Wa0009
Wa0009
Wa0009
TRAINING PROGRAMME
AT
BY
2014/1/49618EC
CIVIL ENGINEERING
DECEMBER, 2018
ABSTRACT
This report is done to fulfill a partial requirement for the award of B.Eng. in Civil Engineering at
Federal University of Tech. Minna. This report outlines my work experience as an intern with
Nahman Construction Company Ltd, a civil engineering construction firm in based in Lagos,
Nigeria, with branches in Abuja and all over the country. This report describes the activities of
the civil engineer in building construction and the progressive phases of the Building project at
Nahman Construction Company. The project phases, responsibilities, and tasks that were typical
of the project are detailed through the descriptions in this report.
Insights of my work experience and the role that my education at Federal University of Technology
Minna played is discussed in the conclusion part of this report.
ii
ACKNOWLEDGEMENT
The internship opportunity I had with Nahman Construction Company was a great chance of
learning and professional development. Therefore, I consider myself as very lucky individual as I
was provided with an opportunity to be part of it. I am also grateful for having the chance of
meeting so many wonderful people and professionals who led me through this internship period.
Bearing in mind previous I am using this opportunity to express my deepest gratitude and special
thanks to the Area Manager, Mr. Elie Antonio’s who in spite of being extraordinarily busy with
his duties, took time out to hear, guide and keep me on correct path. I express my deepest thanks
to my Industrial Supervisor, Engr Humphrey, the Project engineer and Engr. P.B Umoh, the
principal structural engineer of the civic center building for their careful and precious guidance
which were extremely valuable for my study both theoretically and practically, I am forever
indebted to them.
I perceive this opportunity as a big milestone in my career development, I will strive to use the
gained skills and knowledge in the best possible way, and I will continue to work on their
improvement, in order to attain desired objectives.
iii
Table of Contents
TITLE PAGE ..................................................................................................................................................... i
ABSTRACT....................................................................................................................................................... i
ACKNOWLEDGEMENT ................................................................................................................................... ii
LIST OF FIGURES: .......................................................................................................................................... iv
LIST OF TABLES: ............................................................................................................................................. v
CHAPTER ONE: INTRODUCTION ................................................................................................................... 1
1.1 Brief history of SIWES programme ..................................................................................................... 1
1.2 AIMS AND OBJECTIVES OF SIWES. ...................................................................................................... 1
1.2 LITERATURE REVIEW .................................................................................................................... 1
CHAPTER TWO: DISCRIPTION OF PLACE OF ATTACHMENT ....................................................................... 3
2.1 Brief history and description of establishment................................................................................... 3
2.2 Organizational structure: .................................................................................................................... 4
2.3 Departments and Units: ...................................................................................................................... 5
2.4 Brief description of project: ................................................................................................................ 5
CHAPTER THREE: CONSTRUCTION PROCESS ............................................................................................... 7
3.1 Introduction. ....................................................................................................................................... 7
3.2. Setting Out and Excavation: ............................................................................................................... 7
3.3 Foundation Concreting: ...................................................................................................................... 8
3.4. Casting of oversite concrete: ............................................................................................................. 9
3.5 Shuttering and Casting of Columns................................................................................................... 10
3.6 Casting of beams and floor ............................................................................................................... 11
3.7 Laying of blockwork .......................................................................................................................... 16
3.9 Plastering .......................................................................................................................................... 17
CHAPTER THREE: STRUCTURAL DESIGN .................................................................................................... 18
4.1 Overview ........................................................................................................................................... 18
4.2 Exit Staircase ..................................................................................................................................... 18
4.3 Retaining Walls: ................................................................................................................................ 24
4.4 Staircase stringer beam: ................................................................................................................... 27
4.5 Roof Trusses: ..................................................................................................................................... 31
CHAPTER FIVE: CONCLUSION AND RECOMMENDATION .......................................................................... 38
5.1 Conclusion: ........................................................................................................................................ 38
5.2 Recommendation:............................................................................................................................. 39
iv
LIST OF FIGURES:
LIST OF TABLES:
• Provide an avenue for students in the Nigerian Universities to acquire industrial skills and
experience in their course of study
• Prepare students for work situations they likely to meet after graduation.
• Expose students to work methods and techniques on handling equipment and machinery
that may not be available in the universities.
• Make the transition from the university to the world of workers easier and thus enhance
students’ contact for later job placement.
• Enlist and strengthen employers’ involvement in the entire educational process of
preparing university graduates for employment in industries.
Nigeria. The design of the programme is laid on the student’s area of study as applicable to the
society at large. Students will therefore use this opportunity to learn and apply the various
theoretical knowledge they acquire during their study in their institute within programme an
independent commission under the guidance of the industrial training fund is established by the
Nigerian government to look on the student’s training programme during their various attachment.
3
Founded in 1969 by Joseph Nahman, the company initially operated as a building and civil
engineering contractor concentrating on private residential construction projects and pioneering
developments in financing. With projects growing progressively larger and more complex the
company assembled a group of expert construction professionals-both Nigerian and expatriate-
with diverse construction experience. As the company expanded internally, it expanded externally
too-undertaking projects not only in Lagos but across Nigeria. Nahman Construction company
maintains its company headquarters in Lagos and supports full service offices in Abuja, Ogun
State, and Kaduna.
Today led by Nabil Nahman and Nagib António’s, the company operates as a diversified
construction organization offering services in general contracting construction management,
project development, and project management. Nahman construction is involved in a wide variety
of commercial building types ranging from corporate office, facilities and healthcare projects, to
industrial developments, and mechanical and electrical projects. They also specialize in a variety
of civil engineering works, from roads and dredging, to waste water drainage and culverts.
Nahman Construction continues to perpetuate and reinforce the principle and philosophy of its
founder and is committed to superior workmanship and performance. While also looking forward
to the challenges and accomplishments to come as it strives to become and remain the best in the
industry.
4
Managing
director
Area
Manager
Project
Manager
Quantity Project
surveyors Engineers Accountants
Site
Engineers
Store
Supervisors Foremen Headmen
Keepers
1) Management:
i) To make enquiry about the essential certificates and reports and justify them correctly
ii) Make rough estimate report for the projects
iii) Handle all legal aspects of the projects.
iv) Preparing schedule of work for the projects.
2) Accounts:
i) Controls the flow of money and prepares rough estimate.
ii) Receives budget from managing department and sends for approval.
iii) Pay bills of sub-contractors according to the terms and conditions of the company.
3) Quantity Surveying:
i) Preparing tenders and bill of quantities
ii) Carry-out cost valuation on projects
iii) Submits sub-contractor’s bills to account for payments.
4) Project Engineers:
i) Manages and oversee activities on site
ii) Prepare estimates on quantities of materials required
iii) Schedule preparation
iv) Recourse management.
The building is a reinforced concrete framed structure with columns and beams spaced at intervals
there’s a lift core wall towards the entrance, and ramps from the ground floor to the third floor,
there are retaining walls around the basement. The building is founded on pad bases.
A building is set out in order to clearly define the outline of the excavation and the center line of
the walls so that all construction works can be carried out according to the plan. There are basically
two method of setting out, Line-Line and Centerline. The centerline method is generally preferred
and was adopted for this project.
The position and orientation of the structure is generally described in the architect's drawing,
dimensions and references on plan will determine the positioning of the building and in particular
its foundation. These include overall length and width, distances to road center-lines and to other
structures, internal structural measurements, approaches and rights of way and so on.
The controlling points of the structure can then be marked so that the construction team is able to
easily identify them. This usually consists of marking the buildings corners, horizontal and vertical
positions, using stakes(pegs) profile boards with lines, drill holes cut and fill notations or other
method.
(a) Temporary Bench Mark (TBM): The TBM is a fixed point on the site to which all levels are
related. On site it should relate to any permanent fixture such as manhole cover or firmly driven
post.
(b) Baseline: Typically, the first layout task is establishing a baseline to which all the setting out
can be related. The baseline is a straight reference line in respect to which the buildings corners
8
are located on the ground. It often coincides with the building line, which is the boundary of the
area or the outer boundary of a road or curb.
(c) Horizontal Controls: These are the points that have known co-ordinates with respect to a
specific point, to which other points such as layout corners can be located.
(d) Vertical Control: These enables design points to be positioned at their correct levels, the
vertical control points are referenced to the TBM
Framed buildings are usually related to grid, often set out from a baseline. The intersection of the
grid’s lines marks the Centre points for isolated or pad foundations.
The layout of the grid is established using a theodolite and the grid intersections marked using
pegs. Once the grid has been set out, offset pegs or profile boards can be fixed clear of any
subsequent excavation.
3.2.2 Excavation.
After successfully setting out the building the next step is to excavate the soil, for small building
excavations are carried out by means of spades, diggers, shovels etc. In case of large buildings and
deep excavation mechanical earth cutting equipment such as excavators are used. For this very
project subsurface investigation showed the topsoil to be very poor, as a result the foundation depth
was about 2.5m below natural ground level and as much as 4.5m on the basement segment. due to
the nature of the soil been loosed, planking and strutting was used to support the sides from falling.
For important works mixing should be done in a mixer, concrete should be laid (not thrown) in
layers not exceeding 15cm and well compacted.
For Reinforced concrete Pad footing, a levelling course of lean concrete of 75mm is laid in order
to have an even soil free surface for placing the footing reinforcement and the column starter
bars. After which the masonry work over the bed can be started after 3 days of laying the
9
After the masonry wall have been erected to the plinth level, the portions to be floored are
compacted with the laterite to a required level, after which solid hardcore base are placed on the
compacted lateritic soil and then tamped to consolidate into a firm surface well even up. A cement-
sand mortar is applied on the surface to stop the oversite concrete from percolating into the voids.
A damp-proof membrane is applied over the hardcore surface followed by a light reinforcement
connected to the plinth beams. Engineering services drawings are consulted in case of any
specification for installation of pipes or conduits. The final step is to restrict the corners with
formwork and set the gauge for casting. The oversite concrete is mostly constructed with M15
concrete of mix ratio 1:3:6.
10
After tying reinforcement in place, the column formwork is done by marine plywood sheets and it
internal surface covered with form oil, the formwork is fixed to the kickers and then jacks and
props are used to brace against twisting, verticality of the column is also checked using a plumb
bulb prior to casting, after shuttering concrete is poured into the formwork and a Poker vibrator is
used to compact very well to avoid the risk of honeycombing.
Formwork is left four 24 hours before striking down and consequently, curing is done within a
period of 7 days by wrapping with moist polythene bags.
11
Falsework is any temporary structure used to support a permanent structure while it is not self-
supporting either in new construction or refurbishment. It could be made-of Steel (Scaffolds) or
timber.
The falsework consists of props, horizontal and vertical bracing and caps, the installation is done
along insertion axis of beams by taking measurement from the 1000m level to the level of the
bottom of the beam, this is the difference between the top level of the slab and the depth of the
beam. After the formwork for the sides of the beams might have been completed, props are then
inserted to carry the slabs.
12
All falsework should be designed for the loads it is required to support, adequate bracing should
be provided, consequently a competent designated observer should be appointed to continuously
monitor the falsework assembly during loading and be provided with an appropriate
communication system to alert others in case of an emergency.
Formwork is temporary or permanent moulds into which concrete or similar materials are poured.
In the context of concrete construction, the falsework supports the shuttering moulds. Formwork
can generally be made out of steel, timber or plastics.
After all the falsework might have been erected to required level (particularly for the beams), the
beam formwork consist of the bottom board and the side boards, the bottom board is nailed to the
stake first, then the internal side boards followed by the formwork for the slab, the external
sideboards are placed only after the reinforcement must have been completed.
It is common to check insertion point of beams using a plumb bulb in-order to minimize errors
from non-wholly vertical columns, lines and plumb are also used in ensuring correct alignments.
13
All formwork should be strong, and closely spaced in order to increase the safety in withstanding
the imposed loads.
Bar bending schedules are prepared from the structural drawings and then submitted to the Iron
bender, The reinforcement for the beam is tied first, after checking various bar positions sufficient
lapping lengths, the beams are lowered into the formwork and the bottom bars for the slab are
placed first , after placing the bottom bars (main and distribution), Chairs or spacers are tied in
positions in order to create sufficient gab between the top and bottom bars, the top bars are then
placed.
Prior to reinforcement placement concrete biscuit should be attached in order to maintain adequate
cover for the structural elements. All starter bars are also tied in place prior to casting.
Before casting a thorough check should be carried out on the structural elements rebars, such as
lapping length, development length, spacing of stirrups and adequate concrete cover
14
3.6.4 Concreting.
Prior to casting, the top level of the slab is determined and marked using a dumpy level and a staff,
this ensures that there’s sufficient cover and also keeps the slab within the specified thickness, also
electrical and plumbing pipes must have been installed, conduits and ducts for floor drains. Self-
loader concrete mixer was used in transporting concrete, wheel barrows used in collecting and
subsequently poured into the formwork, a poker vibrator is used in compacting the concrete, the
concrete grade for the floor is 25N/mm2, and a mix ratio of 1:1.5:3 was used to achieve this.
Slump test and preparation of concrete cubes for the compressive strength is performed at regular
intervals to keep the concrete within specification. Cubes are cured by method of immersion and
are taken for tests on 7th day and 28th day after casting.
The concrete is been cured through a period of 7 days, curing is done by water ponding and
covering the surface with moist polythene bags.
15
The striking down of formwork depends on the type of cement, grade of cement, dimension of the
section and temperature of the concrete. Minimum striking time for side formwork of beams, soffit
formwork to slabs for concrete made with Portland cement or sulphate-resisting Portland cement.
3.9 Plastering
Cement to sand 1:4 mixture is used for plastering work. Water appropriately used for proper
mixture and usability. Plumb bob and spirit level and feather edges are used in ensuring a smooth
finishing. After few more days the wall preparation (cleaning) and maintenance was done.
During my course of training I had the opportunity to meet the principal structural engineer of the
project who took his time to lecture me on structural design, and gave me the rear opportunity of
carrying out calculations on the project external works which are contained in this chapter.
The exit staircase is been supported by a beam on columns shooting out from a cantilevered
retaining wall as shown in the figure above. The staircase was designed for an imposed loading of
3.5KN/m2. With grade 25-410 concrete.
Staircases are designed as one-way spanning slabs; the dead load is increased slightly to account
for the incline waste of the slab.
19
Loading:
√3002 +1502
Slope factor = = 1.12
300
6
𝑀 8.42×10
𝐾= 2
= 2 = 0.016
𝐹𝑐𝑢 𝑏𝑑 25×1000×144
𝑘
La = 0 ⋅ 5 + √0.25 − 0⋅9 ≤ 0.95 ; La= 0.95
20
𝑀 8.42×106
𝐴𝑠 = = = 158.02mm2 158.02mm2
0⋅95𝐹𝑦 𝐿𝑎 𝑑 0.95×410×(0.95×144)
Second
Flight
Effective span = 1.5 + 3.6/2 = 3.3m
𝑊𝐿2 17.72×3.32
Moment, 𝑀 = = = 24.12KN/m2 24.12KN/m2
8 8
k
La = 0 ⋅ 5 + √0.25 − 0⋅9 ≤ 0.95 ; La= 0.93
𝑀 24.12×106
𝐴𝑠 = = = 455.02mm2 455.02mm2
0⋅95𝐹𝑦 𝐿𝑎 𝑑 0.95×410×(0.93×144)
219N/mm2
2 𝐴𝑆𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 2 455.02
𝐹𝑠 = 𝐹𝑦 = 3 × 410 × = 219N/mm2
3 𝐴𝑆𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑 565
(477−𝐹𝑠 )
M.F = 0⋅ 55 + 𝑀
≤ 2.0 = 1.55
120(0.9+ )
𝐹𝑐𝑢 𝑏𝑑2 1.55
𝑆𝑝𝑎𝑛 3300
dmin = = = 106.55 < 144 𝑜. 𝑘
𝑏𝑎𝑠𝑖𝑐 𝑟𝑎𝑡𝑖𝑜 × 𝑀.𝐹 20×1.55
k
La = 0 ⋅ 5 + √0.25 − 0⋅9 ≤ 0.95 ; La= 0.93
22
𝑀 66.5.12×106
𝐴𝑠 = = = 448.02mm2
0⋅95𝐹𝑦 𝐿𝑎 𝑑 0.95×410×(0.93×407)
𝑤𝐿 90×103
v. = 2 = = 1.12N/mm2 1.12N/mm2
200×407
100𝐴𝑠 100×603
= = 0.74
𝑏𝑑 200×407
Vc = 0.40N/mm2 =0.40N/mm2
𝐴𝑠𝑣 (𝑣−𝑣𝑐 )𝑏 = (1.12−0.4)200
= = 0.354N/mm2
𝑠𝑣 0⋅95𝑓 0.95×410
DEFLECTION:
2 𝐴𝑆𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 2 445.02
𝐹𝑠 = 𝐹𝑦 = 3 × 410 × = 206.34N/mm2
3 𝐴𝑆𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑 602
(477−𝐹𝑠 )
M.F = 0⋅ 55 + 𝑀
≤ 2.0 = 1.65 dmin = 1.65
120(0.9+ )
𝐹𝑐𝑢 𝑏𝑑2
𝑆𝑝𝑎𝑛 3600
= = 109.09 < 407 𝑜. 𝑘
𝑏𝑎𝑠𝑖𝑐 𝑟𝑎𝑡𝑖𝑜 × 𝑀.𝐹 20×1.65
Deflection is satisfied.
SHEET PROJECT: H.F.C.C CIVIC CENTRE BUILDING PROJECT, LIFECAMP1- Calcs by:
NO. ABUJA. Victor O.
1 of 3 Checked:
PART OF STRUCTURE: Cantilevered Retaining Wall Engr. Umoh
Proportioning of section
Overturning Moment:
14.37×2.2 3.63×2.2
O.M = + = 14.53KN 14.53KN
3 2
Vertical Loads:
1
Stem: 2 (0.225 + 0.2) × 24 = 9.70KN
Base: 1.5 x 0.3 x 24 = 10.80KN
Earth: 0.8 x 2.2 x 18 = 31.68KN
Total = 52.18KN
52.18KN
Restraining Moment: 9.70x0.56 + 10.80x0.75 + 31.68x1.1 = 48. 38KN. 48.38KN.m
SHEET PROJECT: H.F.C.C CIVIC CENTRE BUILDING PROJECT, LIFECAMP1- Calcs by:
NO. ABUJA. Victor O.
2 of 3 Checked:
PART OF STRUCTURE: Cantilevered Retaining Wall Engr. Umoh
Bending Reinforcement:
(a) Wall:
𝑀 16.60×106
𝐴𝑠 = = = 265.45mm2/m 265.45mm2
0⋅95𝐹𝑦 𝐿𝑎 𝑑 0.95×410×(0.93×169)
k
La = 0 ⋅ 5 + √0.25 − 0⋅9 ≤ 0.95 ; La= 0.95
𝑀 18.27×106
𝐴𝑠 = = = 192.87mm2/m
192.87mm2/m
0⋅95𝐹𝑦 𝐿𝑎 𝑑 0.95×410×(0.93×244)
Provide nominal reinforcement in the Near face of the wall to avoid cracking.
SHEET PROJECT: H.F.C.C CIVIC CENTRE BUILDING PROJECT, LIFECAMP1- Calcs by:
NO. ABUJA. Victor O.
1 of 2 Checked:
PART OF STRUCTURE: Stringer Beam Engr. Umoh
Loading:
√3002 +1502
Slope factor = = 1.12
300 14.51KN/m2
Dead load Gk = (3.6 + 1.5) x 1.12 + 1.8 = 8.62KN/m2 Impose
Load Qk = = 3.5KN/m2
Total =20.22KN/m2
𝑊𝐿2 20.22.×7.52
Moment, 𝑀 = = = 142.17KN.m
8 8
effective depth, d = 425-25 20/2-10 = 380mm
6
M 142.17×10
K= 2
= 2 = 0.0394
Fcu bd 25×1000×380
29
SHEET PROJECT: H.F.C.C CIVIC CENTRE BUILDING PROJECT, LIFECAMP1- Calcs by:
NO. ABUJA. Victor O.
2 of 2 Checked:
PART OF STRUCTURE: Stringer beam Engr. Umoh
k
La = 0 ⋅ 5 + √0.25 − 0⋅9 ≤ 0.95 ; La= 0.95
𝑀 142.17×106
𝐴𝑠 = = = 944.03mm2 944.03mm2
0⋅95𝐹𝑦 𝐿𝑎 𝑑 0.95×410×(0.93×407)
𝑤𝐿 20.22×7.5
SHEAR: 𝑉𝑀𝑎𝑥 = = = 75.83KN
2 2
𝑤𝐿 75.83×103
v. = 2 = = 0.88N/mm2
225×380
100𝐴𝑠 100×1545
= = 1.80
𝑏𝑑 225×407
Vc = 0.70N/mm2
SHEET PROJECT: H.F.C.C CIVIC CENTRE BUILDING PROJECT, LIFECAMP1- Calcs by:
NO. ABUJA. Victor O.
1 of 4 Checked:
PART OF STRUCTURE: ROOF TRUSSES Engr. Umoh
Span = 11250mm
Spacing of Truss assembly = 3750mm
Height = 4500mm Fy = 275N/mm2
Spacing of purlins = 1200mm (along slope)
𝑤𝐿 10.125×3.7502 10.125KN
𝑧𝑝 = = = 21.09cm3
1800 1800
𝐿 3750
𝐷= = = 83.33cm
45 45
𝐿 3750
𝐵= = = 31.25cm
120 120
Analyzing the roof truss for the following combinations shown gives the result shown in the truss below
SHEET PROJECT: H.F.C.C CIVIC CENTRE BUILDING PROJECT, LIFECAMP1- Calcs by:
NO. ABUJA. Victor O.
1 of 4 Checked:
PART OF STRUCTURE: ROOF TRUSSES Engr. Umoh
Bottom Chord:
Properties:
𝛾𝑥𝑥 = 2.89𝑚𝑚 𝛾𝑦𝑦 = 2.89𝑚𝑚 A = 8.73cm2
Tension capacity:
Pt = Aepy = 8.73 x 100 x 275 = 240.05KN > 126.82KN 240.05KN
>126.82KN
Compression resistance: O.K
1538
𝜆𝑚 = = 53.21
11.7
Pc = 63N/mm2
Compressive resistance Pc =63 x 5.82 = 55KN > 25.63KN O.K. 55KN >
Hence section is adequate. 25.63KN
O.K.
Top Chord:
Properties:
𝛾𝑥𝑥 = 2.89𝑚𝑚 𝛾𝑦𝑦 = 2.89𝑚𝑚 A = 8.73cm2 240.05KN
Tension capacity: >126.82KN
Pt = Aepy = 8.73 x 100 x 275 = 240.05KN > 126.82KN O.K
35
SHEET PROJECT: H.F.C.C CIVIC CENTRE BUILDING PROJECT, LIFECAMP1- Calcs by:
NO. ABUJA. Victor O.
1 of 4 Checked:
PART OF STRUCTURE: ROOF TRUSSES Engr. Umoh
Compression resistance:
1200
𝜆𝑚 = = 102.56N/mm2
11.7
Pc = 163N/mm2
Compressive resistance Pc =162 x 5.82 = 139.81KN > 105.63KN O.K.
139.81KN
Hence section is adequate. >105.63KN
O.K
Internal Members:
Properties:
𝛾𝑥𝑥 = 23.0𝑚𝑚 𝛾𝑦𝑦 = 11. 𝑚𝑚 A = 5.82cm2
Tension capacity: 160.05KN
Pt = Aepy = 5.82 x 100 x 275 = 160.05KN > 76.48KN >76.48KN
O.K
Compression resistance:
1200
𝜆𝑚 = = 102.56N/mm2
11.7
SHEET PROJECT: H.F.C.C CIVIC CENTRE BUILDING PROJECT, LIFECAMP1- Calcs by:
NO. ABUJA. Victor O.
1 of 4 Checked:
PART OF STRUCTURE: ROOF TRUSSES Engr. Umoh
Base Plate:
P = 60KN
60 ×103
Area of plate = = 202.55mm2
275
The educational experience I got for Dept of Civil engineering Federal University of Tech. Minna
served as a template for my professional growth, which also helped me to be able to contribute to
the success of the project. Overall the (SIWES) program provided me with a solid foundation in
the construction industry. I express my optimism that the future undergraduates coming for the
internship programme will find it even more interesting and beneficial to their future careers.
39
5.2 Recommendation:
1. Period of attachment should be increased in order to enhance the experience and training
of students.
2. Students should be advised on deciding a place of attachment related to field of study.
3. Number of visits conducted by the institution supervisors and ITF officials should be
increased.