Installation of Cranes in PS-17
Installation of Cranes in PS-17
Installation of Cranes in PS-17
CLIENT : ASHGHAL
REVISION : 00
PETROSERV LTD
P.O.BOX: 7098
DOHA-QATAR
729/2-GEN-DOC-0111
METHOD STATEMENT FOR
PETROSERV LTD Revision 0
INSTALLATION OF OVERHEAD
DOHA - QATAR Date 09.08.2012
CRANE (PS-17)
Page 2 of 27
INDEX
7.0 Preparations 9
16. Attachments: 18
1. PURPOSE:
The Purpose of this Method Statement is to describe the installation of
single girder EOT (electrically operated overhead) crane and electrically
operated monorail crane in pumping stations PS-17 and the sequence of
activities involved
2. SCOPE OF WORK
This document applies to manage efficiently and control the supply and install
of single girder EOT (electrically operated overhead) crane and electrically
operated monorail crane and accessories s in the pumping station on going
to attain the zero tolerance accident.
4. EQUIPMENTS:
1. Jack hammer
2. Hand tools.
3. Crane capacity 20-50 ton.
4. Chain Block (5 ton)
5. Grinding and drilling machine.
729/2-GEN-DOC-0111
METHOD STATEMENT FOR
PETROSERV LTD Revision 0
INSTALLATION OF OVERHEAD
DOHA - QATAR Date 09.08.2012
CRANE (PS-17)
Page 5 of 27
5. RESPONSIBILITY
5.5 SAFETY OFFICER: -(these responsibilities are included but not limited
to):
5.5.6 Ensures first aid and emergency procedures for the site are
established and maintained.
5.5.7 Coordinates with the client for any safety related requirements at site.
5.5.8 Arranges safety induction program for the site personnel as required.
He ensures that daily toolbox meetings are conducted by Site
foremen/Supervisor.
1. QA/QC Engineer along with project engineer will monitor that all
components are installed as per contract specifications and
approved submittals.
d) Before entering the manhole ensure that the cover has been
removed to give natural ventilation for minimum of 5 minutes.
e) Before enter the drywell and wet well proper ventilation will be
used.
f) Test for toxic and flammable gases, and oxygen deficiency, using
approved detector. If toxic and flammable gases or oxygen
deficiency is detected do not enter the manhole.
729/2-GEN-DOC-0111
METHOD STATEMENT FOR
PETROSERV LTD Revision 0
INSTALLATION OF OVERHEAD
DOHA - QATAR Date 09.08.2012
CRANE (PS-17)
Page 9 of 27
g) Before the any lifting activates the area is cordon of with safety
ribbons.
l) Refer H.S.E plan clause and there sub classes 16, 17, 18, 19, 20, 21,
22, 23, 25, 26, 27, 33, 34, 36, 39, 40. Document No.729/2- GEN-
DOC-0019).
7. PREPARATIONS:
A. DOCUMENTS
A. Entry permits from Ashghal to enter pumping station.
B. Confined space permit.
C. Lock out/tag out (LOTO).
D. Permit of work.
729/2-GEN-DOC-0111
METHOD STATEMENT FOR
PETROSERV LTD Revision 0
INSTALLATION OF OVERHEAD
DOHA - QATAR Date 09.08.2012
CRANE (PS-17)
Page 10 of 27
1. Mechanical Screen.
2. Penstock.
3. EOT Cranes.
4. Ductile Iron Pipes & Fitting.
5. Valves.
6. Dry Submersible Main Pumps.
7. Sump and Transfer Pump
8. Odour Control Unit.
9. High Pressure and Potable Pump
10. Air conditioning & Ventilation.
11. Instrumentation & control system.
12. Electrical items.
13. Civil work.
9. (A) PRE-REQUIRMENTS:
1. Ensure that approved materials are available to carry out the work.
2. Cranes are transported from stores according to good engineering
practice and physical verification.
3. Prior to commencement of work, areas and access will be inspected to
Confirm that safety precautions ensured.
4. All relative documents (approved shop drawing and approved method
statement) will be checked by site engineer prior to commencement of
work.
729/2-GEN-DOC-0111
METHOD STATEMENT FOR
PETROSERV LTD Revision 0
INSTALLATION OF OVERHEAD
DOHA - QATAR Date 09.08.2012
CRANE (PS-17)
Page 11 of 27
5. Since this overhead crane is inside the enclosed building. All the
components of the EOT crane will be shifted inside the building piece by
piece by means of a mobile crane/fork lift or hand palette trolley and will
be erected by a manual chain block piece by piece.
6. Any temporary attachments should be made secure or removed prior to
lift.
7. All lifting eyes to be inspected.
8. Survey of road access to the site for mobilization of mobile cranes, trailers,
etc…
9. All lifting gear shall be certified and certificates shall be reviewed and
approved.
10. Arrangement and checking of lifting gear for the lift.
11. Inspection of the area and positioning of the crane (for shifting the crane
components inside the building)
12. Arrangements for manual lift of the crane inside the building.
13. Arrangements of suitable access / scaffolding for erection.
14. Tool box talk will be conducted with all the people involved in the
operation and discuss about the past lifts observations, assign individual
responsibilities before starting the job.
Ensure that the vehicle parked in a safe area and parking brake is
applied.
729/2-GEN-DOC-0111
METHOD STATEMENT FOR
PETROSERV LTD Revision 0
INSTALLATION OF OVERHEAD
DOHA - QATAR Date 09.08.2012
CRANE (PS-17)
Page 12 of 27
6. ITP will be checked for storage and handling, refer the attached ITP
1. All the riggers, helpers and supervisors will be explained about the safety
aspects and requirements on the project.
2. All the people involved in the lifting operation will be briefed on the
requirement of the job.
3. The area near to the lift will be inspected for access / positioning of the
crane and make sure it is as per the requirement before getting the
equipments on site.
4. Mark the appropriate location of the crane on the site.
5. All the work / lift supervision will be managed by a lifting in charge on site,
who will be responsible for entire operation.
6. Lift will be communicated completely by means of hand signals with crane
operator. The complete lift will be signalled by lifting in-charge during the
complete operation.
7. Cordon of the area and remove all the non-essential persons from the area.
729/2-GEN-DOC-0111
METHOD STATEMENT FOR
PETROSERV LTD Revision 0
INSTALLATION OF OVERHEAD
DOHA - QATAR Date 09.08.2012
CRANE (PS-17)
Page 13 of 27
50 x 30mm (with primer) will be done by tack welding onto the travel beam /
girder by help of welding machine.
During fixing of rails, 3mm tolerance will be kept for expansion of rail if any,
between the rails.
1 Slowly lift the beam girder and push inside the building half way in and rest on
the frame with rollers at one end.
2. Hold the girder at one end with crane and push the girder slowly inside the
building. The girder will be manually guided inside to required position.
3. Similarly take all the components one by one inside the building.
729/2-GEN-DOC-0111
METHOD STATEMENT FOR
PETROSERV LTD Revision 0
INSTALLATION OF OVERHEAD
DOHA - QATAR Date 09.08.2012
CRANE (PS-17)
Page 14 of 27
1. End carriages are lifted up with the same Electric Hoist attached on the roof
2. Both End carriages are tied on the rail using load binders.
3. Electric Hoist is attached to the hooking point provided on the Drop Beam
5. Girders are lifted up bit diagonal to the span in order to reach above the
end carriages.
6. When Girder reach above the End carriage, the girder will be loosening
down to rest on the carriage, bolts are fastened up to 35kN and slings are
released.
8. Load binders are removed from the end carriage after bolting the girders
and moved 1.5m from the lifting point to lift the Hoist Crab unit.
729/2-GEN-DOC-0111
METHOD STATEMENT FOR
PETROSERV LTD Revision 0
INSTALLATION OF OVERHEAD
DOHA - QATAR Date 09.08.2012
CRANE (PS-17)
Page 15 of 27
10. Crane girders will be pushed back after Hoist Unit reaching above the rail
level.
11. Hoist Unit to be loosens down to rest on the cross travel rails and slings are
released.
12. All the electrical components of the crane will be lifted up manually and will
be assembled later.
13. Proper scaffolding will be used for the erection throughout the operation.
1. Marking to be done.
2. Drill the hole for the fixation
3. Raise the monorail beam to the roof.
4. Using the packer plates and shims for level and alignment the beam.
5. With laser range meter keep the horizontal alignment and level as
mentioned in approved shop drawing.
6. Fix the monorail beam in the soffit of slab.
(2) Load Analysis:
Max weight of the Hoist component: 0.250 t
2 nos. x 3 t belt slings (4 m long) : 0.050 t
2 nos. x 2 t bow shackles : 0.008 t
Total : 0.308 t
Capacity of chain block used is : 1.0 t x1 no
729/2-GEN-DOC-0111
METHOD STATEMENT FOR
PETROSERV LTD Revision 0
INSTALLATION OF OVERHEAD
DOHA - QATAR Date 09.08.2012
CRANE (PS-17)
Page 16 of 27
3. Lower the load hook of manual chain block to the electric hoist level
5. The hoist is slowly lifted, once the hoist’s travel wheels are inside the
Once the installation is completed the entire assembly is to be tested with trail runs.
Testing and commissioning will be done by in co-ordination with consultant & client.
729/2-GEN-DOC-0111
METHOD STATEMENT FOR
PETROSERV LTD Revision 0
INSTALLATION OF OVERHEAD
DOHA - QATAR Date 09.08.2012
CRANE (PS-17)
Page 17 of 27
During the installation of cranes the safety procedure will be involved to do works in
safe manner like safety barricades confined space entry procedure, identifying and
controlling the safety hazards and monitoring the works.
This time our well trained working team will be involved with the proper safety
equipments (PPE).
Emergency plan (Section 40) covers all the potential emergencies as per Do.
No. : 729/2- GEN-DOC-0019
16. ATTACHMENTS: