Modul Pre Filter OWS
Modul Pre Filter OWS
Modul Pre Filter OWS
MÓDULO DE PREFILTRO
PRE-FILTER MODULE
MANUAL DE INSTRUÇÕES
MANUAL DE INSTRUCCIONES
INSTRUCTIONS MANUAL
ENGLISH
PRE-FILTER
MODULE
INSTRUCTIONS MANUAL
Pre-filter Module
INDEX
PREFACE....................................................................................................... 5
INTRODUCTION ........................................................................................... 7
ZEPPINI SSAO....................................................................................... 7
PRE-FILTER MODULE ........................................................................... 9
INSTALLATION ............................................................................................. 12
ANCHORAGE ................................................................................................ 27
NECESSARY MATERIALS...................................................................... 27
EXECUTION PROCEDURE.................................................................... 27
OPERATION .................................................................................................. 29
MAINTENANCE ............................................................................................ 30
ANNEX ......................................................................................................... 32
Pre-filter Module
PREFACE
This manual aims to instruct the installers and operators of the Pre-filter
Module about the best installation and handling practices of the equipment.
The rigorous accomplishment of the instructions here contained warrants a
bigger durability of the equipment and a bigger easiness/reliability of its
installation.
We remember that the no accomplishment of any of the instructions here
contained will annul the product warranty.
USED ABBREVIATIONS
In order to facilitate the reading of this manual, some abbreviations are used,
like as:
5
Preface
USED SYMBOLS
Along this manual, you will found some symbols. Their meanings are de-
scribed bellow:
HINT
This symbol indicates that the following instructions can and
will facilitates the installation/operation of the equipment.
WARNING
DANGER
! This symbol indicates that the following instructions are of
extreme importance for the security of the involved people
and of the installation and/or operation of the equipment.
6
Pre-filter Module
INTRODUCTION
Nowadays, many commercial and industrial operations generate oily effluents.
This effluent type can generate environmental contaminations and therefore
needs of previous treatment. The Pre-filter Module is an equipment designed
for, in conjunction with the CSAO – ZP5000 to treat water resultant of this type of
process before to be thrown on the sewerage system or collected, according the
in force legislation, thus preserving the environment.
This equipment realizes a previous filtering of the served water in order to
supply to the CSAO, effluents with the smaller concentration of solid residues,
increasing the efficiency and durability of the entire SSAO system.
ZEPPINI SSAO
Although this manual treats only the Pre-filter Module, it is important to under-
stand that it is part of a bigger system called “Zeppini Water and Oil Separation
System” (SSAO). The more complete is the system, the bigger will be its effi-
ciency.
The Zeppini water and oil separator system is composed by the following equip-
ments: Affluent Collectors, Inspection Box with Filter, Pre-filter Module (MPF),
CSAO – ZP5000, and Oil Collection Module (MCO).
The served waters are, on the track operations, collected by the Affluent
Collectors (Track Gutters) and after passing by the Inspection Box with Filter
(where the debris like leaves and plastic bags are retained), it are thrown on the
Pre-filter Module for the removal of the solid sediments like earth and sand.
After this, they are thrown on the CSAO – ZP5000 that will separate the water and
the oil. The oil is directed toward the MCO and the treated water could be
directed for the sewerage or collected according to the in force legislation.
7
Introduction
For the good operation of the system it is necessary to dimension correctly the
served waters flow and to warrant the no emulsification (undue usage of
detergents with high concentrations, solvents, etc.) and whirling (purge of
pressure vases, etc.) of the served waters flow. On commercial and industrial
facilities that has areas for refueling and washing vehicles or parts, it is recom-
mended to have at least one independent CSAO for each area.
8
Pre-filter Module
PRE-FILTER MODULE
Oil
Output
9
Transportation, Storage and Reception
!
Store carefully the MPF, preserving it from impacts, sharpe-
ned objects and flexion.
Protect the MPF from the ultraviolet rays (UV) keeping it
stored on a protected place until the moment of its installa-
tion.
Don’t put heavy objects over the MPF.
Don’t remove the protective coating from the MPF until the
moment of its installation.
Transport the MPF on adequate vehicles and protected from
sharpened objects that could damage it.
When carrying the MPF, take care for don’t move it during
the transportation. If necessary, tie it, in such a way for
doesn’t deform it.
When transporting the MPF manually or with the aid of
machines, avoid impacts that could compromise its
structures.
10
Pre-filter Module
MPF COMPONENTS
3
4
5
6
7
9 8
6
5
11
Installation
INSTALLATION
NECESSARY TOOLS AND MATERIALS
For to install the MPF it’s necessary, at least, the usage of the following tools
and materials as described below:
1. Hack-saw frame
2. Saw for plastic material (PVC)
3. Cup Saw with diameter of 133 mm
4. Electrical drill
5. Adhesive for plastic tubes (PVC)
6. Sandpaper for plastics (PVC)
7. Spade
8. Hoe
9. Medium sand (according to the pit opening)
10. Type 1 stone
INSTALLATION PROCEDURE
The MPF installation is divided on 6 main phases, as follows:
!
Observe the procedures and security warnings described
along of the installation instructions.
12
Pre-filter Module
Step 1
Prepare a pit with rectangular shape and such dimensions that the dis-
tances between each one of the pit lateral walls are of .30 m.
1.52 m
0.3 m
1.52 m
0.3 m 0.3 m
0.3 m
1.1 m
0.2 m
13
Installation
Step 2
The pit depth must be such that, after to add a .20 m sand layer (as de-
scribed on the Step 4). The upper cover of the module must remain at a dis-
tance of .10 m to .60 m from the finished floor. For the pit depth adjustment, it
must be considered a fall between the served waters gutters and the MPF
entry of at least 2% related to its distance (L), according to the figure below.
On the cases where this dimension can’t be accomplished, please contact
the manufacturer.
2% x L
.
Step 3
Remove the earth removed from the place for an area away from the pit.
!
It’s important to use adequate material for grounding/filling
of the MPF pit. The local earth must be discarded and not
used with this purpose.
14
Pre-filter Module
Step 4
At the bottom of the pit, create a layer of gross sand with depth of .20 m for
the MPF deposition. Compact it hydraulically (the depth of .20 m must be
the layer final measure, after the compactness). For your reference, see the
step 1 figures.
15
Installation
Step 1
Position the MPF in order to keep a minimum distance between the MPF
side faces and the pit walls of .3 m.
Step 2
Be sure that one of the MPF faces is perpendicular to the effluents entry
network and the other face is perpendicular to the CSAO entry.
16
Pre-filter Module
!
Observe attentively the prescriptions of this manual about
the pit grounding/filling in order to don’t compromise the
MPF structure.
Step 1
Fill the MPF with clean water.
Step 2
Put the side covers and the central cover on the MPF.
Step 3
Make a .20 m layer of medium sand distributed evenly around the MPF.
Step 4
Compact hydraulically the sand layer put on the Step 3.
Step 5
Repeat sequentially the Steps 3 and 4 up to reach the MPF input and output
connections.
Step 6
Remove the covers and install the connections and tubing according to the
4th , 5th and 6th Phases and finalize the pit grounding/filling until the complete
tubing coverage.
17
Installation
Step 7
After the last sand layer, for a best finishing, put a type 1 stone layer around
the MPF up to the access cover level.
Concrete
Sand
6 thSand Layer
5 th Sand Layer
4 th Sand Layer
3 rd Sand Layer
2 nd Sand Layer
18
Pre-filter Module
19
Installation
!
The MPF must be installed under a sidewalk layer, since this
equipment isn’t designed for to support any type of traffic.
The equipment can’t remain exposed to the sunrays for
long time, with the risk of to compromise the resistance of
the material used for its manufacturing, could still, be
damaged during its installation or operation.
If the compactness procedure isn’t followed (3rd Phase), there
is the risk of collapsing or crack of the MPF.
The usage of mechanical compacters isn’t recommended,
due the risk of damaging the product.
After the end of the installation phase, make a general
cleaning of the entire system, removing any remaining
debris.
20
Pre-filter Module
Step 1
Define the MPF faces that will receive the input and output connections.
Step 2
Mark the positions to be drilled.
Step 3
Drill the MPF faces according to the defined on the Steps 1 and 2 using a
cup-saw (See specification on “Necessary Materials”).
Step 4
Install the Input Connection according to the Phase 5 of the installation
procedure.
Step 5
Install the Output Connection according to the Phase 5 of the installation
procedure.
21
Installation
Step 6
Install the EFR on the MPF and drill it with a cup-saw in a way that the drilling
remains aligned with the effluents entry connection (see specification on
“Necessary Materials”).
22
Pre-filter Module
Step 1
Put the sealing flange by the reservoir external side.
Step 2
Position the sealing ring by the internal side.
Step 3
Still by the internal side, thread the fixing nut on the flange in order for to
compress the sealing ring against the MPF wall, providing the assembly
tightness.
3 1
– Fixing Nut
– Sealing Ring
– Sealing Flange
– MPF Wall
23
Installation
Step 1
Clean the ends of the PVC tubes and connections in order to remove all the
dirty and oiliness existing. For to provide an efficient connection, apply an
even layer of plastic tube adhesive on the tubing ends.
Step 2
On the MPF affluent input connection, connect the 4 in. PVC tube coming
from the Affluent Manifold, following the connection instructions described
on the Step 1.
Step 3
Define the length and cut a segment of 4 in. PVC tube.
Step 4
Install the tube prepared on the Step 3 on the internal portion of the affluent
entry connection, following the connection instructions described on the
Step 1.
Step 5
Considering that output Collection Tube must remains at a distance of 10
cm from the MPF bottom, adjust the collection tube length according to the
output connection position (see figure).
24
Pre-filter Module
Step 6
Connect the output collection tube on the 4 in. x 90° elbow following the
connections instruction described on the Step 1.
Step 7
Connect the elbow on the internal portion of the MPF output connection
following the connection instructions described on the Step 1.
Step 8
Connect the extension tube on the external portion of the output connection
following the connection instructions described on the Step 1.
!
Be sure that hole made on the EFR is aligned with the
effluent entry hole.
Warrant that the MPF entry tubing hasn’t entered on the
EFR, as this will avoid the EFR removal, impeaching the
equipment operation and maintenance.
WARNINGS
Defects caused to the equipment due installation errors will not be
covered by the product warranty.
If some abnormality on the equipment is detected, contact Zeppini before
the product installation.
25
Anchorage
ANCHORAGE
The Pre-filter Module anchorage procedure is used when the equipment is
installed inside of masonry pit not stanch, there isn’t track over the equipment
or when it’s installed on locals that have elevated groundwater, for to warrant
the equipment stability on the ground.
NECESSARY MATERIALS
For to make the MPF anchorage is necessary the usage of the following
materials:
EXECUTION PROCEDURE
The anchored MPF installation is divided on 2 main phases, as follows:
26
Pre-filter Module
Step 1
Bent the portions of iron bar in an omega shape “?”.
Step 2
Fulfill the 5 liters moulds with concrete.
Step 3
Insert the bent iron bars on the superior portion of the moulds with concrete
still fresh in order to form the anchors hooks where it will be fixed the belt.
Step 4
Wait the concrete cure.
Step 1
Increase the pit depth in .3 m on the lateral portion between the pit wall and
the MPF, according to the figure.
27
Ancoragem
Step 2
Position the anchors on the pit bottom in order to align the fixing hooks for
the coupling of the polyester belt.
Step 3
Cover the anchors with sand and made the compactness, leaving visible
the hooks.
Step 4
Follow the Phase 2, Chapter “INSTALLATION” on the page 16.
Step 5
Execute the 4, 5 and 6 Phases, Chapter “INSTALLATION” on the pages 21,
23 and 24.
Step 6
Put the side covers on the MPF..
Step 7
Fixate the belts on the anchors hooks by the extremities in order to pass
over the module side covers according to the figure.
Step 8
Tension the belts through the turnbuckles on the hooks, two by two,
according to the figure bellow.
Step 9
Conclude the installation following the Phase 3 of the “INSTALLATION”
Chapter on the page 17.
28
Pre-filter Module
OPERATION
The MPF operation is summarized on the removal of solids coming from the
served waters, retained on the filtering element, what must be done according
the following sequence:
Step 1
Remove the MPF upper cover.
Step 2
Remove the EFR pulling it up by hand.
Step 3
Made the EFR cleaning removing the existing solids and taking care for to
the holes doesn’t become obstructed.
Step 4
Reinstall the EFR on the MPF case.
Step 5
Reinstall the MPF upper cover.
!
Keep the MPF cover always fitted and fixed to the case
avoiding the entry of the water coming from track to the
interior, causing overflow and possible earth contamina-
tion.
29
Maintenance
MAINTENANCE
The maintenance of this equipment consists on the verification of the
components integrity and on the cleaning of the debris existing at the bottom
according to the sequence:
Step 1
Block up the served water flow on the MPF entry.
Step 2
Remove the MPF upper cover.
Step 3
Remove the EFR pulling it up by hand.
Step 4
Remove the liquids and residues contained on the MPF interior and storage
it on stanch containers appropriated.
Step 5
Clean the MPF bottom removing the existing debris.
Step 6
Make a visual inspection on the side covers, on the EFR and on the MPF
case for to verify the existence of cracks, deformations or breakages that
could impair the system operation.
Step 7
Reinstall the EFR and the covers on the MPF.
Step 8
Return the served waters flow to the MPF.
Step 9
Through the collection gutters, return carefully the liquids and residues
stored before on the Step 4.
30
Pre-filter Module
!
When making the visual inspection, if any unconformity is
detected on the equipment, get in contact with Zeppini for
analysis and product repair.
31
Anexx
ANEXX
32
Rev.: 01 - Nov.13