Abu Ali project-APCS 1D Using Hempel Paint REV.01
Abu Ali project-APCS 1D Using Hempel Paint REV.01
Abu Ali project-APCS 1D Using Hempel Paint REV.01
Subject:
Coating Procedure for APCS – 1D at Acortec
facility, Jubail for Abu Ali Project.
TABLE OF CONTENTS
1. Purpose
2. Scope of Work
7. Instrument used
13. Qc Documentation
********************************************************
KINGDOM OF SAUDI ARABIA
Subject:
Coating Procedure for APCS – 1D at Acortec
facility, Jubail for Abu Ali Project.
1) Purpose
The purpose of this coating procedure is to provide the workmanship criteria to the
greatest practicable extent and to control of the quality to meet the Saudi Aramco
requirements through complying with the requirements of Saudi Aramco specification,
paint manufacturer datasheet, technical manual and international reference codes and
standards
2) Scope of Work
This coating procedure describes the specific work required to be implemented for
application of Liquid Coating Applications on Pipes, Spools & Steel Structures under
“Saudi Aramco Abu Ali Project”. It covers responsibilities, work execution procedure,
quality control of resource inputs and task activities, as applicable standards for this
particular work phase.
APCS 1D:
Surface preparation: sa2½(SSPC SP10) Surface profile:40-65 Microns
Comply with all Codes & Standards including but not limited to SAUDI ARAMCO
Painting Standards as outlined below:
3.1.References:
7. SAES-H-002 Internal & external coatings for Steel pipe lines &
piping,
15. SIS 055900 Surface Preparation Standards for Painting Steel Surface.
16. ASTM-D-3359 Adhesion Test (Tape test or Peel off test)-Cross cut Method
QA-QC Manager
Responsible for Preparation and maintenance of Quality Plan, Preparation of internal
Audits Schedule, implement of Quality Audits with respect to COMPANY Procedures,
Quality Plan and schedule Q Attachment V. Periodically conducting auditing with sub-
contractors quality plan, Confirming that corrective action have been taken for NCR in
consultation with Project manager, to issue follow-up and closeout the Corrective
action ,evaluate and monitoring the effectiveness of the project Quality Plan and
Quality system of suppliers and vendors within the contractors scope, Make fully aware
KINGDOM OF SAUDI ARABIA
Subject:
Coating Procedure for APCS – 1D at Acortec
facility, Jubail for Abu Ali Project.
of the quality management system and the PQP through quality induction Training,
Advising the Project manager regarding the appropriate preventive action following the
occurrence of any non-conformity work, Preparation/Verify the documents as required
SAFETY MANAGER
Shall be responsible for the implementation of HSE procedures before and during the
execution of Civil activities.
Shall be responsible for check for any unsafe conditions on the working areas and
liaise with field Supervisor ensuring that the work is carried out as per approved
Project safety plan and procedure.
Crew Supervisor:
To monitor day-to-day Operations including Blasting & Painting
activities, safety of Personnel as well as Equipment as per SAUDI ARAMCO / SAES-
H-001 & SAES-H-101V STDs. Crew Supervisor should check all Abrasives, Paint
Materials and take care of the Storage. He should conduct Too Box Meetings regularly
and explain to his operatives in detail about procedures written in the Method
Statement and Safety precautions to be followed. He should supervise all in – process
Blasting & Painting activities. Accordance with SAEP-316
Q/C Inspector:
Q/C Inspector should conduct Visual Inspection, Material Verification,
Take Weather readings,conduct Blotter Test as per ASTM –D– 4285, Chloride Test,
Profile Test, take DFT readings, conduct Addition Tests if required by the Client etc.
He fills up all Q/C Forms, raises RFI's, etc.All Coating Inspectors shall be qualified and
certified to perform their tasks as mentioned in SAEP-316.
Coating Applicator:
Paint applicator will be the responsible for paint mixing & proper
applications. During application, he will make sure that the WFT of the paint is
according
to the requirements. Coating applicator shall be Saudi Aramco and jcc approved in
Accordance with SAEP-316
2. Coating material used at construction site must be covered with the appropriate
canvas, tarpaulins, or equivalent for temporary storage period not exceeding 14 days.
3.Coating shall not be used from the container showing sign of leakage shall be
discarded
4. Coating which have exceeded the shelf life given in the MSDS shell be set aside and
must not be used.
5. Received abrasive material shall be kept in dry place to avoid moisture entrapment.
KINGDOM OF SAUDI ARABIA
Subject:
Coating Procedure for APCS – 1D at Acortec
facility, Jubail for Abu Ali Project.
3. Condition of Steel Surface /appearance can be compared with Pictorial Std. ISO
8501-1.
5. Prior to Abrasive Blasting, surfaces shall be cleaned for moisture, Oil, Dust, Grease or
other contaminants.
6. Compressed Air used for Abrasive blasting shall be free of Oil, moisture and
contamination. Air quality shall be verified in the following method at the start and
midpoint of 8 hour period. A piece of Blotter paper or absorbent shall be attached
to a board and will be held approximately 45-60cms in front of the blast nozzle during air
flow only, with nozzle pressure of 50 PSI and for a period of one minute. Blotter shall be
inspected visually for assessing the contamination.
7. Abrasive Blasting & Painting shall be carried out only when the steel surface is at
least 3 Degree Celsius above the Dew point.
9. After Abrasive Blasting, Surface shall be tested for soluble salts. Chloride levels shall
be less than 40 mg/m2; if Chloride levels are greater than 40 mg/m2, surface shall be
washed as per SSPC-SP-1 or ISO 12944.
10. Spent Abrasives shall be removed from cleaned external surfaces by dry brushing
and blowing down with clean, dry compressed air.
11. Abrasive blast cleaned surface shall not be held for more than 4 hours or less than
that if any chance of contamination. If held for more than 4 hours, need to sweep blast
and re-inspect the surface profile for acceptance.
12. Paint shall not be applied when the surface temperature is less than 10 Degree
Celsius or more than 50 Degree Celsius.
13. Paint shall not be applied when the Relative humidity is more than 85%.
14. Paint shall not be applied when the wind is strong enough to blow sand, salt spray
or dry spray.
15. Paint mixing shall be monitored by approved Supervisor and proper guidance shall
KINGDOM OF SAUDI ARABIA
Subject:
Coating Procedure for APCS – 1D at Acortec
facility, Jubail for Abu Ali Project.
13. On plain end pipes to be welded, leave ends unpainted for a distance of 2.5 cms (1.0
Inches) and not more than 6.4 cms (2.50 Inches) as per SAES –H-100.
17. Welds, edges and nut – bolts shall be stripe coated before spray application.
18. Care shall be taken not to exceed the re - coating intervals for the different coats.
19. Acortec site representative shall utilize the proper testing instrumentation to perform
the following measurements and report readings and test results on Acortec's Quality
Control Forms.
7.INSTRUMENT USED:
✓ Dew point temperature -
Digital Dew Point Meter
✓ Relative humidity -
Digital Dew point Meter
✓ Ambient Temperature -
Digital Dew Point Mater
✓ Surface temperature -
Magnetic Thermometer
✓ Anchor pattern -
Using replica tape (Testex Tape) & Profile Micrometer),
Method C
✓ Degree of cleanliness - ISO - 8501 - 1
✓ Wet film thickness (WFT) - Wet Film Gauge
✓ Dry film thickness (DFT) - DFT Gauge
✓ Salt Test Kit - Bresle Salt Kit
✓ Adhesion Test on Finish Coat by Cross Cut Method A as per ASTM D 3359 on request
from Client,
✓ Compressed air Pressure - Hypodermic needle gauge -
✓ Oil and water - Blotter test paper
✓ Adhesion test - sharp knife
- APCS 1D
Immediately after Abrasive blasting, mask off welded & damage area. Primer Coat will be
applied to protect the surface from environment with “Hempel Paint Primer” Zinc Silicate
“Hempel’s Galvosil 15780” or equivalent using Air less Spray pump at the manufacturer’s
recommended pressure of 1450PSI with Tip Size 0.019” to 0.023” to achieve 65 -100 microns
DFT.
For spray application paint material shall be agitated continuously using low speed
Mixer.
Note:- Manufacturer recommended Paint Mixing ratio, Thinning ratio, Pot life, Shelf life,
inter coat re-interval etc. shall be followed.
KINGDOM OF SAUDI ARABIA
Subject:
Coating Procedure for APCS – 1D at Acortec
facility, Jubail for Abu Ali Project.
Primer Coat surface shall be lightly abraded to remove gloss for Intermediate Coat
application. Abraded Primer coat shall be properly air blown with dry air to avoid any
foreign contamination. “Hempel Paint Intermediate Coat” High solid epoxy “Hempadur
Mastic 45881” or equivalent with Airless spray pump at the manufacturer’s
recommended pressure of 3625PSI with Tip Size 0.017” to .023” to achieve 100 -150
microns DFT.
Note:- Manufacturer recommended Paint Mixing ratio, Thinning ratio, Pot life, Shelf life,
inter coat re-interval etc. shall be followed.
Note:- Manufacturer recommended Paint Mixing ratio, Thinning ratio, Pot life, Shelf life,
inter coat re-interval etc shall be followed.Finish coat will be hard dry after 16 hours at
25 Deg. Celsius.
• For areas greater than 0.1 m², blast clean to obtain the metal surface pre-treatment
originally specified. Feather edge the coating at least 50 mm beyond bare metal.
• Apply Hempel Mastic 45881 as Primer by Brush & Roller @ 65 - 100 Microns DFT.
• Apply Hempel Mastic 45881 as Intermediate by Brush & Roller @ 100 – 150
Microns DFT
KINGDOM OF SAUDI ARABIA
Subject:
Coating Procedure for APCS – 1D at Acortec
facility, Jubail for Abu Ali Project.
• Apply Hempel Top coat 55210 as top Coat by Brush & Roller @ 25 – 65 Microns
DFT.
Note: Brush & Roller application is acceptable if repair area size is less than
0.1m2. Above 0.1m2, spray application is required.
a. General
• All Inspection activity shall be carried out as per the approved Quality control
planning the various phases of execution and inspection.
• Painting Inspector shall check the surface of the blasted materials as per required
surface preparation and ensure the clean surface must be free from mill scale, oil,
grease, soil,
cement, salt, acids or other corrosive chemical, which are harmful for painting.
• Inspection frequency for cleaning of rust etc. shall be one in each area where
surface preparation has been completed before coating.
• Anchor pattern shall be inspected by using Testex Tape (Press-O-Film) the profile
shall be acceptable according to the applicable APCS. Testing area shell be
selected randomly.
• Anchor profile value shall be inspected in Testex tape by using calibrated Dial
gauge micro meter. The values shall be within the acceptable limit. This shall be
ensured by Painting Inspector and the Testex Tape shall be attach with the Painting
inspection report.
The following inspection and testing shall be performed during the application
coating system.
• Checking on materials (integrity of packing, expiry dates etc.)
• Checking of paints documentations (Technical Data Sheet, Material Safety Data
Sheet)
• Checking of meteorological and environmental conditions
• Measurement of wet film thickness (WFT) has to be done with standard eccentric
wheel and comb gauge
• Dry Film Thickness Measurement shall be carried out as per SSPC PA2
• If the dry film thickness does not meet the specified value, additional coats
shall be applied as per repair procedure, except for inorganic zinc(zinc
silicate) primers that shall be re-blasted and re-applied at the required dry film
thickness (DFT)
• Inorganic zinc (zinc silicate) primers applied at dry film thickness greater than
100μm or showing mud-cracking shall also be re-blasted and re-applied at the
required DFT.
e. MEK TEST
MEK soaked pad in contact with the coating surface for one minute and then
rubbing vigorously for 15 seconds. There shall be no softening of the coating or
substantial color removal from the coating.
f. Drying / Curing
For each coat, the Drying/Curing shall be checked as per the Manufacturers
Product Data Sheet and the same shall be ensured by the Painting Inspector.
if the blasting and primer application is performed before fabrication of pipe spool, prior
to blasting and primer application following shall be carried out
• Verify the spool number and heat number is transfer at the end of inside surface
of pipe is available, marked by the piping release department.
• For the small diameter pipe marking is not possible inside surface of pipe, then
aluminum tag which shall be securely attached to the pipe or pipe spool with
stainless steel wire shall be provided by the piping release department
• Material identification i.e heat number, material specification, color coding etc.
shall be transferred to cut out pieces for traceability as above prior to release for
painting
• Material identification after blasting and primer punch shall be provided by AYTB
if client requested
• All PPE not limited to Hard Hats, Coveralls, Leather Gloves for Blasters, Safety
boots, Blasting hoods, Ear plugs, Safety Specs, Cartridge masks etc shall be
worn by the personnel during work execution. Blasters shall wear Blasting hood
with positive air supply and Painters with cartridge masks as per Safety
requirements outlined in SAES - H – 102
• All Equipment shall be grounded not limited to Blast Pots, Blast Hoses, Paint
Pumps, and Air Compressors etc.
• Approved Grit shall be used as Abrasive which is absent from free Silica
• Spent Abrasives shall be disposed of as per Saudi Govt. regulations if not
recyclable. Paint Cans & Paint Flakes will be disposed off as per Saudi Aramco
regulations to avoid contaminating the work place.
• Blasting area, Painting Area, Material Storage Area etc will be demarcated and
sign boards will be placed.
13) QC Documentation.
SAIC-H-2026-Equipment Inspection