource is used in direct heating applications. A typical geothermal plant is shown in
Figure 8.4.
- 125 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
8.8 Photovoltaic
Photovoltaic system uses semiconductors-based cells to directly convert sunlight to
electricity. The semiconductor cells use thin film and crystalline silicon materials. The
greater the intensity of the light, the more power it will generate. Photovoltaic system can
be used to generate electricity at almost any scale, depending on how many modules are
connected together. The cost of photovoltaic cell has been reduced by almost 50 percent
since 1980 and the sales have been increasing steadily particularly in the remote power
operation. PV cell was initially developed in the 1950s for use on satellites and space
program and has been used widely as the source for satellites orbiting earth since 1960s.
With technology advancement in the 1980s and 1990s, many applications of PV cell have
been commercialized. The applications in use today include health care system,
communications, security system, electricity supply and transport aids.
8.9 Cogeneration
8.9.1 Definitions of Cogeneration
Cogeneration or more popularly known as combine heat and power (CHP) refers to the
sequential generation of two different forms of useful energy (e.g. thermal and electrical)
from the same amount of primary fuel input within a manufacturing process. This form of
generation enhances the utilization of energy efficiently and is highly promoted by the
Malaysian Government. Energy efficiency can be increased from 35% to 75 – 80% using
- 126 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
this mode of generation. Figure 8.5(a) and 8.5(b) illustrate this approach of generation and
its increased efficiency when compared to conventional generation.
- 127 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 128 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
The developments of cogeneration are essentially driven by the following key factors:
Advancement in the technology for small-scale power generation e.g. efficient lesser
capacity generators.
Energy efficiency or rational use of energy
Deregulation or competition policy
Environmental awareness – reduction in Green-House-Gas (GHG) emission.
Table 8.4 lists the various technologies used in Co-Generation or CHP plants.
- 129 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 130 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 131 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Figure 8.8: Co-Generation scheme using a gas turbine with waste heat recovery
- 132 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Basic information that can immediately be obtained from the Distributor includes the
followings:
1) Nearest substation, distribution lines or cables to the DG plant and their capacities;
2) The distance to the nearest connection point;
3) Three-phase short-circuit level at nearby substations;
4) Source transmission substation and loading profile (24-hour MW, MVAR for working
days and weekends) of the feeder where the plant would be connected;
5) Development of the network in the area; and
6) Any special problems that the Distributor faces with respect to power supply in the
area.
It is important at this point for the Distributor to indicate to the DG Developer how the
proposed DG plant should have its power output scheduled to ensure no spill-over of
power to the transmission network (operation regime).
- 133 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
For purpose of a preliminary system study, the Developer is required to submit a letter to
local TNB offices. The letter should also describe basic parameters of the proposed DG
plant.
Date:
Thank you.
Yours Sincerely,
(signed)
DG Plant Developer
- 134 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
The official application should be submitted in Form DG001 (see next page). This
application form must be accompanied by details of the plant.
- 135 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
FORM DG 001
Address
Type of Plant
Telephone Handphone
Email
- 136 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 137 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 138 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
10.1 Introduction
This appendix outlines the planning/design criteria as applied by TNB to ensure that the
distribution networks meet the following requirements:
Secure electricity supply;
Reliable electricity supply;
High quality electricity supply;
Optimal equipment utilization;
Optimal network losses; and
Safety of staff and public.
The purpose of the distribution system planning/design criteria is to provide the balance
between the customer’s need for a safe, secure, reliability, high quality electricity supply
and costs by TNB.
In urban, sub-urban and town areas, the distribution networks are configured an open
meshed/ring network that is run radially with open points. By operating the network with
open points, fault levels are reduced (as compared to closed rings or meshed) and simply
technical and operational requirements. Open meshed/ring network arrangement allows
improvements in supply restoration times following an outage.
In rural areas where the total feeder maximum demand is less than 1MVA, the network
operates in radial configuration without alternative supply.
The distribution system is not designed for islanded operation with distributed generation.
DG must be designed to be disconnected from the distribution network if the feeder that the
generator is connected to is separated from the remainder of the distribution system.
- 139 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
reliability and quality, the least cost option is normally chosen. The extent of network
reinforcement works is dependent on the following:
Load forecast projections;
The anticipated max demand of the customers or generation output; and
Age and condition of the existing assets.
Economic analysis is applied in assessing network reinforcement requirements for the
following purposes:
To indicate returns of proposed capital investments;
To choose the best options - least cost being the method used; and
To minimise losses.
Under contingency operating conditions the steady state voltages are to be within the
following limits:
1) ± 10 % at 33 kV
2) ± 10 % at 11 kV
3) ± 10% at 0.415 kV
It must be emphasized that the steady-state voltage limits are measured at metering points
or defined connection/interface and the voltage measured is phase to neutral.
- 140 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
10.4.5Frequency Limits
Under normal conditions, the transmission and distribution network frequency is
maintained at 50 Hz ± 1%. Under emergency conditions that caused the frequency to drop
below 49.5 Hz, under frequency load shedding scheme will operate to reduce load on the
network so as to prevent total failure of the electricity system operated by TNB.
- 141 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
The network shall be planned and designed so that in the event of a failure of a main intake
sub-station transformer in the supply zone:
all of the loads can be transferred to the other transformer in the main-intake sub-
station; or
all the loads can be transferred to other main intake sub-station transformers within
the supply zone or other nearby adjacent supply zones.
In essence, the deterministic criteria of single network element contingency i.e. (N-1)
criterion is applied for medium voltage network planning for urban/sub-urban areas
resulting in no loss of loss load during repair time.
- 142 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Flicker Pst, Pst, 1.0, Plt 0.8 (at 132 kV and Engineering
Plt below) Recommendation P28
Voltage sag % Remaining Voltage 50 % Sag (up to 200 ms) SEMI F47
70 % Sag (up to 500 ms)
80 % Sag (up to 1000 ms)
- 143 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
To achieve cost efficiencies, standard overhead conductors and underground cable sizes
have been designed.
- 144 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
11.1 Introduction
Distribution networks are primarily designed to distribute power from central generation via
transmission system to customer loads. In this configuration the power from the source i.e.
central generation will flow through transmission system and distribution system and
finally absorbed by customer loads. It is a straight forward one way power flow. But when
distributed generation is introduced in distribution system the power flow becomes more
complex and may flow both ways.
In such a configuration the normal conventional way of planning, designing and operating
the distribution system need to be reviewed. The present of local generation will alter the
behaviour of the distribution system either at steady state or transient state. This will
obviously affect the protection strategy and operation, the network design and operation
and restoration operation after fault. Failure of either one of these will affect the safety of
the operating personnel as well as the equipment.
There are two stages of studies carried out by TNB for connection of a DG Plant to the
distribution network:
1) Preliminary system study; and
2) Power system study.
The ‘power system study’ is carried out after DG Developer has submitted formal
application for connection and the study has the following main objectives:
1) To confirm the findings of the ‘preliminary system study’
2) To determine additional control measures; and
3) To be used as guidelines for relevant technical specifications for the DG Plant.
In this appendix methods and approaches to both preliminary and power system studies
are elaborated to be as guidelines for TNB planning and design engineers.
- 145 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 146 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Tables 11.1 through 11.3 provide guidelines on typical data for synchronous machines that
could be used for studies.
- 147 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
If only the d-axis parameters are known, the q-axis parameters can be estimated as:
1) Xq = 0.9 * Xd (0.65 * Xd for hydro)
2) X’q = 2.0 * X"d (can be 3 to 4 times higher)
In some cases, only the transient d-axis reactance X’d is known. In that case, the other
reactances can be estimated using X’d. The relationships can also be used to fill in where
one or two data items are missing. For Round Rotor Machines:
1) Xq = 5.33 X’d
2) Xd = 1.1 Xq
3) X’q = 0.3 Xq
4) X"d = 0.66 X’d
5) Xl = 0.66 X"d
6) T’do = 6.0
7) T"do= 0.035
8) T’qo = 0.6
9) T"qo= 0.07
10) s(1.0)= 0.13
11) s(1.2)= 0.4
- 148 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
If only saturated values of the reactances are known, it is possible to estimate the
unsaturated reactances needed for input stability simulations. The standard method for
labeling reactances is:
1) Reactance at rated voltage (saturated) = X"dv
2) Reactance at rated current (unsaturated) = X"di
Similar terminology is used for the transient reactances. An estimate of the relationship
between the two is:
1) X’di = 1.35 X’dv
2) X"di = 1.35 X"dv
The relationship varies significantly among machines; the range of the factor is about 1.1 to
1.45. There is usually little or no effect of saturation on the steady-state reactances and also
no effect on X’q.
After the loads have been updated, at least 2 additional load snapshots should be prepared,
namely:
1) Intermediate; and
2) Light load.
Figure 11.2 illustrates an example of selecting load snapshots from a 24-hour load profile
given in p.u. Since we require 3 load levels, the load levels from light to peak (0.4 to 1.0
respectively) are divided into three equal sections – in the case of figure E.2, having four
pints at 0.4, 0.6, 0.8 and 1.0. Peak load level should be chosen as 1.0 p.u. and light load
level 0.4 p.u. However, for intermediate load the load level should chosen at the middle of
intermediate load duration, about 0.7. The duration of each load levels are then determined
from the intersections of the four load level points with the load duration curve. These
values are to be for defining the load snapshots of network model in PSS/ADEPT.
- 149 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
1.2
Peak Load
1
Load
Load (p.u.) 0.8
Intermediate Load Level
0.6
Load duration Load
Duration
0.4 Light Load
0.2
0
1 6 11 16 21
Time (hours)
After the network model without the DG Plant has been established and checked, the DG
Plant could then be included in the model.
Before a DG Plant is connected to a network bus, the voltage level at that bus must be
within the criteria range (see Appendix D). A planning/design approach that ignores the
reactive power contribution (sending and absorbing) of the DG Plant is normally used. This
approach ensures that the voltage in the distribution network would be maintained within
criteria limit on loss of the DG Plant. If there is one generating unit, it can be set as
- 150 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
‘constant power’ unit with zero reactive power output (power factor 1.0) as illustrated in
figure 11.3.
If there are several generating units in the DG Plant with its own loads, the generators must
also be set to constant power factor with reactive power output to match the DG Plant
loads. The objective is to have negligible reactive power flow through the interface.
Normally, there may be more than one option of connecting the DG Plant to the network.
Where the DG Plant has its own distribution network, the network together with generating
units and interface transformer(s) must be modelled.
- 151 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
The interface transformer has major influence on the short-circuit contribution of the DG
Plant to the distribution network and therefore its parameters particular positive and zero
sequence impedances must be reasonably modelled. Table 11.4 shows minimum
impedance values for different size transformers in accordance with the requirements of
IEC 76. In PSS/ADEPT, the zero sequence impedance of the transformer would be assumed
to be the same with the positive sequence. What will influence the zero sequence current
contribution is the grounding of the star point of the interface transformer. The minimum
impedance value should be used in the ‘preliminary system study’ for maximum
contribution of fault current from the DG Plant.
Clearly, the potential for greatest voltage rise will occur when the distribution network is
during light load since this condition hinders the local absorption of the exported power.
The degree of voltage rise will be related to:
1) Type of generator and its associated control systems – assume power factor of 1.0;
2) The location of the DG Plant in the feeder;
3) The level of export relative to the minimum load condition;
4) The distribution of load on the feeder; and
5) The size of the feeder conductors and its connections to the DG Plant.
To illustrate voltage profile analysis a distribution network as shown in figure 11.4 is
modeled in PSS/ADEPT. An existing 11kV feeder with uniformly distributed load is where
the DG Plant is to be connected. To illustrate the effects on voltage profile, the DG will also
- 152 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
be connected to the middle and beginning of the feeder. Effects of additional 11kV feeder
and distribution at higher voltage level of 33kV would also be demonstrated.
33kV
33kV connection
alternative 33kV
11kV
DG Plant
Figure 11.4: Example uniformly distributed load feeder for voltage profile
analysis
1.1 Peak
Intermediate
Voltage (p.u.)
1.05 Light
0.95
0.9
0 5 10 15 20 25 30 35 40 45 50
Distance (km)
- 153 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
1.1 Peak
Intermediate
Voltage (p.u.)
1.05 Light
0.95
0.9
0 5 10 15 20 25 30 35 40 45 50
Distance (km)
1.1 Peak
Intermediate
Light
Voltage (p.u.)
1.05
0.95
0.9
0 5 10 15 20 25 30 35 40 45 50
Distance (km)
When a DG is connected at the end of a feeder, voltage profile analysis would indicate the
limit on power export to the distribution network and thus the total size or capacity of the
DG Plant units.
Since the approach is for the DG Plant not to contribute reactive power regulation (constant
power factor at 1.0), a sudden loss of the unit would not result in voltage limit violation.
- 154 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
1.1 Peak
Intermediate
Voltage (p.u.)
1.05 Light
1
0.95
0.9
0 10 20 30 40 50
Distance (km)
1.1 Peak
Intermediate
Voltage (p.u.)
1.05 Light
1
0.95
0.9
0 10 20 30 40 50
Distance (km)
1.1 Peak
Intermediate
Voltage (p.u.)
1.05 Light
1
0.95
0.9
0 10 20 30 40 50
Distance (km)
When located at the mid of the feeder, amount of export could be increased but voltage
remains the limiting factor.
- 155 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
1.1 Peak
Intermediate
Voltage (p.u.)
1.05 Light
0.95
0.9
0 5 10 15 20 25 30 35 40 45 50
Distance (km)
1.1 Peak
Intermediate
Voltage (p.u.)
1.05 Light
0.95
0.9
0 10 20 30 40 50
Distance (km)
1.1 Peak
Intermediate
Voltage (p.u.)
1.05 Light
0.95
0.9
0 10 20 30 40 50
Distance (km)
- 156 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
11kV Parallel
Feeder
We examine the impacts of voltage profile with the additional 11kV parallel feeder. Without
any DG output, the cable capacitance results in slight increase in voltage at the end of the
feeder as shown in figure 11.15.
1.1 Peak
Intermediate
Voltage (p.u.)
1.05 Light
0.95
0.9
0 5 10 15 20 25 30 35 40 45 50
Distance (km)
Figure 11.15: Voltage profile, with parallel 11kV feeder DG output = 0.0 kW
- 157 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
The addition of the long 11kV feeder cause voltage rise to appear at lower DG output as
compared with the one without the additional feeder (see figure 11.16).
1.1 Peak
Intermediate
Voltage (p.u.) 1.05 Light
0.95
0.9
0 5 10 15 20 25 30 35 40 45 50
Distance (km)
Figure 11.16: Voltage rise at 500kW output with parallel 11kV feeder
The above result shows that a feeder reinforcing the network may not serve to eliminated or
reduce the voltage rise problem. Therefore, voltage profile must again be examined when
reinforcement particularly using long circuits is attempted.
33kV
Feeder
- 158 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
The 33kV circuit significantly improves voltage profile performance even with high DG kW
export as indicated in figures 11.18 through 11.20.
1.1 Peak
Intermediate
Voltage (p.u.) 1.05 Light
1
0.95
0.9
0 10 20 30 40 50
Distance (km)
1.1 Peak
Intermediate
Voltage (p.u.)
1.05 Light
1
0.95
0.9
0 10 20 30 40 50
Distance (km)
1.1 Peak
Intermediate
Voltage (p.u.)
1.05 Light
0.95
0.9
0 10 20 30 40 50
Distance (km)
In the example of using 33kV feeder, the limiting factor is overload of circuits.
- 159 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
500
Peak
450 Intermediate
400 Light
Feeder Losses (kW)
350
300
100
50
0
0 1000 2000 3000 4000
DG Output (kW)
1.2
Peak
Intermediate
1.15 Light
Voltage (p.u.)
1.1
1.05
Voltage limit
1
Range
0.95
0.9
0 1000 2000 3000 4000
DG Output (kW)
Figure 11.21: Loss variation with DG connected at the end of the feeder
When a DG is connected to the end of the feeder, voltage limit may be the limiting factor for
export as compared to loss limit.
- 160 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
500
Peak
450 Intermediate
400 Light
Feeder Losses (kW)
350
300
100
50
0
0 1000 2000 3000 4000 5000
DG Output (kW)
1.2
Peak
Intermediate
1.15 Light
Voltage (p.u.)
1.1
1.05
Voltage limit
1
Range
0.95
0.9
0 1000 2000 3000 4000 5000
DG Output (kW)
Figure 11.22: Loss variation with DG connected at the mid of the feeder
When a DG is connected to the mid of the feeder, voltage limit may also be the limiting
factor for export as compared to loss limit.
- 161 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
500
Peak
450 Intermediate
Light
400
Feeder Losses (kW)
350
300
100
50
0
0 1000 2000 3000 4000 5000 6000
DG Output (kW)
1.2
Peak
Intermediate
1.15 Light
Voltage (p.u.)
1.1
1.05
1
Voltage limit
Range
0.95
0.9
0 1000 2000 3000 4000 5000 6000
DG Output (kW)
Figure 11.23: Loss variation with DG connected at the source of the feeder
Based on the above analysis, the output (the quantum of export) of the DG when connected
to existing feeder would significantly limited by voltage limit criteria.
- 162 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
To illustrate the analysis of DG Plant contribution to fault level, a network in figure 11.24 is
used.
25kA, 3-phase
Tx with NER
Tx with min
IEC impedance
Tx with NER
150A, min.
IEC imped.
- 163 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
5) DG interface transformer NER must be modelled for 150A contribution the distribution
network.
When evaluating the impact of DG Plant on fault level, it is important to look at the 415V
busbar after the LV step-down transformer. This is because the fault rating of 31.5kA for LV
equipment may be exceeded with increase fault level due to DG Plant contribution. For fault
level evaluation the LV transformer tap should be set to the maximum, that is, with highest
possible voltage.
The fault current contribution of the DG Plant is most critical when it is located near the
source bus as illustrated in figure 11.25. In this example, the LV bus has exceeded the 90%
limit. The making duty of the 415V and 11kV breakers are 51.6kA and 28.0kA respectively
and these should be checked against the actual make rating.
51.6kA
28.0kA
91.1%
77.9%
- 164 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
4MW
Output
Overload
Figure 11.26: Feeder overload is not limiting export when DG Plant at the end of the
feeder.
If the DG Plant is located in the middle of the feeder, overload would occur at higher MW
output. In this case 5.5MW as shown in figure 11.27. However, as in the previous case, the
limiting factor remains voltage and not circuit capacity.
When the DG is located closed to the source, overload/circuit capacity and voltage issue are
limiting DG output as indicated in figure 11.28.
- 165 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Overload
5.5MW
Output
Figure 11.27: Feeder overload is not limiting export when DG Plant at the end of the
feeder.
6MW
Output
Figure 11.28: Feeder overload and voltage are not limiting export when DG Plant at the
source.
- 166 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
11.3.1Stability Analysis
Study on local distribution network stability and security need to carried out for every DG
installation especially for DG with a capacity of more than 5 MW. For DG installation that is
less than 1 MW the study might be waived.
In this study the frequency and the voltage stability need to be confirmed under fault
condition. Frequency stability is analysed by tracking the frequency at each substation as it
evolves over time. If the frequency values either remain constant (at the nominal value of
50Hz) or converge to a different equilibrium value then the system is stable. On the other
hand if a small disturbance at one substation in the system causes the frequency at one or
more substations do diverge from equilibrium then the system is said to be unstable.
The scenarios for this study are both at peak load and base load conditions with
disturbance introduce at various selected critical points in the network. It is important also
to study the stability and the security of the network that has been detached (if any) from
the grid due to loss of mains -islanded network. This would determine how DG should react
under such a condition.
- 167 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
‘power system study’. TNB also uses PSS/VIPER for dynamic analysis. This way requires
that PSS/ADEPT network model for steady-state analysis be reentered into PSS/VIPER.
However, a new approach is being developed that the PSS/ADEPT network model can be
translated for use with PSS/E for dynamic simulations.
In PSS/ADEPT, the network data can be saved into a HUB format and this format could read
in PSS/ADEPT Utility as shown in figure 11.30. PSS/ADEPT Utility is a program that
converts PSS/ADEPT file to PSS/E and thus ready for stability simulations.
- 168 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Currently the Utility converts PSS/ADEPT generator data to corresponding PSS/E dynamic
data but without excitation and speed-governor controls. The two controls will have to be
added separately to the dynamic data file.
In PSS/ADEPT Utility, stability simulation with PSS/E in the background can be carried out
as shown in figure 11.31 and 11.32.
- 169 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 170 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 171 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Insulation coordination study is not yet carried out by TNB. In this guidebook, insulation
coordination study has been proposed to be carried out and therefore TNB is encourage to
explore further.
- 172 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
12.1 Introduction
The protective requirement must be based on the need to detect system faults and
malfunctions both within the DG installation as well as the TNB distribution feeder. On
detection of fault or malfunction, the relays must trip appropriate circuit breakers to isolate
the faulty section to minimize equipment damage and safety hazards during the faults
whilst maintaining power supply continuity on healthy parts of the system.
Although the design and types of protection for the DG installation including its generating
units is the responsibility of the DG Developer, TNB must ensure that these protections are
properly coordinated for reliable and safe operation of the distribution feeder to protect TNB
equipment and safety of other TNB customers. The basic philosophies for the types and
design of the protection schemes are that:
a) For any internal fault within the DG installation, the DG must not cause problems to the
utility system and the customers.
b) For any distribution fault, the generator must be protected from any damaging effects.
Under voltage (UV) and Under Frequency (UF) relays are designed to trip the generator
when the distribution feeder is taken off. When the feeder is supplying load greater than
the capacity of the generator, under frequency and under voltage are expected to occur and
UV and UF relays will operate to trip the generator (see figure 12.1). The setting of the
under frequency trip (Hz) must be based on the recommendation of the manufacturer.
- 173 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Feeder 1
1. BR3 open
Main Intake 2. DG to supply 5MW with 3MW turbine power limit then:
BR1 • Underfrequency trip; or/and
Feeder 2
• Undervoltage trip.
BR2
S DG Plant
2MW 3MW UF
UV
BR3
DG
Feeder 4
BR4
Total load
5MW
Feeder 5
BR5
When the feeder load is sufficient to be supplied from the generator under islanded
operation, UV and UF relays may not operate. Therefore, under the current operational
practice, this condition where flow to the feeder at the source will result in sustained
islanded operation of the DG Plant with feeder must be avoided by rescheduling the DG
export to the distribution network.
If the resulting feeder load could be totally supplied by the generator under islanded
operation, this may present a hazard to personnel. Generator damage would be likely when
the feeder breaker is reclosed. In distribution systems, feeder breakers are not equipped
with dead line check to prevent reclosing on live feeder. An alternative to dead line check
relays is an automatic transfer trip that upon opening of the utility feeder breaker, a signal
is provided to trip the generator. Any islanded operation required later must be performed
based on operation and safety procedures agreed by both the generator and the utility.
If the feeder load to be supplied by the generator is less than the generation, over-
frequency will occur and therefore OF relay is required as illustrated in figure 12.2. The
setting of the OF relay must also be based on the recommendation of the generator
manufacturer.
- 174 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Feeder 1
1. BR3 open
Main Intake 2. DG to supply only 1MW with 3MW turbine power:
BR1 • Overfrequency trip.
Feeder 2
BR2
S DG Plant
2MW 3MW
OF
BR3
DG
Feeder 4
BR4
Total load
1MW
Feeder 5
BR5
OV relays are installed on the DG side to protect against over-voltage resulting from a
sudden loss of load. However, the generator voltage regulator will take care of the over-
voltage by reducing excitation. Therefore, the over-voltage relay would be useful when the
voltage regulator is defective or limited that it would result in sustained over-voltage.
Transient over-voltages due to switching or lightning should be catered for by the design of
the distribution and DG systems insulation.
To prevent damage on the prime mover due to motoring of the generator during reversal of
power, RP or directional relays are installed. Time delay must be incorporated to prevent
nuisance tripping during synchronization of the generator.
Combined over current and earthfault (OCEF) relays are employed for protection of over-
current and earthfault in both directions. IDMT relays equipped with instantaneous trip are
used in this case. For large generators provided with its own unit protection, the OCEF
relays are used as backup for the generator internal fault. On distribution system fault,
both generator OCEF and feeder OCEF would see these fault currents. Coordination of the
generator OCEF relays with that of feeders would become more difficult due flow of fault
currents from both sources into fault. It is normal practice that on a distribution fault on
the feeder, the feeder OCEF is allowed to trip first followed by the generator. If the fault is
cleared and the generator operates in isolation then frequency and voltage relays would
likely to operate depending on the generation-demand balance. However, if inter-trip is
provided, the generator would also be tripped out.
- 175 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Field failure (FF) relays is employed to detect malfunction of the generator excitation field.
Upon loss of excitation, the generator rotor accelerates to above synchronous speed where
it continues to generate power as an induction generator. Loss of field is normally detected
by an undercurrent relay connected to a shunt in the field circuit.
Negative phase sequence relays are employed to detect excessive unbalanced loading of
the generator.
- 176 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 177 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
All TNB primary equipment shall be protected against damages from any type of faults. For
all external parties such as IPPs, co-generators and bulk customers, their primary
equipment shall also be protected against damage from any type of faults and shall follow
the setup and schemes specified as in the guidebook.
12.4.1General Requirement
12.4.1.1 Maximum Fault Clearing Time, Operating and Reset Time
The maximum fault clearing time is defined as the maximum time interval between the fault
inception and the fault clearance of the faulty element from the power system.
For substation and transformer faults, the fault clearing time must not exceed 150ms, while
for cable and overhead lines the maximum fault clearing time allowed is 600ms. These
requirements applied for 33kV, 22kV and 11kV systems for the Main protection relaying
scheme,
For the Backup protection relaying scheme, the maximum fault clearing time shall not
exceed the short-circuit rating of the primary equipment.
Maximum Pickup time, maximum operating time and maximum reset time shall be
standardized not to exceed 50ms.
- 178 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
8) The relays contacts shall be suitably rated for tripping, control and indication purposes
and sufficient number of contacts shall be provided separately for tripping, control and
alarm functions.
9) The relays, whether mounted in panels or not, shall b provided with clearly inscribed
labels describing their rating and application, including at least the following :
a) Function, e.g., Over-current, Under-voltage
b) Model and version, e.g., REL561 V1.2, 7VK512 V1.0
c) Serial number
d) Nominal input ratings of D.C voltage, A.C current and A.C frequency
All Main protection relays shall be able to initiate auto-reclose cycle. For distribution
network, auto-reclose shall also be initiated by Backup protections. A scheme for live line
maintenance purposes shall be also incorporated. In addition, for 33kV system and below,
direct optical fiber connections shall be applied.
- 179 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
Unit protection relays shall have sufficient contacts to initiate the Breaker failure protection
and other protection, control and signaling function and optical fiber shall be used for new
installation.
For Aerial Bundle Cable (ABC) installation, it shall be treated as underground cable feeder.
In addition, direct optical fiber shall be used for tele-protection, while no auto-reclose
scheme shall be applied for underground cable feeder protection.
- 180 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
All other interconnecting equipment such as power cable etc, to the transformer shall be
protected by their relevant protection scheme. All Main protection relays shall be dedicated,
independent from any other relays except for over-excitation protection relay. In addition,
alarm and tripping indications for all types of transformers shall be separated. The LV side
of earthing and local transformers shall be protected by suitable rated fuses.
Intertripping scheme to the remote end shall be provided for complete clearing of faults,
where it is required. In addition, the D.C supply for the Busbar protection scheme at the
busbar protection panel shall be separated from other protection schemes.
It is only proper that coordination study be carried out to verify the proper operation of the
protective equipment. The following general procedure should be followed:
Initially, the DG should submit proposed setting of all relays given the interface short-circuit
contribution from the utility. The DG should set all the protective relays for the protection
of their installation disregarding any coordination with the utility system. The report to the
utility should include:
a) Protection philosophies adopted;
b) Short-circuit limits including making and breaking capacities of equipment - breakers,
cables, lines etc..
c) Transformer heat withstands capability;
d) Generator limits - reactive, active power, field current and voltage limits, over-speed
and under-speed; etc..
e) Documents on characteristics of the relays and fuses employed;
- 181 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
The utility perform coordination with the generator interconnected and the report should
include:
a) The proposed setting and their coordination; and
b) Changes required on the DG plant relay settings and the reason for the changes.
- 182 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
The communication system between the generator plant where the RTU is located and TNB
could be via wire or wireless configuration. Wire configuration shall include lease lines or
telephone lines. Wireless configuration shall include via microwave, satellite or GSM. The
mode of communication to be used shall depend on the siting of the generator plant,
capacity of the generator plant and/or distance of the generator plant to the nearest TNB
main substation (PMU or PPU). Lease line is the preferred option by TNB. Nevertheless,
TNB will advice the generator plant of the mode of communication to be used.
- 183 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
In the case that TNB has to control the generator, the master system installed does not
cater for AGC (automatic generator controller). Therefore, if TNB has to develop this
function and any other associated function in order to meet the requirement, TNB requires
that 10% of the development cost to be charged to the plant generators
- 184 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
13.1 General
This appendix outlines the possible technical contents of ‘Connection Agreement’ or
‘Connection Operation Manual’ to be established and agreed by both the DG Operator and
TNB.
The connection agreement will contain both commercial and technical sections and
information related to the connection of the DG plant. This appendix contains a list of
possible technical information on the DG plant and the network that the DG is connected to.
Generally, this information should describe the ‘as installed’ plant.
13.2.1.1 This section describes the DG plant and its auxiliaries and may include the following:
13.2.1.2 Electrical system diagram – The electrical system diagram should be a high level diagram
showing the electrical system at the connection point, such as a single line diagram.
13.2.1.3 Machine Data – This should include all the relevant machine capability and data such as:
Data on the turbine
Manufacturers and test data of generator impedances and time constants, mechanical.
Block diagrams of all controls and model parameters
Excitation capability
Protection settings and grounding
Settings of each protective device
Grounding types and values
Generator Transformer data including tap changing facilities
13.2.1.4 Fault level contribution – The fault level infeed into the network should include
contribution from generators and any induction motors.
13.2.1.5 Auxiliary system data – Data on large items of equipment should be included such as
large motors, switchgear capability, auxiliary transformers and interconnecting cables.
13.2.1.6 Control settings – control settings such as interlocking systems, synchronizing systems
should be described and where necessary details provided.
- 185 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
13.2.1.7 Operating regime - The DG plant operating regime should be described and may include
description of:
• Short term Parallel to network
• Intermittent operation
• Continuous operation
• Standby generation
13.2.2.1 List of standards used in the design of the facility and network. It is important that the
current revisions of the standards at the time of design and installation are stated.
13.2.3.1 The metering system should be described. Metering locations and a single line diagram
should be included. The description should include:
- Main and Check Meters
- MW and Mvar meters
- Operational and Tariff Metering
13.2.4.1 This section should list out the technical conditions and any agreed requirements for the
connection. Items include:
13.2.4.3 Excitation Controls – The agreed control regime including agreed settings where
appropriate such as
Power Factor
Voltage control
Var Control
13.2.4.4 Constraints – Agreed constraints and description of the conditions for constraints should
be included here. If the connection has firm and/or non firm offers, the conditions of each
should be described.
13.2.4.5 Max Import – If necessary, the agreed levels of imports, such as Standby and Top Up
supplies should be included. Where necessary, the conditions for the agreed levels may be
included. The levels should include Maximum MW and Maximum Mvar.
- 186 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
13.5.2Communication Facilities
13.5.2.1 This section should describe all the communication facilities and the list of available
indications and control points. It should also include any voice communication equipment.
Items may include:
• SCADA control points
• Remote indications
• Output dispatch controls if any
13.5.3Electricity Characteristics.
13.5.3.1 This section describes the Distribution network characteristics and should include items
such as:
13.5.3.3 Maximum Network Design System fault levels – This is normally the designed capability
of the Distribution network at the point of connection.
Normal configuration
Outage configuration
13.5.3.4 Current System Fault Levels – This is the normal fault level at the connection point. It
should be made clear whether this fault level includes the DG plant.
Normal Configuration
Outage Configuration
13.5.3.5 System Drawing – a system drawing such as a single line diagram at the connection point
should be included. It should have sufficient details as necessary, including protection
system details relevant to the DG plant.
13.5.3.6 Interface protection system – The network protection system relevant to the connection
point should be described. It should include any interlocking facilities implemented.
13.5.3.7 Operating limits – Any other agreed operating limitations should be described. This may
include description of operation such as short term paralleling operation.
13.5.3.8 Auto-reclosing facilities – Any auto reclosing facility that may affect the DG plant should
be described.
- 187 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005
Tenaga Nasional Berhad TNB Research
- 188 –
1_DG_Technical_GUIDEBOOK_Edition_1_MARCH_2005