P 220 Testing Procedure
P 220 Testing Procedure
SUMMARY:
TABLE OF CONTENTS
1. INTRODUCTION
2. EQUIPMENT REQUIRED
3. INITIAL CONFIGURATION
4. PRODUCT CHECKS
6. ON-LOAD TESTS
Page 2 of 8
1. INTRODUCTION
Important :
2. EQUIPMENTS REQUIRED
3. INITIAL CONFIGURATION
1 A CT
Current A 49,50
Current B 51,52
Current C 53,54
Page 3 of 8
Current N 55,56
Short 50-52-54-56
5 A CT
Current A 41,42
Current B 43,44
Current C 45,46
Current N 47,48
Short 42-44-46-48
Load default settings into relay from either MiCOM S1 .By default, the
frequency is set to 50 Hz. Change this to 60 Hz, if required. From – 50
Hz or 60 Hz)
4. PRODUCT CHECKS
After auxiliary voltage is applied, check that LED indicators for “Healthy
light up. After approx. 2-10 seconds the P220 is ready for operation.
Check all the Opto inputs by applying the required field voltage and
see the status of all the inputs in the menu Op Parameter.
During testing please make the Opto input 1 High. Opto input 1 is
dedicated for 52 A contact in this relay .
Now I eq 2= (I +ve) 2
+ Ke ( I -ve)2
Ieq= 0.667 I
Similarly we can check for the times in other thermal time constant
setting s.
5.2 E/F PROTECTION – Set the Pick up value & time value then
inject the required current in E/F terminal ( 55,56 for 1A & 47,48 for
5 A ) and check the operation of the relay after the set time delay .
E/F Protection
I2 = 1/3 (Ia + a2 Ib + a Ic )
First Stage-
Page 6 of 8
5.4 Phase Over Current : This feature will follow DMT curve .
Set the O/C threshold & time delay. Now inject the current in each
phase and check the operation .
Testing format will be like this
1.5 A 2 A OK OK
1.5 A 2 A OK OK
5.6 Excess long start : Set the excess long start current value &
excess long start time delay. Now inject current slightly more than the
excess long start threshold in each phase and check the operation of
the relay. Relay should operate after the set time delay.
Now set the time between two starts if you want to use this
protection and programme the same out put relay ( say out put relay
4 for example ) .
Now use the normally closed contact of the said output relay in the
closing circuit of the breaker/ contactor.
Page 8 of 8
5. ON LOAD TESTS
The Motor needs to be energised for these checks. With the motor
supplying load current check that the relay measurements are as
expected.