Ccdc20edu 2k
Ccdc20edu 2k
Ccdc20edu 2k
20
2 0 0 8
The Canadian Construction Documents Committee (CCDC) is a national joint committee
responsible for the development, production and review of standard Canadian construction
contracts, forms and guides. Formed in 1974 the CCDC is made up of volunteer representatives
from:
*Committee policy and procedures are directed and approved by the four constituent national
organizations.
The Secretary
Canadian Construction Documents Committee
400 - 75 Albert Street
Ottawa, Ontario K1P 5E7
Tel: (613) 236-9455
Fax: (613) 236-9526
www.ccdc.org
CCDC guides are products of a consensus-building process aimed at balancing the interests of all
parties on the construction project. They reflect recommended industry practices. Readers are
cautioned that CCDC guides do not deal with any specific fact situation or circumstance. CCDC
guides do not constitute legal or other professional advice. The CCDC and its constituent member
organizations do not accept any responsibility or liability for loss or damage which may be
suffered as a result of the use and interpretation of these guides.
Must not be copied in whole or in part without the written permission of the CCDC.
Standard Construction Document CCDC 20 – 2008
TABLE OF CONTENTS
A GUIDE TO CCDC CONTRACT FORMS:
What is the CCDC
The Use of CCDC Contract Forms
CCDC Contract Forms
Adapting the CCDC Contracts
Administrative Procedures
Relationship to Division 1 – General Requirements of the Specifications
The Definitions
FURTHER REFERENCES
A GUIDE TO CCDC CONTRACT FORMS
__________
CCDC standard documents are products of a consensus-building process aimed at balancing the
interests of all parties involved in construction projects. They reflect recommended industry
practices.
Readers are cautioned that the guides do not deal with any specific fact, situation or
circumstance. CCDC guides do not constitute legal or other professional advice. The CCDC
and its constituent member organizations do not accept any responsibility or liability for loss or
damage which may be suffered as a result of their use or interpretation.
This guide is intended to assist Owners, Contractors and Consultants. While this guide does not
provide advice on every provision of CCDC 2 – 2008, many of which are self-explanatory, it
explains all key provisions. The guide will avoid restating the wording of general conditions and
listing what is obvious in the contract. Cross-references indicate key interrelationships within
the contracts. The discussion and annotations cannot be comprehensive, as it is simply not
possible to anticipate all circumstances.
CCDC 20 – 2008 1
Copyright
All CCDC documents are protected under copyright law. The use of any CCDC form or content
without the consent of the CCDC infringes on this copyright. A seal must be affixed to all
CCDC contract forms to ensure the integrity of the document. The seal emphasizes that the
CCDC document has not been altered. The absence of the seal constitutes an illegal use of a
CCDC contract form.
2 CCDC 20 – 2008
The CCDC contract forms:
• recognize the need to protect and preserve the interests and rights of both parties in a fair and
equitable manner;
• incorporate current standard practices and procedures used in the industry;
• clearly define the appropriate roles and obligations of the Owner, Contractor and Consultant;
• are intended for use in any jurisdiction within Canada;
• can be used for large or small projects and new construction or renovation work, in both the
private and public sectors; and
• are kept current in an evolving insurance market.
The CCDC contract forms are recognized for clarity and simplicity of language and are drafted
in a style intended to be easily understood by the parties, using terms and expressions familiar to
the industry.
Words such as "reasonable" and "promptly" are often used throughout CCDC 2 – 2008. They
are used to describe the manner in which one of the parties to the Contract must act in relation to
the other party with respect to a task to be performed or a decision to be made.
Determination of what is "reasonable" will depend on the nature, purpose and circumstances of
each case. The word is used when a party is required not to be unreasonable, not to be
unnecessarily adversarial in the decision required to be taken, not to act improperly in the context
of the action being addressed, and where some degree of flexibility is warranted.
The intent behind the word "prompt" and the expression "reasonable time" is to require the
parties not to delay in taking the required action thereby causing a delay in the performance of
the Work, or not to cause further deterioration, or an extension, of an unfortunate event or
situation. These are used in circumstances where imposing a specific time limit would be
impractical in cases where so much would depend on the context and the circumstances.
In the typical construction project, the Consultant is not a party to the Contract. The Consultant
has a separate agreement with the Owner. The CCDC contract forms are consistent with
standard forms for the Owner-Consultant agreements, e.g. RAIC 6 (architects) and ACEC 31
(engineers). A consistent set of terms is used and the responsibilities and obligations of the
various parties are carefully co-ordinated. It is important to confirm that the Consultant’s roles
and responsibilities in the Owner/Consultant agreement are compatible with those in CCDC
contract forms.
The CCDC contract forms are divided into three sections called:
• Agreement Between Owner and Contractor
• Definitions
• General Conditions
The Agreement contains blanks that must be filled-in by the parties in order to complete those
provisions which are unique to the particular Work and Project. The Agreement section of each
of the various CCDC contract forms is distinct to reflect its specific pricing method.
The Definitions establish a specific meaning for terms used repeatedly throughout the CCDC
contract forms. Defined terms are highlighted throughout the forms by capitalizing the first
letter and italicizing them.
CCDC 20 – 2008 3
The General Conditions of the Contract are the part of the Contract Documents that set forth the
rights and responsibilities of the parties and define their relationships. The General Conditions
include those provisions which, to the greatest extent possible, have a consistent application to
all CCDC contract forms as well as to any project on which they are used. With the introduction
of CCDC 41 – CCDC Insurance Requirements, the insurance provisions of the general
conditions (GC11) are easily updated to reflect current insurance market coverages. The same
follows for the mediation provisions of the general conditions (GC8.2) with the introduction of
CCDC 40 – RULES FOR MEDIATION AND ARBITRATION OF CONSTRUCTION
DISPUTES.
4 CCDC 20 – 2008
The CCDC appreciates that certain Owners or market sectors, as a matter of public policy, local
conditions or project-specific particulars, may with legitimacy seek to amend or customize a
CCDC contract form. The CCDC issues these precautions to the four concerns noted above:
1. The CCDC standard contract forms’ General Conditions, Definitions and Agreements are
interrelated. Before introducing any new or amended subject matter, it would be prudent
to review the forms thoroughly to ensure that the subject is not already addressed.
2. Experienced industry participants anticipate and conduct their business operations based
upon familiar document structures with clearly separated (but integrated) components.
Changing that order may introduce confusion and increase the costs of document
preparation, bidding and contracting.
3. A biased and inherently one-sided form of construction contract would likely deter most
contracting parties; reduce (if not eliminate) competition, especially from those who are
more experienced and qualified; change the balance of risk; increase costs; and be
difficult for any Consultant to administer fairly and professionally. Furthermore, such a
contract may not be upheld if tested in court.
4. In addition to those already noted above, altering the standard wording presents a variety
of risks chiefly because the CCDC contract forms have:
(a) compatibility with the standard wording, notes and responsibilities of such critically
interrelated industry documents as agreements between Clients (Owners) and
Architects or Engineers, construction subcontracts, and construction administration
forms;
(b) compatibility with standard wording, terms and forms of industry acknowledged
insurance policies and surety bonds; and, especially
(c) an accumulated history of use and interpretation by the courts.
In order to indicate how to complete some of the blanks provided in the Agreement section or if,
due to particular circumstances, it becomes necessary to adapt the text of a CCDC contract form
for a specific instance, the preferred method of effecting such adaptations is through the use of
Supplementary Conditions. The CCDC Bulletin 7 provides additional information on the use of
supplementary conditions with CCDC standard contract forms.
ADMINISTRATIVE PROCEDURES
Detailed administrative procedures established by the Owner or Consultant for the
administration of the Contract need not be included in Supplementary Conditions. Such
procedures are appropriately the subject of the administrative procedures sections of Master
Format1 Division 1 General Requirements of the Specifications.
1
Master Format (Master List of Section Title and Numbers) is a copyright publication prepared jointly by
Construction Specifications Canada (CSC) and the Construction Specifications Institute (CSI) U.S.A.
CCDC 20 – 2008 5
RELATIONSHIP TO DIVISION 1 - GENERAL REQUIREMENTS OF THE
SPECIFICATIONS
Some of the General Conditions in CCDC 2 – 2008 deal with subject matter normally identified
in Division 1, General Requirements of the Specifications (e.g. GC 3.13 – CLEANUP). In order
to establish a standard procedure, they have been included in the General Conditions. They also
inter-relate with other provisions in CCDC 2. If you decide to delete such work-related
provisions from the General Conditions, you must delete the clause in its entirety and refer to the
appropriate specification section.
The provisions of paragraph 1.1.7 in GC 1.1 – CONTRACT DOCUMENTS outline the priority
of documents to resolve conflicts within the Contract Documents. Placing work-related items
into the Specifications that were previously contained in the General Conditions may lead to a
different result than intended under GC 1.1.7.
General requirements for such items as barricades, progress photographs, field offices, temporary
utilities, supervisory requirements and similar matters should be identified and dealt with in
Division 1 of the Specifications.
6 CCDC 20 – 2008
GUIDE TO THE USE OF CCDC 2 – 2008
The Agreement Between Owner and Contractor (Agreement) contains provisions that relate
specifically to the Work and which shall be completed or filled-in by the contracting parties to:
• identify the date of the Agreement;
• identify the name of the Work;
• identify the parties to the Contract, i.e., the Owner and Contractor;
• identify the Consultant;
• describe the Work to be performed by the Contractor;
• identify the location of the Place of the Work;
• state the Contract Time;
• list the Contract Documents and any negotiations agreed to in writing between the parties;
• state the Contract Price, Value Added Taxes, and total amount payable;
• state the method of payment, holdback, and name of the chartered lending institution whose
prime rate will be used to determine the interest rates applicable to the Agreement;
• record the addresses of the Owner, Contractor, and the Consultant for the purposes of the
delivery and receipt of Notices in Writing;
• identify the language of Contract, if applicable;
• attach copies of the latest revision at the time of bid closing of CCDC 40 – Rules for
Mediation and Arbitration of Construction Disputes and CCDC 41 – Insurance
Requirements; and
• provide for the formal execution of the Agreement by the parties.
CCDC 20 – 2008 7
Identify the Consultant. If the Contract is to be administered by someone other than the person
who prepared the Contract Documents, identify the Consultant who will administer the Contract.
Identify the commencement date and the date for Substantial Performance of the Work. This
constitutes the Contract Time referred to throughout the Contract Documents.
8 CCDC 20 – 2008
Normally, the Invitation and Instructions to Bidders have served their purpose once the bids have
been received; therefore, the Contract Documents in CCDC 2 – 2008 do not include such
bidding requirements. When information contained in these documents is to be included as part
of the Contract Documents, they should be listed under ARTICLE A-3 – CONTRACT
DOCUMENTS. This may include such supplementary bid information as a list of
subcontractors, alternative prices, or itemized prices. However, it is recommended that special
conditions, progress schedules, and labour agreements be set out in the appropriate sections of
the Specifications, not in the Supplementary Conditions.
If, after submission of bids, the parties to the Contract agree to changes, this information, or
reference to documents containing this information, should be included under Article A-3.
CCDC 20 – 2008 9
In the case where one of the parties disappears, or absolutely refuses to take delivery of a
registered letter or of a letter delivered by courier or hand, the Ontario Rules also provide that a
document is deemed to have been received by the party to whom it is addressed on the fifth day
after its transmission by ordinary mail to the address supplied by this party. Recognizing the
need to cope with such circumstances, CCDC also provides this method for sending Notices in
Writing, which it believes the parties would use only as a last resort.
A Notice in Writing may also be transmitted by facsimile or e-mail provided that during
transmission no indication of failure of receipt is communicated to the sender.
10 CCDC 20 – 2008
THE DEFINITIONS
CCDC 2 – 2008
__________
DEFINITIONS
The Definitions section of the CCDC 2 – 2008 contains those terms and phrases which carry a
specific meaning when used in the Contract Documents. Defined words throughout the CCDC
Agreement, Definitions and General Conditions are capitalized and shown in italics.
Bid and Contract Documents should consistently use these terms since they have a definite
meaning and application under the contract. Other terms may have a different connotation.
The Definitions section in CCDC 2 – 2008 may be expanded by supplementary conditions to
provide additional definitions to suit the particular needs of the Work, e.g. tenant, special
consultant, and government agency. Do not modify, nor delete, any of the specific CCDC
definitions, as they are used throughout the contract and any modification thereof will cause
confusion, conflicts or misunderstandings.
Abbreviations, technical terms, and references should be identified in the Specifications or the
Drawings and not added as Definitions.
CCDC 20 – 2008 11
THE GENERAL CONDITIONS
CCDC 2 – 2008
__________
The General Conditions in CCDC 2 – 2008 set forth the specific responsibilities, obligations and
rights of the parties, as well as the respective roles of the Owner, Contractor and Consultant.
The General Conditions contemplate a single construction contract for a specific Project.
However, they may be used in multiple contracts for the same Project. If a Project is to be
constructed under multiple contracts, separate contracts should be awarded using the applicable
CCDC contract forms, all of which should have co-ordinated General Conditions. In these
circumstances, the Contract Documents must clearly define the limits of responsibility for each
Contractor performing Work on the Project.
12 CCDC 20 – 2008
COMMENTS ON SPECIFIC GENERAL CONDITIONS OF CCDC 2 – 2008
Paragraph 1.1.8. Where a limited number of sets of Contract Documents will be issued to the
Contractor without cost, the number of sets to be provided should be stated as a Supplementary
Condition along with the terms for obtaining additional sets. It is good practice that the
information on the addenda be incorporated into the set of construction drawings.
The following is an example of amending the number of copies of documents the Contractor
will receive free of charge and the cost for additional copies.
CCDC 20 – 2008 13
GC 2.1 AUTHORITY OF THE CONSULTANT
The Consultant is not a party to the Contract between the Owner and Contractor; as such, there
is no contractual relationship between the Contractor and the Consultant.
14 CCDC 20 – 2008
The intent of the statement related to tests or inspections designated by the laws or ordinances of
the Place of the Work is to cover requirements of various authorities having jurisdiction. Some
examples include: regulatory inspections by building authorities; electrical inspections of
installed facilities; Construction Equipment compliance inspections; and environmental
compliance of construction methodologies.
CCDC 20 – 2008 15
PART 4 ALLOWANCES
16 CCDC 20 – 2008
PART 5 PAYMENT
CCDC 20 – 2008 17
The Consultant must promptly inform the Owner of the date of receipt of the Contractor’s
application for payment and remind the Owner of the Owner’s responsibility for payment to the
Contractor. The consultant should also advise the Owner of the approximate amount of the
progress payment at this time. If the Consultant determines that the amount claimed is not
properly due and cannot approve the application as presented, the Consultant must immediately
advise the Contractor and endeavour to clarify the differences. If there is no agreement, the
Consultant should amend the amount, issue a certificate for the amended amount and notify the
Contractor, in writing, of the amendment. Failure of the Consultant to issue a certificate
indicating amounts due within 10 calendar days after the receipt of the original application or
failure of the Owner to pay within 20 calendar days after the Consultant’s receipt of the
Contractor’s application for payment can result in a work stoppage or termination of the
Contract as outlined in GC 7.2 – CONTRACTOR’S RIGHT TO SUSPEND THE WORK OR
TERMINATE THE CONTRACT.
18 CCDC 20 – 2008
• Two methods are provided in CCDC 2 – 2008 for the Owner to supply this written
authorization: the Change Order and the Change Directive;
• A Change Directive can only be used to order changes that are within the general scope of
the Contract Documents;
• A Change Order may be used for changes that are within or outside the general scope of the
Contract Documents;
• The Contractor is under no obligation to carry out a change in the Work which is outside the
general scope of the Contract Documents; and
• Only a Change Order can be used to carry out a change which deals solely with the Contract
Time.
Procedures for substitutions are not addressed by CCDC 2 – 2008. Therefore, unless provision is
made for substitutions by Supplementary Condition or in Division 1 of the Specifications, none
are allowed except by Change Order or by Change Directive.
Changes near the end of the Work that would postpone the completion date and create
unreasonable delay in achieving substantial performance and its consequences, including the
release of the holdback amount, should be handled by change orders, separate contracts or
purchase orders, not by change directives. The Owner should consult with legal counsel and
insurance and surety advisors before this is done.
CCDC 20 – 2008 19
The Contractor may propose a change in Contract Price by any method, including:
• Lump sum price. The Contractor should prepare an estimate and submit a lump sum
quotation with a breakdown of costs in a form acceptable to the Consultant. Should the
proposed lump sum price be unacceptable to the Owner, then the parties may negotiate to
reach agreement on an acceptable amount.
• Unit prices stated in the Contract or subsequently agreed upon. Where unit prices are
required for adjusting the Contract Price, they should be as specific as possible, include
overhead and profit, and differentiate between units added and units deducted. For example,
concrete in place should specify the location in the building, the type of element and strength.
The Consultant analyzes the information provided in the Contractor’s submission; further
discussion and negotiation may be required to come to a decision to accept the change in the
Work and the change in the Contract Price and Contract Time. When there is agreement
between the Owner and Contractor on these changes, a Change Order, which is an amendment
to the Contract, is prepared by the Consultant and is signed by the Owner and the Contractor.
20 CCDC 20 – 2008
Paragraph 6.3.11 obligates the Owner to pay the Contractor on an interim basis for work
performed under a Change Directive even though the total amount has yet to be finalized.
GC 6.5 DELAYS
This General Condition describes those circumstances in which the Contract Time may be
extended, and the Contract Price adjusted, as the result of delays.
Paragraph 6.5.3.3 specifies that abnormally adverse weather is a basis for an extension to the
Contract Time. The intent is to equitably allocate risk. The Contractor is expected to assume
weather-related risk arising from “normal” weather conditions and the Owner assumes weather-
related risk arising from “abnormally adverse” weather conditions.
Abnormally adverse conditions might include extended heavy rainfall, ice or snow storms, high
winds, etc., that fall outside the normally expected weather patterns at the Place of the Work for
the proposed time of construction. If the Owner desires to define specific weather conditions for
a specific Project that will not be considered abnormal, then a Supplementary Condition would
be necessary. Examples might include defining the acceptable parameters of:
• a 24 hour rainfall;
• the depth of snowfall over a specific time period; or
• wind speed and anticipated duration.
Paragraph 6.5.3. There may be instances where the extension in the Contract Time may be
longer than the period of the event causing the delay. For example, additional time may be
required to re-establish the workforce and equipment or to work under more difficult conditions.
Paragraph 6.5.3.4 explicitly excludes circumstances resulting from default or breach of Contract
by the Contractor as a basis for an extension of time. An example of such a circumstance would
be the late delivery of a Product for a cause beyond the Contractor’s control, where the
Contractor could still be held responsible for the late delivery if the Contractor had originally
failed to order the Product in a timely manner.
CCDC 20 – 2008 21
Paragraphs 6.5.4 and 6.5.5. The Consultant may recommend a Contract Time extension where
the Contractor experiences conditions that could not reasonably have been contemplated in
setting the completion date of the Work. The Contractor should submit a detailed report in
support of any claim for extension.
Paragraph 6.5.5. Where no schedule is made under paragraph 2.2.13, claims for delay due to a
failure to produce Supplemental Instructions on a timely basis will not be entertained until 10
Working Days after demand for such instructions has been made. Therefore, the Contractor
should make demands for Supplemental Instructions, such as the colour finishing or keying
schedule, as early as possible in order to avoid delays.
Where a change or extension of the Contract Time is agreed upon, such extension must be
confirmed in writing by a Change Order.
The Owner should be careful that the award of separate contracts does not unexpectedly cause
delays.
The Contractor must give the Consultant a Notice in Writing stating the cause of delays within
10 Working Days after the commencement of the delay. The Consultant then recommends
acceptance or rejection of claims for delay promptly and in writing.
Delays should be properly recorded, supported and promptly analyzed so that responsibility and
compensation, if any, can be established. GC 7.2 – CONTRACTOR’S RIGHT TO SUSPEND
THE WORK OR TERMINATE THE CONTRACT provides that the Contractor has a right to
terminate the Contract in circumstances where delays caused by Order of the Court or other
public authority, which are not the fault of the Contractor, extend beyond 20 working days.
22 CCDC 20 – 2008
An important aspect of this general condition is that all notices related to claims shall be given
and acted upon in a timely manner. This ensures that, as the event or series of events giving rise
to the claim occur, both parties are able to take steps to mitigate the effects of the claim and are
not having to deal with the impact of the event afterwards. It is also important that the
Consultant make a prompt finding to resolve a claim. Should the claim not be resolved to the
satisfaction of all parties involved, it enables the parties to immediately initiate the dispute
resolution process.
In paragraph 6.6.3, the party making a claim has until the fifth calendar day before the expiry of
the lien period provided by the lien legislation applicable at the Place of the Work as stated in
GC12.2 – WAIVER OF CLAIMS to provide Notice in Writing of a claim. The written notice of
claim must be in accordance with GC12.2.6.
All claims related rights and obligations are mutual, i.e., they apply equally to both the
Contractor and Owner in respect of claims initiated by either party.
CCDC 20 – 2008 23
Note that the failure of the Owner to provide financing information required of the Owner under
GC 5.1 – FINANCING INFORMATION REQUIRED OF THE OWNER is exempted from the
Consultant’s confirmation that sufficient cause exists.
24 CCDC 20 – 2008
The obligation to determine the location of buried utilities and structures includes those facilities
that are not shown on the Contract Documents but that are reasonably apparent in an inspection of
the area. Examples of this would include utility access chambers or manholes, overhead light
fixtures without obvious overhead power or control lines, or culverts beneath roadbeds.
GC 9.5 MOULD
There is little applicable legislation similar to those for Toxic and Hazardous Substances to
articulate the roles and responsibilities of the Owner, Consultant and the Contractor at the Place
of the Work regarding the presence of mould. Regulators have issued alerts and bulletins
regarding health and safety standards making it the employer's responsibility to protect their
workers. Due to insufficient knowledge about the short and long term affects of mould, it is
presently impossible to determine safe mould exposure thresholds; as such, the scientific and
health communities agree that mould should be removed.
This General Condition outlines the responsibilities of the parties and the procedures to apply in
the event that the presence of mould is observed or is reasonably suspected at the Place of the
Work, whether the mould is found to be toxic or not.
The expertise required to determine the nature and cause of the mould is not the responsibility of
the Consultant. An independent expert is required when called for under the contract. This
General Condition clearly defines when and how the independent expert will be engaged.
CCDC 20 – 2008 25
When mould is observed at the Place of the Work, it is incumbent upon the Contractor to take all
reasonable steps to prevent injury, sickness, death and damage to the property; this may include
stopping the Work, if necessary.
If the Owner and Contractor mutually or through the results of the independent expert's
investigation agree on the nature and cause of the mould, then the party responsible, at their own
expense, shall:
• remediate or dispose of the mould,
• make good any damage to the Work,
• reimburse the other party for the costs of the independent expert, and
• indemnify and hold harmless the other party.
Paragraph 9.5.2.3. If the Contractor agrees that the presence of mould was caused by the
Contractor’s operations under the Contract, a Change Order should be issued to reimburse the
Owner for reasonable costs for the independent expert.
Paragraph 9.5.3. If the Owner agrees that the presence of mould was not caused by the
Contractor’s operations under the Contract, a Change Order should be issued to reimburse the
Contractor for reasonable costs and to extend the Contract Time. The Consultant’s
recommendation under paragraph 9.5.3.3 should also be made in consultation with the expert
referred to in GC 9.5.1.3.
Paragraph 9.5.4. Should the Owner disagree with the findings of the independent expert, the
Owner must proceed with the work stated in paragraph 9.5.3.1. Similarly, should the Contractor
disagree with the findings of the independent expert, the Contractor must proceed with the work
stated in paragraph 9.5.2.1. The rights of both the Owner and the Contractor are not prejudiced
should they proceed with this work. The parties can then attempt to resolve their dispute by
following Part 8 – DISPUTE RESOLUTION.
It is good practice that the Owner take all reasonable steps prior to the commencement of the
Work to determine whether or not mould is present at the Place of the Work and to provide both
the Consultant and the Contractor with a written list specifying the presence of mould. There is
an expectation that the remediation of the mould be completed either before the Work begins or
as part of the Work.
For more information on mould, refer to CCA 82 – MOULD GUIDELINES FOR THE
CANADIAN CONSTRUCTION INDUSTRY at www.cca-acc.com.
26 CCDC 20 – 2008
Since government procedures governing the refund or exemption of taxes and duties may vary, it
is recommended that the appropriate procedures be predetermined in order to provide both
parties to the Contract with clear and precise information for making such applications.
When certain Products are exempt from sales tax, state in a Supplementary Condition who the
purchasing authority will be and identify the forms to be used.
A question often arises when an announced tax change is not to take effect until after bid closing,
but will take effect during the course of the Contract. It is incumbent on the Owner and the
Consultant to clarify for the prospective bidders how this situation is to be handled in the
preparation of bids.
GC 11.1 INSURANCE
Prior to signing the Contract , preferably before the bidding phase, it is important for the parties
to conduct a detailed review of the insurance requirements for the Project with insurance
professionals that are qualified to provide construction insurance. The purpose of the review
should be to identify the types of coverage that may be required to satisfactorily protect the
various parties’ interests in the work. Specialized coverages may be necessary to adequately
insure additional risks presented by some projects.
Users of CCDC 2 – 2008 should also review with insurance professionals risks that are excluded
from standard construction insurance policies, paying particular attention to how these risks may
impact the Project in question. For example, asbestos may be of little or no concern in the case
of stand-alone new construction that will contain none of this material. However, the location of
an otherwise ‘low risk’ project in proximity to what insurers perceive to be a ‘terrorism target’
may render terrorism coverage unavailable or very costly. A risk management strategy that
addresses insurable and non-insurable risks prior to bidding is an important part of the process
that can assure the achievement of the financial goals of the Project.
CCDC 20 – 2008 27
The insurances specified in this General Condition are considered to be recommended minimum
requirements for most projects. The insurance limits and coverages are set out in document
CCDC 41 – CCDC INSURANCE REQUIREMENTS in effect at time of bid closing. Should the
insurance market introduce changes to the insurance limits and coverages, the CCDC will
modify CCDC 41 accordingly without having to reintroduce a revised version of the contract
form. The most current version of CCDC 41 is available on the CCDC web site (www.ccdc.org).
A copy of the latest revision at time of bid closing should be downloaded from the CCDC web
site and attached to the contract for ease of reference.
Paragraph 11.1.1.4. ‘Broad form’ property insurance is another term for ‘all risk property
insurance’. For most projects, insurance coverages are to be maintained until 10 days after the
date of Substantial Performance of the Work. Owners must have their insurance policies in place
at the time of Substantial Performance of the Work, or such other time stipulated under
paragraph 11.1.1.4.2 or 11.1.1.4.3.
Paragraph 11.1.3. The party responsible for the loss is responsible for the deductible amount.
Should there be proportional responsibility between the parties, the responsibility for the
deductible amount is calculated accordingly.
Paragraphs 11.1.6 and 11.1.7 cover the remote possibility that the insurance provisions in CCDC
41 change some time between the bid closing period and the signing of the Contract or the
renewal period of the Contractor’s insurance policy. These changes must be addressed promptly
by Change Order to avoid the risk of not being adequately insured.
If the characteristics of the Project call for revisions to the insurance limits and coverages
specified in CCDC 41 or to any of the insurance requirements in CCDC 2 – 2008, a
supplementary condition must be prepared accordingly.
For additional information on insurance matters see CCDC 21 – A GUIDE TO
CONSTRUCTION INSURANCE and related CCDC Bulletins (www.ccdc.org).
GC 12.1 INDEMNIFICATION
Indemnification is a provision in a contract in which a party undertakes to be financially
responsible for specified types of damages, claims, or losses for which the other party may be
liable or may suffer. Through this provision the contracting parties agree who will assume
liability for losses that arise from the performance of the contract and the limits of that liability.
28 CCDC 20 – 2008
The indemnification clauses in CCDC 2 – 2008 are designed to allocate risk to the contracting
party who is in the best position to control and manage that risk. CCDC 2 – 2008 establishes the
concept of mutual indemnification between the parties. The indemnification provisions render
each party responsible for its own negligence or breach of the terms and conditions.
CCDC 2 – 2008 has introduced limits of liability for claims for indemnity between the parties as
well as claims for indemnity by third parties other than those related to bodily injury and
property damage.
CCDC 2 – 2008 recognizes that the Owner determines the extent of the Owner’s own exposure
to risk and specifies the type and amount of insurance coverage required to be provided by the
Contractor based upon this assessment. In order to limit the risk undertaken by the parties under
the agreement and their efforts to indemnify against insurable direct claims in this General
Condition, that obligation has been limited to the dollar value of the insurance specified by the
Owner. The Owner can always provide further protection by specifying that the Contractor
purchase additional insurance limits.
The risks imposed upon a Contractor by the indemnification clause are typically passed on to the
insurance companies through the purchase of insurance policies specified in the insurance
provisions. However, insurance policies include exclusions such as mould and pollution in their
standard commercial general liability policies. Consequently, the net result is not an absolute
transfer of the risk to the insurance companies. Owners and Contractors need to be aware that
this may result in uninsurable payouts that have the potential to cause insolvency of the
Contractor, resulting in serious financial losses for both parties.
Owners and Contractors must be made aware that modifying the indemnification clause may
pose uninsured risks. Refer to CCDC Bulletin 25 (www.ccdc.org) for a detailed explanation.
A table summarising the various indemnification limits of CCDC 2 – 2008 follows. The parties
will indemnify and hold each other harmless against the stated claims, provided that such claims
arise out of negligent acts or omissions or a failure of either party to fulfill its obligations under
the terms and conditions of the Contract.
CCDC 20 – 2008 29
Summary of the indemnification limits for CCDC 2 – 2008:
GENERAL – With the exception of mould, patent fees and an actual or alleged lack of, or
defect in, title to the Place of the Work, all claims must be caused by negligent acts, negligent
omissions, or a failure to fulfil the Contract.
Owner/Contractor
indemnify and hold Nature of
Monetary limitation Time limitation
each other the claims
harmless
General liability insurance limit
Direct claims Insured for one occurrence as referred to in
between the parties claims CCDC 41 in effect at the time of
bid closing
and
Shorter of 6 yrs from
Third-party claims The greater of the Contract Price the date of
Uninsured
other than those or $2,000,000, but in no event Substantial
claims
relating to bodily greater than $20,000,000 Performance of the
injury or property Work and any
damage limitation Statute of
the province or
Insured territory of the Place
Third-party claims claims No Limit of the Work
relating to bodily
injury or property
damage Uninsured
claims No Limit
Toxic/Hazardous Insured or
Substances Uninsured No limit No time limitation
claims
30 CCDC 20 – 2008
EXCEPTIONS
Owner indemnifies
Nature of
the Contractor Monetary limitation Time limitation
the claims
Model,
Infringement or plan or
alleged design
infringement of a supplied
patent of invention to the
No limit No time limitation
in executing Contractor
anything for the as part of
purpose fo the the
Contract Contract
Documents
Lack of, or defect
in, title to the Place
No limit No time limitation
of the Work
Since the Consultant is not a party to the Contract, indemnification of the Consultant should be
reviewed under the Consultant’s agreement with the Owner.
CCDC 20 – 2008 31
In paragraph 12.2.4, the Owner waives and releases the Contractor for claims for substantial
defects and deficiencies arising out of the Contractor’s actions where there is no written notice
of claim by the Owner within 6 years from the date of Substantial Performance of the Work, or
such shorter period as may be prescribed in any limitation statute applicable to the Place of the
Work. Claims that have been given in writing and that satisfy paragraph 12.2.6 are not waived.
Paragraph 12.2.5. The Owner waives and releases the Contractor from all claims resulting from
acts or omissions which occur after the date of Substantial Performance of the Work except for
indemnification for claims advanced against the Owner by third parties, claims related to toxic
and hazardous substances and those arising under GC 12.3 – WARRANTY and claims for which
Notice in Writing has been received by the Contractor from the Owner within 395 calendar days
following the date of Substantial Performance of the Work. Claims that have been given in
writing and that satisfy paragraph 12.2.6 are not waived.
Paragraph 12.2.7. The requirement for a detailed account of the amount claimed is intended to
discourage frivolous claims by either party.
GC 12.3 WARRANTY
The warranty period specified in CCDC 2 – 2008 is one year from the date of Substantial
Performance of the Work or such other periods specified in the Contract Documents for certain
Products or Work.
Warranties for portions of the Work and Products that specify longer periods are of two types:
• warranties covering the entire installation as well as the Products (e.g. roofing or glazing
systems), and
• warranties covering replacement of the Product.
The Contract Documents will describe the type of warranty.
Warranties for replacement of Products offered by the Product manufacturer usually only cover
the replacement of the Product and not transportation, removal of the failed Product,
reinstallation of its replacement, nor any associated labour costs. These Product warranties will
be obtained by the Contractor and are issued to the benefit of Owner.
Owners and Consultants should be aware when specifying warranties for periods longer than the
one-year period defined in paragraph 12.3.1, that, in most cases, standard Performance Bonds do
not cover guarantees which extend beyond two years and supplementary bonding is generally not
available.
The CCDC Bulletins 17 and 18 (www.ccdc.org) provide additional information on construction
warranties.
32 CCDC 20 – 2008
NOTICE TO USERS OF CCDC 2 – 2008
GOVERNED BY THE CIVIL CODE OF QUEBEC
__________
1. Article 21 of the Definitions included in CCDC 2 – 2008 state that the definition of
Substantial Performance of the Work is as defined in the lien legislation applicable to the
Place of the Work. However, in Quebec, as no definition of Substantial Performance of the
Work exists in the Civil Code, substantial performance will occur, by virtue of the alternative
definition provided in Article 21, when the Work is ready for use or is being used for the
purpose intended and is so certified by the Consultant.
With respect to the issue of legal hypothecs ("liens" in other provinces) in Quebec, one must
refer to the completion of the Work, as defined in Article 2110 of the Civil Code as: by
virtue of Article 2727 of the Civil Code, it is from this event that the time limits concerning
legal hypothecs begin.
2. CCDC 2 – 2008 invites the individuals signing the Agreement (on page 5) to affix a
corporate seal if required. In Quebec, the seal is not mandatory.
3. Paragraph 2.2.6 of GC 2.2 may be considered to be releasing the Consultant from his or her
responsibility; however, one cannot restrict the public order responsibility the Consultant
assumes by virtue of Article 2118 of the Civil Code of Quebec.
4. In Quebec, notwithstanding the provisions of paragraph 2.3.1 of GC 2.3, the Consultant is
governed by Article 2117 of the Civil Code of Quebec, which holds that the client (and
consequently his Consultant) must not interfere with the work.
5. In GC 12.2.1 and GC 12.2.3 expiry of the period within which a Contractor must register a
legal hypothec should be considered synonymous with expiry of the lien period.
CCDC 20 – 2008 33
FURTHER REFERENCES
__________
Reference to the following additional CCDC guides and related documents is highly
recommended:
CCDC 9A/9B – Statutory Declarations
CCDC 21 – A Guide to Construction Insurance
CCDC 22 – A Guide to Construction Surety Bonds
CCDC 23 – A Guide to Calling Bids and Awarding Contracts
CCDC 24 – A Guide to Model Forms and Support Documents
CCDC 40 – Rules for Mediation and Arbitration of Construction Disputes
CCDC 41 – CCDC Insurance Requirements
The latest editions of the following documents are available on the CCDC Web Site
www.ccdc.org
CCDC Bulletin 7 – Use of Supplementary Conditions with CCDC Standard Contract Forms
CCDC Bulletin 17 – Construction Warranties
CCDC Bulletin 18 – Warranty vs. Guaranty
CCDC Bulletin 21 – Statutory Declarations: Purpose and Practical Application
CCDC Bulletin 24 – Do Modern Insurance Specifications and Policies Sufficiently Address
Today’s Construction Contracts.
CCDC Bulletin 25 – Standard Indemnification Clause
34 CCDC 20 – 2008