Program of Works

The document is a program of works for the construction of a kitchen at the Barangay Hall in Purok 05, Barangay Pingit, Aurora. It outlines the materials needed, their quantities, costs, and a total budget of 50,000 pesos from the 20% development fund. The materials include cement, sand, hollow blocks, wire mesh, and stone. It also allocates funds for design work, labor, value-added tax, and other charges to meet the total project cost.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
656 views1 page

Program of Works

The document is a program of works for the construction of a kitchen at the Barangay Hall in Purok 05, Barangay Pingit, Aurora. It outlines the materials needed, their quantities, costs, and a total budget of 50,000 pesos from the 20% development fund. The materials include cement, sand, hollow blocks, wire mesh, and stone. It also allocates funds for design work, labor, value-added tax, and other charges to meet the total project cost.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

REPUBLIC OF THE PHILIPPINES

PROVINCE OF AURORA
MUNICIPALITY OF BALER
BARANGAY PINGIT
oOo

MUNICIPAL ENGINEERING OFFICE


( for BLGU-PINGIT)

PROGRAM OF WORKS

NAME OF PROJECT : Construction of Kitchen


LOCATION : Purok 05, Barangay Hall
SOURCE OF FUND : 20% DF
APPROPRIATION : 50,000.00
MODE OF IMPLEMENTATION : By Administration

UNIT DESCRIPTION OF WORKS QTY UNIT UNIT COST TOTAL COST


NO.

I. TILE WORKS
CEMENT 10 SACKS 240.00 3,600.00
SCREEN SAND 1 Elf Truck 1,200.00 1,200.00
Hallow Blocks 50 Pc 12.00 600.00
9mm 3 Sacks 1,000.00 3,000.00
Stone 1 Elf Truck 1,500.00 1,500.00
Plant/Flowers/Grass 10,000.00
Design Materials 5,000.00

Sub – TOTAL 25,900.00

II. DESIGN ( preparation,plan and supervision) 5,000.00

Sub- TOTAL 5,000.00

Sub – TOTAL 30,900.00

Summary:
A. Materials 30,900.00
B. Labor 17,000.00
C. VAT 1,813.00
D. OCM 287.00

TOTAL 50,000.00

Prepared by: Check by:

KRIZALYN Q. VIRREY SOFRONIO RAUL A. EGARGUE


Civil Engineer Municipal Engineer

Approved by:

LYSANDER R. QUERIJERO
Punong Barangay