This specification has been revised as indicated below and described in the revision record
on the following page. Please destroy all previous revisions.
Record of Revisions
Revision Date Description
No.
0 01/13/2011 ISSUED FOR APPROVAL
TABLE OF CONTENTS
1.0 GENERAL.................................................................................................................................... 4
2.0 REFERENCES ............................................................................................................................. 4
2.1 MARAFIQ............................................................................................................................. 4
2.2 SASO - Saudi Arabian Standards Organization ............................................................... 5
2.3 SAF Directives .................................................................................................................... 5
2.4 Factory Mutual (FM)............................................................................................................ 5
2.5 NFPA - National Fire Protection Association.................................................................... 5
2.6 API – American Petroleum Institute .................................................................................. 5
2.7 OSHA - Occupational Safety & Health Administration .................................................... 5
2.8 UL - Underwriters' Laboratories, Inc ................................................................................. 5
3.0 DEFINITIONS............................................................................................................................... 5
4.0 HEALTH AND SAFETY CONSIDERATIONS .............................................................................. 6
5.0 SUBMITTALS .............................................................................................................................. 6
6.0 QUALITY CONTROL ................................................................................................................... 7
6.1 Regulatory Requirements .................................................................................................. 7
6.2 Products Quality ................................................................................................................. 7
6.3 Electrical.............................................................................................................................. 7
7.0 DESIGN CRITERIA...................................................................................................................... 8
7.1 Filling of Tank ..................................................................................................................... 8
8.0 PRODUCTS ................................................................................................................................. 8
8.1 Tank ..................................................................................................................................... 9
8.2 Isolation Valves................................................................................................................... 9
8.3 Backflow Preventer ............................................................................................................ 9
8.4 Valve Supervisory Switches .............................................................................................. 9
8.5 Pipes, joints and fittings .................................................................................................... 9
8.6 Pipe Hangers and Supports ............................................................................................... 9
9.0 EXECUTION ................................................................................................................................ 9
10.0 INSTALLATION ......................................................................................................................... 10
10.1 Piping................................................................................................................................. 10
10.2 Backflow Prevention......................................................................................................... 10
10.3 Isolation Valves................................................................................................................. 10
10.4 Drainage ............................................................................................................................ 10
10.5 Hanging, Bracing and Restraint of System Piping......................................................... 10
10.6 Supervisory Switches....................................................................................................... 10
10.7 Pressure Gauge ................................................................................................................ 11
10.8 Identification Signs........................................................................................................... 11
10.9 Painting ............................................................................................................................. 11
11.0 START-UP AND INITIAL OPERATION ..................................................................................... 11
11.1 Pipe Cleaning and Flushing ............................................................................................. 11
11.2 Corrosive Chemicals ........................................................................................................ 11
12.0 TESTING.................................................................................................................................... 11
12.1 Retest................................................................................................................................. 11
13.0 CERTIFICATION........................................................................................................................ 11
14.0 DELIVERY, HANDLING AND STORAGE.................................................................................. 11
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-B-4912
Project Name: Date: 28 Nov 2011
Contract Number: Page 4 of 12
Revision 3
1.0 GENERAL
The design information included in this specification is not intended to cover complete details.
This specification describes the requirements for a Welded-Steel Gravity and Suction Firewater
Storage Tank. The objective of installing a firewater storage tank is to assure firewater is available
during a fire scenario.
The design information included in this specification is not intended to cover complete details.
The design of the Firewater Storage Tank shall conform to this specification and the complete
Firewater Storage Tank shall be fully compatible to all components supplied.
2.0 REFERENCES
The referenced codes and standards are intended to provide an acceptable level of quality for
materials, products and workmanship. In case of conflict between these standards and the text of
this Specification, the Specification text shall govern.
The latest revision of the referenced codes and standards shall be used as a minimum guide. In
case of conflict, the Contractor shall propose equipment, materials and processes conforming to one
group of codes and standards.
2.1 MARAFIQ
MQ-SP-P-4900 – PRIVATE FIRE SERVICE MAINS
MQ-SP-P-4901 – PUBLIC FIRE SERVICE MAINS-HYDRANTS AND FLOW
REQUIREMENTS
MQ-SP-P-4911 – STATIONARY FIRE PUMPS
MQ-SP-P-4922– PROTECTED PREMISES AND PROPRIETARY STATION FIRE
ALARM SYSTEM
MQ-SP-P-5001 – PROCESS AND UTILITY PIPING DESIGN, LAYOUT AND
DRAWING
MQ-SP-P-5002 – PIPING – MATERIAL SPECIFICATION LINE CLASS –
PROCESS AND UTILITY PIPING
MQ-SP-P-5003 – SHOP FABRICATION AND HANDLING – PROCESS AND
UTILITY PIPING
MQ-SP-P-5004 – FIELD FABRICATION AND INSTALLATION – PROCESS AND
UTILITY PIPING
MQ-SP-P-5005 – INTERNAL CLEANING OF PIPING SYSTEMS
MQ-SP-P-5007 – BOLT TORQUE AND TENSIONING REQUIREMENTS
MQ-SP-P-5008 – PIPE MARKERS AND VALVE TAGS FOR COMMODITY AND
SAFETY ID
MQ-SP-P-5009 – GENERAL PIPING SPECIFICATION – PIPING STANDARD
DETAILS
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-B-4912
Project Name: Date: 28 Nov 2011
Contract Number: Page 5 of 12
Revision 3
3.0 DEFINITIONS
Refer to NFPA 22.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-B-4912
Project Name: Date: 28 Nov 2011
Contract Number: Page 6 of 12
Revision 3
5.0 SUBMITTALS
The Contractor shall submit to MARAFIQ, the following items for review and approval before
commencing the work:
Compliance Statement
Submit certificates from the manufacturer as evidence that the products meet these
Specifications and the referenced standards and codes.
Statements of NFPA compliance and UL listing, as applicable.
Contractor's Material and Test Certificate as described in NFPA 13.
Product Data
Product data shall include principal dimensions, general construction and material for each
item intended to be furnished and installed.
Manufacturer's catalog data for all isolation valves, check valves and all other accessories
and system components necessary for a complete firewater storage tank.
Installation Instructions
Submit copies of the manufacturer's installation and maintenance instructions for all
equipment. Include valve data and servicing instructions.
Shop Drawings
Working plans, prepared according to NFPA 22, MQ-SP-M-4002 – WELDED STEEL
STORAGE TANKS AND Project Specification. .
Complete field detail, shop fabrication and installation drawings of the firewater tank and
supply piping, including locations of control valves, showing routing of all piping, location of
hangers, supports, pipe restraints and other accessories.
Such plans shall be clear, legible and drawn to scale.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-B-4912
Project Name: Date: 28 Nov 2011
Contract Number: Page 7 of 12
Revision 3
The drawings shall show arrangement, water supply, equipment and all other details
necessary to establish compliance with this standard.
The plans shall also describe all system components.
The plans shall include an elevation diagram.
Define water service and connection with main supply.
As-Built Drawings
Clearly indicate valves, alarms and controls locations.
Identify any variation from Contract Drawings.
Maintenance and Operating Instructions
Submit data conforming to NFPA 22, and 25 for maintenance of the firewater tank.
Equipment manufacturer recommended spare parts and tools list.
Operation and Maintenance Manuals.
Test Reports
Accurately record and report the methods of testing, times and dates of the test, witnesses to
the test, and the results of the test.
Indicate and interpret test results for compliance with performance requirements in NFPA 22.
8.0 PRODUCTS
All goods and products covered by these Specifications shall be procured, when available, from an
in-Kingdom manufacturer. Procurement of all goods and products manufactured out-of-Kingdom
must be approved by MARAFIQ. All products, system components and hardware shall be in
compliance with NFPA 22. Only listed materials and devices shall be used in the installation of
automatic wet sprinkler system. Components that do not affect system operation, such as drain
valves and signs, shall not be required to be listed.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-B-4912
Project Name: Date: 28 Nov 2011
Contract Number: Page 9 of 12
Revision 3
9.0 EXECUTION
All products and equipment shall be installed in accordance with MARAFIQ regulations, applicable
local codes and standards, the manufacturer's written installation instructions and Project
Specifications.
The firewater tank shall be installed in accordance the applicable NFPA standards.
Provisions shall be made to facilitate frequent inspection, testing and maintenance as described in
NFPA 25.
Protect all equipment and materials at all times.
Cover and protect equipment and materials from dirt, water, chemical or mechanical damage.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-B-4912
Project Name: Date: 28 Nov 2011
Contract Number: Page 10 of 12
Revision 3
Close pipe openings with caps or plugs during installation. Cover and protect equipment materials
from dirt, water, chemical or mechanical damage.
10.0 INSTALLATION
All materials and equipment used in the installation of the firewater tank shall be new and the latest
design by the manufacturer.
The firewater tank shall be erected by fully experienced personnel, in the erection of a firewater
tank.
All materials, valves and devices essential to successful system operation shall be UL Listed and/or
FM approved.
Components that do not affect performance such as drain piping, drain valves and signs are not
required to be listed.
System components shall be constructed of materials that will resist corrosion or be suitably factory
protected from corrosion.
10.1 Piping
Installed piping, valves and fittings shall meet the requirements of NFPA 22 and Project
Specifications.
Make connections between underground and above-ground piping using an approved
transition piece strapped or fastened to prevent separation.
Close pipe openings with caps or plugs during installation.
Use pipes, fittings and hangers that resist corrosion; or apply a protective coating to all
unprotected exposed surfaces of the sprinkler system, where corrosive conditions exist
due to moisture or fumes from corrosive chemicals or both.
10.2 Backflow Prevention
Install a listed backflow prevention device where a public or potable water supply is to be
connected to the firewater tank.
10.3 Isolation Valves
At least one listed indicating valve shall be installed at each source of water supply.
Locate valves where they shall be readily accessible and free of obstructions.
Access and signage shall be obvious.
10.4 Drainage
Tank drain valves and auxiliary valves shall be installed in accordance with NFPA 22.
Locate all drain valves where they shall be readily accessible and free of obstructions.
Access and signage shall be obvious.
10.5 Hanging, Bracing and Restraint of System Piping
Installation of hangers, hanger rods, supports and fasteners shall be in accordance with
the requirements of NFPA 22 and Project Specifications.
10.6 Supervisory Switches
Supervise valves on sectional control valves, isolation valves and other valves on the
firewater tank in accordance with NFPA 22.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-B-4912
Project Name: Date: 28 Nov 2011
Contract Number: Page 11 of 12
Revision 3
12.0 TESTING
The firewater tank shall be tested in accordance with NFPA 22.
Upon completion of the tank construction, it shall be filled with water. Any leaks in the shell, bottom,
or roof (if the roof contains water) that are disclosed by the test shall be repaired by chipping or
melting out any defective welds and then re-welding.
The tank shall be tested as watertight.
Concealed work (including underground) shall be tested and approval prior to covering.
12.1 Retest
Any or all of the system component or portion which fail the specified tests shall be
retested after corrective measures have been taken.
13.0 CERTIFICATION
The Contractor shall prepare and submit a set of As-built Drawings, maintenance and instruction
bulletins, and the applicable parts of the Contractor’s material and test certificates covering material
and tests certifying that the work has been completed and tested in accordance with plans and
specifications.