GALAXY ENTERTAINMENT GROUP
银河娱乐集团有限公司
To : WONG & OUYANG (HK) LTD From: 上海建工集团(澳门)有限公司 Shanghai Construction Group(Macau)Limited
Name: Zhou Yi Dong /Zhou Gong Jun
Attn.: Wayne So/ Winson Liem Signature:
w/ encl. w/o encl. Date: 3-Feb-20
CONTRACTOR SUBMISSION
Material Method Statement Others: Inspection & Test Plan
Contract No.: 3C005N077 Ref. No.: 3C005N077-HWT-ITP-00-0002 Revision: 01
Spec./ BQ/ Drawings Ref.: Attachment : Yes, 1 page
pages No
Contractor's alternative proposal: Yes No
Involve extra time/ cost under the contract Yes No
Subject : Inspection & Test Plan for Drywall
Description :
Inspection & Test Plan for Drywall
WONG & OUYANG
Party expected to RLB
reply: ARUP (Struct) Others, pls specify:-
AURECON
Initial of : Expected approval date:_____________________
For Materials Submission Only:
Brand/ Manufacturer:___________________________________________ Info. from Manufacturer
Supplier:____________ Country of Origin:______________ Job Ref.
Catalogue Certificate Sample to: Site Office: Ref. Letter from Authorities
Purpose of Submission : Previous Ref.:
For Review/ Approval For Record For Endorsement
COMMENT FROM THE CONSULTANT
Consultant: Ref. no.: Attachment: Yes, ___ Pages No
WONG & OUYANG ARUP(Struct) AURECON RLB Other, pls specify:
Approved Approved with Comment Reject and Re-submit Consultant Name : WONG & OUYANG / ARUP / AURECON Date:
COMMENT: Signature :
WONG & OUYANG Galaxy - (Endorse if approved)
Name : Name:
Signature : Date: Signature : Date:
cc: External Internal
w/e w/o w/e w/o w/e w/o w/e w/o
Galaxy WONG & OUYANG (Site)
ARUP (Struct) ARUP (Site)
AURECON AURECON (Site)
RLB RLB
w/e - with enclosure w/o - without enclosure
Galaxy Resort Casino Development, Cotai City, Macau Phase 2
3C005N077 – Nominated Sub‐Contract for
Hotel Tower(West) Fit Out
Inspection Test Plan
Drywall Construction
Verifying Document Inspection Code
Item Particular / Activity Inspection Stage Inspection / Testing Activities Required Controlling Document Description NSC MC RSS M&E Remarks
Cont
A. Pre‐construction Stage
Method Statement ,Shop Drawing & Prior work commencement Approval by consultant ‐Approved MethodStatement Approval by consultant
1 Calculation ‐Approved Sh口p Drawing R HP HP N/A
Inspection & Test Plan Prior work commencement Approval by consultant ‐Approved Inspection & Test Plan Approval by consultant
2 R HP HP N/A
Material Approval Prior work commencement Approval by consultant ‐Submission Form Approval by consultant
3 ‐ Product Data Sheet R HP HP N/A
B. Construction Stage
Receipt of material Material delivery Check material conforming to approval record Delivery note Check list
1 IV RI RI N/A
Setting out Prior installation of hanger and Ensure correct drywall alignment and demarcation Approved shop drawing Check list
2 frame IV CP RI RI
Installation of drywall frame (Before board Prior rockwool filling Check spacing and workmanship of stud frame Method statement Check list
3 installation) IV CP RI N/A
Get confirmation from Main Contractor for the Prior drywall closeup Check if clash with existing MEP services and rock wool Confirmation from Main RIN & Check list
4 completion of E&M services (conduit inside infill completed Contractor IV HP HP RI
drywall)
Wall boarding to both side of dry wall Prior finishes application Ensure smooth board surface Method statement Check list
5 IV RI RI N/A
Completion of drywall prior to finishes application After drywall close‐up Check quality of joint taping, applied sealant and Method statement RIN & Check list
6 surface condition of painting works IV HP HP N/A
Verification Code:
Legend:
IV: Inspection & Verification NSC: Nominated Sub-Contractor
RI: Random Inspection MC: Main Contractor
T: Test RSS: Resident Site Staff of the Supervision
RIN: Request for Inspection Form
CP: Control Point
HP: Hold Point