Engineering Design Review and Checklist
Engineering Design Review and Checklist
FT12
Session 9
Engineering Design Review and Checklist
Session Speaker:
Dr Govind R
Dr. R. Kadambi
Session Objectives
Session Topics
• System
y development
p and major
j application
pp enhancement pprojects
j
must conduct a PDR
• PDR is performed during the Design and Engineering Phase when
the System Developer has initially baselined the high-level
high level system
architectural design
© M. S. Ramaiah School of Advanced Studies, Bengaluru
4
PEMP ESE2516
FT12
– System Developer
– System Owner/Manager
– Project
j Owner/Manager g
– Component Lead
– Infrastructure Implementation Agent or Contractor
– Chief Technology Officer (CTO)
– Executive Steering Committee (ESC)
Government Responsibilities
• Project Owner/Manager works with their designated
Component Lead
• Ensures completion of the entrance requirements for the
Preliminary Design Review (PDR)
• Fi
Firstt step-
t C
Completion
l ti off the
th PDR Questionnaire
Q ti i
• Determines readiness to proceed to the PDR and availability
of the input documents
Government Responsibilities
• If a system is being developed in-house without outside
contractor resources, then the government developers are
responsible
ibl for
f the
th contractor
t t responsibilities
ibiliti
• Representatives
p from the keyy stakeholder ggroups p within the
Office of Information Services (OIS) are responsible for
reviewing the input documents prior to the PDR and being
pprepared
p to ppresent anyy critical issues duringg the PDR
Government Responsibilities
Government Responsibilities
• Exit Form by all of the key OIS stakeholder groups and for
tracking
ki all
ll critical
i i l issues
i to closure
l
Contractor Responsibilities
• Following are the responsibilities that the System Developer
has with regard to the PDR
• Would pprovide a high-level
g ppresentation to stakeholders that
addresses the following:
– Project Overview
– Design Drivers & Alternatives Considered
– System Architectural Design
– Software Architectural Design
– Requirements Traceability
– Data Overview
– Enterprise Architecture Compliance
– Resource Sizing Estimates
– Risks & Mitigation
g Strategies
g
– Issues
© M. S. Ramaiah School of Advanced Studies, Bengaluru
10
PEMP ESE2516
FT12
Entrance Criteria/Inputs
• Mandatory artifacts that are prerequisites to the PDR:
– Business Risk Assessment
– Requirements
R i t Document
D t
– System Design Document
– Information Security Risk Assessment
Exit Criteria/Outputs
• Following are the results/outputs that are to be documented
from the PDR:
– Assumptions
– Constraints
– Priorities
– Issue Resolutions
– Unresolved Issues
– Risk Mitigation Strategies
– Recommendations
– Action Items
– Next Steps
Review Process
• Incremental
I t l reviews
i would
ld lead
l d up to
t an overall
ll system
t CDR
• System Developer
• System Owner
• Project Owner
• DPI Project
P j t Manager
M
• ITS Infrastructure hosting office
• ITS Statewide Architecture office
• DPI Enterprise Architect
• DPI Chief Technologygy Officer ((CTO))
• Project Manager should also attend the ESC meeting to discuss the
results
l off the
h CDR
Contractor Responsibilities
• System Developer who has knowledge of the proposed system
architecture and the input documents shall:
– Complete the CDR Entry Criteria Checklist prior to
requesting a CDR and provide a high-level presentation to
DPI stakeholders that addresses the following:
• Project Overview
• Design Drivers & Alternatives Considered
• System Architectural Design
• Software
S f A hi
Architecturall Design
D i
• Requirements Traceability
• Data Overview
• Enterprise Architecture Compliance
• Resource Sizing Estimates
• Risks & Mitigation Strategies
Entrance Criteria/Inputs
• Mandatory prerequisites to the CDR
– Business Risk Assessment.
– Preliminaryy Design
g Review Request
q for Action ((RFA)) forms
– Requirements Document(s)
– System Design Description (SDD)
– Software Requirements Specification
– Software Design Description
– Interface Requirements Specification
– Interface Design Description
– U d t d version
Updated i off Information
I f ti Security
S it (IS) Risk
Ri k Assessment
A t
(RA)
– Logical Data Model
– Interface
e ace Co
Control
o Document
ocu e ((ICD)C )
– Database Design Description
– Test Plans
– Software Installation Plan
– System Security Plan (SSP)
• P
Project
j t Manager
M andd System
S t D l
Developer d
document
t the
th results
lt /
outputs of the CDR and follow-up to ensure that all actions and
any unresolved issues identified during the CDR are
satisfactorilyy addressed
• Introduction
• P i i
Participants
• Entry Criteria Status
• Design Review Results – Subparagraphs summarize the
status of the design approach and discuss any issues or
concerns.
• Exit Criteria Status
• Requirements to complete the CDR
• Conclusion
• Provides a qquick and easyy ppaper p trail that will allow different
reviewers to continue a quality review process in the absence
of the prime reviewer
© M. S. Ramaiah School of Advanced Studies, Bengaluru
30
PEMP ESE2516
FT12
– Notes – providing
pro iding any
an special instructions
instr ctions pertaining to
each given criteria or to the review status for that
submittal
Session Summary
• Project Manager should attend the ESC meeting to discuss the results of
the CDR