Chapter 05S - Decision Theory
Solutions
1. a. Maximax: Expand [$80 is the highest payoff]
b. Maximin: Worst payoffs:
Do Nothing: 50 [best of the worst payoffs]
Expand: 20
Subcontract: 40
c. Laplace: Average Payoff
Do Nothing 55 [indifferent between do nothing
Expand 50 and subcontract]
Subcontract 55
d. Minimax Regret
Low High Worst
Do Nothing 0 20 20
Expand 30 0 30
Subcontract 10 10 10 [best of worst]
2. a. Expected profit
Do Nothing $57 = 50 (.3) + 60 (.7)
Expand 62 [Best] = 20 (.3) + 80 (.7)
Subcontract 61 = 40 (.3) + 70 (.7)
.3
b. $50
$57 .7
Do Nothing $60
$62 .3 $20
Expand
.7
$80
$61 .3
Subcontr. $40
.7
$70
c. EPC: .30(50) + .70(80) = $71
Exp. Profit: 62
EVPI: $9
5S-1
Chapter 05S - Decision Theory
3. Equations:
Do Nothing: 50 + 10P Low High
Payoff 80 Payoff
Expand: 20 + 60P
70
Subcontract: 40 + 30P Do Nothing 60
Optimal ranges: 50
Do nothing: 0 to < .50 40 Subcontract
Expand: > .67 to 1.00
Subcontract: > .50 to < .67 20 Expand
4. a. 1) Draw the tree diagram:
0 .50 .67 1.0
Demand Low (.4) $400,000 (1)
Maintain $50,000 (2)
Build Small
2
Demand High (.6) Expand
1 $450,000 (3)
Demand Low (.4) $-10,000 (4)
Build Large
Demand High (.6) $800,000 (5)
2) Analyze decisions from right to left (i.e., work backwards from the end of the tree
towards the root). For instance, begin with decision 2 and choose expansion because it
has a higher present value ($450,000 vs. $50,000).
3) Compute the expected value of the ends of the remaining branches (numbered 1 to 5 in
the diagram), and then determine the expected value for the two initial alternatives.
(1).4 x $400,000 = $160,000
(2)(eliminated) $430,000 (expected value if build small is chosen)
(3).6 x $450,000 = $270,000
(4).4 x –$10,000 = $–4,000
(5).6 x $800,000 = $480,000 $476,000 (expected value if build large is chosen)
4) Since the expected value of building a large plant has the higher expected value, select
the large plant alternative.
5S-2
Chapter 05S - Decision Theory
b. Expected payoff under certainty: .4(400,000) + .6 (800,000) = $640,000
Expected payoff under risk: 476,000
Expected value of perfect information: $164,000
Low High
Payoff
800
Build Large
Build Large 450
400 Build Small
-10
1.0 .54 0
P (low)
c.
Low High
Payoff Payoff
800
Build Large
Build Small 450
400
-10
0 .54 1.0
P (high)
400,000 + 50,000 P (H) = 10,000 + 810,000 P (H)
760,000 P (H) = 410,000
P(High) = .54
If P (high) is between 0 and .54, build small.
If P (high) is between .54 and 1.0, build large.
or
If P (low) is between 0 and .46, build large.
If P (low) is between .46 and 1.0, build small.
5S-3
Chapter 05S - Decision Theory
Low Demand High Demand Slope Equation
Small 400,000 450,000 50,000 400,000 + 50,000 P (H)
Build
Large 10,000 800,000 810,000 10,000 + 810,000 P (H)
5. EVsubcontract= (.4)(1.0) + (.5)(1.3) + (.1)(1.8) = 1.23
EVexpand = (.4)(1.5) + (.5)(1.6) + (.1)(1.7) = 1.57
EVbuild = (.4)(1.4) + (.5)(1.1) + (.1)(2.4) = 1.35
Since 1.57 > 1.35 > 1.23, Expand.
6. MaxiMax MaxiMin Laplace Minimax
Alternative (a) Max. Payoff (b) Min. Payoff (c) Average (d) Regret
Renew $4,000,000 $500,000* $2,250,000 $4,500,000
Relocate $5,000,000* $100,000 $2,550,000* $3,900,000*
Decision: Relocate Renew Relocate Relocate
7. Alternative Expected Value
a. Renew 500,000(.35) + 4,000,000(.65) = $2,775,000*
Relocate 5,000,000(.35) + 100,000(.65) = $1,815,000
Decision: Renew lease
b.
Approve (.35) E.V.
$500,000
$2,775,000*
Reject (.65)
Renew $4,000,000
Approve (.35)
Relocate $5,000,000
$1,815,000
Reject (.65)
$100,000
c. EVPI = EPC – EMV
= .35(5,000,000) + .65(4,000,000) – 2,775,000 = $1,575,000
Yes, the manager should sign the lease for $24,000 since it is less than the EVPI of
$1,575,000.
5S-4
Chapter 05S - Decision Theory
8. a., b. Let P (application is approved) = x. Then P (application rejected) = 1 – x.
From 7(a)
500,000x + 4,000,000(1 – x) = 4,000,000 – 3,500,000x
and 5,000,000x + 100,000(1 – x) = 100,000 + 4,900,000x
The two alternatives are equally good when
4,000,000 – 3,500,000x = 100,000 + 4,900,000x
3,900,000
i.e. when x = = 0.4643
8,400,000
Exp.
Value
5
(millions) Renewal better than 5
Relocation 100,000 + 4,900,000x
4
Renew Relocate 4
For 8(a) and 8(b) the decision
3 should be to renew the 10 year
3 lease.
4,000,000 – 3,500,000x
2 2
Relocate
1 1
.5
x = .4643
P (application approved)
c. D = amount of decrease in $4,000,000 in order that EV= EV
EV– EV= $2,775,000 – $1,815,000 = $960,000
$960,000 = .65D
D = $1,476,923
$4,000,000 – $1,476,923 = $2,523,077
Range is $2,523,077 or more.
5S-5
Chapter 05S - Decision Theory
9. $ 42 .2(42)
46.8 .2 Low
.8 High 48 Subcontract
42 + 46.8
2
Expand Greatly
48 .8(48)
Small
53.6 44.4 .2 Low 22 .2(22)
Medium
1 .8 High Do Nothing
50 46 44.4
+
2
Expand 50
Large .8(50)
53.6
.2 Low (20) .2(-20)
.8 High + 53.6
72 .8(72)
a. Decision: Build a large facility.
b. Max (42;22;–20) = $42 million.
Decision: Build a small facility.
c. EPC = 42(.2) + 72(.8) = 8.4 + 57.6 = $66.0
EVPI = EPC – EMV = 66 – 53.6=$12.4
d. Let P(high) = x P(low) = 1 – x
I. Small: 42(1 – x) + 48x => 42 + 6x
II. Medium: 22(1 – x) + 50x => 22 + 28x
III. Large: –20(1 – x) + 72x => –20 + 92x
Value of x where expected value for I and III are the same.
42 + 6x = –20 + 92x => 86x = 62 => x = 0.7209
5S-6
Chapter 05S - Decision Theory
72
50
Small
42 48
Medium
22
Large
0 .721 1.0
-20 P (High)
10.
.30 low $90
do nothing
1
.7 high 90
buy 1
subcontract
2 110
buy 2nd
100
.30 low
75
buy 2
2
.70 high 130
EV1 = (.3) (90) + (.7) (110) = 104
EV2 = (.3) (75) + (.7) (130) = 113.5 Since 113.5 > 104
Decision: Buy 2 machines.
5S-7
Chapter 05S - Decision Theory
11. 1/3
0
1/3 60
1
1/3
90
50
49 .30 40
.50
4 44
Alternative A 60
.20
49 1/3
(45)
1/3
2 45
1/3 99
Alternative B 40
46 .30
40
.50
5 50
.20 30
1/2
45 40
3
EV1 = (1/3)(0) + (1/3)(60) + (1/3)(90) = 50 1/2
50
EV2 = (1/3)(–45) + (1/3)(45) + (1/3)(99) = 33
EV3 = (1/2)(40) + (1/2)(50) = 45
EV4 = (.3)(50) + (.5)(44) + (.2)(60) = 49
EV5 = (.3)(40) + (.5)(50) + (.2)(45) = 46
Since 49 > 46, choose alternative A.
12. 1) Draw the tree diagram:
Demand Low (.50) $700
Lease $100
Build Small
2
Demand High (.50) Expand
1 $500
Demand Low (.50) $40
Build Large
Demand High (.50) $2,000
5S-8
Chapter 05S - Decision Theory
Maximin:
The worst possible payoff for small would occur with expanding under high demand: $500k. The
worst possible payoff for large would be $40k for low demand. Hence, build a small warehouse.
Maximax:
The best possible payoff would occur with a large warehouse ($2,000k), so build a large warehouse.
Laplace:
Assume the probabilities of low and high demand to be .50 each. The expected payoffs would be:
Small .50($700k) + .50($500k) = $600k.
Large .50($40k) + .50($2,000k) = $1,020k.
Hence, build a large warehouse.
Minimax regret:
Small: Large:
Large = $2,000k Small = $700k
Small = $500k Large = $40k
$1,500k $660k
Hence, build a large warehouse.
13. Moderate High Very High Worst Best Average
Reassign 50 60 85 85 50 65
New Staff 60 60 60 60* 60 60 (tie)
Redesign 40 50 90 90 40* 60
a. Maximin: New staff
b. Maximax: Redesign
c. Regret table:
Moderate High Very High Worst
Reassign 10 10 25 25
New Staff 20 10 0 20*
Redesign 0 0 30 30
d. Insufficient reason: (tie) New Staff or Redesign
5S-9
Chapter 05S - Decision Theory
14. a. Reassign: .10(50) + .30(60) + .60(85) = $74
New Staff: .10(60) + .30(60) + .60(60) = 60*
Redesign: .10(40) + .30(50) + .60(90) = 73
b.
.10 Moderate
50
c. Opportunity loss table:74
Reassign .30 High
60
.60 Very High
Moderate High Very 85
High EOL
.10 Moderate
Reassign 10 10 25
60 19
New Staff .30 High
60 60 60
New Staff 20 10 0 5*
.60 Very High 60
Redesign 0 0 30 18
.10 Moderate
40
Redesign (.1) (.3)
.30 High (.6)
73 50
.60 Very High 90
5S-10
Chapter 05S - Decision Theory
At an expected cost of $60, the director should hire and train 2 additional staff members.
.10 Moderate
15. 50
Reassign .30 High
74 60
.60 Very High
85
.10 Moderate
Hire 2 60
Initially .30 High
60 60
.60 Very High
New Staff 60
60 60 .10 Moderate
40
.30 High (Hire 1) 75
74.5
Hire 1 .60 V. High (Hire 1) 80
Initially
.10 Moderate
40
Redesign .30 High
73 50
.60 Very High
90
Payoff Payoff
16. a.
#1 #2
140
120 B A
100
C B
80
C
A
40
0 1.0
P(#2)
5S-11
Chapter 05S - Decision Theory
b. Alternative C is lower than Alternative B for all values of P(#2), so it would never be
appropriate.
c. EVB = 120 – 40P; EVA = 20 + 120P. Solving, P = .625.
Therefore, choose Alternative A if P(#2) is greater than .625.
d. For P(#1), choose Alternative A, if P(#1) is less than .375 (i.e., 1.000 – .625).
17. a. [Refer to the diagram in the previous solution]
b. Alternative B is now the one that is never appropriate.
c. EVA = 20 + 120P; EV= 100 – 60P. Solving, P = .444.
Therefore, choose Alternative A for P(#2) less than .444, and choose Alternative C for
P(#2) greater than .444.
d. In terms of P(#1), choose A for P(#1) greater than .556 and C for P(#1) less than .556.
5S-12
Chapter 05S - Decision Theory
18. EV1 = 10 – 12P Payoff for Payoff for
contract 10 no contract
EV2 = 8 – 5P
EV3 = 5 – 0P #1
8 #2
EV4 = 0 + 7P 7
#2 #4
#3 5
5
#4
0 .286 .60 .714 1.0
Payof -2
Payof
.30 .80
f f
#1120 #2
A Profit 110
s
C
D
90 90
60
B
C 40
Costs A
20
10
0 .417 .75 1.0
P (#2)
5S-13
Chapter 05S - Decision Theory
19. EVA = 120 – 100P
EVB = 60 – 20P
EVC = 10 + 100P
EVD = 90
Note that in terms of
P(#1), .30 becomes .70, .80
becomes .20, .417
becomes .583, and .75
becomes .25.
Enrichment Model: Advanced Decision Tree Problems
In this section two additional decision tree problems are presented
1. Space engineers have three alternative designs for the configuration of a component for an
unmanned space shuttle. The space vehicle is likely to encounter one of four different
conditions, which have probabilities of occurrence as listed in the following payoff table with
the payoffs for each combination of design and state of nature. Additional data from previous
flights are available but will require additional expenditures to analyze. However, the project
director is confident that analysis of the data will clearly indicate which state of nature will be
encountered. What amount would be justified for the data analysis?
States of Nature
A B C D
Probability: .3 .4 .2 .1
Design 001 20* 10 10 0
002 15 10 0 40
003 10 20 30 30
* In $ hundreds.
2. Demand for movie rentals at a video store on Saturdays during summer months is related to
the weather. If it is raining, or if the chance of rain is greater than 50%, demand tends to
follow one distribution, whereas if it is not raining and the chance of rain does not exceed
50%, demand follows a different distribution. This is important to the video store because the
manager must decide early on Saturday how many employees to schedule for Saturday
afternoon and early evening.
The two distributions are:
P(Rain) > 50% P(Rain) 50%
Demand Probability Demand Probability
Low .10 Low .60
Moderate .20 Moderate .30
High .70 High .10
The regular staff can handle Low demand. Moderate demand requires two additional
employees, and High demand requires another two employees. The payoff table (profits in
$000) is
5S-14
Chapter 05S - Decision Theory
Demand
5S-15
Chapter 05S - Decision Theory
Moderate High
0 2 3 4
Extra Staff 2 1 4 5
4 0 3 6
a. Construct a tree diagram showing the payoffs for this situation.
b. Determine the number of additional staff needed for a rainy Saturday.
c. Determine the number of staff needed when the chance of rain is 20% for a Saturday.
1.
A B C D
Designs .3 .4 .2 .1 EMV EPC: .3(20) + .4(20) + .2(30) + .1(40) = 24
001 20 10 10 0 12
002 15 10 0 40 12.5
003 10 20 30 30 20 [best] EVPI = 24 – 20 = 4
Low demand
2
2. a. No additional staff Medium demand
1 3
High demand 4
Low demand
1
Two additional staff Medium demand
2 4
High demand 5
Low demand
0
Medium demand
3 3
Four additional staff High demand 6
Low demand (.1)
2
No additional staff Medium demand (.2)
1 3
b. High demand (.7) 4
Low demand (.1)
1
Two additional staff Medium demand (.2)
2 4
High demand (.7) 5
Low demand (.1)
0
Medium demand (.2)
3 3
Four additional staff
High
ma demand (.7) 6
our additional staff
d
EV1 = (.1)(2) + (.2)(3) + (.7)(4) = 3.6 (.2)
EV2 = (.1)(1) + (.2)(4) + (.7)(5) = 4.4
EV3 = (.1)(0) + (.2)(3) + (.7)(6) = 4.8
Since 4.8 > 4.4 > 3.6, hire four additional employees when it is rainy.
5S-16
Chapter 05S - Decision Theory
c. Low demand (.6)
2
No additional staff Medium demand (.3)
1 3
High demand (.1) 4
Low demand (.6)
1
Two additional staff Medium demand (.3)
2 4
High demand (.1) 5
Low demand (.6)
0
Medium demand (.3)
3 3
Four additional staff High demand (.1) 6
EV1 = (.6)(2) + (.3)(3) + (.1)(4) = 2.5
EV2 = (.6)(1) + (.3)(4) + (.1)(5) = 2.3
EV3 = (.6)(0) + (.3)(3) + (.1)(6) = 1.5
Since 2.5 > 2.3 > 1.5, hire no additional employees when the probability of rain is 20%.
5S-17