DD 210714
DD 210714
DD 210714
Technical Specification
Civil
Ownership:
Role Title
Revision Log:
Revision Details:
C10.10.4 Wet weather storage tank & inlet MH added to the table
C3.11.2 Table 3-4 Concrete Curing Time inserted, and clause amended
8 All Sections Major Revisions in all sections. Cross references to all previous
versions and clauses shall be updated from previous versions.
C1 Some clause numbers have changed/ deleted and new clauses
added.
C1.2 Hierarchy of documents added
C1.6 Survey requirements added
C1.7 Requirements on existing services added
C1.8 Requirements on Visual records added
C1.9 Requirements of Hold Points added
C2 Major revision in Earthworks section includes introduction of
compulsory Hold Points throughout construction stages,
Revised earthworks material testing requirements and Revised
compaction testing requirements.
C3 Some clause numbers have changed/ deleted and new clauses
added.
C3.5.6 Term- “Cement” amended to as “cementitious”
C3.6.3 Heading and Table 3.1 amended
C3.6.5 Hold Point in mix design
C3.8.8 New certification requirements for formwork & reinforcement
fixing and Hold Point
C3.14 New requirement for mapping of non-compliant cracks
C3.15.3 Hold Point included for formwork design
C3.19.1 Hold Point included in concrete repair methodology
C3.20 New requirements for reinforced concrete box culverts & open
channels.
C3.21 Clause no amended
C3.22 Hold Point list introduced
C4 Some clause numbers have changed/ deleted and new clauses
added.
C4.1 Additional reference ASTM 380M added
C4.2 Expanded to include materials properties of stainless steel
C4.5 Expanded to cover off site fabrication
C4.6 Hold Point added
C4.6.1 Expanded to limit the method of cutting stainless steel
C4.11 Hold Point added
C4.12 Expanded to cover enlarging corroded holes
Foreword
This Specification is for the design, supply and construction of civil works for Sydney Water
Corporation assets.
Sydney Water makes no warranties, express or implied, that compliance with the contents of this
Specification shall be sufficient to ensure safe systems or work or operation.
It is the user’s sole responsibility to ensure that the copy of the Specification is the current version
as in use by Sydney Water.
Sydney Water accepts no liability whatsoever in relation to the use of this Specification by any party,
and Sydney Water excludes any liability which arises in any manner by the use of this Specification.
For the purpose of this Specification “Sydney Water” or “SWC” is the nominated person or
organisation that has written authority to act on Sydney Water Corporation’s behalf.
This document is uncontrolled once printed or downloaded.
Copyright
The information in this document is protected by Copyright and no part of this document may be
reproduced, altered, stored or transmitted by any person without the prior consent of Sydney Water.
Competent Engineer Suitably qualified and experienced engineer with the ability
to apply knowledge and skills to achieve the intended
design, construction, testing or monitoring task. For
engineering tasks related to design, engineering personnel
who meet requirements of the Sydney Water Engineering
Competency Standard.
WSAA Code- Sydney WSAA Code with modifications by Sydney Water for use in
Water Edition Sydney Water assets; when available.
Table of Contents
C1. General 1
C1.1. Statutory Regulations 1
C1.2. Standards and Codes 1
C1.3. Proprietary Items 1
C1.4. Design 1
C1.5. Recycled and Reused Materials 1
C1.6. Survey 2
C1.7. Existing Services 2
C1.8. Visual Records 2
C1.9. Hold Points 3
C2. Earthworks 4
C2.1. General 4
C2.2. Referenced Documents 5
C2.3. Verification of Ground Conditions 6
C2.4. Site Preparation for Earthworks 6
C2.5. Excavation 7
C2.6. Stockpiling 9
C2.7. Backfill or Fill Material 9
C2.8. Compaction 12
C2.9. Foundation Preparation 14
C2.10. Surface Restoration 14
C2.11. Records 15
C2.12. Hold Points 15
C5.10. Fabrication, Erection and Testing of Circular Liquid Retaining Steel Tanks 71
C5.11. Hold Points 74
C7. Demolition 84
C7.1. General 84
C7.2. Referenced Documents 84
C7.3. Definitions 84
C7.4. Method of Demolition 84
C7.5. Disposal of Demolished Material 85
C7.6. Clean Up 85
C7.7. Submission on Methodology 85
C7.8. Hold Points 86
C8. Roadwork 87
C8.1. General 87
C8.2. Referenced Documents 87
C8.3. Removal of Topsoil 87
C8.4. Subgrade Preparation 87
C8.5. Road Base and Sub-base Materials 87
C8.6. Supply and Transport of Road Base and Sub-base Materials 88
C8.7. Spreading and Compacting Road Base and Sub-base Materials 88
C8.8. Asphaltic Concrete Wearing Surface 88
C8.9. Manufacturing and Transport of Asphaltic Concrete 89
C8.10. Prime Coat 89
C8.11. Spreading and Compaction of Asphaltic Concrete 90
C8.12. Concrete Carriageway 90
C8.13. Kerb and Gutter 91
C8.14. Proprietary Safety Barrier Systems 92
C9. Piling 93
C9.1. General 93
C9.2. Referenced Documents 93
C9.3. Geotechnical Verification During Construction 93
C9.4. Durability of Pile Foundations 93
C9.5. Materials 94
C9.6. Driven Piles 94
C9.7. Bored Cast in-situ Concrete Piles 95
C9.8. CFA Piles 95
C9.9. Screw Piles 95
C9.10. Timber Piles 96
C9.11. Other Pile Types 96
C1. General
C1.1. Statutory Regulations
All Works shall comply with the requirements of all federal and state laws and regulations in force in
New South Wales. Where the Works is subject to the control of statutory or regulatory authorities,
the works shall comply with the requirements of the authorities.
Technical requirements specified herein shall not be used to reduce nor remove any obligations the
Contractor has for health and safety of all personnel; as required by the appropriate regulations.
C1.4. Design
General design requirements in relation to design works are included in Section 10. It sets out the
minimum standards required by Sydney Water.
C1.5.3. Records
Detailed records shall be kept of the quantity and type of recycled materials used in the Works.
C1.5.4. Certification
Where recycled and reused materials are used in the Works, certification shall be provided from an
independent asbestos assessor who is a current member of the Australian Institute of Occupational
Hygienists in the ‘asbestos’ category, or from a NATA laboratory accredited for asbestos fibre
identification. The certification shall state that the material is free from asbestos or asbestos
containing material in both friable and bonded forms.
C1.6. Survey
All necessary survey and setting out shall be to the dimensions and levels shown on the drawings.
All site set-out and survey work, where survey work also includes the production of WAC records,
shall be conducted in accordance with this specification as well as WSA02, WSA03 and WSA04, or
by project specific requirements as nominated by Sydney Water.
All survey work shall be undertaken by a Registered Surveyor.
Each photograph (i.e. digital image) shall be at least 150 x 100 mm when the document is printed at
1:1 scale and each print shall display the date of photography and have a resolution of at least 220
dpi.
The photographs are to be grouped in document chapters or sections which are representative of
each section of the work. Each chapter/section is to be referenced/indexed such that particular
properties and/or chainages can be examined.
Each chapter/section shall carry notation indicating:
Chainage at start and finish
Comments on any existing damage or faults, particularly where they are not obviously visible in
the photographs.
C2. Earthworks
C2.1. General
C2.1.1. Introduction
The technical specifications described in this section are for earthworks only.
C2.1.2. Setting Out and Construction Tolerance for Earthworks
Setting Out
Unless otherwise specified, the shall do setting out to the dimensions and levels shown in the
drawings as specified in C1.6.
In addition to requirements specified in C1, mark on the ground the position and extent of all
cuttings and embankments shown on the Drawings, and any cut/fill transitions, using pegs and
batter profiles or equivalent, prior to commencement of construction.
Backfill or Fill : Earthwork material used as trench fill or backfill or fill; as required by the design,
complying the minimum requirements specified within this section of the
specification
CBR : 4 days Soaked California Bearing Ratio test results as per AS 1289.6.1.1
Compaction : The process whereby the density of soil is increased by mechanical means. This
typically involves, rolling, impact or vibration, or a combination of these
processes
Cutting : An earth or rock excavation within the Site that is made below an existing
surface
Cohesive Soils : Those materials which have a well-defined moisture-density relationship when
tested in accordance with AS 1289.5.1.1 or AS 1289.5.2.1.
Cohesionless Soils : Poorly graded sand and gravel mixtures, generally with less than 5% fines (ie
finer than 75μm), which are non-plastic and which do not exhibit a well-defined
moisture-density relationship when tested in accordance with AS 1289.5.1.1 or
AS 1289.5.2.1.
Competent A third party Geotechnical Engineer who is suitably qualified and experienced to
Geotechnical Engineer: carry out the particular type of work listed in the project specific technical
requirements; in compliance with the Sydney Water’s Engineering Competency
Standard and accepted by Sydney Water, prior to working on the project.
Dewatering Proposal A Dewatering Plan, including a detailed hydrogeological assessment of all the
Plan : groundwater induced impacts on all assets owned by Sydney Water and others
Field Density Testing : Field bulk density tested using is the nuclear density gauge (in accordance with
AS1289.5.8.1) and moisture content measured in the laboratory.
Fill Embankment : An earth or rock fill structure above an existing and/or excavated surface to
create the required works within the site
Imported Material : Material obtained from sources other than that generated by excavation in
cuttings and other specified excavations within the Site
Paved or Trafficable Areas where vehicles are able to traffic or parked such as roads, carparks,
Areas : tracks, driveways, Road easement boundary to boundary
Pipe Embedment Fill material used to fill around the pipe, including bedding
Material :
Relative Compaction : The field dry density of soil expressed as a percentage of the maximum dry
density of the soil determined in the laboratory either by a standard or modified
proctor test
Site won material : Material that is obtained from excavations within the Site
Standard Dry Density Dry density ration determined using Standard Compaction Testing as per
Ratio : AS1289.5.1.1
Temporary Erosion and Control measures which are required in areas currently being worked and are to
Sediment Control : be provided, as and when required, on a day-to-day basis as the work
progresses
Topsoil : Topsoil is natural surface soil that may contain organic matter
WSAA Specifications
Water Services Association of Australia – Product Specifications for Products and Materials
International Standards
ASTM D4647 – Standard Test Method for Identification and Classification of Dispersive Clay Soils
by the Pinhole Test
ASTM D4546-14 – Standard Test Method for One-Dimensional Swell or Collapse of Soils
to commencement of the stripping of topsoil, to ensure effective and continuous erosion and
sediment control.
All temporary erosion and sediment control works shall be maintained in an operative condition at
all times. Silt shall be disposed of in such a manner so as not to cause further erosion and
sedimentation of the site.
Unless otherwise directed, temporary control measures are to be removed prior to the end of the all
construction activities and all materials used therein removed from the site.
C2.4.2. Clearing
The natural ground surface shall be cleared of all trees, stumps, roots and undergrowth, buildings,
fences, poles and debris, such as old foundations, buried pipelines and the like, in the nominated
areas within the construction area.
Tree stumps shall be removed for a minimum depth of 300mm below the designed excavation level
or finished level. Cavities formed by the removal of stumps and disused services shall be backfilled
with the naturally occurring surrounding material or fill material as required by the specific structures
or pavements at that location.
Trees outside the area of works to be cleared shall not be removed or lopped without the written
consent of Sydney Water.
C2.4.3. Stripping Topsoil
Topsoil removal shall not be commenced until:
Erosion and sedimentation controls measures have been implemented;
Clearing, grubbing and removal of cleared materials has been completed.
Before general excavation commences, the ground surface on which fill is to be placed and the area
from which cut is to be removed, shall be stripped of any existing topsoil.
The strip depth shall be a minimum of 150mm or deeper if required by Design and/or the Sydney
Water. Stripped surfaces shall be inspected by a Competent Geotechnical Engineer to confirm
removal of all topsoil.
C2.5. Excavation
All excavation shall be undertaken in accordance with the regulatory and legislative requirements, in
addition to the technical requirements set in this specification.
C2.5.1. Utilities, Services and other Hazards
Prior to commencing excavation, a review shall be undertaken to identify the hazards, assess the
risks and implement control measures. A work method statement shall be prepared for all
excavation works.
No excavation shall occur until;
up-to-date services searches have been completed,
all identified services affected by the earthworks have been physically located and
all necessary precautions to protect, isolate or secure the services have been taken.
No potholing by hand or mechanical means is allowed. All potholing shall be by non-destructive
hydro-vacuum excavation techniques to expose or excavate around underground services.
C2.5.2. Excavation Support
All excavation works more than 1.5m deep, shall require an excavation support system.
Details of the excavation support system shall be submitted for acceptance by Sydney Water, at
least 20 working days prior to the commencement of installation of excavation support system.
The excavation support shall be designed and installed to provide safety to all persons in and
adjacent to the excavation, and to prevent damage to all existing utilities, services, structures,
building and roadways in the vicinity. Where required, dilapidation surveys, prior to installation of
excavation support, dewatering and excavation works shall be undertaken.
The design of the excavation support system shall be prepared and certified by a Competent
Geotechnical Engineer and where applicable, by a Competent Structural Engineer; who meet the
requirements of the Sydney Water Engineering Competency Standard.
C2.5.3. Temporary Fencing and Signage around Excavation Works
Suitable temporary fencing, barriers, handrails and signage shall be erected around all excavations.
C2.5.4. Groundwater Control
Drains, sumps, pits, water channels and the like shall be constructed as required, and any pumping
plant as may be necessary to prevent water from entering or to remove water from the excavation
shall be employed.
If dewatering is proposed, a Dewatering Proposal Plan shall be submitted to the Sydney Water 20
working days prior to any dewatering activity, for acceptance and any such operation shall not
commence acceptance has been given.
Appropriate investigations must be undertaken and control measures implemented to avoid any
damage to structures, buildings and roadways. A detailed hydrogeological impact assessment shall
be carried out; including any control measures implemented, to prevent any damage on all existing
assets, due to the dewatering exercise. The assessment shall be included as part of the Dewatering
Proposal Plan.
Water from excavations shall be discharged to the nearest suitable discharged point approved by
the relevant authorities and accepted by Sydney Water.
C2.5.5. Trenches for Pipe
The line, level and grade of the trenches shall be such as to allow pipelines to be laid as specified
herein or as shown in the drawings.
Trenches for pipes shall be excavated to a width and a depth sufficient to enable the pipe, joint,
bed, haunch or surround shown in the drawings to be accommodated. Additional excavation shall
be provided at the joints to allow for jointing of the pipes.
The width of the trench shall not exceed the limiting width between the faces of the soil that has
been used in the structural design of the pipeline. No pipe shall be laid prior to compacting bedding
material and compacted fill below the bedding layers.
All efforts shall be made to avoid disturbing the finished trench formation. Any wet or soft materials
shall be excavated and made good to the satisfaction to Sydney Water .
C2.5.6. Excavation in Watercourses
Excavations in watercourses are not permitted, unless specifically accepted by Sydney Water .
C2.5.7. Blasting
Explosives or any form of blasting techniques in excavation shall not be used unless specifically
accepted by Sydney Water.
C2.6. Stockpiling
C2.6.1. Stockpiling Areas
Stockpiling areas shall be nominated and submitted for acceptance by Sydney Water prior to any
stockpiling works. A Stockpiling Plan shall be produced which as a minimum includes the following
details of the stockpile:
location,
dimensions,
environmental control measures,
statutory approvals and consents.
This plan must be submitted for review and acceptance by Sydney Water at least 20 working days
before stockpiling.
C2.6.2. Stockpiling of Topsoil
Topsoil material that are stockpiled within Sydney Water sites shall meet the following requirements:
be free from subsoil, other excavated materials, contaminated materials, refuse, clay lumps and
stones, timber or other rubbish;
be trimmed to a regular shape to facilitate quantity measurement, and with a height not
exceeding 2 m and batter slopes not steeper than 2H:1V;
batters track rolled or stabilised by other means acceptable to the Sydney Water; and
be seeded with a sterile cover crop in accordance with Specification RMS R178, to encourage
vegetation cover. Seeding must be carried out progressively within seven days of completion of
each 500 m2 of exposed batter face.
have silt barriers or temporary drainage to prevent the stockpiled topsoil being washed away.
No traffic shall be allowed on or across stockpiles.
C2.6.3. Stockpiling of Contaminated or Unsuitable Material
Stockpiling of contaminated or unsuitable material is not permitted within the works Site unless
otherwise specifically accepted by Sydney Water.
Property Requirement
Particle size distribution:
Percentage passing AS Sieve (by mass)
53 mm 100%
37.5 mm >60%
2.36 mm <50%
75 µm <15%
Coefficient of uniformity (D60/D10) ≥5
Where the paved areas are located within Sydney Water owned land and no specific requirements
are noted, trench backfill shall be as follows:
Trench Backfill material,1m below finished surface levels shall exceed or comply with the
requirements specified in C2.7.6
Trench Backfill material within 1m from finished surface levels and below subbase, shall comply
Select Fill material properties, specified in Table 2-1
Any granular Pavement Base and Subbase material shall comply with RMS QA Specification
3051
C2.7.8. Minimum Frequency of Testing of Source Material
All recommended tests, including Atterberg limits, soaked CBR, dispersivity potential, free swell
index and soluble content shall be carried out as minimum one test per 1000 cubic metres of
material or part thereof. A minimum of three tests shall be carried out per material type and source.
C2.7.9. Filtration Geotextiles
All filtration geotextiles materials shall comply WSA PS 355.
C2.7.10. High Strength Geosynthetics
High strength Geosynthetics including high strength geotextile and geogrid material shall comply
with RMS QA Specification R67.
C2.7.11. Non-Standard Materials
Any non-standard material that are not included in the above specifications (including recycled
material) shall be submitted to Sydney Water for review and acceptance with all necessary testing
details and suitability certification from a competent geotechnical engineer, a minimum 20 working
days prior to being imported to site and/or placed.
C2.8. Compaction
C2.8.1. Compaction Quality Assurance Plan
A Compaction Quality Assurance Plan shall be produced and submitted to Sydney Water for
acceptance. It shall include, but not limited to the following:
The details of the compaction plant to be used on site.
The locations such plan will be used on site.
The loose layer thicknesses to be employed where fill is placed.
The compaction standard to be achieved for each location.
The systematic pattern of compaction to be employed on site.
The visual observation requirements used to identify areas of unacceptable and acceptable
compaction.
The rectification methods to be used to rectify area of unacceptable compaction.
The method to be employed to correlate the locations of placed material against compaction
test and material test results.
The compaction testing requirements for each compaction location to confirm that material has
been homogenously compacted; noting any difference in compaction technique used. Such as
where hand held compaction equipment are to be used.
The materials testing requirements needed to achieve a homogenous material, or alternatively,
the quality assurance certificates and testing results to be provided where manufactured fill
products are brought to site.
A detailed Inspection Test Plan covering all of the points noted above, as a minimum
Level 1 geotechnical inspection shall be provided in accordance with AS3798 for all earthworks
exceeding 3.0m fill or backfill thickness.
Where the property owner or road authority or an alternative specification such as the RMS
Specification or subdivision earthworks specification requires a higher compaction level, the highest
compaction requirement shall be followed.
C2.8.5. Non- Conforming Test Results
When test results are deemed not to comply with the minimum compaction requirements, the entire
compaction layer associated with that test result, and any layers above, shall be removed and
replaced in accordance with the requirements of the accepted Compaction Quality Assurance Plan.
Compaction testing shall be carried out on the replacement material and provided to Sydney Water
for review. No further material shall be placed above the replacement layer until accepted by
Sydney Water.
Following identification of a failed compaction test, a quality incident shall be raised with Sydney
Water and an investigation shall be undertaken to identify the root cause of the failed test. The
quality incident shall then identify what changes need to be made to the Compaction Quality
Assurance Plan.
No further compaction work shall take place until Sydney Water has reviewed and accepted the
revised Compaction Quality Assurance Plan.
C2.11. Records
C2.11.1. Volume of Material
Once excavation works are complete, records of all excavated material; including suitable and
unsuitable material shall be recorded and reported to Sydney Water, with all necessary test and
inspection results.
C2.11.2. Inspection Reports
All inspections reports and verification testing shall be completed by a Competent Geotechnical
Engineer and shall be submitted to Sydney Water, within 20 working days to facilitate necessary
acceptance and release of Hold Points when applicable.
Hold Relevant
Process Held Required Documentation
Point No. Clause(s)
EHP4 Excavation in Provide all necessary control plans as required and C2.5.6
watercourses agreed with Sydney Water, based on project
specific requirements.
EHP5 Blasting Provide all necessary control plans as required and C2.5.7
agreed with Sydney Water based on project specific
requirements.
Hold Relevant
Process Held Required Documentation
Point No. Clause(s)
EPH7a Importing any Test results of the source material AND C2.7 &
material related to 2.8
Compaction Quality Assurance Plan for the
earthworks
proposed material with the assessment of suitability
by Competent Geotechnical Engineer
EPH7b Commencement of Test results of the source material AND C2.7 &
placing fill material 2.8
Compaction Quality Assurance Plan for the
sourced within the
proposed material with the assessment of suitability
site
by Competent Geotechnical Engineer
EHP8 Placement and Compaction test results for each layer of C2.8
compaction of each compaction from preceding total thickness of 1.5m
subsequent layer of Fill placed.
fill or backfill
C3.3. Definitions
The following definitions apply to this Specification:
Cement : Material conforming to AS 3972. It comprises Portland cement and blended
cements.
Concrete: A thoroughly mixed combination of cement, aggregates and water, with or
without the addition of chemical admixtures or other materials, all of which
separately and when combined conform to the requirements of this
specification.
Curing: The control of temperature and moisture in the concrete until the concrete
has developed the required properties.
Cover: The distance between the outside of the reinforcement and the nearest
permanent surface of the member excluding any surface finishing material or
protective coating.
Construction Joint: A joint that is located in a structure for convenience of construction and
made so that the load bearing capacity and serviceability of the structure will
not be impaired by the inclusion of the joint.
Movement Joint: A joint that is made between parts of a structure for the specific purpose of
permitting relative movement between the parts of the structure on either
side of the joint.
Nozzle: Attachment at end of delivery hose from which shotcrete is projected
Overspray: Material projected outside the intended receiving surface
Rebound: Shotcrete material that bounces off the receiving surface
Shotcrete: Concrete pneumatically projected onto a surface at high velocity
SCMs: Supplementary cementitious materials (SCMs) are in the form of fly ash,
slag or silica fumes that may be blended in the cement or supplied
separately to the concrete batching plant
Wet-mix Shotcrete: Shotcrete in which cement, aggregate and water are first mixed together
before introduction as concrete into the delivery hose
Water/Cement Ratio: The ratio, by mass, of total free water including water contained in admixture
solutions, to total cement including all supplementary cementitious materials,
in the concrete mix.
C3.4. Supervision
The concrete supervisor shall be a suitably experienced person accepted by Sydney Water. The
supervisor shall supervise the delivery and placing of all concrete works and shall prepare and
submit to Sydney Water a daily report on all concrete placed. The report shall contain the serial
number of the identification docket for each batch, the classes of concrete, the volume of each
batch, the measured slump, the identification test specimen made, the amount of water, if any,
added on site, the location and the climatic condition during the pour.
The records of mill certificates of all reinforcement and prestressing tendons delivered shall be
retained on site and submitted to Sydney Water when requested.
C3.5.2. Cement
The cement used shall generally be Type GP – general purpose Portland cement to AS 3972.
Where specified, or with the acceptance of Sydney Water, general purpose blended cement (Type
GB), sulphate resisting cement (Type SR), shrinkage limited cement (Type SL) or other types of
special purpose cement shall be used.
C3.5.3. Fly Ash
Fly ash shall be “fine” grade and shall comply with AS 3582.1. The maximum amount of fly ash
shall be 25% by weight of the total cement material.
C3.5.4. Slag
Slag shall be from iron blast furnace and shall comply with AS 3582.2. The maximum amount of
slag shall be 50% by weight of the total cement material.
C3.5.5. Silica Fume
Silica fume shall comply with AS 3582.3. The maximum amount of silica fume shall be 10% by
weight of the total cement material.
C3.5.6. Supplementary Cementitious Materials
The total amount of supplementary cementitious materials shall not be more than 60% by weight of
the total cement material.
C3.5.7. Aggregates
Coarse and fine aggregates for concrete shall comply with the requirements of AS 2758.1. The
maximum nominal size of aggregate shall be 20 mm in reinforced concrete and 40 mm in
unreinforced concrete. Coarse aggregate shall consist of clean, hard, durable particles substantially
retained on a 4.75 mm sieve and shall be obtained from dense, naturally occurring or manufactured
gravel or rock Fine aggregate shall consist of clean, hard tough, durable, uncoated grains, uniform
in quality, comprising material of which not less than 90% passes the 4.75 mm sieve. Recycled
material or slag products shall not be used as an aggregate unless specified otherwise or accepted
d by Sydney Water. All materials shall be free from hazardous substances such as asbestos or
asbestos containing materials.
For special class concrete, the aggregates shall comply for exposure classification “C” of Table 4 of
AS 2758.1.
For normal class concrete, the aggregates shall comply for exposure classification “B1” of Table 4 of
AS 2758.1
The water absorption of aggregate shall be less 3 % when tested in accordance with AS 1141.
The alkali reactivity of the aggregate shall be assessed to Clause 10 of AS 2758.1. When
aggregates are assessed to have a potential for aggregate alkali reaction, they may be used only in
normal class concrete with appropriate safeguards subject to the acceptance by Sydney Water.
Aggregates that are assessed to have a potential for aggregate alkali reaction shall not be used in
special class concrete.
C3.5.8. Water
Water used in the manufacture of concrete shall comply with AS 1379.
C3.5.9. Chemical Admixtures
Admixtures that enhance the workability, reduce water/cement ratio, control slump, minimise
shrinkage and control the setting time of the concrete may be included in the mix in a control
manner, provided they have been proven not to impair the performance concrete.
Where two or more admixtures are proposed for incorporation into a concrete mix, the
manufacturers shall certify the compatibility of the admixtures.
Air-entraining admixtures may be used provided that the air content, determined in accordance with
AS 1012 does not exceed 4%.
All admixtures shall comply with AS 1478.
Notes:
1. Type SR shall be used for sewerage structures including access chambers. Type SL shall be used for
other than sewerage structures including stormwater channels
2. Except for tremie concrete.
37.5 100
19 85 – 100
9.5 0 – 20
4.75 0–5
10-23 2.00
24-26 1.50
27-29 1.00
30-32 0.75
Sydney Water may extend these times in special circumstances provided that the concrete
complies with the specified performance requirements, including slump.
C3.7.5. Temperature at Point of Delivery
Concrete shall not be delivered if its temperature at the point of discharge from the transport vehicle
is less than 10°C or more than 32°C.
In horizontal forms such as for slabs, concrete shall not be allowed to drop into place from a height
exceeding 1.5 m.
Concrete shall not be moved horizontally by the use of vibrators.
If during the progress of the work, if nominated Sydney Water finds that the concrete being placed
does not meet the specified requirements, or is in any way unsatisfactory, he may make direction to
alter the mix design and/or carry out new trial mixes.
Under conditions of rain, the placing of concrete shall not commence or shall be stopped unless
adequate protection is provided to prevent damage to the concrete and the washing of the concrete
surface. Concrete exposed to rain before it has set shall be liable to rejection.
C3.8.3. Sequence of Pours
The proposed pour sequence and the location of construction joints shall be submitted to Sydney
Water for acceptance..
Shrinkage effects shall be minimised by pouring the concrete sections between construction joints
in a sequence such that there will be suitable time delays between adjacent pours.
C3.8.4. Compaction
Concrete shall be compacted immediately after placing by means of internal and /or external
vibration. Vibration shall be carried out in a regular and systematic manner to ensure that all
concrete is thoroughly compacted. Vibration shall be applied to the full depth of each layer and
extended into the top 100 mm of the underlying layer. Concrete shall not be vibrated to the extent
where segregation of the ingredients occurs.
Vibrators shall be of the rotary out of balance type and shall be checked prior to use to ensure
proper working order.
Internal vibrators shall have a minimum diameter of 50 mm and an operating frequency range
between 130 Hz and 200 Hz.
The number of working internal vibrators in use for compacting concrete during a concrete pour
shall not be less than one for each 10 cubic metres of concrete placed per hour, with a minimum of
two. The number of standby vibrators shall be not less than one quarter of the number of vibrators
in use with a minimum of one. Vibrator used for spreading concrete shall not be counted in the
number of vibrators used for compaction.
Internal vibrators shall be inserted vertically at spacing not exceeding 350 mm. The vibrator shall be
left in place for at least 7 seconds until the air bubbles cease breaking the surface, and then
withdrawn slowly. Vibrators shall not be allowed to rest on the reinforcement.
In regions of closely spaced reinforcement, full compaction of concrete directly beneath the closely
spaced horizontal reinforcement shall be achieved prior to encasing the reinforcement with
concrete.
C3.8.5. Placing in Water
Concrete shall not be placed under water unless accepted by Sydney Water. . Details shall be
submitted to Sydney Water of the proposed method of placement prepared by a concrete
technologist experienced in this type of work.
C3.8.6. Cold Weather Concreting
Concrete shall not be placed if the ambient temperature is below 5°C or expected to fall below 5°C
in the 24 hrs after placement.
C3.8.7. Hot Weather Concreting
The placing of concrete in hot weather shall be regulated by approved methods to avoid premature
stiffening. Concrete shall not be placed if the ambient temperature is above 35°C.
< 60 + 10
60 - 80 + 15
80 - 110 + 20
110 - 150 + 30
> 150 + 40
If the measured slump is not within the specified limits, one repeat test shall be made immediately
from another portion of the sample. If the value obtained from the repeat test falls within the
specified limits, the concrete represented by the sample is deemed to conform. Otherwise it shall be
rejected.
C3.12.5. Compressive Strength of Cylinder Specimens
The compressive strength of each cylinder specimen shall be determined, recorded and reported in
accordance with AS 1012.9 by a NATA-approved laboratory.
The compressive strength of a concrete sample shall be the average strength of the two cylinder
specimens taken from the sample and tested at the same age. If the two results differ by more than
10% of their average, the cause for such excessive difference shall be investigated. Inclusion or
exclusion of the specimen results shall be at the discretion of Sydney Water.
The compressive strength of any concrete sample shall not be less than the characteristic strength
of the concrete class.
Where the strength of a sample is less than the characteristic strength, the cause of the non-
compliance shall be investigated and an engineering assessment report shall be submitted to
Sydney Water for a acceptance. Acceptance of the concrete represented by the sample shall be at
the discretion of Sydney Water . Concrete with strength less than 0.85 of the characteristic strength
shall be rejected.
C3.13. Joints
C3.13.1. Construction Joints
The locations of construction joints shall be as nominated in the drawings and they shall not be
altered without the acceptance of Sydney Water.
All construction joints shall be formed perpendicular to main axes of the member. The deviation of
any point on the construction joint from a straight line joining any two points on the joint shall not
exceed 1/250 times the distance between the points or 5 mm, whichever is greater.
Vertical construction joints shall not be permitted in the walls of reinforced and prestressed concrete
liquid retaining circular tanks.
All construction joints in contact with liquid shall incorporate suitable water stop in the middle of
walls and underside of floor slabs and also joint sealants in a preformed groove on the liquid faces.
C3.13.2. Preparation of Surface at Construction Joints
The surfaces of previously placed concrete at construction joints shall be roughened by removing all
laitance and sufficient mortar to expose aggregates to a depth of 3mm.
Coarse aggregates which do not remain firmly embedded in the mortar matrix and laitance from
projecting reinforcement from previous pour shall be removed.
Immediately prior to the placement of adjoining concrete, the surface of the construction joint and
the projecting reinforcement shall be washed clean, and the concrete surface shall be saturated
with water, following which all excess water and loose material shall be removed.
At least seven (7) working days prior to proposed placement of concrete, Sydney Water shall be
notified for acceptance of completed construction joint preparation.
Notification of the completed construction preparation shall constitute a Hold Point
C3.13.3. Movement Joints
The locations of movement joints shall be as nominated in the drawings and they shall not be
altered without the acceptance of Sydney Water.
The movement joints shall have adequate shear strength in the transverse direction to prevent
differential movement either by an adequately proportioned concrete shear key or grade 316
stainless steel dowels. Location of the joints shall be such that the stiffness of the adjoining
members is compatible.
All dowels shall be accurately positioned at right angles to the mating surfaces and rigidly held in
position prior to depositing concrete. A tolerance of no more than 1 in 100 shall be permitted on the
alignment of the dowels. The unbonded end of dowels shall be coated in an approved bond breaker
such as hot 60 -70 Grade bitumen. At expansion joints, the unbonded end of the dowel shall be
sheathed with a dowel cap containing a minimum of 15 mm compressible packer.
All movement joints in contact with liquid shall incorporate suitable water stop in the middle of walls
and underside of floor slabs and also joint sealants in a preformed groove on the liquid faces.
All movement joints in stormwater channels and culverts shall be provided with suitable water stops
and joint sealants.
C3.13.4. Filler & Sealant in Joints
Fillers and sealants shall be as specified in the drawings and they shall not be altered without the
written acceptance of Sydney Water. Where not shown, the minimum depth of sealant in joints shall
be 15mm. The applicator installing the fillers and sealants shall be approved by the product
manufacturer and accepted by Sydney Water.
Fillers and sealants for the joints shall be applied strictly in accordance with the manufacturer’s
written instructions. If these are not adhered to, including directions regarding mixing, pot life,
placing temperature, over-heating, etc., any affected material not yet placed shall be discarded and
any affected material already placed shall be removed and replaced. Where priming is specified,
the primer shall be compatible with the sealant as recommended by the manufacturer.
Prior to the application of primer or sealant, all joint grooves shall be cleaned for the full depth to
ensure the groove faces are free of any loose particles or other defects that would impair bond with
the sealant. Any excess mortar or concrete shall be removed from the joint and any defects
repaired, prior to the application of the sealant.
C3.13.5. Water stops
The installation and jointing of water stops shall be strictly in accordance with manufacturer’s
specification. The jointing of PVC water stops and repairs to damaged PVC water stops shall only
be carried out by using heat welding.
The PVC water stops shall be of sufficient stiffness and be secured in its place firmly in accordance
with manufacturers recommendation so that they remain in the correct position during concreting.
The PVC water stops shall be located in the middle except for the externally placed PVC water
stops in floor slabs. Where not shown, a minimum clearance of 50 mm shall be maintained from the
nearest face of reinforcement.
Hydrophilic expanding water stops shall be either set in a groove or fixed in its position so that they
remain in the correct position during concreting.
C3.15. Formwork
C3.15.1. General
Formwork, including all supporting members shall conform to the requirements of AS 3610.
Formwork shall be designed to account for all load cases in accordance with AS 3610. The design
and details shall also account for traffic impact, ground condition, flooding and any other applicable
conditions. Where formwork is re-used, the design shall allow for the deterioration of the materials
through use and handling.
Formwork shall be so constructed that the concrete can be properly placed and thoroughly
compacted and that the hardened concrete shall conform accurately to the required shape, position
and level, and to the finishes specified. Care shall be taken in the design of the tightness of the
joints during concreting and vibrating operations. All joints in formwork as erected shall be mortar
tight.
Formwork shall be fabricated with a "Plasply" surface or equivalent phenolic coating, steel plate or
accepted equivalent. .Joints shall be minimised on the formwork surface by the use of full size ply
sheets or by grinding flush welds or by other accepted method of surface preparation. Formwork
openings or removable panels shall be provided in vertical forms where necessary for inspection
and cleaning.
Oil used on formwork against surfaces to be exposed shall be of a type that will not stain or
discolour the concrete surface.
Formwork bolts shall be designed so that they may be extracted without damaging the surrounding
concrete. The embedded part of all form ties shall be located no closer than 50 mm to the surface of
the finished concrete. All holes left by form shall be filled with cement grout to match the concrete.
C3.15.2. Formwork Documentation
All relevant construction requirements listed in the project documentation, including the design
assumptions and footing design, shall be noted clearly on the formwork drawings. Pre-camber
diagrams where required shall be included in the formwork documentation. The formwork drawings
shall be sufficiently comprehensive so that erection and inspection can be carried out without
reference to any other documentation.
Documentation, as defined in AS 3610, that describe the formwork assemblies to be erected,
together with a certification shall be submitted to Sydney Water.
C3.15.3. Submission of Formwork Documentation and Certification
At least Twenty (20) working days prior to the commencement of erection of formwork, the formwork
documentation shall be submitted to Sydney Water for acceptance. The documentation shall be
certified by a practising Structural Engineer with the relevant experience in the design of formwork
and a current chartered member of the Institution of Engineers Australia with the relevant
experience in the design of formwork.
Submission of formwork documentation and Certificate shall constitute a Hold Point.
C3.15.4. Test Panels
When test panels are required, they shall be designed and constructed in accordance with AS 3610.
The method of constructing the test panels shall simulate concreting operations under conditions
which reasonably represent the field conditions.
C3.15.5. Removal of Formwork
Formwork shall be removed in such a way and such a time as to achieve the specified
characteristics of concrete, prevent damage to the concrete, and maintain safety at all stages of
removal. Unless otherwise accepted by Sydney Water in writing, superimposed loads to any part of
the structure shall not be applied until the design concrete strength has been achieved.
C3.15.6. Minimum Time for Stripping of Formwork
Unless accepted by Sydney Water in writing, the minimum time for stripping of formwork shall be as
stated in Table 3-6.
Table 3-6 Minimum Time for Stripping of Formwork
Bar chairs on moisture barriers or membranes shall be placed on a metal or plastic plate to prevent
damaging the membrane.
C3.18. Shotcreting
C3.18.1. General
Unless accepted by Sydney, shotcrete shall be applied using the wet mix process.
C3.18.2. Equipment
The type and capacity of the proposed shotcrete equipment shall have performance records of
successful application
Equipment shall be capable of allowing the shotcrete to leave the nozzle in a continuous
uninterrupted stream. Equipment shall be capable of achieving the required level of compaction and
quality whilst minimising rebound and overspray.
Delivery hoses shall have an internal diameter of at least 1.33 times the maximum length of fibres to
be used or five times the maximum size of the aggregates to be used. Dispensing devices for
admixtures added at the nozzle shall be mechanically regulated and have calibrated meters.
C3.18.3. Applicator
Application of shotcrete shall only be undertaken by specialist operators experienced in this type of
work. A minimum of 14 working days prior to the commencement of shotcreting, full details and
relevant experience of the operator shall be submitted to Sydney Water for acceptance. If during the
course of the work, Sydney Water determines that the specialist operator is not sufficiently skilled
or experienced in the application of shotcrete, acceptance to the use of that operator may be
revoked.
Submission of details of the proposed shotcrete applicator shall constitute a Hold Point.
C3.18.4. Shotcreting
The procedure, equipment and personnel involved in shotcreting shall produce an end product that
is dense, homogenous, without segregation of aggregates or fibres and without sloughing,
collapsing, excessive rebound or other visible imperfections. Rebound material shall not be worked
into the construction or re-used in the works.
Shotcrete shall be applied in layers not exceeding 150 mm in thickness and with adequate adhesion
to the surface or previous layers of shotcrete to prevent sagging or slumping.
The shotcrete shall emerge from the nozzle in a steady, uninterrupted flow. Where the flow
becomes intermittent for any reason, it shall be directed away from the works until it becomes
constant.
The distance of manually held nozzles from the receiving surface shall be between 0.5 m to 1.0 m.
Nozzles shall be held perpendicular to the receiving surface, except where necessary an angle of
up to 30° to the vertical may be permitted.
For vertical and near vertical surfaces, application of shotcrete shall commence at the bottom of the
surface with full thickness applied before applying any shotcrete overhead.
If shotcreting is terminated for any reason, the hardened concrete surface shall be prepared in
accordance with this specification before shotcreting is resumed.
C3.20.2. Tolerances
Box culverts and open channels shall be constructed to the tolerances specified Table 3-7
Precast concrete box units Step between On the internal faces of floor of adjacent units 5 mm.
units On the internal faces of walls and roof 20 mm
C3.20.3. Inspection
On completion of the works, a visual inspection of the box culverts and open channels or arrange
for closed circuit television (CCTV) inspections of all box culverts with dimensions that restrict
human access, shall be carried out to verify that the works have been constructed within the
specified tolerances, free of any waste construction material left inside and to check for visible signs
of defect.
A report of these inspections and any nonconformity detected along with the video recording taken
during CCTV inspections Shall be submitted to Sydney Water.
The inspection and reporting shall be in accordance with WSA 05- Conduit Inspection Reporting
Code of Australia.
Prior to commissioning the tank, the procedures and acceptance criteria detailed in Sydney Water
Standard Operating Procedure (SOP) WPIMS5261 shall be followed.
ASTM International:
ASTM F1962 Standard Guide for Use of Maxi-Horizontal Directional Drilling for Placement
of Polyethylene Pipe or Conduit Under Obstacles, Including River Crossings
PVC-U pipes and fittings for drain, waste and vent applications shall comply with the requirements
of AS 1260.
PVC-O pipes shall be Series 2 – Cast Iron Outside Diameter (CIOD) series complying with the
requirements of AS 4441. Minimum material class shall be Class 450.
PVC-M pipes shall be Series 2 – Cast Iron Outside Diameter (CIOD) series complying with the
requirements of AS 4765.
The installation of PVC pipeline systems shall in general be in accordance with AS 2032.
C4.3.7. Vitrified Clay Pipes
Vitrified clay (VC) pipes and fittings shall comply with the requirements of AS 1741.
C4.3.8. Concrete Pipes
Precast concrete pipes for pressure and non-pressure applications shall generally comply with the
requirements of AS 4058.
Reinforced concrete pipes with flexible thermoplastic lining sheet for the purpose of protecting the
concrete from corrosion in aggressive sewage environment shall comply with the requirements of
WSA 113.
C4.4. Joints
Rubber ring and mechanical couplings shall be made using elastomeric gaskets and O-rings to
affect the pressure seal.
Flanges shall be manufactured to the requirements of AS 2129, AS 2528, or AS 4087 as is
appropriate for the design pressure ratings. Flanges shall be drilled as stated in the drawings.
Gaskets shall comply with the requirements of AS 1646 and WSAA specification WSA109.
Drawings of all joints, showing material type, dimensions and tolerances shall be provided to
Sydney Water. Details of any necessary testing reports certifying the performance of the proposed
jointing system shall also be supplied when applicable
Site specific purpose designed thrust blocks shall be provided to ensure that all thrust is resisted by
natural in situ material having adequate bearing capacity.
Thrust forces for parallel pipelines inside at bends shall be transmitted to the outside trench face
without allowing transfer of any part of the inner loading to the outer pipeline. Alternatively, where
trench material has low bearing capacity, which would result in impractical sizing, these blocks may
be keyed to underlying sub grade or both providing adequate structural capacity is achieved.
All field-welded joints shall also be inspected by Sydney Water before any protective coating or
concrete encasement is placed around the outside of the joint.
The structural strength of the carrier pipe shall be checked for installation in the proposed bore
profile and shall withstand all temporary loads during installation, which shall include but be not
limited to the following:
Pre-installation Loads
Hydrostatic test loads.
Self weight spanning between supporting rollers.
Installation Loads
Bending stresses due to radius of curvature.
Stresses due to frictional drag within the hole, ground surface and bends.
Stresses due to frictional drag between pipe and drilling fluid.
Stresses due to frictional drag between pipe and side of hole.
Stresses due to torsional force.
Hydrostatic load due to groundwater, etc.
Earth overburden loads.
Loads resulting from drilling fluid and/or grouting, if any.
All precautionary measures must be taken to avoid damaging the conveying pipe during installation.
During installation, the installation force shall be controlled to avoid overstressing the conveying
pipe. Once any section of pipe is completed it shall be capped off to prevent entry of personnel or
debris, until the adjacent section is ready for connection.
Prior to commencement of work on site, a drilling procedure and method statement shall be
developed and submitted to Sydney Water.
The drilling method shall incorporate a system that will allow tracking of the drilling equipment for
the entire length of the bore or at any section deemed critical by Sydney Water. The system shall be
capable of measuring the elevation, azimuth and gradient of the bore path.
Set-out and alignment survey marks shall be placed and maintained during construction for
verification of the alignment of the works at any time. These shall be transferred to the working area
as required to ensure correct alignment of the invert of the completed pipeline.
Logs shall be containing the dates, times and location, soil conditions, data such as depth, grade
and rate of penetration and utility crossings.
Computer data sheets from survey, guidance and control systems shall also be maintained. These
boring/drilling logs and data sheets shall be made available to Sydney Water for inspection during
the progress of work. On completion of the works, these records shall be submitted to Sydney
Water.
The allowable tolerance for the final position of the carrier pipe shall be:
Tolerance from Target.
The centre of the finished bore at the exit shall lie within a 1.0 metre diameter circle centred on
the designed target.
Tolerance from Grade
Reasonable care shall be taken to achieve the design profile of the carrier pipe. The finished
pipeline shall be smooth in grade and shall not have any reversed grade to that of the design
grade that could result in ponding of flow.
Care shall be taken to control, contain and manage the effects of the ingress of any ground water.
Remedial treatment of joints, fractures and any other defects in the soil strata shall be undertaken in
the event of drilling fluid loss.
The proposed grouting procedures shall be submitted to Sydney Water. It is required to
demonstrate that the proposed grout mixture(s) meet the requirements of this specification and shall
include the provision of material data sheets for the proposed grouting materials to be used. The
method to achieve the grouting at the specified locations shall ensure complete filling of the annulus
and shall be subject to the review and acceptance of Sydney Water. Records shall be maintained
of all grouting operations, which shall include but not be limited to the location of all grout lines,
volume of grout pumped, grouting pressures, commencement and completion times and grout
mixture details. One copy of this record is to be submitted to Sydney Water at the completion of
each day that grouting is undertaken.
The grout composition shall ensure that the following properties are attained:
The grout shall provide an effective stoppage of water ingress and create a permanent seal
between the borehole and the conveying pipe.
The grout shall not undergo any shrinkage.
The grout shall be of a low-heat characteristic during the curing stage.
The cured grout shall be impermeable and not develop micro cracks and paths for water flow.
The adhesive properties of the grout shall ensure no shear movement exists between the
borehole and the grout and the conveying pipe and the grout.
The grout shall remain structurally sound over the long term.
The grout composition shall allow for ease and confidence of placement at the required
location.
The grout composition shall have no adverse effect on the conveying pipe.
The grout shall be compatible with the site conditions and be environmentally harmless.
Grouting shall start at the downstream end of the borehole and shall proceed in a continuous
manner. Prior to and during the entire grouting operation, the carrier pipe shall be filled full with
water.
Drilling fluids to be used shall be environmentally sound and bio-degradable.
Extreme care shall be taken in minimising the loss of drilling fluids into the ground or the
environment. Returned fluids shall be properly contained, reclaimed and recirculated.
Precautionary measures shall be undertaken to minimise the impact of any inadvertent spillage of
fluids on return or at exit of the drill hole. The mixing, storage, and use of drilling fluids shall be
managed so as to prevent spillage to the environment. Drilling fluid shall be disposed of off-site in a
manner acceptable to the authorities.
Any failed bore that cannot be salvaged shall be plugged and cement grouted.
Temporary anchor or thrust blocks shall be constructed as required at the ends, bends and branch
outlets. All concrete anchor blocks shall have achieved the necessary concrete strength before
proceeding with the testing.
C4.22.2. Disinfection of Water Mains
Unless directed otherwise by Sydney Water, disinfection of all potable water mains shall be carried
out before they are placed into service.
Requirements for disinfection are laid down in Sydney Water’s Standard Operating Procedure
(SOP) WPIMS 5027 – Disinfecting New Water Mains, and the WSAA Water Code (Sydney Water
Edition).
C4.22.3. Water for Pressure Testing and Disinfection
Unless directed otherwise, water for pressure testing and disinfection shall be obtained from Sydney
Water’s distribution system.
The total volume of water used for testing and disinfection shall be minimised by re-using water from
a completed section of the main in other sections.
Following testing or disinfection the water shall be disposed of in the manner acceptable to all
statutory authorities including but not limited to local councils and Department of Environment and
Climate Change. The requirements of Sydney Water Standard Operating Procedure (SOP) WPIMS
5021- Discharge Protocols, shall be followed.
Prior to carrying out any testing, a management plan showing how water is obtained, used, reused
and disposed of at the end of testing works shall be submitted to Sydney Water.
C4.22.4. Bacteriological Test
Bacteriological tests shall be carried out on all new disinfected water mains in accordance with the
test procedure and the acceptance criteria stipulated in the WSAA Water Code (Sydney Water
Edition).
C5.5. Materials
C5.5.1. General
All materials supplied shall comply with standards and specifications shown in the drawings unless
otherwise specified.
All supplied structural steel and aluminium shall be manufactured by companies using quality
management systems certified to AS/NZS ISO 9001 by a third party accredited by the Joint
Accreditation System of Australia and New Zealand. All materials shall comply with the relevant
Australian Standards and specifications. A mill certificate with appropriate NATA registration from
the material supplier shall constitute documentary evidence of compliance.
C5.5.2. Steel
Structural steel shall comply with AS/NZS 3678, AS/NZS 3679 or AS 1163.
Stainless steel shall be Grade 316L to ASTM A240M and A276. Stainless steel shall be chromium
nickel austenitic and not hardenable by heat treatment.
Prefinished and pre-painted sheet metal products shall be of the suitable grade, coating class and
surface finish to AS 1397 and AS 2728, as specified.
C5.5.3. Aluminium
Aluminium shall be of the alloy suitable in all respects for the purpose being used and in accordance
with AS/NZS 1734 and AS 1866.
Unless specified otherwise, the minimum alloy for structural applications shall be 6061 or 6082 for
extruded members, 5251, 5454 or 6082 for sheets and plates and 5251 for roof sheeting.
C5.5.4. Bolted Connection
All metric bolts and nuts shall comply with AS 1110, AS 1111, AS 1112 and AS 1252. The threads
shall comply with AS 1275 and AS 1721.
All unified bolts and nuts shall comply with AS/NZS 2465. The thread shall comply with AS 3635.
A flat metal washer shall be fitted under each nut. Washers shall comply with AS 1237.
Bolt lengths shall be such that after joints are made up, the bolts shall protrude through the nuts by
a minimum of two full bolt threads, but not more than 15 mm.
As a minimum all bolts for structural steelwork and mechanical equipment shall be Grade 8.8 to AS
1252 or Grade 8 to AS 2465. Commercial bolts and nuts to AS 1111 are not permitted in steelwork,
except for connections of purlins and girts and in metalwork.
Unless noted otherwise, bolts, nuts and washers shall be galvanised to AS 1214. Where steelwork
is painted, bolts, nuts and washers shall also be supplied with adequate surface preparation and
painted on erection.
Grade 316 stainless steel bolts, nuts, screws and washers shall be used where:
In contact with liquid,
Buried in ground,
Cast into concrete,
Subject to corrosive environment including within 1 km from coastline,
In dismantling joints, gland joints and couplings,
For all propriety equipment such as valves, pumps etc.
The following measures shall be adopted to prevent galling of stainless steel fasteners:
Bolts and nut threads shall be rolled or buffed smooth before installation
Nuts shall be hand tightened at low speed to reduce heat generated by friction
Nuts shall be tightened with a torque wrench to prevent over-tightening.
Threads shall be thoroughly coated with a non-corrosive anti-seize compound prior to
assembly. If in contact with drinking water, the compound shall satisfy the requirements of AS
4020.
Where possible, significantly different hardness grade for nuts such as grade 431 shall be used
All bolts in contact with dissimilar material shall incorporate nylon bushes and washers.
Bolts for connections that are subject to vibration shall incorporate a locknut of the same material
and proof load.
C5.5.5. Fasteners
Fasteners in structural steelwork and aluminium include screws (including fully threaded bolt without
a nut), rivets, nails and proprietary anchors, bolts, clips and clamps.
Screws and nails shall not be used in members and components of thickness 3mm or more.
Screws shall be of Grade 316 to AS 2837 in stainless and aluminium work. Self-tapping and self-
drilling screws and nails may be supplied in Grade 316 stainless steel to AS 2837, subject to the
acceptance by Sydney Water.
Rivets shall not be used in members and components of thickness 3mm or more. Rivets shall not
be used to connect dissimilar metals together. Rivets joining metal parts shall be of the same type
of metal.
The use of proprietary anchors, bolts, clips and clamps shall be accepted by Sydney water.
C5.5.6. Selection of Material
Unless otherwise specified in the drawings the selection of material shall be as shown in Table 5-1.
All dissimilar metals shall be isolated from one another by an appropriate material as accepted by
Sydney Water.
C5.6. Fabrication
C5.6.1. General
Fabrication shall be carried out off-site to suit the assembly on site by means of bolted connections
and pins.
Proper allowances shall be made in detailing and fabrication for the correct fit of joints and
components, and also for proper access of wrenches, sockets and other tools for erection.
C5.6.2. Workmanship
Finished steelwork and aluminium shall be true and free from twists, kinks, buckles, open joints or
other defects. Accuracy shall be observed throughout to ensure all parts fit together properly on
erection. Chipping, sheaving and drilling shall be done accurately.
Before being marked off, straightening of any members shall be done by methods that will not injure
the material or member, such as by cold rolling or pressing. Straightening by hammering will not be
permitted. In addition, the following requirements apply where flame or heating methods are to be
used:
The temperature of the steel shall not exceed 600C and the temperature reached shall be
recorded.
Steel shall not be artificially cooled until the temperature of the steel has dropped below 300C.
Steel shall not be cooled with solid water jets.
Aluminium shall not be straightened by heating processes, unless carried out as detailed in
Section 6.3 of AS/NZS 1664.2.
All steelwork that will be exposed to view shall have spatter, flux, dags and burrs removed and
all weld profile ground smooth prior to surface preparation.
The completed work shall be free from distortions and true to dimensions. Due allowance shall be
made for dimensional changes during welding.
Accepted Materials*
Framing Members and Plates Roof and Wall Sheeting Holding Down Bolts
Location
Prefinished/
Stainless Hot rolled Cold formed Stainless Galvanise
Aluminium Aluminium prepainted
Steel Section Section Steel d Steel
sheet metal
(with appropriate
More than 1 km from (with appropriate
protective
the coastline Grade 316 protective coating Grade 316
coating as per
as per WSA 201)+
WSA 201)
Buildings and structures
Within 1 km from the (with appropriate
(with appropriate
coastline but remain protective
Grade 316 protective coating Grade 316
enclosed coating as per
as per WSA 201) +
WSA 201)
Within 1 km from
coastline generally (with appropriate
remain opened or not Grade 316 protective coating Grade 316
enclosed as per WSA 201) +
All members in clean (with appropriate
Tanks and Process Compartments
water tanks Grade 316 protective coating Grade 316
as per WSA 201) +
Members permanently
and periodically (with appropriate
submerged in liquid Grade 316 protective coating Grade 316
other than clean water as per WSA 201) +
Members not (with appropriate
submerged in liquid Grade 316 protective coating Grade 316
as per WSA 201) +
Members in high
corrosive environments
# Grade 316 Grade 316
Any cut surfaces to be used in the "as cut" condition shall have a surface quality which will not impair
subsequent fabrication and protective coating requirements. Flame cut surfaces may require a light surface
grind to render them suitable for subsequent protective coating requirements.
C5.6.7. Cutting Of Aluminium Components
Unless otherwise specified, aluminium work may be cut by plasma-arc cutting, sawing, grinding or shearing.
Flame cutting shall not be used.
Surfaces produced by such cutting shall be representative of good workmanship, finished square (unless a
bevelled edge is called for), true to the required dimensions and free from defects that would impair the
service performance or compromise the integrity of subsequent fabrication and protective treatment.
Grinding shall not be used on surfaces prepared for welding.
Re-entrant corners shall be smoothly rounded to a radius of not less than 3mm.
Unless shown otherwise in the drawings, all corners on exposed edges shall be rounded to remove sharp
edges, except where such edges are subsequently to be welded. Rolled and extruded edges need not be
rounded provided the corners are not sharp.
Plasma-arc cutting shall be carried out wherever possible by machines which are mechanically guided and
moved at uniform speed. Hand cutting shall only be used for secondary cuts, hole preparation, repairs and
other work where machine cutting is not possible.
Any cut surface to be incorporated in a weld shall comply with AS 1665.
Plasma-arc cutting of plates, sections and other components with surfaces which will be used in the "as-cut"
condition, shall be carried out with procedures giving minimum reduction on properties at the cut surface.
C5.6.8. Splices
Shop splices in the component parts of welded members shall be made before the parts are assembled.
Where splice locations are not shown in the drawings or where splices at locations other than those shown
in the drawings are proposed details of the design and position of the proposed splices shall be submitted to
Sydney Water at least twenty (20) working days for acceptance prior to fabrication.
The submission of proposed spice details shall constitute a Hold Point.
C5.6.9. Holes for Bolting
Unless otherwise specified, the diameter of boltholes shall be in accordance with the requirements of AS
4100 or AS 1664 as appropriate.
Reamed or drilled holes shall be cylindrical and perpendicular to the face of the member unless otherwise
shown in the drawings. Reaming and drilling shall be done by mechanical means.
Connecting parts shall be assembled and held securely while being reamed or drilled and shall be match-
marked before separating the parts. All burrs shall be removed. Assembled parts shall be taken apart if
necessary.
Where existing holes in cleats have been enlarged due to the removal of corroded materials, bolt sizes are
to suit new hole diameters and are to be forwarded to Sydney Water for acceptance prior to bolting.
All bolts, other than stainless steel, must be galvanised to a minimum of 75 microns to AS 1214.
C5.6.10. Alignment of Holes
All matching holes in any contiguous group shall register with each other so that a gauge or drift 2mm less in
diameter than the holes shall pass freely through the assembled contact faces at right angles to them.
All holes shall be placed accurately regardless of variation in dimensions of rolled sections or tolerances
allowed in fabrication.
C5.7. Welding
C5.7.1. General
All welding of structural steel shall be category SP in accordance with the appropriate parts in AS 1554 and
this specification unless shown otherwise in the drawings.
Welding of aluminium shall comply with the requirements of AS 1665.
All welding shall be continuous and no intermittent welding shall be permitted.
The completed item shall be free from distortions and true to dimensions. All connections shall be welded in
a manner such that the finished connections are neat, smooth in appearance, all sharp edges ground and all
projections ground smooth suitable for provision of corrosion protection and aesthetic finishes.
Details of welding procedures shall be submitted to Sydney Water prior to fabrication of members utilising
the particular procedure.
C5.7.2. Welding Personnel
Welding of steel and aluminium items shall be carried out by skilled welders possessing the required
qualifications to AS 1554 and AS 1665 as appropriate, and qualified in the particular welding procedure,
welding position, weld type and weld category.
Welding shall be carried out under the supervision of a competent supervisor possessing the qualifications
required by AS 1554 and AS 1665 as appropriate.
Details of the qualifications of all welders, together with details of any qualification tests carried out by those
welders shall be supplied to Sydney Water prior to the commencement of welding.
All welders shall have an identification number, and that number shall be marked adjacent to weld runs
made by the welder. Identification numbers shall not be stamped into metal.
C5.7.3. Welding Inspectors
Welding shall be inspected by a qualified Welding Inspector with suitable training and experience in the
fabrication and inspection of welded structures satisfying the requirements of:
Clause 7.2 of AS/NZS 1554.1 for structural steel
Clause 7.2 of AS/NZS 1554.6 for stainless steel
Clause 7.2 of AS 1665 for aluminium
The Welding Inspector is responsible for ensuring that all welding conforms to the requirements of this
Specification.
C5.7.4. Non Destructive Testing (NDT) Technician
All various non-destructive tests (NDT e.g. ultrasonic examination, radiography etc.) shall be carried out by
technicians suitably qualified and accredited for carrying out the examination method employed satisfying
the requirements of:
Clause 7.4 of AS/NZS 1554.1 for structural steel
Clause 7.4.2 of AS/NZS 1554.6 for stainless steel
Clause 7.4.2 of AS/NZS 1665 for aluminium
Such a technician shall be accredited by the Australian Institute of Non-destructive Testing (AINDT).
The currency of the above qualifications and accreditations shall comply with the requirements of the issuing
institution. Lapsed qualifications and accreditations will not be acceptable.
All non-destructive test reports shall be prepared by qualified and accredited NDT technicians, and shall
contain the NDT technician’s signature and registration number of the NDT technician’s qualification and
accreditation.
C5.7.5. Welding Equipment and Safety
All welding machines and equipment shall comply with AS 1674 and the safety requirements of the relevant
Statutory Authorities. The machines and equipment shall be designed, installed, operated and maintained
to such a standard that welds can readily be made by the machine operators.
C5.7.6. Welding Consumables
A Maker's Certificate of Compliance shall be supplied for each batch of consumables used.
Steel
Electrodes used in all manual arc welding shall conform to and be selected in accordance with AS/NZS
4854, AS/NZS 4855, AS/NZS 4856 and AS/NZS 4857.
Electrodes and fluxes for submerged arc welding shall confirm to and be selected in accordance with AS
1858.
Welding consumables shall be stored in a manner, which meets the manufacturer’s recommendations. Low
hydrogen electrodes drawn for use by a welder shall be kept in a suitable heated container until used.
Unused low hydrogen electrodes shall be returned to storage and re-baked before further use.
The minimum nominal tensile strength of weld metal used shall be 480MPa (e.g. E48xx, W50x etc. or
stronger) for all structural steel unless indicated otherwise in the drawings or accepted by Sydney Water.
The use of low-hydrogen electrodes is mandatory for manual welding of shell plates, permanent
attachments to the shell plates, fittings and for welds joining the shell plate to the bottom plates of liquid
retaining tanks.
Aluminium
Welding consumables shall conform to AS/NZS ISO 18273. Welding consumables shall be selected in
accordance with Section 2 of AS 1665 and shall only be used in accordance with the manufacture’s
recommendations and AS 1665.
Certification shall be obtained, by a recognised authority satisfying the requirements of AS 1665, that the
classification and grade of the welding consumables are suitable for welding the aluminium type nominated
in the welding procedures.
C5.7.7. Alignment
Members to be welded shall be brought into correct alignment and held in position in such a manner to
maintain dimensional requirements and uniform gap. Suitable allowances shall be made for warpage and
shrinkage.
C5.7.8. Surfaces to be Welded
Surfaces to be welded shall be free of loose scale, slag, heavy rust, grease or other material likely to be
detrimental to welding or weld properties. The use of weld through primers shall be permitted, provided that
the welding procedure is qualified using similarly primed plate. Surfaces to be welded shall be smooth,
uniform and free from fins, tears, or other defects, which adversely affect welding.
C5.7.9. Tack Welds
Tack welds may be used to hold edges in correct alignment for welding. Tack welds shall be the same size
as the root run to be used in the joint and not less than four [4] times the thickness of the thicker part or 100
mm, whichever is the smaller, in length. Tack welds, which are to be incorporated in the final weld or to
remain on the completed structure, shall be subject to the same quality and workmanship requirements as
the final welds.
C5.7.10. Weld Quality
Welds shall show a good even contour, a good penetration and fusion with the parent metal. The surface of
the weld along and across the joint shall be reasonably smooth and free from sharp irregularities, grooves
and depressions and shall merge smoothly into the plate surface. Unacceptable welds shall be cut out and
replaced or otherwise remedied in a manner accepted by Sydney Water .
C5.7.11. Defective Welds
Where welds do not meet the surface finish requirements of this specification, they shall be ground to a
smooth surface free from sharp crests, sharp troughs and pits. Care shall be taken not to reduce the weld
below the design size and not to overheat the joint or introduce grinding cracks. Sharp edges including
shear edges, shall be ground to a radius of curvature of not less than 2mm. Weld spatter not capable of
ready removal by subsequent cleaning or blasting shall be removed by mechanical means.
C5.7.12. Weld Procedure Qualification
Weld procedures shall be developed to meet the requirements of Section 4 of AS 1554.1 for structural steel.
Such procedures shall be fully documented on an approved form as indicated in Appendix C of AS 1554.1,
and accompanied by NATA endorsed Test Certificates for any tests required.
Welding procedures of stainless steel structures shall meet the requirements of Section 4 of AS 1554.6.
Such procedures shall be fully documented on an approved form as indicated in Appendix C of AS 1554.6
Welding procedures of aluminium structures shall meet the requirements of Section 4 of AS 1665 and
documented on an approved form as indicated in Appendix D of AS 1665.
C5.7.13. Submission of Qualifications for Acceptance
Weld qualification test records, weld procedure specification and a weld map, indicating the procedures to
be adopted on each welded joint shall be submitted to Sydney Water for acceptance at least twenty (20)
working days prior to the commencement of welding.
C5.7.14. Weld Inspections and Testing
All welds shall be inspected in accordance with AS 1554.1 for structural steel, AS 1554.6 for stainless steel
and AS1665 for aluminium. Non-destructive testing (NDT) of welds shall be carried out by a NATA approved
independent inspection authority.
Sydney Water shall be provided access to the fabrication workshops to check records and work progress for
the purpose of quality surveillance.
25 mm Radiographic NA 100%
Floor 1 spot every 3 m
up to 25 mm Radiographic NA
of length
25 mm Radiographic 100 % 100 % 100 %
Wall 1 spot every 1 spot every 3 m
up to 25 mm Radiographic 100 %
3 m of length of length
Wall/Floor
All Ultrasonic NA 100%
On Ground Junction
Tank Annular Plate
All Ultrasonic NA 100%
(floor)
1 spot every 3 m
Ultrasonic NA
of length
Floor All
Vacuum Test
NA 100%
To API 650
C5.7.15. Weld Acceptance Requirements
Acceptance requirements shall be as detailed in AS 1554 and AS 1665 as appropriate. The weld surface
shall be free from excessive weld ripple and smoothly blended with the plate surface. No weld spatter or
welding fume shall be permitted on the weld or adjacent plate surface.
At least twenty (20) working days prior to the commencement of welding, a drawing (developed longitudinal
section for reservoirs) detailing proposed non-destructive test locations shall be submitted to Sydney Water
for acceptance.
The submission of proposed weld testing shall constitute a Hold Point.
The locations and records of NDT shall be submitted to Sydney Water for keeping on completion of the
tests.
C5.7.16. Defective Welds
Defective welds shall be repaired only with the prior acceptance of Sydney Water. Repairs shall be made
using qualified procedures and personnel.
All welds failing the testing shall be rectified prior to hydrostatic test.
C5.7.17. Passivation of Stainless Steel after Fabrication
All stainless steel fabrications shall be passivated in accordance with ASTM A360 after all welding has been
completed to restore corrosion resistance. Passivating of the welded areas shall be carried out in the
fabricator’s workshop unless accepted by Sydney Water.
Where passivation on site is unavoidable, it shall be carried out in accordance with the Manufacturer’s
instructions. No waste shall be flushed down the existing drainage system, unless diluted or neutralised
satisfactorily
Small items such as nuts, bolts, washers, and screws shall be passivated by immersing them overnight in a
plastic bucket containing 15%-20% by volume of nitric acid in water. The items shall be thoroughly rinsed in
fresh water before use.
Larger items shall be passivated by coating with a proprietary acid paste such as Sandvik pickling paste or
suitable equivalent. The articles shall be coated and left overnight then rinsed thoroughly in clean water. As
this product is highly corrosive and gives off fumes, it shall be used in a well-ventilated area and personnel
shall use rubber gloves. The manufacturer’s safety precautions on the label shall be carefully complied with.
After passivation, fabricated components shall have a clean, matt finish free from scale and discolouration
caused by welding or heating.
C5.7.18. Handling and Storing Structural Steel
Care shall be taken in the packing and methods of support and lifting during handling of all structural
steelwork to prevent distortion or damage to the steelwork and its protective coating.
All open joint ends and projecting parts shall be protected from damage in transit in such a manner as to
stiffen the member and prevent distortion.
All components shall be stored at least 200mm above the ground on platforms, slabs or other supports, and
in a manner to minimise the risk of contamination or corrosion. Each stack shall be located so that it is kept
free from accumulation of dust, mud or moisture.
Galvanised components shall be transported and stored under dry, well-ventilated conditions to prevent the
formation of wet staining in accordance with AS/NZS 4680. A passivation treatment after galvanising shall
be used to minimise the wet staining which may occur on articles unable to be stored in well ventilated
conditions. Prior to erection, all wet staining shall be removed without damaging the galvanised surfaces.
C5.7.19. Handling and Storing Stainless Steel
All stainless steel components shall be packed in such a manner that they are protected from damage
during transport. They shall be handled and transported such as to prevent distortion or fracture, and if
necessary braced to prevent flexing. Self-adhering protective plastic film shall be used for finishes brighter
than dull finish.
Bare steel wire rope slings shall not be used in handling the stainless steel components. Any minor scores
or gouges in the stainless steel surface shall be carefully filed down with mild abrasives and finished
smooth. Where such rectification cannot be satisfactorily carried out, the item shall be treated as
nonconforming.
Appropriate care shall be taken when handling stainless steel before, during and after fabrication to prevent
contamination with mild steel materials, dust, shavings, weld splatter and the like. Such care is particularly
important after passivation and during transport to site, storage and installation as these small particles rust
quickly and discolour the surface of the stainless steel. This can destroy the protective oxide film and render
it liable to pitting corrosion.
The following practices shall not be used:
Cleaning with steel wool, wire brushes, emery paper
Delivery of Paints
All coating materials shall be brought to the site in their original, unopened containers, bearing the
manufacturer's label, batch number, instructions for application and expiry date where applicable.
Storage of Paint
All paint containers shall be stored under conditions that do not lead to deterioration of the paint. Stock
rotation shall be employed so that all paints are used in the same sequence as they are received.
C5.8.6. General Requirement for Application of Coating
PCCP Certification
The coatings shall be applied by Sydney Water pre-qualified painting contractors who hold a Class 3
Certificate issued by the Painting Contractors Certification Program (PCCP). Where the work involves the
maintenance or removal of coatings that contain lead compounds or other toxic substances, such work shall
only be undertaken by pre-qualified contractors holding a PCCP Class 5 Certificate.
Painting Contractors certificates shall be submitted to Sydney Water for acceptance at least fourteen (14)
working days prior to commencing any painting work.
The submission of proposed painting contractors shall constitute a Hold Point.
Blast cleaned surfaces shall be free of abrasives and surface dust prior to application of primer. Blowing
down to remove spent abrasive, removed paint particles and dust from surfaces shall be carried out under
full containment conditions with air extraction as specified above. All surfaces to be primed shall be dry and
free of any deleterious liquid.
Brushing In
Paint shall be applied by brush to the following areas prior to the general application of each coat of paint by
spray:
All rivets, bolts, nuts and washers.
All areas shadowed from paint spray by flanges, rivets, bolt heads and other projections.
All other area that is difficult to spray.
Wet-on-wet application is permitted.
Stripe Coating
Prior to the application of each coat of paint, a stripe coat of the paint shall be applied to all exposed edges,
corners, and welds as well as repaired pitted areas and crevices. Wet-on-wet application is permitted.
Feathering of Edges
Where paint is to be applied to surfaces adjoining a cured coating, the edge of the cured coating shall be
feathered by a method approved by the manufacturer.
C5.9. Erection
C5.9.1. Handling, Delivery to Site and Storage
All fabricated items shall be handled in a manner that will not overstress or deform either members or
components
Members yet to be erected shall be stored above ground so as to avoid contamination.
C5.10. Fabrication, Erection and Testing of Circular Liquid Retaining Steel Tanks
C5.10.1. General
All steel plates shall be cold rolled to suit the curvature of the tank and the erection procedure.
Any required straightening of material shall be carried out by methods that will not injure the steel, such as
by cold rolling or pressing. Straightening by hammering shall not be permitted. Heating may be used only
with the prior acceptance of Sydney Water and subject to being certified by a civil/structural engineer who is
a Member of the Institute of Engineers, Australia.
Welding sequence shall be devised to minimise deformation of the bottom plates of the floor.
The shell wall shall be erected plumb and circular to the dimensional tolerances specified in API 650. Until
the floor and the bottom shell strake have been inspected and accepted by Sydney Water, further erection
of the tank shall not proceed.
All exposed sharp edges shall be either rounded to a radius of not less than 5mm or alternatively shall be
provided with a chamfer not less than 1mm wide. Rounding off or bevelling of such edges shall be carried
out prior to preparation for and application of corrosion protection measures.
C5.10.2. Roof Steelwork
In fixing the roof members to the steel shell brackets, allowance shall be made to accommodate the
rounding of the tank shell when the tank is filled.
All roof steelwork except for roof beam support brackets welded to the steel tank shell and the columns
welded to the tank floor plate, shall be protective coated as specified.
Roof beam support brackets shall be painted with the same paint system as used for the internal shell as
specified.
The tank top stiffening ring shall be painted in the following manner:
Top horizontal face shall be painted with the same paint system as used for the internal shell as
specified.
Other faces shall be painted with the same paint system as used for the external shell as specified.
All overlapping galvanised surfaces shall be isolated from each other by the application of an inhibitive
jointing compound accepted by Sydney Water.
C5.10.3. Purlin System
Purlins shall be aluminium. Cold-formed purlins are not an equivalent substitute.
All angle or channel section trimmers or purlins shall be fixed with the flanges facing down the slope of the
roof to prevent moisture being trapped on the flange. Where this configuration cannot be achieved, purlins
shall contain drain holes to facilitate the removal of collected moisture. The location and size of such drain
holes shall not compromise the structural integrity of the purlin.
All potential contact points between steel and aluminium shall be insulated in the same manner as described
herein.
C5.10.4. Roof Cladding - Material
The roof sheeting shall consist of stucco embossed mill finish high strength corrosion resistant aluminium
alloy. Typical acceptable alloy grades are 5251. The colour of the roof sheeting shall be as nominated by
Sydney Water.
Roof flashing, ridge capping, gutter and moulded closure strips shall be made from the sheeting
manufacturer's standard form aluminium roof accessories.
Aluminium hatch frames shall be fabricated from Alloy 6061-T6 or 6082-T6. Flat sheets for hatch and
ventilator frames and covers shall be fabricated from Alloy 5251-F or 6082-T6.
Floor plates around access and equipment hatches shall be 6 mm thick aluminium fabricated from Alloy
5251-F.
Aluminium treadplates including perimeter of roof, up to and around ventilation hatches and along one ridge
to the central ventilator shall be 3 mm thick Grade 5251or 6061 with raised angular pattern on the top face.
Each piece of tread plate shall be 600mm wide and nominally 1200mm long maximum.
The roof supporting members shall be fabricated from structural steel, Grade 300, to AS 3679, galvanised;
or aluminium plates and extruded sections to AS 1734 and AS 1866.
For stitching purposes, only the aluminium M6 tri-fold, positive mandrel retention, "Bulb-Tite" aluminium
rivets or accepted equivalent shall be used. Each rivet shall have a neoprene seal.
C5.10.5. Roof Cladding- Installation
Fixing details shall be submitted at least twenty (20) working days prior to installation of the roof cladding.
The laying of the sheeting shall comply with AS 1562 and the following minimum requirements:
The corrugated roof sheets shall be laid as shown in the drawings such that in each bay the
corrugations are laid at right angles to the purlins and parallel to any semi-rafter. The sheets shall span
across the purlins and shall be fixed so that there will be no distortion or stressing from thermal
movement or other causes.
No forced fitting or spring fixing of the roof sheeting over the rafters or semi-rafters is permitted.
Provision shall be made for accommodating expansion / contraction movement where appropriate.
Side laps shall not be less than one [1] full corrugation, and shall be stitched with aluminium M6 "Bulb-
Tite" pop rivets at 450 mm centres through the crest of each rib.
End laps shall be kept to a minimum, but where necessary, shall not be less than 225 mm. The centre
line of end laps shall coincide as nearly as possible with the centre line of the supports and the sheets
shall be arranged such that all holes for the main fixing are more than 40 mm from the end of the sheet.
All sheet laps shall be given two [2] coats of aluminium pigmented bituminous paint or accepted
equivalent.
As a minimum, the sheets shall be fixed to the roof purlins using the 'Capral Positive Fix System' or
accepted equivalent. Each fixing shall consist of 6 mm diameter 304/305 stainless steel screws,
aluminium formed washers in alloy 5251 and rubber sealing washers through the crest of every second
corrugation at intermediate supports and every crest along the ridge lines at the sheet ends. After
drilling a pilot hole through the crown and the purlin, the hole in the sheeting shall be opened to 6 mm in
diameter, after which the fastener is to be installed.
To allow for temperature expansion of the sheets, for all fixings further than 6 m from the centre of the
tank, the hole in the rib crown shall be slotted after drilling the tapping hole. For these expansion fixings,
an EPDM rubber washer with an elongated hole and a PTFE facing on one side shall be used. The
washer shall be installed with the PTFE side facing up towards the head of the screw. For these fixings,
elongated holes for the main fastenings shall be made in the sheeting in accordance with the 'Capral
Positive Fix System'. The elongation of the holes shall be in the radial direction. The washer plate shall
protect the PTFE from UV light attack.
It is important that the roof be completely bird-proof, corrugations shall be completely sealed at all sheet
ends with formed aluminium closure strips.
Any cutting of sheets shall be done in such a manner as to avoid distortion of the profile.
The termination of the roofing sheet at hips and apex shall have the pan turned up.
At the outer edge of the roof, the roof sheeting is to be fixed to the stiffener ring through every
corrugation. The method of fixing should preferably be by a standard method specified by the sheeting
manufacturer.
Allowance shall be made to accommodate the rounding of the tank shell when the tank is filled, by
checking the degree of out-of-roundness of the tank after the top stiffening ring is welded in place.
Ridge and hip lines which are at every radial beam, shall be covered with the sheeting manufacturer's
standard capping and "tee"-shaped hip support, cut to match the corrugations, lapped a minimum of
225 mm at transverse joints and stitched at 450 mm centres, with aluminium M6 AVDEL tri-fold, positive
mandrel retention, Bulb-Tite aluminium rivets or equivalent rivets along longitudinal joints. The capping
shall be secured in each wing at centres corresponding to roof fixings. The trough of the sheet ends
beneath the ridge and hip capping shall be sealed by filling with a suitable bituminous based filler or
another method specified by the sheeting manufacturer that is acceptable to Sydney Water.
Tread plates for working platform around hatches as indicated in the drawings shall be aluminium, 6mm
thick minimum and fixed to supporting framing members with M12 countersunk stainless steel bolts at
maximum 500 mm centres. Where the support member is not aluminium, nylon washers and bushes
shall also be used to isolate the dissimilar metals.
Tread plates shall be stitched to the top of the aluminium roof sheeting ribs with M6 tri-fold, positive
mandrel retention, "Bulb-Tite" aluminium rivets or equivalent shall be used. Each rivet shall have a
neoprene seal.
All drilling swarf shall be cleared both inside and on the rooftop.
C5.10.6. Connection between Aluminium and Steel Roof Components
All potential points of contact between aluminium and other metallic members shall be insulated with the
following:
For the connection of roof sheets to rafters or purlins, use 0.25mm thick "TESA -51482" PVC tapes or
PTFE equivalent.
For the connection of galvanised tread plates to roof sheets, use 0.8mm thick neoprene strips.
For connections of all structural members use a minimum 1.5mm thick neoprene sheet.
The separation tapes or sheets shall be sufficiently wide to provide a minimum overlap of 5 mm on
either side of the purlin, beam etc. on which they are stuck.
All fasteners shall be of stainless steel. Nylon bushes and/or nylon washers shall be provided to prevent
contact of with steel or aluminium parts.
C5.10.7. Hydrostatic Testing of Steel Tanks
The tanks shall be hydrostatically tested, at a time that is accepted by Sydney Water.
Determination and application of suitable and appropriate rates for filling and emptying of tanks shall be
undertaken.
For the purpose of such testing the tank shall be filled with water to the top water level and shall be kept full
for a period of not less than 48 hours. Any leaks including visible wet patches, or defects which may cause
leakage, shall be rectified and retested until the tank is completely watertight. If a leak is detected while the
tank is being filled with water, the defects responsible for the leak shall be repaired before continuing filling
the tank to the top water level.
If there is a need to discharge water to the environment, Sydney Water Standard Operating Procedure
(SOP) WPIMS 5021 shall be followed.
In the case of evidence of indication of leakage through a tank's steel floor where the location of the defects
or damages responsible for such leakage cannot be ascertained by means of the conventional hydrostatic
test, vacuum tests on the welded joints in the floor shall be conducted. Vacuum testing shall be carried out
generally in accordance with the relevant requirements of AWWA D100. Alternatively, Sydney Water may
agree to testing of the floor joints by the magnetic particle method. The tests shall be witnessed by Sydney
Water, and the costs of these tests, including the cost of providing the necessary equipment shall form part
of the contract.
A copy of the hydrostatic test results shall be submitted to Sydney Water at least twenty (20) working days
prior to acceptance of the tank.
The submission of the hydrostatic test results shall constitute a Hold Point for commissioning the tank. The
procedures and acceptance criteria detailed in Sydney Water Standard Operating Procedure (SOP)
WPIMS5261 shall be followed.
Table 5-3 Summary of Hold Points for structural steel and aluminium works
Hold Relevant
Process Held Required Documentation
Point No. Clause(s)
SHP1 Fabrication Shop drawings C3.6.5
SHP2 Fabrication Splices not identified in design drawings C3.15.3
SHP3 Weld testing Location and type of testing C5.9.15
SHP4 Painting PCCP certificates of painting contractors C5.10.6
SHP5 Tightening of high Tensioning of bolts C5.11.7
strength friction bolts
SHP6 Acceptance of liquid Hydrostatic test results C5.12.17
retaining tanks
C6.3. Masonry
All masonry units shall be fired clay, concrete or calcium silicate to AS/NZS 4455. Unless specified
otherwise, properties shall be not less than:
Masonry units shall comply with Dimensional Category DW1, except that split or irregular faces may be
DW0.
Concrete units shall comply with Dimensional category of DW4
Masonry units shall meet General Purpose Salt Attack Resistance Grade, except for applications
requiring exposure Grade. Applications requiring exposure Grade:
– Saline wetting or drying.
– Aggressive soils.
C6.5. Cement
Cement shall be Type GP or GB to AS 3972.
C6.7. Lime
Lime shall be hydrated building lime complying with AS 1672.
C6.8. Sand
Sand shall be well graded and free from salts, vegetable matter and impurities. Sand shall not contain more
than 10% of the material passing through the 75 micron sieve. Sand within the limits shown in Table 6-1 is
deemed to be suitable
4.76 mm 100
2.36 mm 95-100
1.18 mm 60-100
600 µm 30-100
300 µm 10-50
150 µm 0-10
75 µm 0-4
C6.10. Mortar
Unless specified otherwise, the durability requirements of mortar shall comply with Table 12.2 of AS 3700.
Metal slip joint materials shall not be used in locations that are subject to rising salt damp.
shall be placed into the masonry at a depth, which permits the finish of the control joints to match the mortar
joints.
For control joints or articulation joints in cavity walls (i.e. not in veneer walls), extendible masonry ties shall
be built into every fourth course.
Where a control joint is located adjacent to a door or window frame, a 10 mm gap shall be provided between
the edge of the frame and the masonry to allow for movement.
C6.22. Lintels
Except in the case of arches, masonry over openings shall be supported.
Unless specified otherwise, for openings up to 600 mm width, masonry may bear directly on a timber
window head. For openings up to 900 mm width, masonry may be supported by a metal frame. In other
cases, masonry shall be supported on lintel of the following types:
Steel member in accordance with Clause 12.4.2 of AS 3700.
Reinforced masonry lintels in accordance with Clause 12.4.3 of AS 3700.
Reinforced concrete in accordance with AS 3600.
Durability requirements of lintels shall be in accordance with Table 12.2 of AS 3700.
At least 3 working days prior to the proposed erection of masonry, Sydney Water shall be notified of the
completed installation of lintels.
Control joints shall be built into reinforced concrete masonry at all points of potential cracking and at the
locations shown in the drawings. The spacing of control joints should not exceed 8.0 metres, except that
the spacing of control joints may be increased in reinforced masonry walls meeting the following criteria:
Consisting of at least 190 mm hollow concrete units.
Built less than 3.0 metres high.
Incorporating a top reinforced bond beam.
Incorporating N16 horizontal reinforcement at not greater than 400 mm centres.
On site classifications A & S to AS 2870.
With a reinforced concrete footing of adequate stiffness.
Cavities shall be kept clear of mortar droppings and adequate temporary openings shall be provided
along the bottom to clean out loose material from the bottoms of hollows before being filled with grout.
C6.25. Grouting
Grouting shall not commence until grout spaces have been cleaned out and the mortar joints have attained
sufficient strength to prevent blowouts.
The height of the individual lifts in any pour shall be limited in accordance with the fluidity of grout and shall
be certified by a civil/structural engineer who is a member of the Institution of Engineers Australia.
Compaction of the grout shall be by vibration or rodding.
On completion of the last lift, the grout shall be topped up after a waiting period of 15 minutes and the
topping vibrated or rodded so as to merge with the previous layer.
Sydney Water shall be given at least seven (7) working days’ notice after cleaning out the bottoms of
hollows and ready for grouting.
The submission of proposed grouting shall constitute a Hold Point.
C7. Demolition
C7.1. General
This specification includes the requirements for the demolition of existing structure and the disposal of
resulting materials and components which may or may not be contaminated. It also includes the additional
safety and environmental protection requirements to the relevant legislations.
The demolition work includes demolition of any temporary supports and removal of any debris caught in the
existing structure.
C7.3. Definitions
The following definitions shall apply to this Specification
Demolition: The complete or partial dismantling of a structure by pre-planned and
controlled methods of procedures
Contaminated Materials: Any material that contains or is made of hazardous substances
Hazardous Substances: A substance that is either listed in NOHSC 10005 or fits the criteria for
hazardous set out in NOHSC 1008
Competent: Suitably qualified, adequately trained and appropriately experienced for the
particular class or kind of work specified.
Notification to commence the demolition work shall be submitted to WorkCover and obtain written approval
before commencement of demolition work.
Where asbestos materials are present, only licensed asbestos removalists shall handle these materials in
accordance with the Occupational Health and safety Regulations. Any permits and notifications as required
by the relevant parts of the Regulation shall be obtained.
Sydney Water shall be notified immediately .f any other hazardous materials are found that require permits
by relevant regulatory authorities for handling and disposal.
Records of all licences, notifications, approvals and permits shall be maintained.
C7.4.3. Noise Levels
The noise generated by the demolition activities shall comply with the Noise Abatement Act, the
requirements of the EPA, local Council and any other conditions prescribed by Sydney Water.
C7.4.4. Supports and Shielding of Adjoining Structures
Supports and shielding shall be provided to adjoining structures where necessary to prevent damage
resulting from the demolition activity. These shall be deemed to be temporary works unless the specified
otherwise.
C7.4.5. Use of Explosives
No explosives shall be permitted for demolition work unless demonstrated that there are no other practical
alternatives.
Where explosives are proposed, at least twenty (20) working days prior to commencing any demolishing
work, details of the types of explosives, type of detonators, method of placing and firing explosives, firing
pattern and delay sequence to be used shall be submitted to the Sydney Water. These details shall be
verified by a competent person prior to being submitted. For demolition work involving the use of explosives
or induced collapsed methods, approval shall be applied for and given by WorkCover.
Where accepted, the transport, storage and use of explosives shall comply with all the relevant parts of AS
2187.
C7.6. Clean Up
In addition to the requirements specified in the drawings and specifications, all excavations shall be
reinstated to the levels and profiles existing prior to the demolition works.
C8. Roadwork
C8.1. General
Roadwork shall generally be carried out as shown in the drawings. The position and extent of all cuttings
and filled areas shall be marked and pegged out on site prior to the commencement of construction.
Base and sub-base materials shall be unbound materials consisting of hard, durable particles and fragments
of either natural or manufactured material that can be compacted readily to form a firm and stable base or
sub-base. All base and sub-base material shall comply RMS QA Specification 3051.
Unbound materials are those that have not been modified or stabilised by any added chemical agent.
Unbound material may include recycled crushed concrete building material free from foreign matters like
metal, glass, asphalt, ceramics, plaster, clay lumps, rubber, plastic and wood.
Recycled materials where accepted, shall also be free from hazardous substances such as asbestos or
asbestos containing materials in both friable and bonded forms.
The formation level of the base and sub-base shall be finished to the design levels within a tolerance of +0
mm / -20 mm.
The grading of the combined aggregate shall be determined in accordance with AS 1141.11. The grading of
aggregate and the binder content in an asphalt mix shall be determined in accordance with AS 2891.3.1,
AS2891.3.2 or AS 2891.3.3.
The air void content and the voids in mineral aggregate shall be determined in accordance with AS2891.8.
The prime coat shall be sprayed at a nominal rate between 0.2 and 0.4 litre per m2. The application rate
shall be doubled for joints and chases.
All contact surfaces of kerbs and other structures and all joints shall have a uniform application of prime
coat.
The surface to which the prime coat is applied shall be clean and free from loose stones, dirt, oil or foreign
materials.
Consistence of the concrete determined by measuring the slump in accordance with AS 1012.3 shall be 55
to 65 mm.
Forms shall be designed and constructed so that they can be removed without damaging the concrete and
shall be braced in a substantial and unyielding manner. Forms shall be mortar tight and de-bonded to
ensure non-adhesion of concrete to the surface of the forms.
Concrete shall be deposited continuously between the specified joints and spread uniformly in the forms
without segregation. The concrete shall then be compacted to the full thickness of the slab in one operation.
The surface texture of the finished concrete surface shall be uniform and shall be effected by brushing
evenly across the slab in one direction at right angles to the longitudinal axis of the carriageway. Brushing
shall be carried out using a texturing comb after the moisture film has disappeared from the concrete
surface and before the initial set is complete. Texture depth shall be 0.5mm nominally.
Curing compound shall be applied to the concrete surface immediately after the surface has been textured.
Traffic shall not be allowed on the concrete surface until an in-situ compressive strength of 30 MPa is
reached.
Materials for joints shall be used in accordance with manufacturers' recommendations or as otherwise
shown in the drawings. Dowel bars, tie bars and sleeves shall be securely fixed in position through holes in
the formwork. Joints shall be formed perpendicular to the top surface of the slab.
Transverse joints shall be straight and perpendicular to the longitudinal axis of the carriageway and shall be
formed only at the specified positions. The joints shall be continued through kerbs, edges and gutters and
their foundation and backing.
Longitudinal joints shall be formed only at the specified positions.
Grooves in concrete carriageway slabs shall be straight and formed either by sawing to the specified width
and depth, or by fixing forming strip to the surface of the adjacent hardened concrete slab.
Immediately before sealing of the groove, dirt and loose material shall be removed from the groove.
Caulking material if required shall be firmly packed in the bottom of the groove. Bond breaker tape shall be
fixed continuously and evenly along the bottom of the groove for the full width and length of the groove.
Primer for the joint sealant shall be applied to the sides of the groove. The joint sealant shall be mixed and
applied strictly to the manufacturer's recommendation
The allowable deviation of the finished carriageway from the design level and lines are +10 mm in layer
thickness, +5 mm in level at any point, and shall not deviate from the bottom of a 3 m log straight edge by
more than 10 mm when placed parallel or transverse to the centreline of the road.
The difference in level of the concrete surfaces across joints shall not exceed 3 mm.
Two pairs of 100 mm diameter cylindrical test specimens shall be moulded for compressive strength testing
in accordance with AS 1012, one at 7 days and the other at 28 days. The frequency of sampling shall be
one sample per 25 m3 or part thereof the concrete delivered to site on the day of concreting.
The compressive strength shall not be less than 32 MPa at 28 days.
C9. Piling
C9.1. General
This specification sets out the minimum requirements for the design, construction and testing of pile
foundation systems to support permanent structures.
Unless otherwise specified, exposure classification for all piles as per AS 2159 shall apply for the range of
conditions in the soil and groundwater surrounding the piles. Minimum cover for concrete piles shall be in
accordance with AS 2159.
Minimum corrosion allowance of 2mm per face shall be allowed for all steel piles. Where Acid Sulfate soils
are present, durability of steel piles shall comply RMS BTD 2007/13.
Where cathodic protection is applied to steel piles, it shall conform to AS 2832.
C9.5. Materials
Unless otherwise specified, all materials used in pile construction shall comply with the appropriate
Australian Standard. Concrete for plain, reinforced and prestressed concrete piles shall comply with the
requirement of AS 3600, AS 2159 and AS 1379.
Steel for piles and pile fitments shall comply with the requirements of AS 1163, AS 1450, AS 3678, AS
3679.1 and AS3679.2.
Timber pile material, where permitted shall be hardwood in accordance with AS 3818.3 and treated for H6
as per AS1604.1.
The specialist pile driving contractor shall assess the driving conditions and may increase the pile section
properties and adjust the driving shoe detail to suit their assessment. any proposed change to the pile
properties shall be submitted to Sydney Water for acceptance.
Where a pile achieves the required driving resistance based on the parameters set by the representative
pile(s) at a depth greater than 1.0m higher than the contract level, the piling contractor shall conduct PDA
load testing of the pile to prove sufficient capacity has been achieved.
Piles shall be constructed within ±60mm in plan from the design position. Pilot holes shall only be drilled (to
facilitate driveability) with the acceptance of Sydney Water.
Min. 1 PDA test shall be carried out on a pile constructed with pilot holes; in addition to the PDA tests
originally required by design drawings.
Unless accepted prior by Sydney Water, each pile tested shall represent each type of pile used in
construction and ground conditions encountered on site. Each test shall represent and verify the
geotechnical capacities adopted for the permanent pile.
Number of test piles and location shall be agreed with Sydney Water, 20 working days prior to the testing.
Design Calculations
Design calculations shall be documented, checked and verified by competent design personnel in
accordance with the Sydney Water Engineering Competency Standard.
Design calculations shall clearly show the following:
Applicability of codes and standards.
Aim of design.
Basis of design including strength and serviceability performance, design assumptions, economic,
physical, aesthetic and other constraints.
Design life.
Design actions or loads.
Design resistance or strength.
Analytical methods and software used.
Safety considerations.
Environmental considerations.
Design Verifications
Where required by the Engineering Competency Standard or as per the Contract, all necessary verification
records from all verifiers and independent verifiers as defined in the Engineering Competency Standard
shall be provided.
Design Drawings
Design drawings shall be prepared and submitted in discrete and complete packages for elements or
components of the Works.
Each drawing shall be complete and shall have been checked for accuracy and verified fit for purpose prior
to submission.
All drawings shall be prepared in accordance with Sydney Water’s Computer Aided Design (CAD) Standard
for civil, structural, mechanical and electrical engineering drawings. The Standard and attachments are
available on the Sydney Water website under
http://www.sydneywater.com.au/BuildingDeveloping/SupplierInformation/CADStandard.cfm.
If appropriate, design drawings for water and sewage pipelines shall comply with the requirements set out in
Appendix SW3 – Drafting Requirements of the WSAA Water and Sewerage Codes (Sydney Water Edition).
To facilitate drafting, a software package (AutoCAD utility) and Drafting Software User Guide are available
for use.
Design Report
A design report shall be prepared and submitted which meets industry accepted norms as well as meeting
the requirements for Safety in Design. The design report shall inform the reader of all atypical hazards
associated with the fabrication, construction, installation, commissioning, testing, operation, maintenance
and demolition of the works so designed. Mitigation measures to reduce the level of risk to as low as
reasonably practicable shall also be provided.
Project Specification
When requested as part of the scope of work, a specification customised for the project shall be prepared
based on this specification, Sydney Water’s DTC drawings and any other relevant Sydney Water
specifications.
The inclusions of such a specification will be determined on a project-by-project basis but shall include:
Reference to this specification and other relevant Sydney Water specifications
Reference to specific Sydney Water DTC drawings
Project specific civil and structural requirements
Existing Sydney Water WAE drawings (if applicable)
Scope of Works
Work by others and works excluded from the Scope of Works
C10.1.5. Safety in Design
The requirements of the Safety in Design procedure specified in Sydney Water’s D0000653: Safety in
Design Procedure shall be complied with. All necessary documentation related to Safety in Design shall be
produced.
Apart from office buildings and buildings that house instruments only, the default design life of all other
assets shall be 100 years.
The design life of buildings and buildings that house instruments only, shall be 50 years.
ANSI/AWWA D103 Standard for Factory-Coated Bolted Carbon Steel Tanks for Water Storage
BS EN ISO 28765 Vitreous and porcelain enamels. Design of bolted steel tanks for the storage or
treatment of water or municipal or industrial effluents and sludges
API 650 Welded Steel Tanks for Oil Storage
BTD 2007/13 RMS Technical Direction for Durability of Steel Piles in Contact with Acid Sulfate
Soils
RMS QA R64 RMS QA Specification for Soil Nails
RMS QA R57 RMS QA Specification for Reinforced Soil Walls
RMS QA B114 RMS QA Specification for Ground Anchors
CIRIA C760 CIRIA Guideline on Embedded Retaining Wall Design
Doc no. CPDMS0023 Document uncontrolled when printed Page: 100 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
The document shall also include all necessary safe work, health and safety documentation related to
the proposed works.
The geotechnical investigation proposal shall be submitted to Sydney Water, minimum 10 working days
prior to mobilisation to site.
C10.3.3. Geotechnical Investigation Factual Report
Where geotechnical investigations are carried out, a Geotechnical Factual Report shall be produced to
document all field investigations results, geotechnical logs and laboratory test results.
The Factual Report shall consist the following as a minimum:
Purpose of the geotechnical investigations,
Fieldwork methodology,
Summary table of location of investigation and levels, the accuracy of investigation locations shall have:
– Horizontal location accuracy = ±1.0m MGA
– Vertical levels accuracy = ±0.1mAHD
Piezometer or Water standpipe installation details (where applicable),
Groundwater monitoring records,
Laboratory test results,
Plan of geotechnical investigations carried out in relevance to the proposed design elements overlaid on
latest aerial photograph and utilities and services,
Detailed Geotechnical borehole logs and where applicable, coloured photographs of rock cores,
Laboratory test results from NATA accredited test laboratory
C10.3.4. Geotechnical Interpretation and Design
Doc no. CPDMS0023 Document uncontrolled when printed Page: 101 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
Specific characteristics of groundwater, expansive soil, ground heave, negative skin friction effects and
slope stability,
Provide recommendations on the type(s) of foundations, temporary and permanent earth retention,
Bearing capacity values of the soils and rock at each proposed founding levels of structures, together
with the recommended strength reduction factor;
Estimate of the anticipated total and differential settlements for the proposed structure due to imposed
dead and live loads at each structural foundation and pipes,
Provide advice on excavability of the material present on site,
Provide advice on material re-useability as earthworks material to satisfy technical requirements
specified in this specification,
Provide recommendations on construction procedures and construability considerations,
Provide recommendations on earth pressure coefficients for design actions and design resistance,
Provide recommendations on geotechnical, groundwater related impact on existing assets in vicinity,
The potential effect of site conditions on pile durability, such as soil and ground water aggressivity,
Provide advice on geotechnical risks, limitations, gaps in available geotechnical data and where
applicable, provide recommendations for further geotechnical investigations,
Provide recommendations for geotechnical ground verifications required on site, during construction.
The Geotechnical Interpretive Report shall be updated at the end of each design stage of the project to suit
any design change in the design elements and shall be consistent with the overall design.
C10.3.5. Geotechnical Stability Checks
Shallow Footings
Geotechnical stability of shallow footings shall be checked in accordance with AS5100.3.
Slope Stability
All cut slopes and fill embankments shall be designed with a minimum long-term Factor of Safety (FOS) of
1.5 and a minimum short term FOS of 1.25. Short term loading conditions shall include (but not limited),
seismic load,
flooding,
rapid drawdown,
scour,
impact loads transferred to the slope
Where an existing slope is proposed to be modified or support new structures; the existing slope shall be
treated as a new structure and shall meet the above factor of safety requirements.
C10.4. Roadworks
C10.4.1. General
Roads shall be provided to service all buildings, facilities and structures where vehicular access is required.
Roads shall extend to locations where installation and removal of heavy equipment requires mobile cranes
and truck transportation.
Roads are required to carry traffic for the operation and maintenance of assets including mobile cranes,
tankers, articulated vehicles, transportation trucks carrying sludge and chemicals, coaches, vans and
passenger cars.
Doc no. CPDMS0023 Document uncontrolled when printed Page: 102 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
Roads shall be provided with turning areas, passing bays, kerbs and gutters, stormwater surface drainage,
sub-surface drainage, trench drains and edge drains.
Hardstand areas shall be provided for the standing of heavy vehicles, mobile lifting equipment such as
cranes, and for areas where regular cleaning and washing of the ground surface is required.
Parking areas shall be provided for parking of cars, vans and service vehicles.
Appurtenances such as fencing, railing and vehicular barriers shall be provided to protect facilities and
structures from damage and people from injury by vehicles using the road.
Road lighting, road marking and traffic signage shall be provided where appropriate.
C10.4.2. Width of Roads
The widths of roads shall provide passageway and passing clearances for the appropriate vehicle class
using the road.
The minimum width for two-way roads shall be 6.2m. The minimum width for one-way roads shall be 4.0m.
Unless otherwise specified, the following AUSTROADS Design Vehicles shall be used in the design:
Roads for use by heavy transportation vehicles – Single Articulated (19.0m long, 2.5m wide).
Roads for use by normal service vehicles – Service Vehicle Class (8.8m long, 2.5m wide).
Roads for use by cars and vans – Car/Van Vehicle Class (5.2m long, 1.94m wide).
The geometry and turning radii of roads shall comply with the requirements of AUSTROADS AP-G34/06 for
the appropriate Design Vehicle classes.
For the design of parking areas, the requirements of Australian Standard AS 2890.1 or AS 2890.2 shall be
met.
C10.4.3. Pavement Design
The assessment of design input parameters and design methods for both flexible and rigid pavements shall
be in accordance with AUSTROADS AGPT 02/08 – Part 2.
The minimum pavement design shall be as follows for a subgrade of minimum CBR=5% for minimum 1m
depth below subbase level:
Rigid pavement – 150mm thick reinforced concrete slab over a minimum of 100mm thick DGB20 base
course.
Flexible pavement – 45mm thick wearing course of AC14 asphaltic concrete, 150mm thick DGB20 base
course, and 200mm thick DGS40 sub-base course.
Site specific pavement design shall be produced for ground conditions with CBR<5% for minimum 1m depth
below subbase level.
C10.4.4. Rigid Pavement
Rigid pavements of reinforced concrete shall be provided for:
Vehicle washing bays.
Hardstand area, parking area, loading bay, boom gate approach slabs, etc. for vehicles transporting
chemicals, sludge and corrosive materials.
C10.4.5. Kerb and Gutters
Kerbs shall be of the semi-mountable type integral with formed gutters or trays as shown in AS 2876.
Doc no. CPDMS0023 Document uncontrolled when printed Page: 103 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
C10.4.6. Flooding
Roads shall be designed at levels free from flooding during storm events having an ARI of not less than 100
years, or other higher ARI events specified by Local Government Councils or other appropriate authorities.
Doc no. CPDMS0023 Document uncontrolled when printed Page: 104 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
Mild steel floor plates shall have a thickness not less than 6mm. Plating shall have a surface pattern which
shall be of a no-slip type.
Both the load bearing and transverse bars in rectangular panels shall be positioned symmetrically around
the centre-line of the panel in both directions so that when the panels are fixed together the bars are in line
with each other.
Removable plating and grating panels shall be in sizes suitable for removal by hand and be provided with
cut-outs or devices for lifting. The maximum weight of each removable panel shall be not more than 16 kg
for manual handling by one person, or not more than 32 kg for two persons. Otherwise, the maximum weight
of each panel shall be not more than 45 kg.
If there is a risk of objects falling through gratings or open flooring causing injury to persons, a protective
mesh or net shall be provided.
In cases where security is required, the plates or grating hatches shall be lockable using a key-alike system.
C10.7.3. Cut-outs
Cut-outs in floor plates and gratings shall be provided in positions required for operation of valve spindles,
etc. Cut-outs shall be approximately 150 x 150 mm and the exposed edges shall be fitted with welded trim
bars across the longitudinal runners. Band bars shall be provided around all cut-outs and butt joints between
panels.
C10.7.4. Deflection Limits for Beams Supporting Platforms and Walkways
Deflection limits for support beams of platforms and walkways shall be as shown in Table 10-1.
Table 10-1 Deflection Limits of Beams Supporting Platforms and Walkways
Supporting Platforms and Walkways for Accessing Span / 350 Span / 175
Valves, Penstocks and similar operational items
Installation of stanchions and handrails shall be strictly in accordance with the manufacturers printed
instructions and no deviations shall be permitted unless accepted in advance by Sydney Water.
A 6 mm thick kickplate shall be provided unless exempted in advance by Sydney Water and shall project
100 mm above the floor level of the platforms and walkways.
Stairway openings on platforms and walkways shall be protected with self-closing safety gates or booms.
Chains shall not be used.
Doc no. CPDMS0023 Document uncontrolled when printed Page: 105 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
C10.8. Buildings
C10.8.1. General
Unless otherwise specified, all buildings shall be designed to satisfy the requirements of the Building Code
of Australia 2008, the NSW State Government building regulations, the requirements of the local Council
and any other legislative technical requirements applicable to the site in which the buildings are located.
The style, appearance and colour scheme of new buildings shall be similar to existing similar buildings in the
compound as far as practical.
If existing buildings are altered, the alterations shall ensure that the new works are in keeping with the style,
appearance and colour of the existing building.
C10.8.2. Performance Requirements
All buildings shall be designed to prevent progressive collapse and minimise local damage and loss of
amenity through excessive deformation, vibration and degradation It must be designed to withstand the
combination of loads and other actions to which it may reasonably subjected.
All buildings and rooms shall be functional and sized to facilitate easy access to equipment. All doors and
passageways shall be designed so that equipment and machinery can be moved in and out of the building.
Natural ventilation shall be provided as far as possible except where odour control is required. Forced air
ventilation or air-conditioning shall be provided to underground spaces, galleries and in controlled
environment where comfort of people and protection of equipment are required.
Building systems and materials shall be selected to suit the environment.
C10.8.3. Construction Materials
Unless otherwise specified, all buildings shall have reinforced concrete floors.
Protective coating to steelwork shall comply with WSA 201 and Sydney Water’s Supplements.
All buildings shall be fit for purpose, secure from weather, vermin and resistant to attack from vandals. All
external doors shall be solid core doors with deadlocks. All locks shall be master-keyed, or keyed alike to
the system already in use.
The interior shall be finished neatly using lined ceilings (except in plant rooms) and face brick or rendered
walls with slip resistant floors. Translucent roof sheeting or skylights may be used to maximise natural
lighting.
Unless otherwise specified, metal roof and wall sheets shall be marine grade aluminium, Colorbond, Ultra
Steel sheetings, or accepted equivalent.
Adequate tread plates or cat–walk shall be provided on metal roof where access is required for operational
needs. Where access is required on metal roof, the deflection of the roof sheeting under design load shall
not exceed 1/250 of the span, with a maximum value of 5 mm.
Flashings, eave gutters, outlets, downpipes and the like shall be provided. Rainwater goods, accessories
and fasteners shall be powdered coated aluminium, or zinc/aluminium alloy-coated steel to AS 2179 and
shall be designed in accordance with AS 3500.
Doc no. CPDMS0023 Document uncontrolled when printed Page: 106 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
Note: # Roof surface must be at least 300mm above the adjacent ground level, or protected with adequately
designed barriers/bollards to exclude vehicular traffic.
C10.9.4. Importance Levels for Earthquake and Wind Loads
For the assessment of wind and earthquake loads for new structures, the “Importance Level” shall be in
accordance with the guidelines in Table F1 of AS 1170.0 and the Building Code of Australia. Unless
accepted in advance by Sydney Water, the values for importance levels shall be as in Table 10.3.
The internal wind coefficient for the reservoir shell shall be more severe than -0.5 (suction).
Doc no. CPDMS0023 Document uncontrolled when printed Page: 107 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
Doc no. CPDMS0023 Document uncontrolled when printed Page: 108 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
Doc no. CPDMS0023 Document uncontrolled when printed Page: 109 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
A minimum surcharge loading of 20 kPa where unrestricted vehicular access is required for
maintenance purposes.
Earthquake induced additional soil pressure.
Compaction induced additional soil pressure.
All design checks shall be carried out using load combinations presented in AS 5100.3.
C10.9.8. Spacing for Bollards & Design Loads for Restricting Vehicular Access
The bollards shall be spaced at no more than 2.0 m centres and shall be designed for an ultimate load of
45 kN applied at 1 m above the pavement level.
C10.9.9. Vibration Loads
The effect of vibration and torque of the equipment on footings shall be considered. If data for the design of
the footings is not available from the manufacturer or investigation is not carried by an industry recognised
specialist, the weight of the footing W 1 shall not be less than 3 times of the weight of the equipment W 2.
For vertical vibration, W 1 shall be confined to the area (a+2t) x (b+2t), where:
a & b refer to the plan dimensions of the equipment.
t refers to the thickness of the supporting slab.
For horizontal vibrations, W 1 may be taken as the weight of the horizontal bracing structure.
C10.9.10. Dynamic Loads
Dynamic loads related to Crane Runways and Monorails shall be calculated to AS 1418.1 shall not be less
than the following:
Vertical - 25 % of the total load including trolley.
Horizontal transverse - 20 % of the total load including trolley.
Horizontal longitudinal – 10 % of the total load including trolley.
C10.9.11. Thrust Loads
Thrust loads from all anchored components of hydraulic conveyances shall be considered on the structure.
Doc no. CPDMS0023 Document uncontrolled when printed Page: 110 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
C10.10.2. Durability Requirements (concrete grade & cover to reinforcement) for Concrete
Structures
The durability requirements for non-liquid retaining structures designed for 50 year design life shall be in
accordance with AS 3600 and 100 year design life shall be in accordance with AS5100.
For liquid retaining structures, Table 10-4 lists the minimum durability requirements for typical exposure
categories for 50 year design life and Table 10-5 lists the minimum durability requirements for typical
exposure categories for 100 year design life
For structural members formed by spinning or rolling concrete with water/cement ratio of less than 0.35, the
minimum cover to liquid retaining surfaces shall be
Exposure classifications B1 & B2 - 20 mm & 30 mm for design lives 50 years & 100 years respectively
Exposure classifications C & D - 30 mm & 40 mm for design lives 50 years & 100 years respectively
C10.10.3. Reduction in Cover Requirements for Galvanised and Austenitic Stainless steel
Reinforcement
The normal cover requirements may be reduced by up to 10 mm for galvanised reinforcement and 20 mm
for austenitic stainless steel reinforcement. The minimum cover provided shall not be less than 25 mm or 50
% more than the largest aggregates used in the concrete.
C10.10.4. Areas to be Designed as Alternate Wet and Dry to AS 3735
All surfaces above the minimum operating level shall be designed as being subjected to alternate wetting
and drying (Table 3.5 of AS 3735).
Table 10-4 Minimum Durability Requirements for Typical Exposure Classifications in Liquid
Retaining Structures For 50 Year Design Life
Concrete Grade S40 Concrete Grade S50
Liquid Retaining Rigid
Structure Type Surfaces / Exposure Rigid Formwork &
Standard Standard Formwork &
Classification Intense
Formwork Formwork Intense
Compaction
Compaction
Sewerage Structures Walls & Roof / D 75 mm1 60 mm1 55 mm1 45 mm1
Floor / C 75 mm 60 mm 55 mm 45 mm
Sewage Wet Weather Walls & Roo f / D 75 mm1 60 mm1 55 mm1 45 mm1
Overflow Storage
Tanks – Sharing the Floor / C 75 mm 60 mm 55 mm 45 mm
same air space as the
dry weather wet wells
Sewage Wet Weather Walls, Roof & Floor / C 75 mm
Overflow Storage 60 mm 55 mm 45 mm
Tanks – Not sharing
the same air space as
wet wells
Sewage Treatment Walls & Roof / D 75 mm1 60 mm1 55 mm1 45 mm1
Plants– Inlet Structures
Floor / C 75 mm 60 mm 55 mm 45 mm
Doc no. CPDMS0023 Document uncontrolled when printed Page: 111 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
Table 10-5 Minimum Durability Requirements for Typical Exposure Classifications in Liquid
Retaining Structures For 100 Year Design Life
Concrete Grade S40 Concrete Grade S50
Liquid Retaining Rigid
Structure Type Surfaces / Exposure Rigid Formwork &
Standard Standard Formwork &
Classification Intense
Formwork Formwork Intense
Compaction
Compaction
Sewerage Structures Walls & Roof / D NA 70 mm1 70 mm1 55 mm1
Floor / C NA 70 mm 70 mm 55 mm
Sewage Pumping Walls & Roof / D NA 70 mm1 70 mm1 55 mm1
Stations - Wet Wells,
inlet access chambers Floor / C NA 70 mm 70 mm 55 mm
Doc no. CPDMS0023 Document uncontrolled when printed Page: 112 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
Doc no. CPDMS0023 Document uncontrolled when printed Page: 113 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
Doc no. CPDMS0023 Document uncontrolled when printed Page: 114 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
C10.10.12. Load Combinations for Serviceability to AS 3735 for Liquid Retaining Concrete
Structures
In addition to the requirements of serviceability to AS 3735, the following additional load combinations shall
be considered typically for walls and floors of structures founded below ground level:
Normal operating conditions – external soil pressure and ground water table shall not be taken into
account in Group A serviceability calculations. However, the desirable effect of external soil pressure
may be used when the earth pressure coefficient, subject to a maximum value of 0.20, is substantiated
by adequate soil testing corresponding to a characteristic value for design resistance.
Maximum overload conditions - external soil pressure and ground water table shall not be taken into
account in Group B serviceability calculations. However, the desirable effect of external soil pressure
may be used when the earth pressure coefficient, subject to a maximum value of 0.20, is substantiated
by adequate soil testing.
As (1) above with earthquake load for Group B serviceability.
Structure empty with design earth pressure (excluding surcharge loads) and design ground water table
for Group B serviceability.
Structure empty with design earth pressure including surcharge loads for Group B serviceability.
Individual compartments with adjacent compartment empty for normal operating condition for Group A
serviceability.
Individual compartments with adjacent compartment empty for maximum overload condition for Group B
serviceability.
Individual compartments with adjacent compartment empty for normal operating condition with
earthquake for Group B Serviceability.
Baffle walls for normal operating condition with a minimum of 1 m hydrostatic pressure differential for
Group A serviceability.
Baffle walls for normal operating condition with earthquake for Group B serviceability.
Baffle walls without adequate openings for flow balancing shall be designed as 6, 7 & 8 above.
The effects of shrinkage and swelling effects and, temperature variations and temperature gradients shall be
combined with the above load combinations as appropriate in accordance with Clause 2.4 of AS 3735.
C10.10.13. Reinforcement Details at Opening “L” and “T” joints
The reinforcement details in all opening joints (e.g. wall to floor and wall to wall) shall conform to
recommended practices to avoid premature diagonal cracking of concrete inside the joint.
For details not conforming to published recommended practices, appropriate reduction in the actual moment
capacity of the joint (not member capacity adjacent to the joint) shall be taken into consideration.
Details complying to published recommended practices, as a minimum shall include the following:
At “L” joints, the reinforcement from the joining members shall overlap within the joint as “U” bars with
transverse reinforcement located inside each corner of the overlap. The extension of the “U” bar past
the inside face of corner shall be at least equal to the anchorage length.
At “T” joints, the cogs of the starter bars shall be turned towards the opposite face reinforcement. The
extension of the cog past the opposite face reinforcement shall be at least equal to the anchorage
length.
Doc no. CPDMS0023 Document uncontrolled when printed Page: 115 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
Doc no. CPDMS0023 Document uncontrolled when printed Page: 116 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
Fillet Welds
The size of fillet welds shall make allowance for long term corrosion.
Minimum 6 mm continuous fillet welding shall be used for all connections, including seal welds.
Intermittent welding shall not be permitted.
Welding
Weld details shall comply with the following:
Full penetration butt welds shall be adopted for wall and sketch plates with backing run for wall plates.
Continuous fillet welds shall be adopted for floor plates.
Minimum size of fillet weld shall be 6 mm.
Joint efficiency of the weld shall be 100%.
No seal weld or intermittent weld shall be permitted.
General
Bolted tanks shall not be used unless the following is demonstrated and accepted by Sydney Water
Minimum design life shall be fifty (50) years
Maintenance free ten (10) year performance records of at least three tanks of identical construction in
Australia shall be provided
All material components shall a minimum warranty period of15 years
The requirements of AWWA D103 shall be complied to factory-coated bolted carbon steel tanks for
water storage. Bolted steel tanks for other cargo e.g. wastewater sludge and chemicals, the
requirements of ISO 28765 shall apply.
Interior and exterior coatings shall be glass fused-to-steel (vitreous enamel) coating. Prior to fabrication
of the steel panels, an Inspection and Testing Plan for the coating shall be submitted to Sydney Water
for acceptance. The inspection and testing shall be undertaken by a certified 3rd party coating
Inspector. Sydney Water (and its representative) reserves the right to carry out quality audits on the
work from time-to-time.
Sealants and gaskets shall have adequate chemical resistant to the intended cargo. For drinking water
purpose, they shall be demonstrated to have long-term chemical resistant to a minimum of 2 ppm of
free chlorine solution.
25 mm x 50 mm joint sealant shall be provided in a preformed recess on both faces of the embedded
section of the wall stakes.
Neoprene strip of appropriate harness shall be inserted in every lap joints
Doc no. CPDMS0023 Document uncontrolled when printed Page: 117 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
Doc no. CPDMS0023 Document uncontrolled when printed Page: 118 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
( + )
=
2
For materials where the nominal wall thickness of the pipe is close to the specified minimum wall thickness,
the minimum wall thickness shall be used for calculating ring bending stiffness.
Typically, DI pipe and Steel pipe are supplied with cement mortar lining (CML). The CML shall not be
included in the calculation of the overall pipe stiffness.
Design Loads
Vertical earth pressures shall comprise the full height of soil above the pipe without reductions for trench
effects (e.g. load reduction due to friction against the trench wall). Bulk unit weight of fill shall be 20 kN/m3.
Doc no. CPDMS0023 Document uncontrolled when printed Page: 119 of 120
Version: 8 Issue date: 14/08/2019
Technical Specification- Civil
Road vehicle loads shall be taken as SM1600 as given in AS5100.2 for the following loading types listed in
Table 10-6.
The pipe shall be designed to resist hydrostatic pressures from a water table located at the surface, or
where suitable information is available, the ground water level with an annual probability of exceedance of 1
in 100. External hydrostatic load due to grouting shall be considered where applicable.
C10.14.4. Rigid pipe structural design (non pressure)
Structural design of Reinforced Concrete (RC) pipes shall be in accordance with AS/NZS 3725. Structural
design of Vitrified Clay (VC) pipes shall be in accordance with AS 4060 or BS EN 1295-1 National annex A.
Doc no. CPDMS0023 Document uncontrolled when printed Page: 120 of 120
Version: 8 Issue date: 14/08/2019