Project Management - Destiny Case
Project Management - Destiny Case
Project time 43
Total Slack 31
Notes:
Total time for project move will be from April 27 to December 21 ~34weeks
Highlighted fields in yellow reflect the critical path
Slack=
Earliest Latest Latest (LS-ES) or
Finish Start Finish (LF-EF)
4 0 4 0
14 4 14 0
12 6 14 2
30 17 33 3
30 14 30 0
28 19 33 5
32 33 35 3
34 39 43 9
33 35 36 3
39 36 42 3
40 42 43 3
42 30 42 0
42 30 42 0
43 42 43 0
43 43 43 0
Estimated After
Immediate Time crashing time
Activity Description Predecessor (weeks) (weeks)
A Finalize lease - 4 4
B Obtain Permits A 10 10
C Zoning approval A 8 8
D Electrical and pneumatic construction B,C 16 16
E Quality/supervisor pod construction B,C 16 13
F Anodizing line installation B,C 14 14
G Machine shop equipment removal and reinstallation D,F 2 1
H Climate controlled proving room construction E 4 4
I Assembly relocation G 1 1
J Paint line relocation I 6 1
K Auxiliary equipment J 1 1
L Office construction E 12 6
M Information technology services E 12 6
N Office move L,M 1 1
O Project end H,K,N 0 0
Project time 34
Slack Remaining 7
Used-up Slack 24
Slack=
Earliest Earliest Latest Latest (LS-ES) or
Start Finish Start Finish (LF-EF)
0 4 0 4 0
4 14 4 14 0
4 12 6 14 2
14 30 14 30 0
14 27 14 27 0
14 28 16 30 2
30 31 30 31 0
27 31 30 34 3
31 32 31 32 0
32 33 32 33 0
33 34 33 34 0
27 33 27 33 0
27 33 27 33 0
33 34 33 34 0
34 34 34 34 0