Contract Termination Review Committee
Contract Termination Review Committee
Province of Bataan
City of Balanga
OFFICE OF THE CITY MAYOR
(047) 237-2256 / 237-2969 / 237-3510
WHEREAS, Republic Act No. 9184, otherwise known as the Government Procurement
Reform Act, governs the procurement of infrastructure projects, goods and consulting services,
regardless of source of funds, by all branches and instrumentalities of government, its
departments, offices and agencies, including government-owned and/or-controlled
corporations and local government units;
WHEREAS, pursuant to the guidelines, the Head of the Procuring Entity (HOPE) renders
the decision within ten days upon receipt of verified position paper, based on the grounds
stated in the notice to terminate;
WHEREAS, due to the nature of the function involved, especially the review of items and
works involved, it is imperative to establish a body that will provide technical, financial and
legal assistance to the HOPE prior to contract termination;
SECTION I
COMPOSITION
The Contract Termination Review Committee in the City of Balanga shall be composed
of the following :
2nd Floor, Balanga City Hall, Barangay Poblacion, Balanga City, Bataan 2100
[email protected]
Page 1 of 8
___EXECUTIVE ORDER NO . 17, S.2020
SECTION II
FUNCTIONS, DUTIES & RESPONSIBILITIES
The Contract Termination Review Committee in the City of Balanga shall have the
following functions, duties and responsibilities pursuant to the “Guidelines on Termination of
Contracts (Annex I of the “2016 Revised Implementing Rules and Regulations of Republic Act
No. 9184), to wit:
1. Receive and review the Verified Report to be submitted by the Implementing Unit,
which details the acts or causes which may constitute as ground for termination of
government procurement contract;
2. Recommend to the HOPE and facilitate the preparation of the Notice to Terminate to be
approved by the HOPE, which shall state:
a. that the contract is being terminated for any of the ground(s) afore-mentioned,
and a statement of the acts that constitute the ground(s) constituting the
same;
b. the extent of termination, whether in whole or in part;
c. an instruction to the Supplier/Contractor/Consultant to show cause as to why the
contract should not be terminated; and
d. special instructions of the Procuring Entity, if any;
2nd Floor, Balanga City Hall, Barangay Poblacion, Balanga City, Bataan 2100
[email protected]
Page 2 of 8
___EXECUTIVE ORDER NO . 17, S.2020
3. Receive and review the Verified Position Paper to be submitted by the supplier,
contractor or consultant, as the case may be;
4. Submit a recommendation and facilitate the preparation of the Decision to be approved
by the HOPE;
5. Whenever necessary, coordinate with the concerned offices during the conduct of the
contract termination process;
6. Monitor the timelines involved and ensure compliance with the procedure for the
termination of government procurement contracts.
SECTION IV
MEETINGS
The Contract Termination Review Committee shall convene/meet for special and
emergency meetings as the need arises. A majority of all the committee members shall
constitute a quorum.
SECTION V
GUIDELINES ON TERMINATION OF CONTRACTS
The Contract Termination Review Committee shall be guided by the following guidelines
as provided for under Annex I of the “2016 Revised Implementing Rules and Regulations of Republic
Act No. 9184”, to wit :
2nd Floor, Balanga City Hall, Barangay Poblacion, Balanga City, Bataan 2100
[email protected]
Page 3 of 8
___EXECUTIVE ORDER NO . 17, S.2020
The Procuring Entity shall terminate a contract for default when any of the
following conditions attend its implementation :
2nd Floor, Balanga City Hall, Barangay Poblacion, Balanga City, Bataan 2100
[email protected]
Page 4 of 8
___EXECUTIVE ORDER NO . 17, S.2020
The Procuring Entity shall terminate a contract for default when any of the
following conditions attend its implementation :
a) Due to the Contractor’s fault and while the project is on-going, it has
incurred negative slippage of fifteen percent (15%) or more in
accordance with Presidential Decree 1870;
b) Due to the Contractor’s fault and after the contract time has expired, it
has incurred a negative slippage of ten percent (10%) or more in the
completion of the work; or
c) The Contractor :
i. abandons the contract works, refuses or fails to comply with a valid
instruction of the Procuring Entity or fails to proceed expeditiously
and without delay despite a written notice by the Procuring Entity;
ii. does not actually have on the project site the minimum essential
equipment listed on the Bid necessary to prosecute the Works in
accordance with the approved work plan and equipment deployment
schedule as required for the project;
iii. does not execute the Works in accordance with the contract or
persistently or flagrantly neglects to carry out its obligations under
the contract;
iv. neglects or refuses to remove materials or to perform a new work
that has been rejected as defective or unsuitable; or
v. sub-lets any part of the contract works without approval by the
Procuring Entity.
The Procuring Entity shall terminate a contract for default when any of the
following conditions attend its implementation :
The Procuring Entity may terminate the Contract, in whole or in part, at any time
for its convenience. The Head of the Procuring Entity may terminate a contract for
the convenience of the Government if he has determined the existence of conditions
that make Project Implementation economically, financially or technically impractical
and/or unnecessary, such as, but not limited to, fortuitous event(s) or changes in law
and national government policies.
2nd Floor, Balanga City Hall, Barangay Poblacion, Balanga City, Bataan 2100
[email protected]
Page 5 of 8
___EXECUTIVE ORDER NO . 17, S.2020
The Procuring Entity may terminate the contract in case it is determined prima
facie that the Supplier/Contractor/Consultant has engaged, before or during the
implementation of the contract, in unlawful deeds and behaviors relative to contract
acquisition and implementation. Unlawful acts include, but are not limited to, the
following :
E. Termination by Contractor/Consultant :
The Contractor may terminate its contract with the Procuring Entity if the
works are completely stopped for a continuous period of at least sixty (60)
calendar days through no fault of its own, due to any of the following reasons :
The Consultant may terminate its agreement with the Procuring Entity if
the latter is in material breach of its obligations pursuant to the contract and has
not remedied the same within sixty (60) calendar days following its receipt of the
Consultant’s notice specifying such breach.
1) Verification. Upon receipt of a written report of acts or causes which may constitute
ground(s) for termination as aforementioned, or upon its own initiative, the
Implementing Unit shall, within a period of seven (7) calendar days, verify the
existence of such ground(s) and cause the execution of a Verified Report, with all
relevant evidence attached;
2nd Floor, Balanga City Hall, Barangay Poblacion, Balanga City, Bataan 2100
[email protected]
Page 6 of 8
___EXECUTIVE ORDER NO . 17, S.2020
3) Show Cause. Within a period of seven (7) calendar days from receipt of the Notice of
Termination, the Supplier/Contractor/Consultant shall submit to the Head of the
Procuring Entity a verified position paper stating why the contract should not be
terminated.
5. Decision. Within a non-extendible period of ten (10) calendar days from receipt of the
verified position paper, the Head of the Procuring Entity shall decide whether or not
to terminate the contract. It shall serve a written notice to the
Supplier/Contractor/Consultant of its decision and, unless otherwise provided, the
Contract is deemed terminated from receipt of the Supplier/Contractor/Consultant
of the notice of decision. The termination shall only be based on the ground(s)
stated in the Notice to Terminate.
6. Contract Termination Review Committee (CTRC). The Head of the Procuring Entity
may create a committee to assist him in the discharge of his function under these
Guidelines. All decisions recommended by the CTRC shall be subject to the approval
of the Head of the Procuring Entity.
a) to have any portion delivered or performed and paid at the contract terms and
prices; and/or
b) to cancel the remainder and pay to the Supplier an agreed amount for partially
completed or performed goods and for materials and parts previously procured by
the Supplier.
2nd Floor, Balanga City Hall, Barangay Poblacion, Balanga City, Bataan 2100
[email protected]
Page 7 of 8
___EXECUTIVE ORDER NO . 17, S.2020
If the Supplier suffers loss in its initial performance of the terminated contract,
such as purchase of raw materials for goods specially manufactured for the
Procuring Entity which cannot be sold in open market, it shall be allowed to recover
partially from the contract, on a quantum meruit basis. Before recovery may be
made, the fact of loss must be established under oath by the Supplier to the
satisfaction of the Procuring Entity before recovery may be made.
V. AMENDMENTS :
SECTION VI
SEPARABILITY CLAUSE
If, for any reason, any portion of this Order is declared unconstitutional or invalid, the
same shall not affect the validity of the other provisions not affected thereby.
SECTION VII
REPEALING CLAUSE
All orders, rules, regulations and issuances or parts thereof, which shall be found
contrary to or inconsistent with the provisions of this Order are hereby amended, repealed or
modified accordingly.
SECTION VIII
EFFECTIVITY
This Executive Order shall take effect immediately upon approval and shall remain valid
and effective, unless sooner revoked, amended or terminated.
SO ORDERED.
Done this 20th day of February 2020 in the City of Balanga, Province of Bataan.
2nd Floor, Balanga City Hall, Barangay Poblacion, Balanga City, Bataan 2100
[email protected]
Page 8 of 8