The mockup of pipe supports and hangers was not fully approved and needed to be updated to match specifications. Some pipe clamps and supports were also not installed correctly or did not have the required documentation. Alignment of support rods needed adjustment at a few locations. Duct and pipe clashes were identified and resolved by shifting pipes as per the clash-free model.

Uploaded by

amit rajput
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views1 page

Mock Up

The mockup of pipe supports and hangers was not fully approved and needed to be updated to match specifications. Some pipe clamps and supports were also not installed correctly or did not have the required documentation. Alignment of support rods needed adjustment at a few locations. Duct and pipe clashes were identified and resolved by shifting pipes as per the clash-free model.

Uploaded by

amit rajput
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

S.

no OBSERRVATION Updated Status


Pipe supports,hanger used in mock are not approved yet.DIAL yet to receive the
1 MAS of supports is approved with Code-B
documents and subject to DIAL approval.
2 The pipe clamps used in CPVC pipes mock up was not split type with rubber seal. Done
3 As discussed and agreed L&T must ensure pipe support near Y joint. Done
Supporting details for CPVC piping need to be updated.Pipe supports provided is not as
4 Done as per ER Specification
per ER specs.
5 Celvis hangar MAS not yet received by DIAL & subject to DIAL approval. MAS of Clevis hanger is approved with code-B

6 CPVC pipe BOP is not as per GFC available at site and need to be corrected as per GFC. DONE
Duct support & CPVC pipe clash found in Mock up.L&T to identify why clash occurs as all NOTED:-25mm shifted and reinstalled as per
7
services GFC released through BIM clash free model. GFC Drawing.
CPVC pipes does not have detrimental effects
of water i.e., corrosion resistant ( refer IS:
15778 clause 9.2)
CPVC pipe installed are also not exposed to
sun.
8 Pipe marking missing and need to be painted before installation as per the specs. Surface of CPVC pipe is also smooth in nature.
( refer IS 15778 clause 9.1.1)
IS code & ASTM standards also does not
specifies about paint.
So, we will follow above codes and standards
for CPVC pipe installation.

9 Alignment of rod was not proper at few locations and need to be adjusted. DONE