007 Markelj
007 Markelj
007 Markelj
net/publication/286453396
CITATIONS READS
0 64
1 author:
Viktor Markelj
University of Maribor
11 PUBLICATIONS 2 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Viktor Markelj on 11 December 2015.
Viktor MARKELJ
civ.eng.- bridge designer
Ponting d.o.o.,
Maribor Slovenia
Summary
The article presents the conceptual design and the structural solutions for the longest Slovenian bridge over
the Mura River, consisting of two separated 833.0 m long and in all 28 m wide bridge structures. The main
span over the river is 80.0 m long while the characteristic structural span amounts to 40 m in length.
The design particularity is the 2.40 m deep steel deviator underneath the superstructure at the main span, leading the
external tendons outside the bridge profile. Launching in the final position over the final and temporary supports was
achieved with only one launching equipment, although the bridge has a double curved (Rh = 2400 m, Rv = 40000 m)
geometry and is 833 m long. The construction of the bridge took 3 years.
Keywords: bridge ; prestressing ; external tendons ; cables ; deviator ; incremental launching
1 Introduction
In October 2003 a 15 km long section of the motorway between cities Maribor and Lendava was opened that
will improve the traffic connections in the direction of Hungary and also bring nearer the most eastern
Slovene region Prekmurje. South of city Murska Sobota the motorway crosses the river Mura and its
inundation area.
In this place the inundation zone of the river Mura is the narrowest, only a good kilometre wide, which was one of the
criteria to locate the motorway in this area. The river Mura, having a lowland character with meanders and backwaters
in the lower river course, here is partly improved in the riverbed width of 70 m. The most pretentious, unique and
innovatory structure in this part of the motorway is the 833 m long bridge across the Mura, the longest bridge (across
water) in Slovenia.
most satisfactory offer the least expensive solution Brod3 (girder with prestressed tie) of GIZ Gradis
Ljubljana (12.5 millions EUR), upon the design of Ponting Maribor, was selected.
3 Conceptual design
The bridge over the river Mura and the inundation zone crosses a naturally very intense biotope, due to
specifically rhythmic floods containing also rare and jeopardized animal and vegetable species. The
inundation flat land is densely overgrown with high trees, and the riverbanks with dense bushes.
Morphologically the area between embankments is practically flat with smaller depressions at the location of
former – today dead - branches of the river. At this place the river bed is 70 m wide, and the inundation zone
between safety embankments a good kilometre.
The main idea of the design was to create a structure of a suitable shape, yet at the same time of good
quality, durable and economical one, which by a unified technology solves the structural problem of bridging
equable smaller spans at the inundation area and – as an exception – one larger span over the river.
4 Technical description
The bridge over the Mura consists of two separated parallel bridge structures, one for each driving direction, of the total
width 27.93 m and length 833 m. The structure runs continuously over 20 spans with the main span of 80 m over the
Mura, without piers in water, and with typical spans of 40 m in both inundation areas.
The route axis of the structure is in the ground plan radius 2400 m, the longitudinal alignment in the convex
curvature 40.000 m with symmetric tangents 1.3%. The structure cross fall is constant 2.5%, the walkways
are inclined inwards with the inclination 4% (fig. 2).
Fig. 2 Elevation
The static system is a continuous girder with a prestressed tie in the main span, with theoretical spans as follows:
30.0 + 10 x 40.0 + 50.0 + 80.0 + 50.0 + 4 x 40.0 + 34.0+26.0 = 830.0 m
The bridge has no piers in the river, while in the inundation area it has 38 piers in total (19x2) with the height
from 7.0 to 8.5 m and an oval cross-section. Such a shape is hydraulically convenient for outflow of
inundation or periodic waters in old riverbeds.
The foundations are deep on concrete piles of 120 cm diameter and 15 to 20 m long. For each typical pier 4
reinforced concrete piles are used. Each of the two main – river bank piers with fixed bearings for
longitudinal forces are founded on 10 piles of 120 cm diameter.
Fig. 7 Section through the perforation in the bottom slab for the cable outlet
5 Structural analysis
The bridge over the Mura is a unique structure with new structural solutions. In the literature there are only some cases
known of using the prestressed ties on bridge structures, yet they are not directly comparable with the execution of the
Mura bridge. We had no experience of our own available neither the foreign ones for the comparison and guidance at
the design, design analysis and the construction itself. Therefore, an exact analysis of all phases during the construction
and of all influences for the structure exploitation was essential, while the work was pretentious and extensive.
The structure has been analysed as a space prestressed frame structure. In the analysis and structural design DIN norms
and partly Eurocode Nr. 2 were considered, as well as the seismic load in accordance with Eurocode Nr. 8 Part 2 –
Bridges. For steel elements Eurocode Nr. 3 was taken into account.
6 Construction
The bridge construction began in November 2000 with earth works and foundations and was completed in
October 2003 with the final works. The superstructure was constructed by the method of incremental
launching, the left and the right bridge structure consist each of 43 concrete segments of average length 20
m. In the spans 50 m + 80 m + 50 m temporary supports were additionally used, so that for the loads in the
construction stage the typical span of 40 m was decisive.
The structure of the length over 800 m and in such a pretentious geometry was launched by only
one set of hydraulic equipment Eberspeacher AH123. As the anticipated forces were at the limit of
the launching possibilities, special attention was paid to this problem. The left and the right bridge
have 16.000 tons each. At the active abutment the hydraulics pushed upwards with the inclination
of approximately 1%, at the end abutment the elevation has the direction 1.3% downwards. The
intermediate temporary bearings had different inclinations at each pier, in accordance with the
vertical curvature R = 40.000 m. Therefore the conditions and the resistance force at each pier were
different. On the basis of the Designer’s detail analyses the Contractor decided to use only one set
of hydraulic launching equipment of capacity V = 15700 kN and H = 6080 kN. For the last pushing,
when due to the lack of the vertical reaction the friction mode of moving is not sufficient any more,
the Contractor prepared a pulling device, that can pull the structure additionally with a steel frame
and the equipment for tendon prestressing.
Concrete Structures : the Challenge of Creativity
Fig. 8 Force diagram for incremental launching (no of segment / force kN)
Due to the extraordinary length and mass as well as due to pretentious geometry we followed precisely the
forces during launching, registered and analysed them. The statements were very interesting. The pushing
force namely did not grow linearly with the length and mass increase, as it could be expected. First a great
friction influence was noticed in the formwork casting yard, due to various causes (different slip slabs,
smaller specific pressure, influence of concreting and formwork) much bigger than on temporary sliding
bearings. Therefore at the beginning of launching greater pushing forces are necessary than the theoretical
ones. When a large number of segments is completed, e.c. more than ten, the share of the segment being still
on the launching rail in the casting yard, becomes smaller and later, after more than 20 segments, negligible.
Even more interesting are the measurements at larger lengths, when the superstructure elastic deformation
occurs, which is noticeable only at lengths greater than 500 m and depends on the force size, friction
coefficients and stiffness characteristics of the superstructure and piers. The top of the pier elastically follows
the movement of the superstructure, up to the movement causing a reaction in the pier that is equal to the
friction force or initial friction. As the stiffness of individual piers is different as a rule (pier height, concrete
and reinforcement characteristics, foundation conditions etc.) moving the very long elastic superstructure
over a number of piers is a very complex dynamic system. This is partly evident also from the pushing forces
measurements at the beginning and in the middle of each segment, which is shown for the right structure in
the diagram in Fig. 8.
Fig. 9: Crossing the river with the first structure - Fig. 10: The river, inundation zone and bridge
November 2001 during construction – May 2002
Symposium 2004 – April 26-28 – Avignon, France
Fig. 11: Tendons under the structure Fig. 12: The main span of the bridge
7 Conclusion
• By using the prestressed tie in one span the entire bridge - in spite of very different spans -
could be executed with a concrete structure of a constant height;
• Therefore the technology of incremental launching in the total length of the structure could
be used with the help of only one casting yard and one set of launching equipment;
• In this way an economic and durable structure of good quality was obtained;
• Consecutively new details of the deviator under the structure, the transition of tendons
through the bottom slab had to be solved and many structural analyses to be made;
• The measurements during the construction, the loading test and the successful use of the
structure proved the correctness of presumptions in the design.