19 Pre Hydro Testing
19 Pre Hydro Testing
19 Pre Hydro Testing
Review and
00
approval
Rev Date Description Prepared by Checked By Approved
SBES SBES By IOCL/PMC
SHREE BALAJI ENGINEERING SERVICES
Job Procedure No.:
SBES-IOCL-REWA-ML-JP-19
INDEX
Page
Sr. Description
No.
1. Scope 3
2. Applicable Codes & Specification 3
3. Method 3
4. Precautions during Hydro test 4
5. Documentation
Inspection Test Plan
Inspection Report
1.0 SCOPE
The scope covers working methodology for the pre hydro testing of pipe sections of rail-
road, road, minor water course, canal & mainline test headers and testing of HDD/Crossing
String during the execution of REWA MADHAY PRADESH CONNECTIVITY PROJECT.
.
3.0 Method
Acceptance:
Termination:
After recording the results, test shall be terminated with the consent of the
PMC/IOCL, and the loop shall be depressurized.
The line and equipment shall be completely drained by suitable means after
completion of hydrostatic test of the system. Vent shall be opened before draining
the section. Subsequently, de-watering operation shall be carried out. Water shall be
disposed off at suitable location with the approval of the PMC/IOCL.
Before start of work SHREE BALAJI ENGINEERING SERVICES shall take safety clearance
from PMC/IOCL.
The testing team shall not leave the premises until the pipe section is de pressurized
after the test.
Signs stating “PIPE UNDER TEST- KEEP AWAY” with local language, translations shall
be placed where the pipeline is uncovered, and particularly where the provisional
traps, all valves and flange connections and stations are located. Such areas shall be
suitably fenced in such a way as to prevent access of unauthorized personnel.