UP Rajkiya v. Indure
UP Rajkiya v. Indure
UP Rajkiya v. Indure
MANU/SC/0362/1996
Decided On: 09.02.1996
Hon'ble Judges:
K. Ramaswamy, S. Saghir Ahmad and G.B. Pattanaik, JJ.
Subject: Contract
Subject: Arbitration
Catch Words
Mentioned IN
Acts/Rules/Orders:
Indian Contract Act, 1872 - Sections 3, 4, 7, 10, 31, 32 and 33; Arbitration Act, 1940 -
Sections 2 and 33; Constitution of India - Articles 125 and 126
Case Referred0:
Ramji Dayalwala & Sons (P) Ltd. v. Invest Import MANU/SC/0502/1980
Authorities Referred:
"Russell on Arbitration" [19th Edn.]
Prior History:
From the Judgment and Order dated 10.04.1992 of the Delhi High Court in O.M.P. No. 62 of
1987
Citing Reference:
ORDER
K. Ramaswamy, J.
1. Leave granted.
2. This appeal by special leave arises from the judgment and order passed on April 10, 1992
by the Delhi High Court in O.M.P. No. 62 of 1992.
3. The appellant filed an application under Section 33 of the Arbitration Act, 1940 [for short,
"the Act"] for declaration that there exist no agreement between the appellant and the first
respondent-Indure Pvt. Ltd. on the basis of which a dispute for a claim of Rs. 1,68,73,628
could be referred for arbitration as the agreement set up by the respondent was honest and
alternatively the dispute was not arbitrable under the agreement. Accordingly it sought
declaration to set aside the said agreement. The learned single Judge of the High Court in
the impugned order held that the draft agreement dated June 22, 1984 contains provision
for arbitration under Clause (14) and the appellant is bound thereby; consequently, the
arbitrators are entitled to arbiter the dispute.
4. The dispute arose in the backdrop of the facts that the U.P. State Electricity Board had
floated tenders for construction, supply and erection of mechanical equipment and
construction work including consultancy services. Last date for submission of the tender was
June 30, 1984. The appellant-Nigam, an Undertaking of State of U.P. had purchased tender
documents from the Board on February 6, 1984. The respondent approaches the appellant
for their joint participation to submit the tenders to the Board. In furtherance thereof,
negotiations were set on foot and they decided to enter into an agreement in that behalf
and ultimately draft agreement dated June 22, 1984 was sent to the respondent for
signature. The appellant did not sign the draft agreement. On June 27, 1984, the
respondent sent a counter-proposal deleting Clause (10) of the agreement suggested by the
appellant and materially altering Clause (12) therein after signing the same. The tenders
were submitted on June 30, 1984, i.e., the last date for submission of tenders; but before
negotiating with the Board on.
In February 23, 1985 the appellant had withdrawn the tenders. On February 25, 1985, the
respondent had offered in its letter to the Board agreeing to undertake the entire contract
by itself and offered to complete the formalities with the Board. Simultaneously, on March
3, 1985, the respondent sent a notice through its counsel claiming damages stating therein
that there was no arbitration agreement between the parties. On January 21, 1986, the
respondent had further sent a notice nominating an arbitrator an arbitrator on its part and
called upon the appellant to nominate its arbitrator. The respondent purported to have
exercised that right under Clause (14) of the draft agreement proposed by the appellant on
June 22, 1984 alleging that they had accepted the same by letter dated June 27, 1984. The
appellant by letter dated February 28, 1986 disputed the existence of the arbitration
agreement and also asserted that no concluded contract existed between the parties. It was
further stated therein that deletion of material Clause (10) of the draft agreement and
material alteration of Clause (12) constituted substantial modification of the draft
agreement and consequently it did not accept the counter-proposal of the respondent and
that, therefore, no valid agreement came into existence which was admitted by the
respondent in their letter dated March 5, 1985. The question of appointing an arbitrator on
their behalf did not arise. However, without prejudice to their right to claim that no valid
agreement, much less arbitration agreement, was in existence, they nominated an
arbitrator on their behalf to arbiter on the question "whether there existed any valid or
subsisting agreement between the parties and whether there existed any valid and binding
arbitration clause between the parties?" Since the arbitrator nominated by them expired,
the respondent was called upon the appellant to nominate another arbitrator. At that stage
the appellant filed above petition under Section 33 of the Act.
5. The High Court found that the respondent returned the agreement duly signed but after
deleting Clause (10) and materially altering Clause (12) thereof. There was no
communication by the appellant refusing or negativing the alternations made in the draft
agreement. Tenders were submitted on June 30, 1984 after receipt of the modified
agreement. Till March 1, 1986, the respondent had not received any communication
disowning the contract between it and the appellant. Clause (14) of the agreement
contained an arbitration clause for adjudication of the disputes. The withdrawal of the
tenders by the appellant caused damages as claimed by the appellant in the notice.
Therefore, the respondent called upon appellant to nominate their arbitrator to adjudicate
the dispute intimating in their letter appointment of the arbitrator on their part. From this
there emerged a concluded contract containing Clause (14) providing for arbitration for
adjudication of the disputes.
6. As stated earlier, the High Court came to the conclusion that from the correspondence
between the parties there emerged a concluded contract. After due discussion between the
parties draft agreement duly signed with official seal of the respondent affixed thereon, was
communicated to the appellant on June 27, 1984 which contained Clause (14) which formed
an integral part of the contract. The modifications suggested by the respondent were acted
upon by the appellant. At no point of time it was suggested by any communication that the
modifications were not accepted. On the other hand, tenders were submitted on June 30,
1984 for the joint participation of the appellant and the respondent. The respondent had
sent a bank Draft for a sum of Rs. 2 lakhs on October 29, 1984. "(1)t is clear that the
petitioner had accepted the agreement and in such an eventuality, the petitioner cannot
deny the existence of arbitration clause". "Therefore, from the conduct of the petitioner the
inference can be drawn that the agreement had come into force the moment it was signed
by the respondent and sent the same to the petitioner and the petitioner though did not
sign it but acted upon it which amounts to indirect acceptance".
8. From this factual matrix, the question arises : whether there emerged any concluded
contract pursuant to which the parties are bound by the terms and conditions of the tenders
submitted to the Board and for further performance? It is seen that the tenders were not
jointly signed by the appellant and the respondent but were unilaterally submitted to the
Board by the appellant and were later on withdrawn. There did not exist any concluded
contract between the Board and the appellant for the performance of the work as per terms
and conditions of the tenders floated by the Board. Under Section 32 it was a contingent
contract until it was accepted by the Board. In this background, the question emerges :
whether there is an arbitration agreement between the parties ? It is seen that Clause (14)
of the agreement [subject to the dispute whether it is arbitrable under Clause (14) which is
yet another issue with which were are not concerned] independently does not come into
existence unless there is a concluded contract pursuant to the proposal made by the
appellant on June 22, 1984 or a counter-proposal by the respondent dated June 26, 1984.
It is not the case of the respondent that there exist any such independent arbitration
agreement.
9. Shri R.F. Nariman, the learned Counsel for the respondent, therefore, contended that the
counter-offer made by the respondent amounts to acceptance by conduct of the appellant
and he placed reliance on paragraphs 53 [Acceptance by conduct] and 99 [Agreement in
principle only of the Chilly on Contract. Paragraph 53 provides that "an offer may be
accepted by conduct. For example, an offer to buy goods can be accepted by supplying
them; and an offer to sell goods, made by sending them to the offeree, can be accepted by
using them". The substance of paragraph 99 is that parties may reach agreement in
principle but the details may be worked out at a later date. There is no dispute to the
proposition of law but two factors have to be kept in mind, viz., when the counter-offer was
made by the respondent and whether the unilateral offer amounts to acceptance by
submitting the tenders by the appellant to the Board. We find that it does not amount to
acceptance of counter proposal. It is seen that admittedly, Clause (10) which thrusts
responsibility on the first respondent was deleted in the counter-proposal. In Clause 12, for
joint responsibility unilateral liability was incorporated. In other words the respondent
disowned its material responsibilities. Unless" there is acceptance by the appellant to those
conditions no concluded contract can be said to have emerged. It seen that the appellant is
a Government Undertaking and unless contract is duly executed in accordance with the
Articles of Association, the Appellant is not bound by any such contract. Shri Nariman
sought to rely on the passage from Palmer on Companies Law containing that it is an indoor
management between the appellant and its officers. When the negotiations were
undertaken on behalf of the appellant, the respondent was led to believe that the officer
was competent to enter into the contract on behalf of the appellant. When the counter-
proposal was sent, the appellant had not returned the proposal. Therefore, it amounts to
acceptance and thus concluded contract came into existence. We fail to appreciate the
contention. As seen, material alterations in the contract make world of difference to draw an
inference of concluded contract. The joint liability of the parties was made unilateral liability
of the appellant. Thereby, the respondent sought to absolve itself from the liability of
further performance of the contract with the Board. Similarly, Clause (10) which contains
material part of the terms for the performance of the contract with the Board was deleted.
Thereby, there is no consensus ad idem on the material terms of the contact which contains
several clauses. In the absence of any consensus ad idem on the material terms of the
contract to be entered into between the parties, there emerged no concluded contract.
Apart from the draft agreement and the counter-proposal, there is no independent-contract
for reference to arbitration. Clause (14) which is an integral part of the draft agreement
proposed by the appellant and the counter-proposal is the foundation for reference to the
arbitration.
10. Section 31(2) of the Act provides that notwithstanding anything contained in any other
law for the time being in force and save as otherwise provided in the Act, all questions
regarding the validity, effect or existence of an award or an arbitration agreement between
the parties to the agreement or persons claiming under them shall be decided by the Court
in which the award under the agreement has been, or may be, filed, and by no other Court.
Section 33 envisages that any party to an arbitration agreement or any person claiming
under him desiring to challenge the existence or validity of an arbitration agreement or an
award or to have the effect of either determined shall apply to the Court and the Court shall
decide the question on affidavits. Under the proviso, if the Court deems it just an expedient,
it may set down the application for hearing on other evidence also and may pass such
orders for discovery and particulars as it may do in a suit.
12. We find no force in the contention of Shri Nariman that the appellant had submitted to
the jurisdiction of the arbitrators and having nominated the arbitrator, they are estopped to
go back upon it. Acquiscence does not confer jurisdiction.
13. The arbitrability of a claim depends on the construction of the clause in the contract.
The finding of the arbitrator/arbitrators on arbitrability of the claim is not conclusive as
under Section 33, ultimately it is the Court that decides the controversy. It being a with
jurisdictional issue, the arbitrator/arbitrators cannot cloth themselves with jurisdiction to
conclusively decide the issue. In "Russell on Arbitration" [19th Edn.] at page 99 it is stated
thus :
It can hardly be within the arbitrator's jurisdiction to decide whether or not a condition
precedent to his jurisdiction has been fulfilled. It has indeed several times been said bluntly
that an arbitrator has no power to decide his own jurisdiction and in one case where rules of
an institution prepared to conduct arbitrations gave the arbitrator such power, the court will
ignore this when asked to enforce the award, and decide the question itself. However, an
arbitrator is always entitled to inquire whether or not he has jurisdiction. An umpire faced
with a dispute whether or not there was a contract from which alone his jurisdiction, if any,
can arise can adopt one of a number of courses. He can refuse to deal with the matter at all
and have the parties to go to court, or he can consider the matter and if he forms the view
that the contract upon which the claimant is relying and from which, if established, alone his
jurisdiction can arise is in truth the contract, he can proceed accordingly.
14. In "Law of Arbitration" by Justice Bachawat [2nd Edn.] at page 155 it is stated that "the
question whether matters referred to were within the ambit of clause for reference of any
difference or dispute which may arise between the parties, it is for the Court to decide". The
arbitrator by a wrong decision cannot enlarge the scope of the submission. It is for the
Court to decide finally the ambit of the clause in dispute or any clause or a matter or a thing
contained therein or the construction thereof. We, therefore, hold that the arbitrators
cannot cloth themselves with jurisdiction to decide conclusively the arbitrability of the
dispute. It is for the Court under Section 33 or on appeal thereon to decide it finally. The
appellant, therefore, is not estopped to challenge the action and to seek a declaration under
Section 33.
15. The clear settled law thus is that the existence or validity of an arbitration agreement
shall be decided by the Court alone. Arbitrators, therefore, have no power or jurisdiction to
decide or adjudicate conclusively by themselves the question since it is the very foundation
on which the arbitrators proceed to adjudicate the disputes. Therefore, it is rightly pointed
out by Shri Adrash Kumar Goel, learned Counsel for the appellant that they had by mistake
agreed for reference and that arbitrators could not decide the existence of the arbitration
agreement or arbitrability of the disputes without prejudice to their stand that no valid
agreement existed. Shri Nariman contended that having agreed to refer the dispute, the
appellant had acquiesced to the jurisdiction of the arbitrators and, therefore, they cannot
exercise the right under Section 33 of the Act. We find no force in the contention. As seen,
the appellant is claiming adjudication under Section 33 which the Court alone has
jurisdiction and power to decide whether any valid agreement is existing between the
parties. Mere acceptance or acquiescing to the jurisdiction of the arbitrators for adjudication
of the disputes as to the existence of the arbitration agreement or arbitrability of the
dispute does not disentitle the appellant to have the remedy under Section 33 through the
Court. In our considered view the remedy under Section 33 is the only right royal way for
deciding the controversy.
16. Since the tenders - the source of the contract between the parties -had not transformed
into a contract, even if the proposal and counterproposal are assumed to be constituting an
agreement, it is a contingent contract and by operation of Section 32 of the Contract Act,
the counterproposal of the respondent cannot be enforced since the event of entering into
the contract with the Board had not taken place.
17. In Ramji Dayawala & Sons (P) Ltd. v. Invest Import MANU/SC/0502/1980 :
[1981]1SCR899 , a two-Judge Bench of this Court considered the existence of the contract
and arbitration clause thereunder. This Court had held that in the facts of a given case
acceptance of a suggestion may be sub silentio reinforced by the subsequent conduct.
Where there is a mistake as to terms of a document, amendment to the draft was
suggested and a counter-offer was made, the signatory to the original contract is not
estopped by his signature from denying that he intended to make an offer in the terms set
out in the document. Where the contract is in a number of parts it is essential to the validity
of the contract that the contracting party should either have assented to or taken to have
assented to the same thing in the same sense or as it is sometimes put, there should be
consensus ad idem. In that case a sub-contract was signed and executed by the Managing
Director of the appellant-Company but part of the contract was altered subsequently since
counter-proposal was given by the respondent. This Court had held that one such case is
where a part of the offer was disputed at the negotiation stage and the original offeree
communicated that to the offeror saying that he understood the offer in a particular sense;
this communication probably amounts to a counter-offer in which case it may be that mere
silence of the original offeror will constitute his acceptance. Where there is a mistake as to
the terms of the documents as in that case, amendment to the draft was suggested and a
counter-offer was made, the signatory to the original contract is not estopped by his
signature from denying that he intended to make an offer in the terms set out in the
document; to wit, the letter and the cable. It can, therefore, be stated that where the
contract is in a number of parts it is essential to the validity of the contract that the
contracting party should either have assented to or taken to have assented to the same
thing in the same sense or as it is sometimes put, there should be consensus ad idem. It
was held that there was no consensus ad idem to the original contract. It was open to the
party contending novatio to prove that he had not accepted a part of the original agreement
though it had signed the agreement containing that part.
18. As found earlier, there is no signed agreement by a duly competent officer on behalf of
the appellant. The doctrine of "indoor management" cannot be extended to formation of the
contract or essential terms of the contract unless the contract with other parties is duly
approved and signed on behalf of a public undertaking or the Government with its seal by
an authorised or competent officer. Otherwise, it would be hazardous for public
undertakings or Government or its instrumentalities to deal on contractual relations with
third parties.
19. In view of the fact that Section 2(a) of the Act envisages a written agreement for
arbitration and that written agreement to submit the existing or future differences to
arbitration is a pre-condition and further in view of the fact that the original contract itself
was not a concluded contract, there existed no arbitration agreement for reference to the
arbitrators. The High Court, therefore, committed a gross error of law in concluding that an
agreement had emerged between the parties, from the correspondence and from
submission of the tenders to the Board. Accordingly it is declared that there existed no
arbitration agreement and that the reference to the arbitration, therefore, is clearly illegal.
Consequently arbitrators cannot proceed further to arbiter the dispute, if any. The
conclusion of the High Court is set aside.
20. The appeal is accordingly allowed with costs quantified at Rs. 15,000.