HVDC PTV PDF
HVDC PTV PDF
HVDC PTV PDF
Investment Proposal
2 BACKGROUND ................................................................................................................. 4
7 CONTINGENCIES........................................................................................................... 11
7.1 Price Contingencies ...................................................................................11
7.2 Interest During Construction.......................................................................13
7.3 Physical Contingencies ..............................................................................13
7.4 Summary ....................................................................................................14
1 Summary
Part V contains the estimated capital costs of the HVDC project. Transpower has
submitted cost estimates in good faith and expects to be able to recover actual costs
reasonably incurred in relation to the approved project through the transmission pricing
methodology. The costs contained in this document are estimates only.
The estimated costs for Transpower’s HVDC project including transmission works,
property and project management is approximately $795 million.
If the actual project costs are greater than the estimated cost included in this
submission and Transpower was unable to recover these costs, Transpower would
incur an economic loss. Forecasting errors could lead to windfall losses and could
deter efficient investment. While considerable effort is made to ensure estimated
costs represent the expected efficient investment, inevitably such forecasts are
subject to imperfect foresight.
It would therefore be inappropriate to establish a final set of project costs for recovery
5 years out from commissioning of an approved investment. Such an approach
would create unacceptable commercial risks for Transpower, and for electricity
consumers. Transpower does not believe it is the Government’s intention that this be
the case.
Figure 3-1: Relationship between Project Stage and Accuracy of Cost Estimates
The cost estimates are “At Approval” costs. As the project progresses, scenario
analysis techniques will be used to quantify expected variations, and establish a risk
profile for more refined costings. This process will allow the refinement of risk
mitigation strategies and the establishment of appropriate bounds for sensitivity
analysis. For clarity, Transpower expects to be able to recover the costs of risk
mitigation in addition to direct project costs.
A number of the cost risks (described below) relate to specifics of market conditions
and commercial requirements at the time tenders are let.
For clarity, operating and maintenance costs are not included in this Part in any detail
as they do not form a part of the project capital costs. However, for completeness a
description of the basis for estimating operating and maintenance costs has been
included in Section 4.
As discussed in the introduction to this part, cost estimates for the preliminary design
provided are subject to a high degree of uncertainty which would tend to reduce as
the project progresses.
Budget costs obtained from suppliers indicate that the cost of a 700 MW thyristor
pole would cost approximately $290 million.
The costs of decommissioning the existing Pole 1 are estimated to be of the order of
$5 million.
4.1.2 AC Switchyard
Table 4-1 provides a detailed breakdown of the AC substation work required for
replacing Pole 1 with a 700 MW thyristor pole.
With the replacement of the Pole 1 mercury arc converters with a 350 kV, 2 kA,
700 MW thyristor pole, the total inter-island transfer will be constrained by the
capacity of the existing cables to 1200 MW. In order to utilise the full capacity of the
thyristor poles, one additional cable is required to be installed.
Analysis has shown that with the installation of a new 500 MW cable in parallel with
an existing 500 MW cable, the link could be operated to 1400 MW (700 MW per
pole). With this arrangement, a failure of the new 500 MW cable or an old 500 MW
cable will reduce the link capacity to 1200 MW.
Installing an additional new cable (rated at 500 MW) as a spare will ensure a firm
capacity of 1400 MW, in the event of a failure of a new 500 MW or old 500 MW
cable. The costs of procuring and installing one or two 500 MW cables are shown in
the following table (Table 4-2).
An allowance for replacement of the Pole 2 controls in the order of $10 million has
been made. This replacement is required regardless of the options for Pole 1’s
future. There could be some economies of scale achieved by incorporating the Pole
2 control replacement together with Pole 1 replacement, but the level of savings will
not be known until detailed technical specifications and commissioning details are
finalised.
Transpower’s estimates of the cost to secure the necessary property rights for
location and operation of the under sea cable (and spare) between Fighting Bay and
Oteranga Bay are based on the annual fees currently payable for the existing cables.
Costs for securing a designation and resource consents pursuant to the RMA have
been estimated at $1.6 million. These estimates are limited to Council processing
costs, costs to Transpower of engaging specialist professional and legal advice,
Transpower staff, and attending various hearings and court appeals. They do not
attempt to allocate value to the environment or any environmental degradation
resulting from the project.
Economic costs of securing environmental approvals are closely linked to the likely
timeliness of securing designation. Where greater adverse environmental effects are
likely to occur, there is an increased requirement for input from technical specialists,
and additional consultation (to fully document and identify ways in which to mitigate
adverse effects), reporting, compensation, and property negotiation periods. These
commitments carry an additional economic cost.
The operating and maintenance costs used in the Part IV economic analysis were
estimated as shown in the table below:
Real costs
Capital cost estimates are in 2005 NZ dollars. No allowance has been made for
escalation of prices due to inflation or market conditions.
Allowances for detailed engineering and contractor’s project management costs have
been based on past experience and are subject to contract type (Engineer, Procure,
Construct or Erect only) and market conditions at the time of tendering.
Exchange Rates
Budgetary costs have been obtained in the currency of origin and have been
converted to $NZ using the 5-year forward exchange rates tabled below.
1
For the 1987-1992 DC Hybrid Upgrade project, 15% was used.
2
In a national cost/benefit framework the opportunity cost of an investment to society is represented
though the discount rate. Interest during construction represents the opportunity cost of an investment
to providers of funds, and is in essence a value transfer paid by beneficiaries to investors to ensure that
the investment takes place. As a general principle such value transfers should net out of the economic
analysis.
3
ANZ National Bank, 23 March 2005.
Hedging
The cost of hedging exchange rates and commodity prices has been included in the
cost estimates only to the extent that these are represented in forward rates and
prices used to prepare the estimates. It has been assumed that any additional costs
of hedging can be expensed during project implementation.
Commissioning
Commissioning of the new Pole 1 thyristor converter may require generation to be
constrained on or off. Detailed work will be required to identify commissioning issues
in the current market framework. No allowance has been made for any constrained
generation costs incurred for commissioning the new HVDC thyristor converter or
control systems.
• The real capital cost estimate reflects the costs from the perspective of an
investor today examining the economic commitment involved in a project from
a market benefit perspective. It has been prepared using mid-range cost
estimates, and excludes financing costs. The estimate is in real (constant)
terms and is expressed in 2005 dollars.
• The estimated nominal cost reflects the costs from the perspective of the
asset owner at the time the assets are commissioned, i.e. it reflects the value
that will need to be included in the regulated asset base and recovered
through regulated charges (including funding costs). The estimated nominal
cost figures also include allowances for variation in price and scope. Costs
are nominal (dollars of the day) at the time the project is commissioned.
Phasing of expenditure
200.00
180.00
160.00
140.00
Administration and Overheads
Engineering and Investigations
120.00
Project Management and Engineering costs
$million
Pole 1 Decommisisoning
100.00 Submarine Cables
AC Switchyard
80.00 Pole 2 Control System Replacement
New Pole 1 Converters
Environmental and Property
60.00
40.00
20.00
0.00
2005/06 2006/07 2007/08 2008/09 2009/10 2010/11 2011/12
Financial year begining July
The purpose of this section is to provide a bridge between the project capital costs,
and those that might ordinarily be presented in a business case. They are,
necessarily, indicative figures. As noted in Section 2, it is envisaged that detailed
design for the HVDC Converter replacement project will be carried out under some
form of “turnkey” or “engineer, procure and construct” contract. Such an
arrangement is likely to have a bearing on, amongst other things the design, timing
and currency of project expenditures, and therefore the magnitude of actual costs.
In short, this analysis should not be seen as a substitute for the scenario based risk
profiling which must take place during the next stage of project implementation.
Capital cost estimates been calculated in real (2005) dollars in order to maintain
consistency with the real discount rate used in the calculation of expected net market
benefits, to simplify the calculation of market benefits and costs and to provide
greater transparency in the comparison of the proposed transmission investment with
non-transmission investment options. The use of real or nominal costs should have
no impact on the outcome of the economic analysis in expected net market benefit
terms provided the treatment of inflation is consistent throughout the analysis.
Transpower wishes to recover the actual costs of the proposed HVDC investment.
The nominal cost estimate of $795 million including contingencies represents a good
faith estimate of what those actual costs might be. The $795 million is comprised of
$710 million in nominal capital costs (including interest during construction) with a
further $85 million nominal allowed for cost contingencies. Figure 7-1 below shows
the relative impact on major capital items.
Nominal $
300 Real $ (2005)
250
200
$m
150
100
50
0
Environment HVDC AC Submarine Control Dismantling Project
and Converter Substations Cables System Management and
Property Pole 1 Engineering Studies
Cost Cate gory
In preparing the capital cost estimates Transpower has used 5 year forward
exchange rates to reflect the rates at which the foreign currency denominated
components of the investment might be hedged.
Approximately 18% of the project costs are denominated in New Zealand dollars, and
approximately 3% in US dollars. The remainder of the project costs will be
denominated in the currency of the equipment supplier4.
While the exchange rates used in preparing Transpower’s cost estimates are forward
rates against which Transpower could hedge, it is important to understand the
sensitivity of estimated costs to changes in the exchange rate assumptions.
As an alternative to the forward rates assumed in the capital cost estimates, the NZD
was assumed to depreciate against the USD from 0.70 NZD per USD to 0.60 in
2010, with a similar level of depreciation against the other main currencies. Rates
used in the sensitivity are shown in Table 7-1 below.
4
For the purposes of undertaking this analysis these costs have been split equally between the Euro
and Swedish Krona.
Adoption of the alternate exchange rate assumptions reduced the nominal capital
cost of the HVDC Pole 1 replacement proposal by $5 million.
Interest during construction has been omitted from the capital cost estimates used in
the economic analysis because it is not consistent with the measurement of national
benefit5.
Transpower wishes to recover the actual costs of the proposed HVDC investment,
including a return on capital invested during the commissioning of the project. As
noted in Section 4, Transpower’s preference is to recover these costs during
implementation of the project. An estimate of the scale of nominal interest during
construction costs implied by the preliminary cost estimates has been prepared,
using a 10% pre-tax nominal discount rate6. This amounts to $131 million over the
period of project disbursements.
High level estimates of physical contingencies have been estimated for major
components of the capital spending using Monte Carlo simulation in conjunction with
the estimates provided in Section 3. Physical contingencies account for both quantity
and cost. Note however that these contingencies are not intended to cover variations
in design or specification.
Converters
5
In a national cost/benefit framework the opportunity cost of an investment to society is represented
though the discount rate. Interest during construction represents the opportunity cost of an investment
to providers of funds, and is in essence a value transfer paid by beneficiaries to investors to ensure that
the investment takes place. As a general principle such value transfers should net out of the economic
analysis.
6
This is consistent with the 7% pre-tax real discount rate applied in the economic test, adjusted for 3%
inflation.
AC Switchyards
7.4 Summary
Table 7-2 provides a summary of the various contingent amounts that have been
discussed in this section.
Real Cost Impact Exchange Interest Nominal Cost
excluding of Rate During Physical including
Contingencies Inflation Variation Construction Contingency Contingencies
$m 2005 $m $m $m $m $m
Engineering Studies 9 6 15
Environment and 2 0 0 1 3
Property
Transmission Works
HVDC Converter Pole 1 291 37 -2 67 61 454
AC Substations 52 5 -2 17 9 81
Submarine Cables 90 11 -1 23 15 138
Control System 10 2 0 1 13
Dismantling 5 1 0 1 7
Project Management 61 8 0 15 84
TOTAL 520 64 -5 131 85 795
Table 7-2: Relationship between Project Costs in Real and Nominal Terms.
The difference between estimated capital costs and nominal costs including
contingencies is approximately $275 million. However interest during construction
and inflation (which do not affect the economic merits of the project) represent $195
million of this difference. In real terms physical contingencies are 13% of capital
costs, but it should be noted that these cover only a limited number of potential
variations in project costs.
Transpower wishes to recover the actual costs of the proposed HVDC Pole 1
replacement investment. The nominal cost estimate including contingencies
represents a good faith estimate of what those actual costs might be. However,
given the substantial uncertainties at this time, it would be inappropriate to establish
a final set of project costs for recovery at this stage.