This progress report provides the status of a proposed storage building project in Davao City for owner Alan B. Uy. It lists 10 tasks with their relative weight, actual completion percentage and current status. As of January 30, 2020, 72.57% of the project has been completed, with ongoing work on the roofing installation, wall cladding, and steel prefab installation.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
103 views1 page
Progress-Report Toril 01.30.2020
This progress report provides the status of a proposed storage building project in Davao City for owner Alan B. Uy. It lists 10 tasks with their relative weight, actual completion percentage and current status. As of January 30, 2020, 72.57% of the project has been completed, with ongoing work on the roofing installation, wall cladding, and steel prefab installation.