Technical Specification For HVAC 1of 2

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 39
At a glance
Powered by AI
The specification outlines the scope of work for installing a central HVAC system including various equipment like chillers, pumps, air handling units etc. and details regarding piping, insulation, valves and other components.

The main components include air cooled chilling machines, pumping systems, air handling units, fan coil units, hot water generator, centrifugal and propeller fans, motor control centers and associated piping, ducting, insulation etc.

The different types of valves mentioned are butterfly valves, gate valves, globe valves, check valves, balancing valves, miscellaneous valves like gauge cocks and drain valves. Their purposes include isolation, throttling of flow, non-return of flow, pressure measurement etc.

5.

TECHNICAL SPECIFICATION FOR HVAC SYSTEM

1. General :

These are special conditions to the contract and intended for the same.

2. Scope of works :

The general character and the scope of work to be carried out under this contract
is illustrated in drawings, specifications and the schedule of the quantities. The
contractor shall carry out and complete the said work under this contract in every
respect in conformity with the contract documents and with the direction of and to
the satisfaction of the owner’s site representative. The contractor shall furnish all
labor, materials and equipment as listed under the schedule of quantities and
specified otherwise, transportation and incidentals necessary for supply,
installation, testing and commissioning of the complete air conditioning system as
described in the specifications and as shown on the drawings. This also includes
any material, equipment, appliances and incidental work not specifically
mentioned herein or noted on the drawings/documents as being furnished or
installed. But which are necessary and customary to be performed under this
contract. The central heating, ventilating and air conditioning shall comprise of
the following :

a) Supply and installation of the screw compressor type air cooled chilling
Machines
b) Pumping Systems.
c) Air Handling Units (AHUs).
d) Fan Coil Units (FCUs).
e) Hot water Generator.
f) Centrifugal and propeller fans for mechanical ventilation.
g) Motor Control Centers.
h) Expansion tank along with the accessories.
i) Chilled water, hot water, condensate drain piping inclusive of all valves,
fittings and chilled/hot pipes insulation .
j) Sheet metal ducts inclusive of external insulation, acoustic lining, canvas
connection, volume Control Dampers and smoke & fire dampers as
specified.
k) Supply of return air registers and diffusers.
l) Insulation of pipes, pumps and tanks.
m) Vibration isolation for HVAC equipments
n) Automatic Controls and instruments.
o) Wiring and earthing from MCC panels to various refrigeration, air-
conditioning and mechanical ventilation equipment control wiring and
interlocking.
p) Cutting holes, chases and the likes through all types of non structural
walls and finishing for all type of wall crossings, including sealing,
framework, fire proofing, providing sleeves, cover plates, making good
structure and finishing to an approved standard.
q) Balancing, testing and commissioning of the entire HVAC and mechanical
ventilation installations.
r) Test report, list of recommended spares, as installed drawings, operation
and maintenance manuals for the entire HVAC installations.
s) Training of owner’s staff.
u) Integrated Building Management system allied works for field devices.

3. Associated Civil Works:

Following civil works associated with HVAC installations shall be excluded in the
scope of the contract.
i. RCC foundation for water chilling machines/Hot water Generator with
angle iron framework at the edges to protect these from damage.
ii. PCC floating foundation blocks for pumps and centrifugal fans with angle
iron framework at the edges to protect these from damage.
iii. PCC foundation blocks for Motor Control Center with angle iron frame
work at the edges to protect these from damage.
iv. PCC foundation for Pot Strainers.
v. PCC foundation blocks for all Air Handling Units.
vi. Airtight fire doors with minimum 11/2 Hr fire ratings for plant Room, AHU
rooms, Fan Rooms and other equipment Rooms.
vii. Water proofing of the floors of AHU rooms, air-washer rooms and fan
rooms.
viii. Masonry drain channels and sumps with CI gratings in AC plant Room
including provision for sump pump and disposal.
ix. Supply and fixing of GI/wooden frames for fixing the grilles in masonry
walls.
x. Supply and fixing of GSS frames for mounting of grilles/diffusers in false
ceiling /boxing.
xi. Thermal Insulation of terraces above air-conditioned area exposed to sun.

4. Associated Services works :

4.1. All associated electrical works listed below are excluded from the scope
of this contract. These shall be installed by other agencies in accordance
with the shop drawings and under supervision of the air conditioning
contractor.
i. Providing power supply with earthing at the incoming of the control panel
in A/C plant room.
ii. Providing 15 amps power outlet within 3 meters reach of fan coil units at
locations called for on air-conditioning contractor’s shop drawings.
iii. Providing 15 amps power outlet within 3 meters reach of single phase fans
at locations called for on air-conditioning contractor’s shop drawings.
iv. Providing wiring and earthing for the sump pumps in the air-conditioning
plant room.
4.2 All associated plumbing works listed below are excluded from the scope of
this contract. These shall be installed by other agencies, in accordance
with the approved shop drawing of and under the direct supervision of the
air-conditioning contractor.
i. Providing soft make up water at cooling towers, air-washers, humidifiers
and at chilled water /hot water expansion tanks.
ii. Providing sump pump and necessary piping for drainage of air-
conditioning plant room and other machine rooms at ground level.
iii. Providing for drains/traps in cooling tower area and air handling unit
rooms.
iv. Make up water for the chilled water and the hot water circuit.

5. Project Execution and management:

The contractor shall ensure that senior planning and execution personnel from
his organization are assigned exclusively for this project. They shall have
minimum 10 years experience in this type of installations.

For quality control & monitoring of workmanship, contractor shall assign at least
one full time engineer who would be exclusively responsible for ensuring strict
quality control ,adherence to the specifications and ensuring top class
workmanship for the air-conditioning installation.
The contractor shall arrange to have mechanized and modern facilities for
transportation of materials to the place of installation for speedy execution of
work.

6. Performance Guarantee :

The Contractor shall carry out the works in accordance with the drawings,
specifications, schedule of the quantities and other documents forming part of the
contract. The contractor shall be fully responsible for the performance of selected
equipment (installed by him) at the specified parameters and for the efficiency of
the installations to deliver the required end results. The contractor shall
guarantee that the HVAC system as installed shall maintain the inside conditions
in the air-conditioning spaces as described under the Basis of Design in the
specifications. The guarantee shall be submitted in the performa sheet. Complete
set of architectural drawings are available in the architect/Consultants office and
reference may be made to same for any detail or information. The contractor
shall also guarantee that the performance of various equipment individually, shall
not be less than the quoted capacity ,actual power consumption shall not exceed
the quoted rating, during testing and commissioning ,handling over and
guarantee period.
7. Bye–Laws and Regulations :

The installations shall be in conformity with the by-laws and regulations and
standards of the local authorities concerned, in so far as these become
applicable to the installations. But if these specifications and drawings call for a
higher standard of material and /or workmanship than those required by any of
the above regulations and standards then these drawings and specifications shall
take precedence over the said regulations and standards. However if the
drawings and specifications require something which violates the bye-laws and
regulations, then the bye-laws and regulations shall govern the requirement of
the installations.

8. Fees and permits :

The contractor shall obtain all permits/licenses and pay for any or all fees
required for inspection, approvals and commissioning of their installations.

9. Drawings :

The HVAC drawings listed herewith , which may be issued with tenders are
diagrammatic only and indicate arrangement of various systems and the extent
of works covered in the contract. These drawings indicate the points of supply
and termination of services and broadly follows the routes to be followed. Under
no circumstances shall dimension be scaled from the drawings. The
architectural/interior drawings and details shall be examined for exact location of
the equipment, controls, grilles and diffusers.

The contractor shall follow the tender drawings in preparation of his shop
drawings and for subsequent installation work. He shall check the drawings of
other trades/services to verify spaces in which his works shall be installed.

Maximum headroom and space conditions shall be maintained at all points.


Where head room appears inadequate the contractor shall notify
architect/consultant/owner’s site representative before proceeding with the
installations. In case installation is carried out without notifying the works shall be
rejected and the contractor shall rectify the same at his own cost. The contractor
shall examine all the architectural, structural, plumbing , electrical and other
services drawings and check the as built works before starting the work , report
to the owners site representative of any discrepancies and obtain clarification.
Any changes found essential to coordinate his work with other services and
trades, shall be made with prior approval of architect/consultant/owner’s site
representative without additional cost to the owner. The data given in the
drawings and specifications as exact as could be procured , but its accuracy is
not guaranteed.
10. Technical Datas :

Each tenderer shall submit along with his tender, the technical data for all items
listed in the indicated fromat. Failure to submit complete data with the tenders
may result in summary rejection of the tender.

11. Shop Drawings :

11.1 All the shop drawings shall be prepared on computer through Autocad
system based on the architectural drawings, site measurements and
interior designers drawings. All heat load calculation shall be done within
eight weeks of the award of the contract, contractor shall furnish for the
approval of the architect /consultant two set of detailed shop drawing of all
equipment and material including the layouts of the plant rooms, AHU
rooms, Fan rooms, Cooling Towers, fan coil units, ventilation fans.
Detailed ducting drawing showing exact location of supports, flanges,
bends, tee connections, reducers, guide vanes, silencers, distribution
grids, Volume control dampers, collars, grilles, diffusers, detailed piping
drawing showing exact location and type of supports, valves, fittings etc.
acoustic lining and external insulation details for ducts, pipe insulation etc.
Electrical panels inside/outside views, power and control wiring
schematics, cable trays, supports and terminations. These shop drawings
shall contain all information required to complete terminations. These shop
drawings shall contain all the information required to complete the project
as per specifications and as required by the Architect/Consultant/Owners
site representative. These drawings shall contain details of constructions,
size arrangement, operating clearances, performance characteristics and
capacity of all items of equipment, also the details of all related items of
work by other contractors. Each shop drawing shall contain tabulation of
all measurable items of equipment/material/works and progressive
cumulative totals from other related drawings to arrive at a variation in
quantity statement at the completion of all shop drawings. Minimum 7 sets
of drawings shall be submitted after final approval along with their floppies.

Each item of equipment/material proposed shall be a standard catalogue


product of an established manufacturer strictly from the manufactures listed
in Appendix and quoted by tenderer in technical data part of Appendix .

When the Architect/Consultant makes any amendment in the above


drawings, the contractor shall supply two fresh sets of drawings with the
amendments duly incorporated along with check prints for approval. The
contractor shall submit further 7 sets of the shop drawings
When the Architect/Consultant makes any amendments in the above
drawings, the contractor shall supply two fresh sets of drawings with
amendments duly incorporated along with check prints for approval. The
contractor shall submit further seven copies of shop drawings to the owners
site representative for the exclusive use of the owner’s site representative
and all other agencies. No material or equipment may be delivered or
installed at the job site until the contractor has in his possession the
approved shop drawing for the particular material/equipment/installations.
11.2 Shop drawings shall be submitted for approval four weeks in advance of
planned delivery and installation of any material to allow
Architect/Consultant ample time for scrutiny. No claims for extension of time
shall be entertained because of any delay in works due to his failure to
produce shop drawings at the right time in accordance with the approved
programme.
11.3 Manufacturers drawings, catalogues, pamphlets and other documents
submitted for approval shall be in four sets. Each item in each set shall be
properly labelled, indicating the specific services for which the material
/equipment is to be used, giving reference to the governing section and
clause number and clearly identifying in ink the items and the operating
characteristics. Data for general nature shall not be accepted.
11.4 Samples of all materials like grilles, diffusers, controls, insulation, pre-
molded pipe section, control wires etc. shall be submitted to the owners site
representative prior to procurement. These will be submitted in 2 sets of
approval and retention by owners site representative and shall be kept in
their site office for reference and verification till the completion of the project.
Wherever directed a mockup or sample installation shall be carried out for
approval before proceeding for further
Installations.
11.5 Approval of shop drawings shall not be considered as a guarantee of
measurement or that of a building dimension. Where drawings are approved
said approval doesn’t mean that the drawings supercede the contract
requirements, nor does it in any way relieve the contractor of the
responsibility or requirements to furnish material and perform as required by
the contract.
11.6 Where contractor propose to use an item or equipment other than that
specified or detailed on the drawing which requires any redesign of the
structure, partitions , foundations, piping, wiring or any other apart of the
mechanical ,electrical and architectural layouts ,all such redesign and all
new drawings and detailing required therefore shall be prepared by the
contractor at his own expenses and gotten approved by the
architect/consultant/owners site representative. Any delay on such account
shall be at the cost and consequences to the contrcator.
11.7 HVAC contractor shall prepare coordinated service shop drawings based on
the drawings prepared by electrical, plumbing & low voltage contractors to
ensure adequate clearances are available for installation of service for each
trade.
Where the work of the contractor has to be installed in close proximity to or
will interfere with the work of other trade he shall assist in working out
space conditions to make a satisfactory adjustment. If so directed by the
owner’s site representative , the contractor shall prepare composite working
drawings and sections at a suitable scale, not less than 1:50 clearly showing
how his work is to be installed in relation to work of the other trades. If the
contractor installs his works before coordinating with other trades or so to
cause any interference with work of other trades he shall make all
necessary changes without extra cost to the owner.
11.8 Within four weeks of the approval of the relevant shop drawings the
contractor shall submit four copies of a comprehensive variation in quantity
statement and itemized price list of recommended (by manufacturer)
imported and local spare parts and tools covering all the
materials/equipment in the contract. The project manager shall make
recommendation to owner for acceptance of anticipated variation in contract
amounts and also advise Owner to initiate action for procurement of spare
parts and tools at the completion of project.

12. Quite Operation and Vibration Isolation :

All equipment shall operate under all conditions of load without any sound
and vibration which is objectionable in the opinion of the owner’s site
representative.
In case of rotating machinery sound or vibration noticeable outside the room
in which it is installed or annoyingly noticeable inside its own room shall be
considered objectionable. Such condition shall be corrected by the
contractor at his own expenses. The contractor shall guarantee that the
equipment installed shall maintain the specified NC levels.

13. Accessibility :

The contractor shall verify the sufficiency of the size of the shaft openings,
clearances in cavity walls and suspended ceiling for proper installation of his
ducting and piping. His failure to communicate insufficiency of the same.
The contractor shall locate all equipment which must be serviced ,operated
or maintained in fully accessible positions. The exact location and size of
all access panels required for each concealed damper ,valves or other
devices requiring attendance shall be finalized and communicated in
sufficient time to be provided in the normal course of work. Failing this the
contractor shall make all necessary changes and repairs at his own
expenses. Access panel shall be standardized for each piece of
equipment/device/accessory and shall be clearly nomenclatured / marked.

14. Materials and equipment :


All materials and equipment shall conform to the relevant Indian standards
and shall be of the approved make and design. Makes shall be strictly in
conformity with the list of approved manufactures.

15. Manufactures Instructions :


Where manufacturer has furnished specific instructions relating to the
material/equipment used in this project ,covering points specially not
mentioned in these documents, such instructions shall be followed in all
cases.

16. Electrical Installations :

The electrical work related to air-conditioning services , shall be carried out


in full knowledge of ,and with complete coordination of contractor . The
electrical installation shall be in total conformity with the control wiring
drawings prepared by the contractor and approved by the architect
/consultant .All air-conditioning equipments shall be connected and tested in
the presence of an authorized representative of the contractor.

The air-conditioning system shall be commissioned only after the contractor


has certified in writing that the electrical installation work for air-conditioning
services has been thoroughly checked, tested and found to be totally
satisfactory and in full conformity with the contract drawings ,specifications
and manufacturers instructions . It is to be clearly understood that the final
responsibility for the sufficiency, adequacy and conformity to the contract
requirement s of the electrical installation work for air-conditioning
services ,lies solely with the contractor.

17. COMPLETION CERTIFICATE :

On completion of the electrical installation for air-conditioning, a certificate


shall be furnished by the contractor , counter signed by the licensed
supervisor ,under whose direct supervision the installation was carried
out .This certificate shall be in the prescribed form as required by the local
authority .

The contractor shall be responsible for getting the entire electrical


installation for air-conditioning system duly approved by the local authorities
concerned and shall bear expenses, if any in connection with the same.

18. BALANCING , TESTING AND COMMISIONING

Balancing of all air and water systems and all tests as called for the
specifications shall be carried out by the contractor through a specialist
group, in accordance with the specifications and ASHRAE guidelines and
standards. Performance test shall consist of three days of 10 hrs each
operation of each season .Witness testing of major equipment at factory
with two personnel from owners/ consultant shall be included .

The results for summer , monsoon and winter air conditioning in


quadruplicate ,shall be submitted for scrutiny .Four copies of the certified
manufacturers performance curves for each piece of equipment
,highlighting operational parameters for the project ,shall be submitted
along with the test certificates. Contractors shall also provide four copies
of record of all safety and automatic control settings for entire installation .

The installation shall be tested again after removal of defects and shall be
commissioned only after approval by the owners site representive. All
tests shall be carried out in presence of the representatives of the
architect/consultant and owner’s site representative.

19. COMPLETION DRAWINGS

Contractor shall periodically submit completion drawings as and when


work in all respects is completed in a particular area . These drawings
shall be submitted in the form of two sets of floppies/CD’s and four
portfolios (300 x 450mm ) each containing complete set of drawings on
approved scale indicating the work as installed .These drawings shall
clearly indicate complete plant room layouts ,location of wiring and
sequencing of automatic controls ,locations of all concealed piping ,valves,
controls, dampers, wiring and other services .Each portfolio shall also
contain consolidated control diagrams and technical literature on all
controls. The contractor shall frame under glass , in the air-conditioning
plant room , one set of these consolidated control diagrams.

20. Operating Instructions & Maintenance Manual :

Upon completion and commissioning of part HVAC system the contractor


shall submit a draft copy of operating instructions, maintenance schedules
and log sheets for all system and equipment included in this contract. This
shall be supplimentry to manufacturers operating and maintenance
manual. Upon approval of the draft the contractor shall submit four
complete bound set of typewritten operating instructions and maintenance
manuals. One each for retention by consultant and the clients
representative and two for owners operating personnel. These manuals
shall also include basis of design ,detailed technical data for each piece of
equipment as installed ,spare parts manual and recommended spares for
3 years period of maintenance of each equipment.

21. On Site Training :

Upon completion of all works and all tests, the contractor shall furnish
necessary operator’s labor and helpers for operating the entire installation
for a period not less than two weeks of ten hours each to enable the
owners staff get aquainted with the operation of the system. During this
period the contractor shall train the owners personnel in the operation,
adjustment and maintenance of all equipment installed.
22. Maintenance during defects Liability Period :

22.1 Complaints :

The contractor shall receive calls for any or all problems experienced in
the operation of the system under this contract, attend to these within four
hours of receiving the complaints and shall take steps to immediately
correct any deficiencies that may exist.

22.2 Repairs :

All equipment that require repairing shall be immediately serviced and


repaired. Since the period of mechanical maintenance runs for two years
concurrently with the defects liability period , all replacement parts and
labor shall be supplied promptly free of charge to the owner.

23. Uptime Guarantee :

The contractor shall guarantee for the installed system an uptime of 98%. In case
of shortfall in any month during the defects liability period, the defects liability
period gets extended by a month for every month having shortfall. In case of
shortfall beyond the defects liability period the contract shall get extended by a
month for every month having the shortfall and no reimbursement shall be done
for the extended period.

The contractor shall provide log in the form of diskettes and bound printed
comprehensive log book containing tables for daily record of all temperature.
pressure, humidity, power consumption starting and stopping times for various
equipment, daily service rendered for the system alarms, maintenance records of
unusual observations etc.
Contractor shall also submit preventive maintenance schedule.

Each tenderer shall submit along with the tender, a detailed operation assistance
proposal for the owners site representative / consultant’s review. This should
include the type of service planned to be offered during the defects liability period
and beyond. The operation assistance proposal shall give the details of the
proposed monthly reports to the management.

The tenderer shall include a list of such project where such an operation
assistance has been provided.

24. Operation and Maintenance (Optional) :

Contractor may be required to carry out the HVAC installation for a period of two
years from the date of commissioning and handing over of the entire system, i.e.
during the defects liability period . Further he may also be required to carry out
operation and all inclusive maintenance of the entire system for a period of three
years beyond the defects liability period. Cost of such proposal shall be quoted
separately as per the BOQ.

25. Operation Contract :

i) 24 hours a day, year round


ii) All standby equipment to be operated as per mutually agreed program.
iii) Proper entry and upkeep of relevant log books.
iv) Maintain complaint register. Submit weekly reports.
v) Proper housekeeping of all areas under the contract.
vi) Prepare daily consumption report and summary of operation.

26. Terms of Payment :

i) Monthly at the end of the month on pro-rata basis.

27. All inclusive maintenance Contract :

a) Routine preventive maintenance schedule to be submitted.


i) Schedule to cover manufacturers recommendations and/or common
engineering.
practice (for all plant and machinery under the contract)
ii) Plant and history card giving full details of equipment and frequency of
check and overhaul.
iii) Monthly status report.
iv) Entire HVAC installation to be painted in fourth year (from commissioning)
before the expiry of operation and maintenance contract.

b) Uptime during maintenance Contract :

i) 98% uptime of all system under contract.


ii) Uptime shall be assessed every month and in case of shortfall during any
month the contract shall be extended by a month.
iii) There shall be no reimbursement for the extended period.
iv) Breakdown shall be attended within ten hours of reporting.
v) Spare compressor/motor assembly shall be made available within seven
calender days in case of total breakdown/burnout.

c) Manpower :

i) Adequate number of persons to the satisfaction of the owner’s site


representative shall be provided including relievers.
ii) Statuary requirements of EPF, ESIC and other applicable labor legislations
to be complied with : and monthly certificate to that effect be submitted.
iii) Duty allocation and roaster control shall be contractors responsibility.
iv) No overtime shall be paid by the owner for reasons whatsoever.

d) Shutdowns :

i) Routine shutdowns shall be permitted only during winter season.


ii) Contractors shall be at liberty to carry out routine maintenance as and
when required but with due permission of the Owner’s representative.

28. Soft water and power requirement :

The contractor shall submit with their tender ,the requirement of soft make up
water and power at each of their equipment/system wise/floor wise/section wise.

End of Section
SPECIFICATIONS

Section 2
SYSTEM DESIGN DATA

A. DESIGN PHLOSOPHY;
HVAC system in the Hospital/healthcare stands out for its complexities and
stringent demands on indoor air quality, airflow patterns, cross contamination
control, odour control and noise control etc. The hospital air conditioning system
further demands more care in energy aspects due to its longer hours of
operations.

The following factors have been considered for the design of hospital HVAC
services:

1 Individual and quickly responding temperature control for each area.


2 Draft-free air distribution.
3 Labs, kitchen, isolation rooms and toilet exhaust.
4 Fresh air or makeup air supply to maintain IAQ.
5 Humidity control
6 Acceptable noise level.
7 Separate AHU’s for different zones to avoid mixing of air and operational
flexibility.

To effectively design an HVAC system for this hospital building, the design is
made as per the building layout and the departmental areas or zones. These
zones are broadly classified as follows.

1. Inpatient Wards/ ICUs : For residential patient.

2. Clinical Services Areas : Surgical department,Radiology,X-ay


MRI/CAT Scan, Laboratories.

3. Administration/Faculty : Office,conference and staff facilities.


/academic areas examination halls/tutorials/professors

ZONING :

From the isolation point of view, the building area will be segregated into the
following zones.
 Sensitive areas like operation theatres and intensive care units, labs, X-
Ray, MRI etc.
 Treatment and recovery areas, wards and administrative areas

The individual requirements of the above will be considered for designing the
system

B. General :
The system design , basis of design, requirements and other relevant data
are outlined in this section. The detailed specifications and specific
requirements are outlined in the subsequent sections.

C. Location:

The proposed ESIC hospital renovation and PGI is coming up Maniktala


Kolkata (West Bengal).

D. Scope of works :

The work proposed under this tender includes providing and fixing air-
conditioning, heating and ventilation systems for the above work.

Providing and fixing at site all main equipment associated with air-
conditioning and ventilation for the above.

To execute all incidental work at site including material supply at site


associated with the system asked in the specifications.

Nature of such works will be sheet metal ductwork, air distribution devices
viz. grilles and diffusers , copper refrigerant piping and its insulation , drain
piping etc., incidental civil works, incidental electrical works ,cable , control
panel etc. at site for all manufactured items at works and also items
fabricated at site.

Routine Testing, pressure testing of fabricated components,


commissioning of complete plant at site.

Performance Testing at site of complete air-conditioning, air-cooling and


ventilation system / installations at site.

E. Basis of Design :

Station Name - Kolkata (West Bengal)

Latitude - 22.32°North

Altitude - 6 Metre from MSL


Daily Range - 20°F

Out side Conditions Summer : Dry bulb temperature 37.8C/100F


Wet Bulb Temperature 28.3C/83F
Monsoon: Dry bulb temperature 32.2C/90F
Wet Bulb Temperature 28.3C/83F
Winter : Dry bulb temperature 13.3C/58F
Wet Bulb Temperature 8.8C/48F
F. Inside Design Conditions :

Inside Design Conditions


Sr. No. Space Name -----------------------------------------------------------------------
TemperatureRH% Pressure type
=============================================================
1. Sample collection °C
Treatment Rooms 23.3A1.1 50A5% (A)

2. X-ray/MRI/CAT Scan 23.3A1.1 50A5% (-)

3. Labs 23.3A1.1 50A5% (-)

4. Administration/
Conferences/academics 23.3A1.1 50A5% (-)

5. Pre/Post IPD 22.2A1.1 50A5% (+)

6. Intensive Care Unit 22.2A1.1 50A5% (+)

7. Operation Theatres 21.0A1.0 50A5% (+)

8. Doctors Rest Rooms 23.3A1.1 50A5% (A)

9. Clean Utilities 23.3A1.1 50A5% (-)

10. Patient Room 23.3A1.1 50A5% (A)


=============================================================

Ventilation : 10 cfm per person

Lighting Load : 2w/ft2 in all areas ,3w/ft2 in OTs


Roof Insulation : All the exposed roof to be
insulated with 50 thick
expanded polystyrene
insulation / or equivallant
insulation

Toilets/Labs - 10 air changes per hour

Kitchen -10 air changes per hour

Dirty utility Room - 10 air changes per hour

Based on the area wise detailed heat loads of the above design data and the
details the estimated loads are summarized as below :
=============================================================
Sr.No. Area Description Area (ft2) Load TR
===============================================================
1. Basement Floor 21564 102
2. Ground Floor 19867 117
3. First Floor 19562 108
4. Second Floor 18338 125
5. Third Floor 19596 142
6. Fourth Floor 19616 110
7. Fifth Floor 19616 120
8. Sixth Floor 6975 48
=============================================================
Total 145134 ft2 873 TR
System Design :

Heating,ventilation and Air-conditioning System:

The total air-conditioning load for the above areas works out to be 873 TR. It is
proposed to install central chilled water air cooled type air-conditioning system to
provide year round thermal environmental control for the above areas. It is
proposed to use 4 Nos. 290 TR Cooling Capacity air cooled Screw compressor
type water chilling Machines (one standby), 2 nos 300 KW capacity hot water
generator for heating with four nos. chilled water primary pumps (one stand by) ,
four nos. chilled water secondary pumps(one standby), three nos. hot water
pumps(One standby), Air Handling Units, TFA units, HRV units and Fan coil units
as per the requirements at various floors/areas.

The plant shall be installed at the Plant space allocated in Ground floor and
chilled water from this plant shall be supplied to various AHUs at the basement,
ground floor, first floor, second floor, third floor, fourth floor, fifth floor & sixth floor
areas as per requirements and as shown in the drawings. The system shall be
complete with electrical panel boards, power cabling, control cabling, earthing
and controls.

Ventilation System :

The toilet areas shall be ventilated with inline fans, propeller fans as per the
CFM requirements.

The system shall be complete with electrical panel boards, power cabling, control
cabling, earthing and controls.

End of section
Section 3
AIR COOLED SCREW PACKAGE CHILLING MACHINE

3.1 SCOPE

The scope of this section comprises supply, erection, testing and


commissioning of Air cooled screw package chilling Machines conforming
to these specifications and in accordance with the requirement of
Drawings and schedule of Quantities.

3.2 TYPE

The chilling machine shall be with hermetic/semi hermetic type (and not
open type) compressor, consisting of mono/ twin screw compressor,
squirrel cage induction motor, closed transition star-delta starter, air cooled
condenser, shell and tube chiller, refrigerant piping, micro processor
control, all mounted on a steel frame and control power wiring/cabling.

3.3 ACTUAL CAPACITY

Actual refrigeration capacity of chilling machine shall be as shown on


drawings and in schedule of Quantities.

3.4 AIR COOLED PACKAGE CHILLER

The packaged air cooled liquid chiller will consist of accessible


hermetic/semi- hermetic, direct driven screw compressor with independent
circuits evaporator, condenser, microprocessor based control and a unit-
mounted motor starter, refrigerant charged, factory run-tested and rated in
accordance with ARI 550-90 and ready for operation.

3.5 SCREW COMPRESSOR

The compressor will be mono/ twin screw (helical Rotary) type design for
positive displacement for use with ozone friendly refrigerant conforming to
prevailing international standard.

During function, it will be pure rotary motion providing uniform gas flow,
even torque and positive displacement to ensure vibration-free operation
over a wide range of operating conditions.

The rotor tip clearance will be optimized to reduce leakage between high
and low pressure cavities during compression and also to achieve high
energy-efficiency.
The capacity controlling device shall be arranged for unloaded start power
consumption shall proportionately reduce with the stepping down of
compressor capacity to as low as 25% of full load in direct response to
refrigeration load changes.

3.6 COMPRESSOR MOTOR ASSEMBLY

The screw compressor will have, accessible hermetic direct drive motor
with 2950 rpm (or as per manufacturer’s design speed), working on 415V+
10%,3 phase, 50 HZ power supply, as normally available in India. The
motor will be squirrel cage two pole induction type will be section gas-
cooled. Due consideration will be given while deciding the protection
devices to take care of probable voltage fluctuations prevailing at site.

The system will be provided with oil separator and filtration devices.

3.7 CONDENSER

Condenser coil shall be air cooled with integral sub-cooler constructed of


aluminum fins mechanically bonded to seamless copper tubes which shall
be then cleaned, dehydrated and sealed.

Condenser fans shall be direct driven propeller/axial type, with totally


enclosed air over motor, having class ‘F ’ insulation and IP 54 protection,
discharging air vertically upwards and shall be equipped with the following
features.

a. Permanently lubricated bearings.


b. Steel wire safety guards duly coated with PVC
c. Statically and dynamically balanced fan blades.

Air cooled condenser coil shall be leak tested at 150 Psig (1034 KPa) and
pressure tested at 450 Psig (3103 KPa).

3.8 CHILLER (COOLER)

Chillers shall be direct- expansion/flooded type comprising mild steel shell,


integrally finned copper tube Rolled into tube sheets, cast iron water
headers, liquid line connection, suction header, drain plug and purge
valves.
Shell and tube type chillers shall have the following components:

a. SHELL AND WATER BOXES


The chiller shell shall be formed of carbon steel , provided with
cast iron water boxes having standard flange type connections
suitable for 10 KG .per sq.cm (150 psig ) working and 21 KG/sq.cm
(300 PSIG) test pressure. Water boxes shall be provided with drain
connections and shall be easily openable for tube cleaning.
Suitable tappings shall be provided in the water boxes/water lines
for temperature control bulb and gages.

b. TUBE SHEETS

A thick steel tube sheet shall be welded to each end of the shell
and shall be drilled and reamed to accommodate tubes. Annular
grooves in the tube sheets shall prevent leakage at the tube sheet
bond. Tube support sheets shall be placed along the length of the
shell to avoid relative motion between the tubes.

c. TUBES

12.5 to 19 mm dia. Seamless copper tubing, not less than 24G wall
thickness, shall be used for evaporator surface. Tube shall be rolled
into the tube sheets and shall pass through intermediate supports
so that the refrigerant side of the evaporator shall be leak free and
there shall be no relative motion between tubes and tube supports.
Each tube shall be individually replaceable.

d. INSULATION

The chiller shell be covered with closed cell insulation material.

Salient features of the chiller will be as briefed below :

a. It will be shell be shell-and tube type with removable heads .

b. Tubes shall be internally enhanced seamless-copper type rolled into tube


sheets.

c. It will be equipped with victaulic- type fluid connections.

d. Shell be insulated with closed- cell insulation material.

e. Design shall incorporate minimum 2 nos. independent direct expansion


refrigerant circuits.

f. Cooler (Chiller) shall be tested and stamped in acco-dance with ASME


Code for a refrigerant working side pressure of 278 Psig (1916 KPa).
Cooler shall have a maximum fluid –side pressure of 300 psig (2068 KPa).

3.9 REFRIGERANT PIPING AND COMPONENTS


Refrigerant piping and fittings inter connecting compressor, condenser and
chiller shall be all copper and valves shall be brass/ gun metal
construction as explained in section ‘PIPING’

Refrigerant circuit components shall include hot gas muffler, high side
pressure switch, liquid line shut off valves, suction and discharge shut off
valves, filter drier moisture-indicating sight glass, electronic expansion
valve and compressor oil.

3.10 Salient features of the Cabinet will be :

a. Frame shall be of heavy-gage galvanized steel members.

b. Cabinet shall be galvanized steel casing with a pre-painted finish.

c. Cabinet shall be capable of withstanding 500-hour salt spray test in


accordance with the ASIMB-117 standard.

d. The assembly shall be installed outdoor and should, therefore,


have adequate weather protection/resistance.

3.11 COTROLS

a. Unit Control Module

The unit shall be provided be with microprocessor control system for air
cooled Rotary chiller with latest chiller control technology.

It shall have control logic with the Clear Lauguage Display which will have
various functions that allow the operator to read unit information and
adjust set points. The Clear Language Display panel will have sufficient
keys (normally 15 nos.) The read –out screen shall be a four lines ,20
character liquid crystal with a backlight. The backlight shall allow the
operator to read the display in low – light conditions.

b. Unit Control Module Features.

Equal Compressor Sequencing


The control system shall maximize both compressor and motor life by
equalizing the number of starts and the operating hours. The UCM will
start the compressor with the least number of starts and turn off the
compressor with the most operating hours, equalizing starts and running
hours, This will provide equal compressor wear to various units.
Chiller Flow Protection

The in-built protection will automatically detect a no water flow condition.

c. Chiller System Logging

The UCM will display data required to log the chiller system. The following
information will be available as standard feature with the Air-Cooled
Rotary Chiller microprocessor.

- Entering and leaving chilled water temperatures


- Ambient air temperature
- Evaporator and condenser refrigerant temperatures and
pressures.
- Compressor suction temperature.
- Percent line voltage
- Compressor starts and running hours
- Active set points;
Chilled water set point
Current limit set point
Low ambient lockout set point
- Over 90 diagnostics: and operating conditions
- Part failure diagnostics:
Water temperature sensors
Refrigerant temperature sensor
Compressor contactors

d. Remote Display Panel

The system shall be provided with a twisted pair connection to an optional


remote display panel. With this provision it will be possible to control chiller
operation from the remote panel similar to the control interface on the
chiller itself , and it will be possible to turn ‘On’ Or ‘Off’ change the chilled
water set point, and display all operating and diagnostic condition from this
panel. The remote display panel shall be mounted indoors so that it can
be accessed without the need to go to the chillers plant room/site.

Remote clear language display will have the ability to control multiple
units. In the multiple unit configuration, the Remote Clealer Language
Display Panel will have the capability to communicate with upto four units.
Each unit will require a separate communication link with the Remote
display Panel.

e. Interface To The Building Management system


The system should have provisions and facility for interfacing the chiller
with building management systems:
Chiller inputs will include:
- Chiller enable/disable
- Circuit enable/disable
- Chilled water set point
- Current limit set point
- Chiller outputs will include:
- Compressor running indication
- Alarm indication (for each circuit)
- Maximum capacity

3.12 QUALITY ASSURANCE (AIR COOLED SCREW PACKAGE CHILLERS)

a. Chillers shall be rated in accordance with parameters stipulated in


specifications and schedule of quantities. Pressure vessels shall be
designed, constructed, tested and complete with safety devices in
accordance with ANSI/ASHRAE 15-1989 Safety Code and ASME
Code.
b. The Chiller shall be designed, manufactured and tested in accordance
with the applicable portions of the latest revisions of the following
recognized standards and Codes.

ISOs :
ISO 9001:1994, ! Design manufacture and testing of Air
EN ISO 9001: 1994, ! Cooled screw Water Chilling Package.
BS EN ISO 9001: 1994, !

ARI 550-90 - Air Conditioning and Refrigeration Institute :


Standard for Air Cooled Screw water Chilling Packages
(General Specifications, Testing and Rating)

ARI 575 - Air Conditioning and Refrigeration Institute: Standard


Method of Measuring Machinery soundWithEquipment Rooms (Basis of all data
presented or field testing of equipment, with relation to sound requirements).

ASME CODE - American Society of Mechanical Engineers


Code :For Unfired Pressure Vessels – Section VIII (Design,
Construction, testing and Certification of Pressure
Vessels).
ANSI-B9.1- American National Standards Institute Safety, Code
For Mechanical Refrigeration (Overall general safety
Requirements, relief device sizing etc.)

ANSI-B31.5 -American National Standards Institute Code


TEMA - Tubular Exchanger Manufacturer’s Association.
ISO R 281 - Rolling Bearings – Dynamic Load Ratings and
Rating Life

End of Section
Section 4 :
Electric Hot Water Generator

The hot water generator shall be vertical/horizontal shell type designed,


constructed and tested for the specified water flow and temperatures.

The shell of the generator shall be made of steel with electric fusion welded
seams. The shell shall be designed for 50 Deg C of water circulation unless
specified otherwise.

The shell with insulation shall be mounted inside a cabinet of angle iron frame
with 16 SWG mild steel covers held with lock/bolts and hinges. The cabinet shall
be provided with sufficient louvers and rat proofing to ensure ventilation of heater
terminals of boilers shall be installed above the finished surface of insulation and
angle iron frame. The angle iron frame shall be provided with fittings lugs and
pedestals.

Electric heaters shall be provided in banks of equal capacity distributed on three


power phases. Heaters shall be mounted within seamless incoloysheathed
electrically resistant U tubes. The heaters shall be easily removable externally
without opening the terminal plate or disturbing other components. The heater
mounting socket shall be made leak proof. Heaters shall be suitable for
415V+_10%/50hz/3phase power supply.

 The hot water generator shall be provided with following accessories :


 Interlocking of electric panel cover with incoming switch/limit switch.
 Flow switch, float switch, automatic alarm for low water level and high
temperature / pressure switch with respective indication lights.
 Drain point with valves.
 Descaling Valves
 Automatic air vents and automatic high temperature / pressure relief valve.
 Manual thermostat for individual heater bank and master safety thermostat
of fixed setting.
 Insulation of shell with 100 mm thick resin bonded fiberglass and 26
Guage Al cladding.
 Falnges for water piping connections.

The Electrical control cabinet shall be made as detailed above and mounted
directly on the main frame. All controls and terminals shall be factory wired and
tested. The control cabinet shall consist of following major controls and rated
capacities unless specified otherwise.
 Incoming MCCB
 On/off toggle switch for individual banks
 Starter with HRC fuses.
 HRC fuses and individual heaters
 Indicating lights for on status and individual bank.
 Fault indicating lights
 Alarm with manual reset
 Thermostats
 Cabling and control wiring
 Three phase ammeter with selector switch
The panel shall be openable only after switchingoff the incoming supply.

The external surface of the shell shall be cleaned ,derusted and applied with
three coats of primer and panted.

End of section

Section 5
AIR HANDLING UNITS
1 SCOPE

The Scope of this section comprises the supply, erection, testing and
commissioning of double skin Air Handling Units conforming to these
Specifications and in accordance with requirements of drawings and
schedule of quantities.

2 TYPE

The Air Handling Units shall be of floor mounted draw through type having
sections such as filter section with pre-filters, microvee filters and HEPA
filters as required under BOQ ,cooling coil section with suitable chilled
water cooling coil, fan section with DIDW fan, mixing section where
required under BOQ, humidification section with centrifugal fan as per
schedule of quantities and arrangement shown on the drawings.

3 CAPACITY

The air moving and coil capacities (Air Conditioning Load) shall be as
shown in Schedule of equipment and quantities and on drawings.

4 CASING

The housing/ casing of the air handling unit shall be of double skin
construction. The housing shall be so made that it can be delivered at site
in total/ semi knock down conditions depending upon the conditions. The
frame work shall be of extruded aluminium hollow sections fitted with pre-
formed insulated sections. All the members shall be assembled thru
mechanical joints to make a sturdy and strong frame work for various
sections.

Double skin panels (each not exceeding 750mm wide) shall be made of
22G pre-coated Galvanised sheet steel and 22G galvanised sheet inside
with pressure injected PU foam insulation of 25mm thick X 38 Kg/Cu.M in
in between. The panels shall be bolted from inside on to the frame work
with soft rubber gasket in between to make the joints air tight.

Frame work for each section shall be bolted together with soft rubber
gasket in between to make the joints air tight. Suitable doors with powder
coated hinges and latches shall be provided for access to various panels
for maintenance.

The fan and the motor arrangement shall be mounted on to the extruded
aluminium frame work. The entire housing i.e. The Air Handling Unit shall
be mounted on extruded aluminium base channel framework.

Drain pan shall be constructed of 16 SS sheet having 12 mm thick 32


Kq/Cu. XPE insulation.The pan shall have necessary slope to facilitate for
fast removal of condensate.

5 MOTOR AND DRIVE

Fan motors shall be 230 ± 10% volts 50 cycles 3 phase totally enclosed
fan cooled with IP-55 rotation. Motor shall be especially designed for quite
operation and motor speed shall not exceed 1440 RPM. Drive to fan shall
be provided through belt drive arrangement. Belts shall be of oil-resistant
type. Adjustable sheaves shall be provided.

6 FAN

The fan shall be forward, curved double inlet double width type complete
with motor and drive package. The wheel and housing shall be fabricated
from heavy gauge galvanized steel. The fan impeller shall be mounted on
a solid shaft supported to housing with angle iron frame and pillow block
heavy duty ball bearings. The fan shall be selected for a speed not
exceeding 1000 RPM. The fan outlet velocity shall not be more than 1800
rpm. Fan housing with motor shall be mounted on a common steel base
mounted inside the AHU on anti vibration springs or cushy foot mount. The
fan shall be direct driven type. Another fire retardant canvass connection
shall be provide at unit outlet to connect the ducts.

7. Cooling Coils :

The cooling coil shall be seamless copper tubes not less than 0.437 mm
thick and 12.5 mm O.D. The coil shall have continuous aluminium fins.
The tube shall be staggered in the direction of air flow. The fins shall be
uniformaly bonded to the tubes by mechanical expansion of the tube. The
coil shall be tested against leaks
At a hydraulic pressure of 21kg/m3 for a period of two hours.The water
headers shall be of copper pipes to connect all the tubes. The header
shall be complete with water In/Out connections, vent plug and drain at
the bottom and designed to provide a water velocity between 0.6 to 1.8
m/s ( 2 to 6 FPS)

8. Filters :

As asked for under Bill of quantities.

9. Electrical Panel :

Each unit shall have its own electric panel consisting of MCCB / fuse
switch unit, starter, indicating lamps ,incoming/outgoing internal and
external wiring and earthing as per the details in BOQ.

10 Fresh Air Control :

An adjustable damper of GI sheet along with bird screen ,air inlet louvers
and air filters shall be provided for fresh air entry. The damper shall be
sized for 50% of designed air quantity.

11 Limitations :

The air velocity across the cooling coils shall not exceed 500 fpm.
The fan outlet velocity shall not exceed 1800 fps (9m/s) in any case.
The velocity across the filters shall not exceed 500 fpm in any case.

End of section
Section 6
FAN COIL UNITS
1 General

The fan coil units shall be ceiling mounting box type complete with finned
coil, fan section with motor, insulated drain pans, cleanable air filters and
fan speed regulator and other controls as described.

2 Cooling Coil

The coil shall be of seamless copper tubes not less than 5/8" O.D, 0.56
mm thick. The coil shall have aluminium fins. The fins shall be spaced by
collars forming integral part of the fins. The tubes shall be staggered in the
direction of air flow. The coil circuit should be sized for adequate water
velocity but not exceeding 1.8 M/S (6 FPS) the fins shall be uniformly
bonded to the tubes by mechanical expansion of the tubes.

The coils shall be tested against leaks at a hydraulic pressure of 10


kg/sq.cm. This pressure shall be maintained for a period of 24 hours. No
drop should be observed indicating any leaks.

3 Fan

This shall consist of (2) two light weight aluminium impellers of forward
curved type, both statically and dynamically balanced, along with properly
designed G.I. sheet casings.

The two impellers shall be directly mounted on to a double shaft, single


phase multiple winding motor capable of running at (3) three speeds.

A G.I. plenum shall connect the fan outlets to the coil.

4 Drain Pans

The drain pan shall be sandwich type fabricated out of deep drawn single
piece stainless steel sheet, covering the whole of coil section and extended
on one side for accommodating coil connection valve, etc. and complete
with a 25mm drain connection. The drain pan shall be insulated with 12mm
XPE insulation .
5 Air Filter

The filter shall be cleanable type 15mm thick with 90% efficiency down to
20 micron of rubberised coir to be mounted behind the return air grille in the
unit casing.

6 Speed Control

A sturdy switch shall be provided with the unit complete with wiring, for off
and with minimum (3) three speed control, of the fan.

7 Automatic Controls

Each unit shall have a room type thermostat and a 3 way motorised
modulating water valve. The valve shall be fixed at a convenient location.
The thermostat shall be mounted along with the speed control switch on a
common plate. The plate shall clearly indicate the fan positions.

The water valves on inlet line shall be of gun metal ball type with internal
water strainers, having BSP (FPT) inlet and flare type MPT outlet
connection. The valves on return line shall be as above, but without the
water strainer.

8 Water Connections

The water lines shall be finally connected to the coil of the fan coil unit, by at
least 300 mm long, type L seamless solid drawn copper tubing, with flare
fittings and connections.

End of Section
Section 7
PUMPS

1. General

The various items of pump shall be complete in all respect and comply with
the specification given below:

2. Pump Sets

The pump sets shall be vertical split casing type with end suction and top
discharge flanged connections, mounted on drip proof squirrel cage
induction motor with suitable starter as specified.

Pumps shall be as per IS:1520-1960, IS:9079, IS:325 and shall be of the


following construction:

1. Casing Cast Iron/Cast Steel

2. Impeller Bronze

3. Shaft High Tensile Steel

4. Shaft sleeve Bronze

5. Bearings Heavy Duty Ball/Roller bearings

6. Base Plate Cast Iron/Fabricated M.S.

7. Flanges BIS 1536/1960

8. Packing Graphited Asbestos

9. Max. Speed 1500 RPM/2900 RPM


10. Drive TEFC motors for monobloc upto
3.7 KW & SPDP motors for higher
ratings.
11. Starter See Section "Electrical
Switchgears"

a) Drive ratings shown are only tentative and Tenderers shall select their
drivers at least 5% in excess of the maximum BHP of the pump plus
transmission losses, if any. Drivers shall be supplied with starters unless
otherwise stated.

3. Accessories & Fittings

The following accessories/fittings shall be provided with each pump among


other standard accessories/fittings required:

i) Lubrication fittings and seal piping


ii) Test and/or air vent cocks
iii) Steel channel base frame for fixing pump on the concrete foundation
iv) Suction and discharge pressure gauges not less than 150mm dia. and of
the appropriate rating, with gauge cocks, etc.
v) 25 mm G.I. gland water drain piping.

4. Installation

Pumps shall be installed as per manufacturer's recommendations. Pump


set shall be mounted on concrete block which in turn is mounted on
machinery isolation cork or any other equivalent vibration isolation fitting.

Concrete foundation will be made by the Contractor as per approved


drawings and specifications and the isolation pad foundation bolts, etc.,
shall also be supplied by the Contractor. Contractor shall ensure that the
foundation bolts are correctly embedded.

Pump sets shall preferably be factory aligned whenever necessary, site


alignment shall be done by competent persons. Before the foundation bolts
are grouted and the coupling bolted, the bed plate levels and alignment
results shall be submitted to the Engineer.

5. Insulation
Pumps used for chilled water service shall be insulated so that the
dismantling of pumps not affected. Insulation shall be provided in a manner
so as to minimize the damage to the insulation in case of maintenance of
pumps or other components.

6. Testing

Tenderers shall submit the performance curves of the pumps. They shall
also be responsible for the selection of capacity and total head
requirements of each pump to match his own piping and equipment layout.

On completion of the entire installation, pumps shall be tested for their


discharge head, flow and B.H.P. Test results shall correspond to the
performance curves.

Tenderers shall furnish the required testing instruments and arrange for
their connection as required.

7. Painting

After complete installation and testing, pumps accessories and fittings shall
be given two coats of approved finishing paint.

8. On-line Water Treatment Equipment


Equipment shall be fabricated from `B' class GI pipe. It should have a
metallic core with turbulance base capable of causing galvanic action. The
core shape shall be such that colliodal particles should not settle on it.

End of section
Section 8:
Pipes & Valves :
1. General

The scope shall comprise the supply, installation of pipe, fittings, valves,
etc. and testing/balancing of complete system. Pipe sizes shown on
drawing are for the guidance of Contractor and shall not relieve Contractor
of responsibility of providing smooth, noiseless circulation of fluid.

2. Pipes

All piping work shall conform to quality standards and shall be carried out
as per specifications and details given hereunder:

All pipes shall be of schedule 40 thick as per ANSI-B-36.1.

All pipes in sizes upto 150mm dia shall be M.S. ERW pipe heavy class as
per IS:1239-Part-I (as per latest amendment).

All pipes in sizes 200mm and above shall be M.S. ERW pipe heavy class
as per IS:3589 (as per latest amendment).

3. Fittings

The dimensions of the fittings shall conform to I.S. 1239-Part-II (as per
latest amendment) unless otherwise indicated in the specifications.

All bends in sizes upto and including 150mm dia. shall be ready made of
heavy duty, wrought steel of appropriate class.

All bends in sizes 200mm and larger dia. shall be fabricated from pipes of
the same dia. and thickness with a minimum of 4 sections, and having a
minimum centre line radius of 1.5 diameter of pipes.

All fittings such as branches, reducers, etc. in all sizes shall be fabricated
from pipes of the same dia. and thickness and its length should be at least
twice the dia. of the pipe.
The branches may be welded straight to the main line, without making a
separate fitting, where specified on drawings or required by
Engineer-in-Charge.

Blank ends are to be formed with flanged joints and 6mm thick blank
between flange pair for 150mm and over in case where, a future extension
is to be made, otherwise blank end discs of 6mm thickness are to be
welded on, with additional cross stiffners from 50mm x 50mm x 5mm heavy
angles.

4. Flanges

All flanges shall be of mild steel as per IS:6392/71 and shall be steel
slip-on-type, welded to the pipes flanges thickness shall be to suit class-II
pressures.Flanges may be tack welded into position, but all final welding
shall be done with joints dismounted. 3mm thick gaskets shall be used with
all flanged joints. The gaskets shall be fibre reinforced rubber as approved
by the Engineer-in-Charge. Special adhesive compound shall be used
between flanges of steam, air and gas lines.

Flanges shall be used as used as follows :

Counter flanges for equipment having flanged connections.


Flanged pairs shall be used on all such equipment, which is required to be
isolated or removed for service e.g. pumps, refrigeration machines, air
handling units, etc.

All threaded valves shall be provided with nipples and flanged pairs on both
sides to permit flange connection, for removal of valves from main lines for
repair/replacement.

5. Valves

a) Butterfly Valves, Gate Valves, Globe Valves and Check Valves :

All gate valves, globe and check valves upto and including 40mm dia. Shall
be of gun metal screwed type, conforming to class 1 of IS:778.

All butterfly valves of 50mm dia. and above shall be flanged type, have cast
iron body with black nitrile rubber seat and conforming to class PN-10 of
IS:780 (for sizes upto 300mm) and of IS:2906 (for sizes 350mm and
above).

All globe and check valve of 50mm dia. and above shall be flanged type in
cast iron construction and conforming to class PN-10.

Air valves shall be provided at all higher points in the piping system for
venting as per the sizes shown in the BOQ.

All air needle valves shall be of gun metal and tested upto a pressure of
class 1 pressure rating. All globe valves of size 50mm and above shall be of
rising spindle type.

b) Balancing Valves

All balancing valves of upto and including 50 mm dia. shall be in gun metal
screwed type construction. The valves of 65 mm dia. and above shall be in
cast iron flanged end construction.

The valve shall have PTFE/SS disc with special erosion/ corrosion proof
sealing.

The valves shall be capable of delivering metered quantity of water and


subsequently should function as isolating valve. All the valves shall have
built in pressure drop measuring facility to ascertain water flow rate. The
valves shall have temper proof adjustable and lockable arrangement for
required water quantity after commissioning. The valve shall be to the
minimum requirement of IS:778 Class-1.

The valves shall be complete with drain cock, pressure test cocks, etc.

c) Miscellaneous Valves

All gauge cocks shall be of gunmetal plug type, complete with siphon (brass
chrome plated).

All drain valves shall be of gunmetal with a hose union connection on one
end or extended upto the drain pit as the case may be.
All valves on the supply line of fan coil units shall be of gunmetal ball type
with integral water strainers, having (BSP) FPT inlet and flare type MPT
outlet connection.

All valves on the return line of fan coil units shall be as above but without
integral water strainer.
d) Strainers

The strainers shall either be 'pot' type or 'Y' type with cast iron or fabricated
steel body, tested to a pressure of 10 kg/sq.cm. applicable for the butterfly
valves as shown on the drawings.

The strainers shall have a perforated bronze sheet screen with 3mm
perforation, 0.63mm thick.

Pot strainers and Y strainers shall be provided with flanged connections.


The strainers shall be designed to facilitate in easy removal of filter screen
for cleaning, without disconnection of pipe line

Pot strainer shall be fabricated out of M.S. sheet and the sizes shall be as
under:
==============================================================
Pipe size Pot Dia Pot HT Basket dia Basket HT
(mm) (mm) (mm) (mm) (mm)
===========================================================================
50 300 400 200 240
80 350 450 250 250
100 450 500 300 280
125 500 600 330 340
150 540 700 360 390
200 610 815 400 470
250 800 955 550 510
300 1000 1105 750 580
350 1190 1300 895 678
400 1350 1500 1020 785
450 1518 1700 1060 890
500 1690 1800 1100 900
==============================================================

You might also like