0% found this document useful (0 votes)
128 views10 pages

A PDF

This document provides a submittal log for the Highland Mall project located in Cainta, Rizal City, Philippines. It includes one item, a neoprene rubber strip submittal from Tapemaster, which was received on November 15, 2019. The item is pending and overdue with the RBSE (Rizal Building and Safety Enforcement) office. No other submittals are included on the log.

Uploaded by

Kimberly Heray
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
128 views10 pages

A PDF

This document provides a submittal log for the Highland Mall project located in Cainta, Rizal City, Philippines. It includes one item, a neoprene rubber strip submittal from Tapemaster, which was received on November 15, 2019. The item is pending and overdue with the RBSE (Rizal Building and Safety Enforcement) office. No other submittals are included on the log.

Uploaded by

Kimberly Heray
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

PROJECT: HIGHLAND MALL

LOCATION: FELIX AVENUE, BRGY. STO. DOMINGO, CAINTA, RIZAL CITY


DATE: 1/7/2020
STRUCTURAL SUBMITTAL LOGS

DESCRIPTION RBSE MEGAWORLD


ITEM NO. STATUS STATUS
14-DAYS TURN STATUS 14-DAYS TURN
SUBMITTAL CODE TITLE DATE RECEIVED STATUS
STOUND Aging
DATE RECEIVED
(RESPONSE) STOUND Aging
REMARKS

RFA-MATERIALS SUBMITTAL STRUCTURAL

NEOPRENE RUBBER STRIP BY TAPEMASTER Sent thru APPROVED AS Received by


1.0 MCC-SKM323-MSA-ST-001 15-Nov-19
E-mail to RBSE
29-Nov-19 -5
NOTED
03-Dec-19
Engr. Eisel Cuales
17-Dec-19 -35 PENDING OVERDUE TRN-SKM323-E-064
MARKETING

LEGEND: LEGEND:

0 APPROVED 0 APPROVED

1 APPROVED AS NOTED 0 APPROVED AS NOTED

0 RESUBMIT (SUPERSEDED) 0 RESUBMIT (SUPERSEDED)

0 DISAPPROVED 0 DISAPPROVED

0 PENDING APPROVAL 0 PENDING APPROVAL

0 PENDING OVERDUE 1 PENDING OVERDUE

TOTAL 1 TOTAL 1
DESCRIPTION RBSE MEGAWORLD
ITEM NO. STATUS STATUS
14-DAYS TURN 14-DAYS TURN
SUBMITTAL CODE TITLE DATE RECEIVED STATUS
STOUND Aging
DATE RECEIVED STATUS
STOUND Aging
REMSTKS

RFA-DOCUMENT SUBMITTAL STRUCTURAL

LEGEND: LEGEND:

0 APPROVED 0 APPROVED

0 APPROVED AS NOTED 0 APPROVED AS NOTED

0 DISAPPROVED 0 DISAPPROVED

0 RESUBMIT (SUPERSEDED) 0 RESUBMIT (SUPERSEDED)

0 PENDING APPROVAL 0 PENDING APPROVAL

0 PENDING OVERDUE 0 PENDING OVERDUE

TOTAL 0 TOTAL 0

DESCRIPTION
ITEM NO. STATUS STATUS
14-DAYS TURN 14-DAYS TURN
SUBMITTAL CODE TITLE DATE RECEIVED STATUS
STOUND Aging
DATE RECEIVED STATUS
STOUND Aging
REMARKS

RFA - SHOPDRAWING STRUCTURAL (BUILDING)

RECEIVED BY
APPROVED AS
1.0 MCC-SKM323-RFA-SD-ST-001 SHOP DRAWING FOR TEST FILE 28-May-19 ENGR. JOREZZA 11-Jun-19 -2
NOTED
DUQUE

SENT THRU
APPROVED AS
2.0 MCC-SKM323-RFA-SD-ST-002 SHOP DRAWING FOR TEST FILE 03-Jun-19 EMAIL TO R.B. 17-Jun-19 -3
NOTED
SANCHEZ

RECEIVED BY
3.0 MCC-SKM323-RFA-SD-ST-003 SHOP DRAWING FOR TEST FILE (12m/16m) 06-Jun-19 ENGR. EISEL 20-Jun-19 -18 CANCELLED CANCELLED
ZARVIC CUALES

RECEIVED BY
4.0 MCC-SKM323-RFA-SD-ST-004 SHOP DRAWING FOR TEST FILE (24m) 06-Jun-19 ENGR. EISEL 20-Jun-19 -18 CANCELLED CANCELLED
ZARVIC CUALES

RECEIVED BY
RE-BAR CUTTING LIST FOR DOMESTIC WATER APPROVED AS
5.0 MCC-SKM323-RFA-SD-ST-005 11-Jun-19 ENGR. JOREZZA 25-Jun-19 -31
NOTED
TRN-SKM323-E-014
TANK DUQUE

RECEIVED BY
RE-BAR CUTTING LIST OF SEWAGE TREATMENT APPROVED AS
6.0 MCC-SKM323-RFA-SD-ST-006 11-Jun-19 ENGR. JOREZZA 25-Jun-19 -31
NOTED
TRN-SKM323-E-014
PLANT DUQUE

RECEIVED BY
APPROVED AS
7.0 MCC-SKM323-RFA-SD-ST-007 RE-BAR CUTTIMG LIST OF RAIN WATER TANK 11-Jun-19 ENGR. JOREZZA 25-Jun-19 -31
NOTED
TRN-SKM323-E-014
DUQUE

RECEIVED BY
APPROVED AS
8.0 MCC-SKM323-RFA-SD-ST-008 RE-BAR CUTTING LIST OF PILE CAP 11-Jun-19 ENGR. JOREZZA 25-Jun-19 -17
NOTED
TRN-SKM323-E-014
DUQUE
RECEIVED BY
RELOCATION OF TEST PILE 11 IN CONFLICT WITH APPROVED AS
9.0 MCC-SKM323-RFA-SD-ST-009 11-Jun-19 ENGR. JOREZZA 25-Jun-19 -9
NOTED
TRN-SKM323-E-014
EXISTING MANGO TREE DUQUE

REBAR CUTTING LIST OF THE FOLLOWING:


RECEIVED BY
1. ELEVATOR PIT APPROVED AS
10.0 MCC-SKM323-RFA-SD-ST-010 14-Jun-19 ENGR. JOREZZA 28-Jun-19 -28
NOTED
2. ESCALATOR PIT DUQUE
3. STAIR FOOTING
REBAR CUTTING LIST OF THE FOOTING RECEIVED BY
APPROVED AS
11.0 MCC-SKM323-RFA-SD-ST-011 TIE BEAM 09-Jul-19 ENGR. JOREZZA 23-Jul-19 -14
NOTED
DUQUE

REBAR CUTTING LIST OF THE FOOTING RECEIVED BY


APPROVED AS
12.0 MCC-SKM323-RFA-SD-ST-011A TIE BEAM (SHORT SPAN) 26-Jul-19 ENGR. JOREZZA 09-Aug-19 -5
NOTED
DUQUE

REBAR CUTTING LIST OF THE FOOTING RECEIVED BY


APPROVED AS
13.0 MCC-SKM323-RFA-SD-ST-011B TIE BEAM (LONG SPAN) 26-Jul-19 ENGR. JOREZZA 09-Aug-19 -14
NOTED
DUQUE

RECEIVED BY
REBAR CUTTING LIST OF COLUMN APPROVED AS
14.0 MCC-SKM323-RFA-SD-ST-012 09-Jul-19 ENGR. JOREZZA 23-Jul-19 -14
NOTED
DUQUE

RECEIVED BY
REBAR CUTTING LIST OF COLUMN APPROVED AS
15.0 MCC-SKM323-RFA-SD-ST-012A 26-Jul-19 ENGR. JOREZZA 09-Aug-19 -5
NOTED
DUQUE

SENT THRU
REBAR CUTTING LIST OF SLAB ON GRADES APPROVED AS
16.0 MCC-SKM323-RFA-SD-ST-013 11-Jul-19 EMAIL TO R.B. 25-Jul-19 -40
NOTED
SANCHEZ

RECEIVED BY
APPROVED AS
17.0 MCC-SKM323-RFA-SD-ST-014 PDA RESULT 22-Jul-19 ENGR. JOREZZA 05-Aug-19 -4
NOTED
DUQUE

SENT THRU
REQUEST TO CONVERT FTB STRENGHT FROM APPROVED AS
18.0 MCC-SKM323-RFA-SD-ST-015 29-Jul-19 EMAIL TO R.B. 12-Aug-19 -16
NOTED
6000PSI TO 5000PSI SANCHEZ

SENT THRU
19.0 MCC-SKM323-RFA-SD-ST-016 HOLLOW CORE TO BEAM CONNECTION 09-Aug-19 EMAIL TO R.B. 23-Aug-19 -151 PENDING OVERDUE
SANCHEZ

SENT THRU
APPROVED AS
20.0 MCC-SKM323-RFA-SD-ST-017 TEST PILE LOCATION OF TP-9 01-Aug-19 EMAIL TO R.B. 15-Aug-19 -8
NOTED
SANCHEZ
SENT THRU
21.0 MCC-SKM323-RFA-SD-ST-018 TOWER CRANE FOUNDATION CUTTING LIST 09-Aug-19 EMAIL TO R.B. 23-Aug-19 -151 PENDING OVERDUE
SANCHEZ

SENT THRU
21.0 MCC-SKM323-RFA-SD-ST-018A TOWER CRANE FOUNDATION CUTTING LIST 03-Oct-19 EMAIL TO R.B. 17-Oct-19 -5 PENDING OVERDUE
SANCHEZ

SENT THRU
APPROVED AS
22.0 MCC-SKM323-RFA-SD-ST-019 CONNECTION DETAIL OF PILE TO PILE CAP 14-Aug-19 EMAIL TO R.B. 28-Aug-19 -28
NOTED
SANCHEZ

SENT THRU
APPROVED AS
23.0 MCC-SKM323-RFA-SD-ST-020 TOWER CRANE LOCATION 20-Aug-19 EMAIL TO R.B. 03-Sep-19 -36
NOTED
SANCHEZ

RECEIVED BY
APPROVED AS
24.0 MCC-SKM323-RFA-SD-ST-021 UPPER GROUND FLOOR GIRDER AND BEAMS 28-Aug-19 ENGR. JOREZZA 11-Sep-19 -37
NOTED
DUQUE

RECEIVED BY
25.0 MCC-SKM323-RFA-SD-ST-022 FOOTING TIE BEAM (SHORT FTB) 28-Aug-19 ENGR. JOREZZA 11-Sep-19 -132 PENDING OVERDUE
DUQUE

SENT THRU
CONSTRUCTION JOINT LOCATION FOR LOWER APPROVED AS
26.0 MCC-SKM323-RFA-SD-ST-023 29-Aug-19 EMAIL TO R.B. 12-Sep-19 -83
NOTED
GROUND FLOOR SANCHEZ

SENT THRU
APPROVED AS
27.0 MCC-SKM323-RFA-SD-ST-024 ELEVATOR PIT ON TOP OF PILE CAP 04-Sep-19 EMAIL TO R.B. 18-Sep-19 -82
NOTED
SANCHEZ

SENT THRU
APPROVED AS
28.0 MCC-SKM323-RFA-SD-ST-025 ADJUSTMENT OF COLUMNS AT PERIMETER 10-Sep-19 EMAIL TO R.B. 24-Sep-19 -22
NOTED
SANCHEZ

RECEIVED BY
FOOTING TIE BEAM (LONG SPAN AND SHORT APPROVED AS
29.0 MCC-SKM323-RFA-SD-ST-026 11-Sep-19 ENGR. JOREZZA 25-Sep-19 -7
NOTED
SPAN) DUQUE

RECEIVED BY
30.0 MCC-SKM323-RFA-SD-ST-027 THIRD FLOOR GIRDER AND BEAMS 19-Sep-19 ENGR. JOREZZA 03-Oct-19 -110 PENDING OVERDUE
DUQUE

RECEIVED BY
31.0 MCC-SKM323-RFA-SD-ST-028 RETAINING WALL CUTTING LIST 20-Sep-19 ENGR. JOREZZA 04-Oct-19 -109 PENDING OVERDUE
DUQUE

RECEIVED BY
MEZZANINE FLOOR BEAMS ANN GIRDERS
32.0 MCC-SKM323-RFA-SD-ST-029 20-Sep-19 ENGR. JOREZZA 04-Oct-19 -109 PENDING OVERDUE
CUTTING LIST DUQUE

SENT THRU
APPROVED AS
33.0 MCC-SKM323-RFA-SD-ST-030 PILE CAP WITHOUT HOOK 27-Sep-19 EMAIL TO R.B. 11-Oct-19 -3
NOTED
SANCHEZ

SENT THRU
APPROVED AS
34.0 MCC-SKM323-RFA-SD-ST-031 CONNECTION OF RETAINING WALL TO COLUMN 28-Sep-19 EMAIL TO R.B. 12-Oct-19 -4
NOTED
SANCHEZ

SENT THRU
FOOTING TIE BEAM APPROVED AS
35.0 MCC-SKM323-RFA-SD-ST-032 30-Sep-19 EMAIL TO R.B. 14-Oct-19 -9
NOTED
(ADDITIONAL) SANCHEZ
SENT THRU
36.0 MCC-SKM323-RFA-SD-ST-033 PROPOSED TOWER CRANE LOCATION 30-Sep-19 EMAIL TO R.B. 14-Oct-19 -99 PENDING OVERDUE
SANCHEZ

SENT THRU
APPROVED AS
37.0 MCC-SKM323-RFA-SD-ST-033A PROPOSED TOWER CRANE LOCATION 01-Oct-19 EMAIL TO R.B. 15-Oct-19 0
NOTED
SANCHEZ

SENT THRU
APPROVED AS
38.0 MCC-SKM323-RFA-SD-ST-034 LONG PILE REFUSAL 25-Sep-19 EMAIL TO R.B. 09-Oct-19 -5
NOTED
SANCHEZ

SENT THRU
APPROVED AS
39.0 MCC-SKM323-RFA-SD-ST-035 LAYOUT POF HOLLOW CORE AND DETAILS 08-Oct-19 EMAIL TO R.B. 22-Oct-19 -16
NOTED
SANCHEZ

SENT THRU
APPROVED AS
40.0 MCC-SKM323-RFA-SD-ST-036 REMOVAL OF FTB-10 10-Oct-19 EMAIL TO R.B. 24-Oct-19 -4
NOTED
SANCHEZ

SENT THRU
41.0 MCC-SKM323-RFA-SD-ST-037 100mm THK GRAVEL BEDDING (SOG) 16-Oct-19 EMAIL TO R.B. 30-Oct-19 -83 PENDING OVERDUE
SANCHEZ

RECEIVED BY
42.0 MCC-SKM323-RFA-SD-ST-038 STP CUTTING LIST 24-Oct-19 ENGR. JOREZZA 07-Nov-19 -75 PENDING OVERDUE
DUQUE

RECEIVED BY
APPROVED AS
43.0 MCC-SKM323-RFA-SD-ST-039 SECOND FLOOR BEAMS AND GIRDERS 24-Oct-19 ENGR. JOREZZA 07-Nov-19 -53
NOTED
DUQUE

SENT THRU
38.0 MCC-SKM323-RFA-SD-ST-040 HOLLOW CORE DETAILS AND CALCULATIONS 08-Nov-19 EMAIL TO R.B. 22-Nov-19 -60 PENDING OVERDUE
SANCHEZ

SENT THRU
REQUEST FOR CONFIRMATION TO USE EXISTING APPROVED AS
39.0 MCC-SKM323-RFA-SD-ST-041 22-Nov-19 EMAIL TO R.B. 06-Dec-19 -25
NOTED
DETAILS OF STP ON REVISED LENGTH SANCHEZ

REQUEST TO DRILL 10 PCS 12 MM DIA.


SENT THRU
HORIZONTAL BARS TO COLUMN WITH 200MM APPROVED AS
40.0 MCC-SKM323-RFA-SD-ST-042 22-Nov-19 EMAIL TO R.B. 06-Dec-19 -3
NOTED
DEPTH DUE TO METHODOLOGY ON SITE SANCHEZ
CONSTRUCTION
REQUEST TO DRILL 38 PCS 12 MM DIA. VERTICAL
SENT THRU
BARS TO ELEVATOR PRESSURE SLAB WITH 150 MM
41.0 MCC-SKM323-RFA-SD-ST-043 02-Dec-19 EMAIL TO R.B. 16-Dec-19 -36 PENDING OVERDUE
DEPTH DUE TO METHODOLOGY ON SANCHEZ
MECHANICAL ADJUSTMENT
SENT THRU
PROPSED CUTTING OF STRAND OF HOLLOW
42.0 MCC-SKM323-RFA-SD-ST-044 02-Dec-19 EMAIL TO R.B. 16-Dec-19 -36 PENDING OVERDUE
CORE DUE TO 200 MM PIPE SLEEVE SANCHEZ

SENT THRU
PROPOSED CONNECTION DETAIL OF
42.0 MCC-SKM323-RFA-SD-ST-045 05-Dec-19 EMAIL TO R.B. 19-Dec-19 -33 PENDING OVERDUE
ESCALATOR PIT TO FTB SANCHEZ

RE-ORIENTATION OF HOLLOW CORE AT GRID SENT THRU


APPROVED AS
42.0 MCC-SKM323-RFA-SD-ST-046 LINES K-L AND 1-2 DUE TO MECHANICAL BLOCK 16-Dec-19 EMAIL TO R.B. 30-Dec-19 -2
NOTED
OUT AT 2ND FLOOR FRAMING SANCHEZ
RE-ORIENTATION OF HOLLOW CORE AT GRID
LINES K-L / 12-13, I-J / 13-14 DUE TO SENT THRU
42.0 MCC-SKM323-RFA-SD-ST-047 MECHANICAL BLOCK OUT AND GRID LINE H-I / 19-Dec-19 EMAIL TO R.B. 02-Jan-20 -19 PENDING OVERDUE
11-12 DUE TO ADDITIONAL ESCALATOR AT 2ND SANCHEZ

FLOOR FRAMING

ADJUSTMENT OF B-2 AT UPPER GROUND SENT THRU


APPROVED AS
42.0 MCC-SKM323-RFA-SD-ST-048 FRAMING PLAN DUE TO THE REORIENTATION OF 19-Dec-19 EMAIL TO R.B. 02-Jan-20 -1
NOTED
ESCALATOR SANCHEZ

SENT THRU
PROPOSED TYPICAL PIPE SLEEVE DIAGONAL BAR
42.0 MCC-SKM323-RFA-SD-ST-049 27-Dec-19 EMAIL TO R.B. 10-Jan-20 7 PENDING APPROVAL
DETAIL ON BEAMS SANCHEZ
LEGEND: LEGEND:

0 APPROVED 0 APPROVED

36 APPROVED AS NOTED 0 APPROVED AS NOTED

0 DISAPPROVED 0 DISAPPROVED

0 RESUBMIT / SUPERSEDED 0 RESUBMIT / SUPERSEDED

1 PENDING APPROVAL 0 PENDING APPROVAL

15 PENDING OVERDUE 0 PENDING OVERDUE

TOTAL 52 TOTAL 0

DESCRIPTION
ITEM NO. STATUS STATUS
14-DAYS TURN 14-DAYS TURN
SUBMITTAL CODE TITLE DATE RECEIVED STATUS
STOUND Aging
DATE RECEIVED STATUS
STOUND Aging
REMSTKS
RFA - SHOPDRAWING STRUCTURAL (SITEDEVT)

DESCRIPTION
ITEM NO. STATUS STATUS
14-DAYS TURN 14-DAYS TURN
SUBMITTAL CODE TITLE DATE RECEIVED STATUS
STOUND Aging STOUND Aging
REMSTKS

RFI - STRUCTURAL (BUILDING)


REQUEST FOR INFORMATION OF THE FOLLOWING
RECEIVED BY
TOWER CRANES:
1.0 MCC-SKM323-RFI-ST-001 18-Jun-19 ENGR. JOREZZA 02-Jul-19 -48 RESPONDED
1. 18 TONER (1SET) DUQUE
2. 20 TONER (3SETS)
REQUEST FOR INFORMATION OF THE SENT THRU
2.0 MCC-SKM323-RFI-ST-002 PRODUCTION PILE LENGTH TO BE USED WITHIN 07-Jul-19 EMAIL TO R.B. 21-Jul-19 -29 RESPONDED
THE AREA OF TP 17, 18, 19 AND 20 SANCHEZ

SENT THRU
REQUEST FOR INFORMATION ON THE TREATMENT
3.0 MCC-SKM323-RFI-ST-003 02-Sep-19 EMAIL TO R.B. 16-Sep-19 -68 RESPONDED
OF BROKEN PILES SANCHEZ

SENT THRU
4.0 MCC-SKM323-RFI-ST-004 RETAINING WALL DETAIL 05-Aug-19 EMAIL TO R.B. 19-Aug-19 -30 RESPONDED
SANCHEZ

SENT THRU
5.0 MCC-SKM323-RFI-ST-005 STRUCTURAL DETAILS OF STP 10-Sep-19 EMAIL TO R.B. 24-Sep-19 -21 RESPONDED
SANCHEZ

SENT THRU
6.0 MCC-SKM323-RFI-ST-006 STRUCTURAL DETAILS OF SKYLIGHT 10-Oct-19 EMAIL TO R.B. 24-Oct-19 -89 PENDING OVERDUE
SANCHEZ

SENT THRU
7.0 MCC-SKM323-RFI-ST-007 BEAMS WITHOUT DETAILS 10-Oct-19 EMAIL TO R.B. 24-Oct-19 -11 RESPONDED
SANCHEZ

CONFIRMATION IF THE PROPOSED ELEVATED SENT THRU


8.0 MCC-SKM323-RFI-ST-008 WATER TANK CAN BE CARRIED BY EXISTING 24-Oct-19 EMAIL TO R.B. 07-Nov-19 -75 PENDING OVERDUE
STRUCTURAL FRAMING SANCHEZ

SENT THRU
9.0 MCC-SKM323-RFI-ST-009 REVISED FRAMING BASED ON ROOF PLAN 05-Nov-19 EMAIL TO R.B. 19-Nov-19 -63 PENDING OVERDUE
SANCHEZ

SENT THRU
10.0 MCC-SKM323-RFI-ST-010 REQUEST FOR RC WALL DETAIL 07-Nov-19 EMAIL TO R.B. 21-Nov-19 -15 RESPONDED
SANCHEZ

SENT THRU
11.0 MCC-SKM323-RFI-ST-011 GIRDER DESIGNATION 07-Nov-19 EMAIL TO R.B. 21-Nov-19 -4 RESPONDED
SANCHEZ

SENT THRU
REQUEST FOR CONFIRMATION OF THE NEW PILE
12.0 MCC-SKM323-RFI-ST-012 25-Nov-19 EMAIL TO R.B. 09-Dec-19 0 RESPONDED
CAP AND PILE LAYOUT SANCHEZ

SENT THRU
13.0 MCC-SKM323-RFI-ST-013 FRAMING OF ADDITIONAL STAIR 30-Nov-19 EMAIL TO R.B. 14-Dec-19 -38 PENDING OVERDUE
SANCHEZ
SENT THRU
14.0 MCC-SKM323-RFI-ST-014 COVER SLAB OF STP 13-Dec-19 EMAIL TO R.B. 27-Dec-19 -5 RESPONDED
SANCHEZ

SENT THRU
REQUEST FOR CONFIRMATION IF LINK SLAB CIP
15.0 MCC-SKM323-RFI-ST-015 13-Dec-19 EMAIL TO R.B. 27-Dec-19 -25 PENDING OVERDUE
CAN BE CONVERTED TO HALF SLAB SANCHEZ

LEGEND: LEGEND:

10 RESPONDED 0 RESPONDED

0 WAITING FOR RESPONSE 0 WAITING FOR RESPONSE

5 PENDING OVERDUE 0 PENDING OVERDUE

TOTAL 15 TOTAL 0