Arup Journal - Issue 1 - 2018
Arup Journal - Issue 1 - 2018
1.
4
First held in 1906, the Cross Harbour in 1994 and was completed in 2001. The
Swim across Hong Kong’s iconic Victoria second stage, renamed the Harbour Area
Harbour was one of the city’s most Treatment Scheme (HATS), led by Arup,
celebrated sports events until it was started in 2007 and was commissioned in
halted in 1978 because the water was December 2015. The quality of this stretch
deemed unfit for swimming. of water has improved to the extent that in
2011 the beaches reopened and, last year,
At the time, up to 2 million m3 of sewage, the authorities declared the water in the
with only a very minimal level of treatment, harbour clean enough to resume the Cross
was discharged straight into the harbour Harbour Swim along its original route.
every day, with serious consequences for
the water quality in the harbour. As well as In October 2017, against the backdrop of
the swimming race being stopped, nearby the city’s famous skyline, almost 3,000
sandy beaches, such as Hong Kong’s Gold people took part in the race, swimming from
Coast near Tuen Mun, had to be closed Tsim Sha Tsui Public Pier on the Kowloon
down to bathers. Peninsula to Wan Chai Golden Bauhinia
Square Public Pier on Hong Kong Island.
The upgrading of the city’s main sewage
treatment system was required to meet both Ambition
the existing and the future demands of The aim of the HATS was to collect
Hong Kong. The largest environmental sewage – previously discharged into
infrastructure project in the territory’s the Victoria Harbour with only minimal
history, the Strategic Sewage Disposal treatment – from both sides of the harbour
Scheme was proposed in the late 1980s. and channel it into a centralised sewage
The first stage of the scheme commenced treatment works on nearby Stonecutters
1: Stonecutters
Island Sewage
Treatment Works,
located in Victoria
Harbour
2: The annual Cross
Harbour Swim was
halted in 1978 owing
to the poor water
quality in the harbour
2.
Kwai Chung
Tsing Yi
Outfall
system
Kwun Tong
Cyberport
Island. There it would be processed in built up over more than 20 years designing 3: As part of HATS 2A eight existing preliminary
one of the largest treatment facilities of water treatment plants in the UK. treatment works were upgraded and connected
its kind. Stage 1 of the project provided via new tunnels. The partially treated water is
treatment for about 75% of the sewage Awarded the contract in August 2007 by transferred to SCISTW via a tunnel running under
the harbour
from urban areas around the harbour, the Hong Kong Government’s Drainage
with an average dry weather flow (ADWF) Services Department, Arup’s commission
of 1.7 million m3 per day. included civil, mechanical, electrical,
geotechnical, tunnelling, hydraulic
Stage 2A was a commission to treat the modelling, process, environmental, control
remaining 25% of Hong Kong’s sewage, and automation engineering, as well as
bringing the treatment capacity up to a programme and project management. preliminary treatment works that carry
2.45 million m3 per day average and a out initial screening of the sewage were
4.1 million m3 per day peak flow. This Arup’s design included modelling the upgraded and connected via new tunnels
was achieved by taking all sewage from complete hydraulic system to optimise running along the western and northern
the Victoria Harbour area to the upgraded the waste water collection and conveyance coasts of Hong Kong Island.
Stonecutters Island Sewage Treatment Works across the harbour, as well as the upgrade
(SCISTW) for chemically enhanced primary of the treatment works on Stonecutters The overall treatment process when finally
treatment (CEPT) and disinfection. Island, including the design and construction commissioned collects sewage from around
of one of the world’s largest underground Victoria Harbour to be treated at the
Arup tendered for Stage 2A of the project on pumping stations. As part of the project, preliminary treatment works, removing
the basis of the firm’s extensive experience eight of the existing Hong Kong Island large solids, before travelling via tunnels
6
4: The Stonecutters Island site (shown in 2008) is
located adjacent to two other Arup projects: the
Stonecutters Viaduct and Stonecutters Bridge
5: Plan of the upgraded SCISTW
Challenges
In addition to designing the complex system
of sewage treatment works, Arup had to
ensure the construction programme allowed
4.
5.
Pumps Pumps
˜ 20m
˜ 40m
Side
chamber
6: Plan and section of the pumping station, infrastructure and detailing how the When designing such facilities, a tunnel of
which has a volume equivalent to 38 standard contractors should phase the construction. this shape (forming an inverted siphon) is
swimming pools generally avoided because waste can settle
Hydraulic system at the bottom. To ensure that did not happen,
After the initial screening, the partially the tunnel was sized so that the waste water
treated sewage drops down 120m through velocity was fast enough to exit from the
shafts at each treatment works, entering riser shaft at the Stonecutters Island end
a tunnel that crosses below the harbour, without solids settling in the tunnel along
before coming up through a riser shaft into the way. The system also needed to cope
the project to proceed in stages to ensure the the pumping station on Stonecutters Island with large differences in flow rates between
system could remain online at all times, as for treatment prior to discharge into the summer and winter months. With wet
there could be no interruption to the operation harbour. Arup modelled the hydraulic weather in the summer, resulting in high
of Hong Kong’s existing sewerage systems. system for sewage transportation from flow rates of water, and dry winters resulting
Hong Kong Island to Stonecutters Island in the opposite, Arup designed the system so
Upgrading the existing extremely congested (with the tunnel design by others). that the velocity of flow stayed within
facility on Stonecutters Island also presented acceptable parameters all year round, with
difficulties. In the 1990s, the island was The design challenge was to ensure the minimal overflow. These two constraints
expanded through land reclamation, waste water could travel to Stonecutters meant the tunnel had to be narrow enough to
connecting it to the mainland. Arup had Island through the tunnel without backing maintain a flow of sufficient velocity to keep
to find a way of increasing the capacity up or overflowing at the preliminary works the tunnels clean during the drier months,
of the sewage treatment works within the and without solids dropping to the bottom taking into account the inverted siphon,
existing site boundaries. of the tunnel floor. Typically, sewerage but wide enough to not overflow during the
works use gravity to keep the flow of waste wetter months. To establish the most
Working closely with the client, Arup constant, with the treatment works located efficient and cost-effective diameter for the
proposed a procurement strategy to suit the at a lower level than where the waste tunnel, Arup developed an extensive
capabilities of both local and international originates. In Hong Kong, however, this was hydraulic model of the complete system for
design and build contractors. Detailed not possible: the tunnels had to be deep both existing and future treatment volumes
planning was required on the placement enough to go under the harbour and below in Hong Kong. This included modelling the
of various elements of the plant, designing the foundations of the buildings on the Stage 1 systems of 23.6km of underground
how they would fit with the existing shoreline of Hong Kong Island. tunnels, which collected sewage from
8
Kowloon and the north-east of Hong Kong
Island, as well as the proposed upgrades as
part of Stage 2A.
9.
9: Arup’s solution for the effluent tunnel and model of the final system. This allowed the combining the effluent tunnel and
disinfection facility significantly reduced excavation to commence early ahead of conveyance system within the same 8.5m
excavation and construction costs the awarding of the main contract, helping diameter, 90m deep, 880m long tunnel, with
to speed up the overall project programme. disinfection taking place along the tunnel.
It was constructed using drill and blast
Effluent tunnel and disinfection facility techniques, advancing on two faces from
To minimise pollution levels in the drop and riser shafts. By disinfecting the
discharged water, Arup used a computational effluent in the tunnel, it eliminated the need
fluid dynamic model to determine the to construct an above-ground chlorine
A priority was given to the efficiency of the required contact time for the treatment contact tank (originally sized at 174m x
pumps to minimise electricity consumption. chemicals. Arup also designed a cost-saving 34m x 14m and proposed to be located
The detailed design for the diaphragm walls solution using the outfall tunnel as the close to a piled viaduct). This significantly
of the underground portion of the pumping chlorine contact tank.
station was carried out early in the project,
rather than as part of the main contract Originally, the proposal was for a
works. The pump station was sized to ensure conventional arrangement for disinfection
it would be large enough to accommodate comprising a short effluent tunnel with a
the equipment of any contractor. To prove large above-ground combined chlorine
the concept, Arup developed the design contact tank and dechlorination facility with
within a 3D digital model, with Hong Kong connection culverts. Instead, Arup
University building a 1/15th physical scale developed a more efficient solution
10
14.
reduced excavation and construction costs. of the pumping stations as and when the risk of water entering the TBM launching
It also released valuable space above ground maintenance is required on the other. The chamber. To minimise the potential flood risk,
for development. tunnel has a 3.9m internal diameter, is 250m a series of holes were drilled from the surface
long and is at a depth of 30m. The tunnel to approximately 30m below ground level,
The design for this aspect of the scheme was constructed using a slurry type tunnel with the ground chilled to -10°C for several
achieved a saving of 40% in lifecycle boring machine (TBM), supplemented weeks until the groundwater froze. The TBM
costs and significantly reduced the by a state-of-the-art specialist ground was launched through the frozen ground,
environmental footprint. freezing technique for the TBM break-in preventing any flooding of the launch
and break-out. chamber. This was a novel construction
Other works method for Hong Kong at the time.
At SCISTW, Arup designed an The treatment works are located in an area
interconnecting tunnel between the existing that has a very high water table and is As part of the project, each of the
and new main pumping stations. This allows adjacent to the sea. It was therefore essential preliminary treatment works on Hong Kong
flexibility to divert flows through just one for measures to be put in place to minimise Island was upgraded to increase the capacity
13.
12
18.
discharged waste on the marine environment day, which makes it one of the largest CEPT project, delivering it on time and
were monitored by an independent plants in the world. The 10.6ha plant serves within budget. Since completion, Arup
inspector, with the results made public on 5.7 million people on both sides of Victoria has expanded its water business in East
the project’s webpage. Harbour – equivalent to 70% of Hong Asia, using the HATS project – and its
Kong’s population – processing 900 million innovative use of data and computer
Future-proofing m3 of sewage per year. modelling on the project – as a reference
With demographic shifts and the impact of to develop sewage treatment projects
climate change, Hong Kong’s needs for Arup was able to draw on both local elsewhere in Hong Kong, as well as
sewage treatment will change. To future- and international expertise to design in mainland China, Singapore and
proof the project, Arup’s role included and manage this large-scale, complex the Philippines.
predictive work on flows and loads in the
treatment works. This entailed working
with the Planning Department of the
Government of the Hong Kong Special Authors Bernard Cheng, Anson Cheung, Eric Cheung,
Administrative Region to understand its David Pickles was Project Manager managing Carrie Chu, Daniel Chu, Corey Fan, Arlene
development plans for the next few the overall technical design on the project. He is Goode, Raymond Sy Guan, Gary Hung, Lewis
decades, as well as looking at historical a Director in the Leeds office (formerly in Hong Hwoi, Jeff Ip, Mark Knowles, Anil Kumar, Andrew
Kong). Lai, David Lai, Gabriel Lai, King-Chak Lai,
data, potential land use, industrial growth,
Antony Lau, Jak Lau, Michael Lau, Vicki Lau,
projected population change and the impact Fergal Whyte was Project Director. He is a Lawrence Lee, Donald Leung, Rex Li, Ronald Li,
of climate change with increased rainfall. Director in the Hong Kong office, a member of Yuvi Luo, Edwin Mak, Louis Mak, Wilson Mak,
This work means the system is designed to the Arup Group Board and is the firm’s Director Nick Ng, Tin-Chi Ngai, David Pickles, Dora
be resilient until at least 2030. of Health, Safety and Wellbeing. Shum, Franki So, Monique So, James Sowden,
Jeremy Sparrow, James Sze, Stanley Sze, Lara
The success of the HATS project has been Project credits Tang, Ted Tang, Paul Taylor, Simon Tsang, Iris
widely recognised, both by the government Client Drainage Services Department, Hong Tse, Simon Tso, Shanshan Wang, Fergal Whyte,
and the community in Hong Kong. It has Kong Government Billy Wong, Peter Wong, Jenny Yip, Simon Yu.
won local and international awards, including Civil, Mechanical, Electrical, Geotechnical,
Tunnelling, Hydraulic Modelling, Process, Image credits
the Global Water Awards, the British
Environmental, Control and Automation 1, 3, 4-7, 9-16: Arup
Construction Industry Awards, the Tien Yow Engineering, Programme and Project 2: CY Yu/South China Morning Post
Jeme Engineering Prize in China and the ICE Management Arup: Gamini Ananda, Bill Au, 8: Sun Fook Kong
Edmund Hambly award for sustainability. Kitty Au, Robert Bates, Agnes Chan, Alan Chan, 17: Image under licence from Shutterstock
Albert Chan, Chris Chan, Ivan Chan, Paul Chan, 18: Sam Tsang/South China Morning Post
The upgraded Stonecutters Island facility Sing-Wa Chan, Siu-Yuen Chan, Andy Chee,
now has a capacity of 4.1 million m3 per
1.
14
A silo in form only
Advanced engineering transformed an abandoned 90-year-old grain
silo complex into a cultural hub and the jewel in the crown of Cape
Town’s bustling V&A Waterfront district
Authors Francis Archer and Tessa Brunette
3.
16
It became apparent that by re-sleeving the complex glazing design. A series of pillow-like surface of a sphere proved unsatisfactory.
retained silo walls with a new inner skin of faceted windows was proposed, bulging out of Turning to a more principle-based approach,
reinforced concrete, all of the structural the building where existing infill masonry could Arup established a series of geometric rules
challenges could be solved. be removed in between the structural grid of – horizontal and vertical planes meeting at the
concrete-encased steel; both along the top rim same focal point – intersected by a sphere to
A new 250mm layer was cast directly against of the storage annexe and upwards on all sides create the bulging pillow shape. The primary
the original concrete, which was used as a of the working house. The architectural concept constraint was to keep the whole length of each
one-sided shutter. In addition to holding in was inspired by the convex glass elements of of the main vertical and horizontal framing
place all the retained original walls, the lanterns, where glass is blown out of gaps in a members in one plane so that they could be
re-sleeved perimeter walls also supply the grid. These delicate elements would contrast made with flat steel bars that would intersect
vertical load path for the new gallery floor against the bulk of the concrete frame and neatly at the nodes in a way that made welding
slabs and act as shear walls resisting lateral refract the light as it entered the building. possible. Arup turned to parametric design
loads. Above the atrium the overflying using Grasshopper, a visual programming
re-sleeved cylinders were connected to each Arup had to find a way of realising these language for the Rhinoceros 3D computer-aided
other via reinforced shear keys through the elements in a pragmatic, cost-effective and design software. By programming a script using
retained original concrete, creating a spanning buildable manner. Working with Heatherwick the geometrical rules with an interface that gave
portal structure. Studio, this process began by determining the the architects complete control to manipulate
optimum number of facets for each ‘pillow’ the projection of each node and the main joint
Arup’s solution allowed the architectural window. The greater the number of facets, the lines, each possible solution was already
design to be practically realised, while still more complicated the fabrication process. pre-tested for viability. This allowed a specific
retaining the building’s grandeur and Fewer facets would overly simplify the aesthetic geometry to be developed for each of the five
authenticity, and displaying the inner intent and lose the delicate yet industrial different window designs, but with the same
workings of the original building. appearance that was desired. The number settled patterns and overall constraints.
on was 56 facets as the optimum balance
Foundations between appearance, cost and buildability. This iterative parametric tool locked in the
Prior to excavation there were plans to add necessary structural constraints for fabrication,
additional short piles down to the bedrock A parametric solution allowing for Heatherwick Studio to experiment
under the new internal columns. However, Arup experimented with a range of methods to with multiple iterations, each of which had
during the excavation stage the original 3m conceptualise the windows. An initial attempt to effectively been pre-assessed for viability,
deep raft structure was found to be more project the architectural geometry onto the reducing the time and cost required to
robust than expected. This meant new
foundations did not need to be built, offering
a significant cost saving.
5: Isometric view showing the carved-
The working house out atrium and silo demolition
The structural independence of the working
house tower from the storage annexe was
maintained in the redevelopment. With large
sections of the original perimeter walls that
supplied the stability for the tower removed,
both at ground level and high up on the hotel
floors, new stability cores were constructed
containing stairs and lifts.
6.
7.
Fabrication
The final window design comprised a frame
9.
made of slender flat steel 500mm by 160mm
bars welded together at central nodes. Rather
than aluminium, steel was chosen for the frame,
allowing for very slender members to minimise
the frame’s visible bulk, while still maintaining
6 & 7: Each pillow
strength and allowing for welded connections.
window was handmade
in a sequence devised
by Arup and the Fifty-six small triangular insulated glass units
subcontractor to were structurally bonded to an aluminium
ensure loads were glazing bar that was fixed to the steel frame.
distributed evenly Double-glazing and high strength structural
8: Arup designed the silicone seals provide a high level of acoustic
window lifting bracket so performance, and reduce the noise entering the
each window could be building from the working harbour outside.
fitted to a tight tolerance These seals were sized specifically to take
9: One of the account of the climatic pressure brought about
windows in situ by the small double-glazed triangular shapes.
8.
18
The next step was to build the windows. In 10 & 11: The silo bins
contrast to the digitalised design process, the were topped with
manufacturing stage called for craft skills; skylight windows that
each element was to be cut and welded form the floor of the
rooftop sculpture
together by hand. Arup communicated the
garden. Bespoke
design intent to a high level of detail before
artwork made of ceramic
tender by using the 3D models produced frits was printed onto
through the parametric process. This allowed the glass. The pattern
the design intent model and the shop drawing controls light levels in
model to be reviewed and compared in a 3D the atrium and also acts
virtual environment, rather than using 2D as an anti-slip measure
drawings. This lessened the possibility of
errors. A local subcontractor, Mazor
Aluminium, came on board in 2015 to deliver
Arup’s prescriptive design.
Authors Executive architects Van der Merwe Miszewski Khan, Jacob Knight, Adam Lane, Adam Ozinsky,
Francis Archer was Arup’s lead structural Architects, Rick Brown & Associates Architects, Guillermo Martinez Pajares, Pine Pienaar, Martin
engineer on the project during the scheme Jacobs Parker Radley, Gianluca Rapone, Rui Rodrigues, Rudolf
design phase and is an Associate Director in Electrical engineer Solution Station Le Roux, Vanesh Seganathirajah, Jolyon Smith,
the London office. Quantity surveyor MLC Surveyors Nic Smith, Con Strydom, Michael Stych,
Project manager Mace Innocent Svodziwa, Calvin Taylor, Matilde Tellier,
Tessa Brunette was involved in the project from Main contractor WBHO Max Walker, Manja Van De Worp.
concept stage as the overall design manager Façade, mechanical and wet services
and led the façade design during the engineer Arup Image credits
construction stage. She is a Senior Façade Structural engineer Arup and Sutherland 1, 3, 4, 6-12, 14: Arup/Tessa Brunette
Designer in the Cape Town office. Arup: John Abbott, Francis Archer, Rossouw Van 2: V&A Waterfront
Der Bank, Willem Bosman, Michael Bradbury, Ian 5: Arup
Project credits Braithwaite, Charlotte Briggs, Tessa Brunette, 13: InfrastructurePhotos
Client V&A Waterfront, Cape Town, Ryan Collins, Gaye Dalton, Naeem Ebrahim,
South Africa Simon Gill, Terence Govender, Philip Guthrie, Ed
Design architects Heatherwick Studio, London Hoare, Ben Jones, Darren Kent, Shaai-Qah
20
The masterplan
f Façades
s Sustainability
m Mechanical
w Wet services
s Structural
* Full multi-
disciplinary
services to
scheme design
13.
Collaborative science
The Francis Crick Institute is one of the largest biomedical facilities in
Europe, created by bringing six of the UK’s top scientific institutes together
under one roof
Authors Steve Berry, Andrew Harrison, Clodagh Ryan, Richard Smith, Catherine Wells and Julie Wood
1.
22
The Francis Crick Institute is one of the
world’s leading biomedical discovery
institutes. Its research focuses on why
diseases develop and how they can be
prevented, diagnosed and treated.
3: General cross-
section through the
building showing
plant and laboratory
layout
4: A full-scale
laboratory mock-up
created off-site for
user group testing
5: A finished
laboratory in use
by scientists
4. 5.
24
The services in the general laboratory areas
were designed to operate as a Containment
Level 2 area. Higher containment levels are
located in dedicated areas. The write-up/office
areas are located outside the laboratories.
9.
26
facilities are still subject to considerable scope, also needed to be completed and Conclusion
scrutiny by the Home Office and various external approvals obtained from the Health Francis Crick’s Nobel Prize showed how
government agencies. These facilities have and Safety Executive, the Home Office and collaboration between disciplines can
significant ventilation requirements and were the local authority, to allow occupation. significantly aid scientific research. The
designed to be capable of achieving 20 air Arup developed a comprehensive handover Francis Crick Institute continues to foster
changes per hour. plan that set out detailed requirements to this collaborative spirit, both in terms of the
be achieved by the contractor prior to layout of the building, and in the way the
These facilities incorporate stringent odour practical completion, as well as the project team worked together to project
control and ventilation regimes. Odour interfaces with the client-supplied manage, design and build the institute. The
modelling was conducted using numerical and equipment and provisions for client project team’s collaboration has also reaped
empirical testing of facility waste and feed inspections, familiarisation and training. rewards: the institute has secured BREEAM
materials on exhaust streams. This was incorporated in the construction Excellent accreditation, a particularly
contract to minimise risk and allow a notable accolade given the nature and size
As the facility accommodates advanced successful handover. of this heavily serviced building.
scientific equipment, including electron
microscopes, temperature control was
required to within ±0.1°C over a period of one
hour while maintaining airflow at low Authors Anna Coppel, Marc Crompton, Tim Crow, James
velocity. This was achieved by designing a Steve Berry was the Project Manager and the Davison, Grzegorz Delikat, Jennifer Dimambro,
specialist three-stage air conditioning system. building service design team lead. He is an Vipul Dudhaiya, Ryan Dunne, Mike Durtnall, Sam
Associate Director in the London office. Dust, Adam East, Mike Ebsworth, Stuart Edwards,
Controlling costs Max Eyre, Bronwyn Field, Elizabeth Fletcher,
Richard Foster, Malcolm Fullard, Rafal Gawlowski,
Comprehensive value engineering studies Andrew Harrison was the Project Director for
Steve Gilchrist, Jerell Gill, Vullnet Gjakolli, Ben
were led by Arup, together with the the building services element of the project. He is
Glover, Artur Gorlovsky, Milan Graovac, Blair Gray,
contractor, Laing O’Rourke. These a Director in the London office and the firm’s
global science and industry business leader. Tony Greenfield, Ross Griffiths, Amaury Guillais,
demonstrated the value of a pre-assembled Shane Haines, Kori Hamilton, Andrew Harrison,
modular approach to much of the building Clodagh Ryan led the project management Naveed Hassan, Mike Hastings, Malcolm Heath,
services owing to the challenging construction services related to the building services. She is David Hewlett, Simon Humphreys, John Hunt, Jay
programme and constrained site. Arup worked an Associate Director in the London office. Hussain, Helen Jackson, Lucas Janssen, Richard
with the contractor to accommodate the Jeffs, Rishi Jobanputra, Chris John, Ian Johnson,
modular construction, factoring this into early Richard Smith was the lead mechanical Andrew Jones, Mario Kaiser, Pawel Karwat,
designs and reviewing proposals. engineer and is an Associate Director in the Joanna Kennedy, Peter Kinson, Simon Lee, David
London office. Lester, Mark Van Lith, Gareth Lloyd, Jenna Lobb,
Michael Lorimer, Jacek Madej, Andrew Marks,
Arup used a comprehensive 3D model, which Thomas Marr, Nazir Mawjee, Keith Mccall, Laura
was passed to the contractor to assist them. Catherine Wells was the Project Manager for
Mccann, Andrew McConachie, Ross Mills, Rayna
This was used for clash detection and routing, the overall project management and contract
Mistry, Kalpana Nepaul, Claudia Newsam, Pamela
administration element. She is an Associate
as well as to review how the services would be Nwaneri, Oliver O’Brien, Ed Oelman, Sebastian
Director in the London office.
installed – critical for such a heavily serviced Oleksiak, Alberto Padilla-Peinado, Jessica Parsley,
building. This information was tagged to assets Julie Wood was Project Director for the overall
Steve Pennington, James Perou, Charlotte Perry,
within the building and given to the client’s project management and contract administration
Hugh Pidduck, Mathura Ponnuthurai, Garry Porter,
Facility Management team at handover. element. She is a director in the London office
Anthony Proctor, Simon Rainsbury, Craig Reid,
Daniel Reid, Marcin Rerak, Charles Richardson,
and the firm’s global skills leader for programme
Kat Roberts, Michael Roberts, Alice Robertshaw,
The contractor incorporated more than 4,000 and project management.
Kathrine Rusling, Adam Russo, Clodagh Ryan,
pre-assembled building services modules, Stefan Sadokierski, Jodh Sahambi, Peter Samain,
along with a further 2,000+ prefabricated Project credits
Demetri Serghiou, Jamie Shantonas, Celia Smith,
sections of pipework, containment and Client Francis Crick (UK Centre for Medical Richard Smith, Thomas Smith, Michal Smolicki,
valve assemblies, within the building Research and Innovation) Yeside Sogunro, Andrew Somerville, John Steele,
services systems. Architects HoK/PLP and BMJ Hannah Stevenson, David Stoker, Jon Stokes,
Cost Consultant Turner and Townsend Jiaxi Sun, Glen Swinney, Joanna Tolloczko
Handover Structural Engineer AKT II Theodore, Mark Togher, Christopher Tolmie, Gary
The client’s objective was to start moving Main Contractor Laing O’Rourke Towens, Mutlu Ucuncu, Mike Underhay, Gregory
staff in and operate the facility immediately Project Manager and MEP Engineer Arup: Visscher, Gary Walker, Ricky Watcham, Oliver
Davar Abi-Zadeh, Michael Adams, Jim Aitken, Webber, Catherine Wells, Annabel West, David
following handover. Demonstrating correct
Christian Allison, Stuart Allison, Luke Bannar- West, Antaeus Wheatley, Will Whitby, Gordon
performance of building systems and Wills, Marcin Wojewski, Chris Wood, Julie Wood,
Martin, Alan Beadle, Steven Berry, Francesco
compliance of building construction with Biancelli, Martyn Biss, Nicolas Bittner, Stephanie Jeff Yuen, Eduard Van Zyl.
the client’s requirements was essential to Black, Dora Boese, Miroslaw Bogusz, Bartosz
achieve practical completion of a project Borowicz, Anita Bramfitt, Darren Briggs, Damian Image credits
that incorporates complex environmental Bronowski, Andrew Brooks, Nathan Bryce, Kevin 1, 2: Paul Carstairs
conditions and controls. Integration of the Burke, Kevin P Burke, Keith Butler, Lee Carter, 3, 4, 6: Arup
client’s specialist equipment, which was Greg Chandler, James Connell, Shane Cooney, 5, 7-10: Paul Grundy
installed outside the main contractor’s
1.
28
Every April, the global design industry At the end of Salone del Mobile, the entire
descends upon Milan for the world’s best structure was dismantled within five days,
known design fair. packed up and moved to a permanent
location, leaving no trace of its short
In the lead up to the 2018 event, the existence on the Piazza Cesare Beccaria as
organisers of Salone del Mobile – the everyday life resumed in the city.
furniture fair at the centre of Milan Design
Week – published a manifesto calling for The future of construction
designers to up their game when it came to Over the past few years, governments and
tackling the global challenge of sustainability. industry bodies around the world have
hailed off-site manufacturing as the future of
With this in mind, Arup worked with Italian construction. The large-scale fabrication of
practice CLS Architetti to create a temporary building components in factories ahead of
installation that went on to win the festival’s assembly on site has the potential to
Best Sustainability award, which celebrates revolutionise the way our built environment
the project that puts ethics and sustainability is produced by speeding up the construction
at the centre of design. What started as a plan process and improving quality. It also has
to build a wall using 3D printing for an the added benefit of a more controlled and
industrial building evolved into the first safe environment for workers than the
3D-printed concrete house constructed in the average building site.
EU, and one of the first in the world made
using a portable robot manipulator. The technology used to 3D-print concrete
buildings is still a step behind that of
3D Housing 05 – a 100m² structure with off-site construction, but it is arguably an
curved walls that enclose a living area, even more compelling commercial
bedroom, kitchen and bathroom – was built proposition, as it means the advantages of
on a busy square in Milan’s city centre in full industrial off-site production could be
public view. It took just 48 hours to create the brought to the construction site itself.
house’s 35 concrete modules, each 3.2m high, Greater flexibility in building shape is also
which were printed in 60 to 90 minutes. The possible, allowing more complex shapes
completed structure, which was assembled in and structures such as double curved walls.
two weeks, weighed about 50 tons, or 1,000kg Digital plans could be used to print modules
per linear metre of printed wall. in situ, pushing the speed and efficiency of
3.
construction to its limits, as was the case with relative ease, either for use elsewhere Design and fabrication
with this project. or to recycle the basic material. Also, as Arup, collaborating with architects CLS
artificial intelligence technology develops, Architetti, provided structural engineering
In such a scenario, every centimetre of several printing robots could work in and materials consulting services. While
material produced is used and placed exactly combination quickly and efficiently Arup had previously done research into the
where needed without the requirement for without human intervention. potential of robotics in 3D concrete printing,
formwork. This minimises materials, this was the first time the firm had used the
reduces waste and conserves energy. Using Today, there are still only a few examples of technology to create a real building. The
digital technology, the structure can be 3D-printed buildings erected directly on site. design process commenced in January 2018,
analysed and the design refined before it is At present, China is the furthest ahead in the leaving just 90 days to plan and complete the
rendered in real life and without the risk of race to complete 3D-printed buildings of scheme. With no time for test runs, the team’s
miscommunication or human error. several storeys. The designs for these tend to capability would be demonstrated for the first
mimic those of traditional houses, with 90° time live on site, with no room for error.
Such structures, designed to the principles angles, rather than the complex shapes Arup
of the circular economy, can be dismantled helped create in Milan. Conscious of the risk, the Arup team spent
the months leading up to Milan Design
Week conducting simulations to ensure that
– at least in theory – the process was
5 & 6: 3D Housing 05 was built in Milan’s busy
Piazza Cesare Beccaria in just two weeks,
seamless. Arup used GSA, LS-DYNA® and
demonstrating the flexibility of this technology, Rhinoceros 3D software to develop the
which can create distinctive shapes such as design, with the 3D model used on site
curved walls with ease during the construction process, all of which
helped visualise and resolve issues in
advance. Before starting on site, the team
needed to consider factors such as the curing
time of the concrete, the intricacies of
3D-printing unusual shapes, and the
reinforcement that would allow each panel
to be lifted out when the house was
dismantled at the end of the design fair.
30
Its flexibility and range mean it can move 7: After the design
horizontally as well as vertically to create fair, 3D Housing 05
shapes that are difficult – and therefore was rapidly dismantled,
expensive – to achieve with traditional leaving no trace in
techniques, at a speed of 200mm per second. the piazza
The robot can extend up to 4.5m, but with
some adjustment, it could go much higher,
potentially allowing buildings of several
storeys to be constructed.
Making it a reality
Building a temporary structure to
demonstrate a technology’s potential does not
of course necessarily translate to the real
world. The installation in Milan, as it was
temporary, was not required to meet some of
the regulations and codes that would apply to
a permanent building. In addition, the reality
is that 3D printing is currently not cheap.
1.
32
By 2030, the Singapore government aims to the public. Downtown Line Stage 3 1: Bencoolen Station opened to the public
for 80% of households to be within a (DTL3) comprises 16 stations linked by after completion in October 2017
10-minute walk of a metro station. A key 21km of tunnels. It connects the central
part of the strategy for achieving this is business district with the eastern residential
a significant expansion of the city-state’s areas of Bedok and Tampines.
Mass Rapid Transit (MRT) system, a vital
part of its transport infrastructure that Arup’s involvement in the project began in
is used by more than three million people 2008, when the firm undertook alignment
every day. design for the entire length of DTL3. A year
later, Arup was appointed to carry out the
In October 2017, the final phase of the latest full engineering design for Package A of
line to be added to the network was opened DTL3, through the historic districts of Fort
Key
Canning, Bencoolen and Jalan Besar, and 2: Downtown Line set against the
the neighbourhoods of Bendemeer and pre-existing MRT system and planned lines East West Line
Geylang Bahru. The scope included the
Downtown Line – Stage 1
design of a station in each of those five
locations, along with 5km of connecting
Downtown Line – Stage 2
twin tunnels and associated escape shafts.
Downtown Line – Stage 3
The line’s central location means it runs challenges, while maximising ridership
under a dense, complex mix of modern and the benefits of a mass transit system for
and historic buildings, making it the city’s commuters and businesses. Arup carried
deepest underground link. It also weaves out more than 1,000 building impact
under and over various existing subterranean assessments along the proposed route, environment. In doing so, it has set a
infrastructure, including telecommunications, with design solutions suggested and precedent for sustainability and innovation
fibre optics, power, traffic and street implemented to navigate the varied for future rail developments in the city-state.
lighting cables; water and gas pipes; and design constraints, including developing
three existing MRT lines. In addition to the concept for temporarily diverting the Alignment
those obstacles, the line drops below the Singapore River during construction. The latest addition to Singapore’s MRT
Singapore River and skirts arterial roads and system, the 42km Downtown Line is the
underground road tunnels. This combination Arup worked with Singapore’s Land longest underground and driverless rail
of design constraints made it one of the most Transport Authority (LTA) to develop line in Singapore and was designed to link
technically challenging underground safe, buildable designs that were not only the downtown district with commuters in the
projects ever undertaken in Singapore. innovative but improved the overall north-western and central-eastern parts of
productivity of the construction works, the city. The line was developed in three
When Arup took on the project, it was while pushing the boundaries of ground stages. Stage 1 opened in 2013, Stage 2 in
conscious of the need to tackle all these engineering methods in an urbanised 2015 and Stage 3 in 2017.
34
HDB Block 34
State Courts
Arup worked on the early phases of the DTL up an in-depth understanding of the ease of access. This was vital because of
Stage 2, carrying out the reference design challenges involved in designing, building the built-up density of the corridor. For
for the 10km stretch of tunnels and stations and operating such a mass transit system, example, the tunnels between Fort Canning
from Chinatown to Botanic Gardens. Arup and how these could be resolved. and Bencoolen stations were constrained
was subsequently appointed to develop a by existing MRT lines, and passed directly
concept design for DTL Stage 3, including For the concept alignment study, Arup below a national monument, the National
station location and alignment within all developed a comprehensive horizontal Museum of Singapore. The tunnels had to
the existing under- and above-ground and vertical alignment of the tunnels, pass over the North East Line, with a 1.3m
infrastructure. This allowed Arup to build considering buildability, operations and clearance, then under the North South and
Circle Lines, with clearances of 8.7m and
3.2m respectively. The tunnels between
Fort Canning and Chinatown stations had to
pass through a very narrow corridor between
the State Courts and a public Housing and
Development Board (HDB) building,
requiring the tunnels to be in a stacked
configuration. At one point in this corridor,
the MRT tunnels had to be constructed a
mere 640mm away from the foundations
of one structure.
5.
manage the impact of station and tunnelling The overall aim was for the underground made the design more efficient, optimising
works on existing structures. Building type, works to be as shallow as possible, saving the construction process to make DTL3
condition and heritage value were all construction cost as well as improving safer and quicker to build, with significant
considered when assessing the horizontal public access and passenger experience financial savings for the client.
and vertical rail alignment. In addition, when entering stations and inter-changing
several investigations were carried out for between lines. By challenging past practices Diverting Singapore River
key buildings and structures along the and rail geometry design requirements Arup’s role in DTL3 Package A involved
alignment to determine building foundations without compromising operations, Arup not only designing a future-proofed transit
where as-built information was not available
or the accuracy of records was in question.
This helped to minimise construction risk by
determining if they impeded the tunnel
boring construction. Arup carried out design
checks to ensure that where some piled
foundations were removed during
tunnelling, the buildings above would
remain stable.
36
6: As the deepest potential risk of debris left behind in the
station in Singapore, riverbed. If the tunnelling machines
Bencoolen sits encountered any remnants from these
below pre-existing activities during construction under the
MRT tunnel levels river, both the DTL3 construction works
and potentially the adjoining live railway
lines could have been flooded.
8. 9.
Cripple siding
10.
embankment and the temporary bridge were structure for the siding. This was a design 10: The cripple sidings for temporary train storage
removed, and the diversion canal filled in, and operations first for Singapore. were placed within Fort Canning Station rather
restoring the river to its original route. than along the tunnels, which significantly
Jalan Besar Station reduced costs
Fort Canning Station The construction of the four-level Jalan
Located within a constrained site on the Besar Station was particularly challenging.
north side of the Singapore River bank The station is immediately adjacent to
between Liang Court and the CTE, this conservation shophouses that are founded
station extends towards the southern end in soft soils and required retention. The
of the historical Fort Canning Hill. Station proximity to these heritage buildings posed
Entrance A is located next to the CTE significant space constraints for the works,
tunnel, with a minimum clearance of as well as prompting concerns that the deep
approximately 5m. A robust design excavation (>30m) could cause damaging
solution comprising propped diaphragm vibrations or movement to these buildings.
walls and top-down construction methods
was required to control movement of the During the design stage, Arup carried
sensitive CTE. An extensive impact out pre-construction inspections to establish
assessment was necessary to demonstrate the existing condition of all structures within
that the effect of the main station 250m of the station excavation. This
excavation works on the existing CTE determined if there were any pre-existing
tunnel was acceptable. building defects and what type of
foundations were in place supporting the
Fort Canning cripple sidings buildings. Building impact assessments
Arup designed the cripple siding, which were conducted to predict the potential
is an extra track that is used to facilitate effects of the station work and show that
withdrawal or storage of trains, to be located impacts were acceptable.
within Fort Canning Station. Typically,
cripple sidings are located along the tunnel Shophouses that required precautionary
length, but given the very tight site protection had propping systems installed
constraints along DTL3, there was no for the façade and were monitored closely
suitable site available between stations. during construction.
Arup’s solution to locate the cripple sidings
on each side of the Fort Canning Station The earth retaining and stabilising system
platforms made the station wider, but at the station comprised a combination
ultimately saved significant construction of 1.2m and 0.8m thick diaphragm walls,
cost by removing the need to find additional crosswalls, ground improvement and
land to construct a discrete cut and cover concrete walers. This retaining system
12.
38
11: Tunnel boring machine access shaft at Fort
Canning Station
12: Arup demonstrated, using traffic simulations,
that even with Bencoolen Street closed during
DTL3 construction the surrounding roads could
accommodate the temporary arrangement
13: While closed for the station works, Bencoolen
Street was redeveloped to be ‘car-lite’, creating
better access for bikes and buses
11.
provided the necessary high level of wall The monitored ground and building roadside parking was removed at Waterloo
restraint against deflections and ground movements were within acceptable limits. Street, and Selegie Road, previously a
movements in this critical area. The one-way street, was made two-way.
station, measuring 170m long, 23m wide Bencoolen Station These adjustments ensured the extra traffic
and 35m deep, was constructed using At rail level, Bencoolen Station is 43m volumes along existing streets were
top-down methods, further enhancing below ground, and is the deepest accommodated even with the closure of
movement control. underground station in Singapore. It Bencoolen Street.
required the temporary closure of a nearby
major street because of the complexity of Following completion of the works, a
construction work required within the tight redesigned Bencoolen streetscape was
construction programme. This station depth constructed with wider pavements, an
was required to avoid the existing North all-day bus lane, dedicated cycle paths
South Line and Circle Line tunnels and more bicycle parking. This ‘car-lite’
immediately west of the station. The station streetscape is one of the first in Singapore.
comprises six levels and is 190m long.
Critically, it is only 23m wide in order to fit Steel fibre reinforced concrete
within the streetscape corridor. The Arup Arup proposed the use of steel fibre
team not only developed a system of reinforced concrete as permanent lining
escalators and lifts that allowed rapid for a section of the bored tunnels of DTL3,
and seamless vertical transportation of a system not previously used for tunnels in
passengers from the concourse to platform South-East Asia. The decision to use this
level, but also designed the interiors to method was made to reduce the need for
make this journey memorable. labour to fix and place traditional steel
reinforcement, saving time and costs during
During construction, Bencoolen Street lining fabrication, resulting in increased
was closed to traffic. Arup prepared a construction productivity. The use of fibres
microsimulation model of the road network in concrete also enhances durability and
surrounding the site, incorporating all improves concrete performance under fire
junctions and other relevant infrastructure loads. Using less material is also more
such as car parks and traffic exit points. This sustainable: a typical steel ratio for a tunnel
allowed the traffic pattern to be simulated to in Singapore averages about 120kg/m³,
ensure that the existing road network could compared with a steel fibre ratio of 30-40kg/
carry the increase in traffic volumes with the m³. Arup developed the approach for testing
temporary Bencoolen Street road closure. the material and its performance, as well as
proving the feasibility of using steel fibre
The surrounding road network required concrete in underground construction in
a number of junction upgrades. In addition, Singapore. This required Arup to engage
13.
14. 15.
with the Building Control Authority and develop and use Building Information construction. Designing through BIM is now
work collaboratively with the supply chain Models (BIM) for design. Arup led this mandated on all the city’s transit projects.
to ensure the new material was approved drive. Using these digital methods of The standards of coordination and quality
and adopted smoothly. collaborating and coordinating, through 3D set by DTL3 contributed to this process.
models containing every feature of each
Digital modelling station and tunnel, meant that any clashes in Results
DTL3 Package A was one of the first the design were identified and removed prior DTL3 opened towards the end of 2017,
construction projects in Singapore to to tender rather than during on-site offering a swifter commute between
16. 17.
40
Authors Lee, Kah Peck Lee, Mandy Lee, Sazlynda
Charles Im was the Project Manager during Lee, Sean Lee, Sebastian Lee, Wong Lei Lei,
construction. He is an Associate Principal in Anthony Leversedge, Siyu Li, Yangyang Li,
the Singapore office and the Geotechnical Hasta Lie, Keithson Liew, Daniel Lim, Deyuan
Leader in Singapore. Lim, Jia Yuan Lim, Lip Boon Lim, William
Lim, Angie Lin, Chris Liu, Ashley Lloyd, Tom
Gordon Lee was the Deputy Project Manager Lok, Ragavendra Lokaranjan, Annabelle
during construction. He is an Associate in the Loke, Chunrong Lu, Steven Lucianto, Neville
Singapore office. Lui, Farong Luo, Xiangyue Luo, Malcolm
Lyon, Serene Mah, Noraziza Mahbob, Juan
Michael McGowan was the Project Director Maier, Swee Chiang Mak, Israel Maraddag,
during construction and led the project Mukunthan Manickavasakar, Noel Manuel,
management element. He is a Principal in Haruko Masutani, Chandana Medagoda,
the Singapore Office leading Arup’s Michael McGowan, Wing Sze Mo, Zin Soe
infrastructure business. Moe, Junaideen Sainulabdeen Mohamed,
Daniel Mulyawan, Sudhakaran Nair, Andrew
Project credits Nelson, Betty Ng, Jia Le Ngai, Rain Nguyen
Client Land Transport Authority of Singapore Pham, Rosella Obordo, Nurmarlia Omar,
Architect Aedas Pte Ltd Shahnaz Omar, Khine Khine Oo, Abner
Contractors: Paredes, Benjamin Pascua, Michael Dela
Fort Canning Station – GS Engineering & Pena, Brett Perez, Hai Pham, Alan Philp,
Construction Corporation Luis Piek, Seng Tiok Poh, Jason Poon, Chris
Bencoolen Station – Sato Kogyo (S) Pte Ltd Pynn, William Quah, Virgilio Quinones, Nizar
Jalan Besar Station – Leighton John Holland Abdul Rahim, Hamed Rahimi, Ashish Raikwal,
Joint Venture Pablo Romero, Ken Roxas, Ali Sadeghi,
Bendemeer Station – Penta Ocean Norliah Sanusi, Wisnu Saputra, Jeyabalan
Construction Co Ltd Sathaiah, Dennis Seah, Sau Fong See, Kartini
Geylang Bahru Station – China State Shabani, Xiao Shan, Nikki Shaw, Hongwei Shi,
Construction Engineering Corporation Limited Ming Simon, Ernesto Siochi, Sai Sivarajah,
Seng Siong Soh, Jeremy Su, Lifeng Su,
the eastern part of Singapore and the Full engineering design: Arup Leo Suhaendi, Kevin Suhartono, Arbaiyah
downtown area. It is a key part of the Roel Abubo, Nur Liyana Ahmad, Michael Sulaiman, Barry Sullivan, Qian Sun, Podianko
government’s transport strategy. Daily Alder, Lioni Alvarez, Victor Andrade, Pei Wen Surya, Sharifah Syed, Cheryl Tan, David
weekday ridership on the DTL has grown Ang, Serene Ang, Anton Arceo, Jhunel Arroyo, Tan, Fook Aik Tan, Lawrence Tan, May Tan,
by more than 50%, from 300,000 to Harry Asilo, Camelia Badeo, Daniel Bali, Yoong Heng Tan, Yunyou Tan, Lim Mei Tang,
470,000, after the opening of DTL3. Warren Balitcha, Jomar Baquiran, Rolando Xin Ning Tang, Joo King Tay, Kelvin Teheri,
Bautista, Tim Bennett, Roger Blackwell, Tamas Kim Keong Teo, Handoko Tham, Lin Than,
About 60% of journeys involving DTL3
Bodri, Nigel Casey, Kartigayen Poutelaye Nagadurai Thangavel, Vivian The, Andra Thedy,
have been shortened by up to 10 minutes, Cavounder, Gary Cequena, Peggy Chan, Angelina Theng, Mart Umali, Henry Vong,
compared with previous travel routes, Ricky Chan, Naimet Cheema, Andrew Cheng, Ekarin Wattanasanticharoen, Kenny Wen,
while 20% of journeys are shortened by Joy Cheong, Alvin Cheung, Heidi Cheung, Gary Weston, Ryan Williams, Berlina Winata,
more than 10 minutes. Henry Chia, Lok Ching Choi, Fann Chong, Jin Ambrose Wong, Ling Chye Wong, Peter Wong,
Thai Chong, Ricky Chong, Ts Choong, Shiao Eddie Woods, Nelson Xiong, Da Xu, Jingfeng
The opening of DTL3 has brought people Teng Chow, Wai Fun Choy, Steve Colomb, Xu, Alan Yang, Kimm Ho Yap, David Yeung,
who live and work in the east closer to train Jonathan Constantinou, Argoon Chuang, Edwin You, Pippen Yung, Jie Zhang,
stations. Today, 64% of households across James Daish, Yang Dang, Christopher Daniel, Yimin Zhou.
Singapore are within a 10-minute walk of John Davies, Lauren Davis, Chris Deakin,
Sheryl Demesa, David Derige, Deirdre Devery, Image credits
a station, bringing the city-state closer to
Symur Diche, Lu Lu Din, Ronaldo Domingo, 7, 8, 9: Land Transport Authority
achieving the goal of 80% of households Ryan Edano, Hidayah Edward, Fendy Edy, Yu All other images: Arup
being within a 10-minute walk of a train Ting Fan, Shuhong Feng, Ting Yi Foo, Vivien
station by 2030. Foo, Arvin Francisco, Ezel Gabriana, Sacha
Gebbie, Mercy Guevarra, Xinrui Guo, Hasnita
Following the success of this project, Hashim, Kok Hui Heng, Andrew Henry, Ka
Arup has secured a number of other Fui Hiew, Siaw Ling Hiew, Arge Hipolito, Kent
rail projects in Singapore, including Ho, Sai Ho, Dongmei Hu, Hangyu Huang,
the Thomson-East Coast Line, where Sarah Huskie, Jamilah Hussain, Charles Im,
Arup is the designer of 14 stations Bradley Jackson, Gladys Jahja, Nur Hayati
Jamalludin, Rohani Jamalludin, Henry Jeens,
and nearly 20km of tunnels. Subsequently,
Jimmy Jiang, Damien Jolly, Subash Kathiresan,
Arup was engaged to develop the design Zahid Khan, Rachel Khoo, Nam-Jo Kim,
for the 50km long Cross Island Line. Yan Ru Kiu, Christofer Kristo, Siang Meng
Arup will continue playing a leading Kua, Ben Kwong, Francis Lai, Aishah Abdul
role in helping the Singapore government Latiff, Ching Lau, Vicki Lau, Alice Laung,
create one of the world’s best urban Phil Lazarus, Cheryl Lee, Faith Lee, Gordon
transport systems.
1.
42
2.
1: Opened in The Bloomberg Center was the first production offsetting the building’s
September 2017, the academic building completed on Cornell consumption. Cornell Tech, a partnership
Bloomberg Center Tech’s new New York City campus. The between the Technion-Israel Institute of
was the first
building has the aspiration of net-zero Technology and Cornell University, won a
academic building
on Cornell Tech’s
energy use as part of the campus’s competition run by New York City to secure
new campus on broader sustainability programme the site for the development of a campus.
Roosevelt Island and has achieved the highest LEED
2: The Bloomberg
Platinum certification. Collaboration
Center (left) and Tata Cornell Tech was willing to change the typical
Innovation Center Through close collaboration with Cornell form and function of an academic building to
(right) under Tech and Morphosis Architects, Arup pushed promote collaboration and innovation and set
construction the boundaries of what could be achieved in new standards in building performance and
creating such a large-scale, low-carbon sustainability. Flexible spaces were designed
energy-efficient building. to encourage collaboration, and open-plan
offices were adopted.
Arup provided multidisciplinary services,
including: structural, mechanical, electrical, The culture of collaboration that the finished
plumbing and fire protection engineering; building needed to facilitate was also to be
acoustic and audio-visual consulting; found in the project team during the design
communications, façade and lighting/ process. Arup worked in partnership with
daylighting design; security; and Cornell Tech and Morphosis Architects
smart building consulting. In addition, with the aim of creating a net-zero building
Arup’s responsibilities included key that would serve as a model for future
sustainability services, LEED advice and development on the campus. This
net-zero-energy goal consulting for the collaboration was essential to meet the energy
160,000ft² (15,000m²) facility. efficiency goals, and Arup’s multidisciplinary
design philosophy helped with the delivery.
Roosevelt Island development
The new university campus is located on the Sustainability
two-mile-long Roosevelt Island in New York The aim was to create a building that is
City’s East River. The campus had its genesis low-carbon, energy-efficient, healthy and
in an initiative of the administration of then pleasant to be in. Throughout the design, Arup
New York City Mayor Michael Bloomberg to evaluated opportunities for reducing energy
promote the city as a hub for tech innovation. demand through internal load reductions; for
The development on Roosevelt Island example, through the use of low-energy
represented a great opportunity for the city, as workstations and lighting, energy recovery
large sites such as this do not become systems and design for reduced solar heat gain.
available very often.
To achieve this, the façade and roof canopy
The city focused on a net-zero-energy were used to limit solar heat gains, thereby
development, with on-site energy lowering the amount of energy needed within
3: Arup produced a
Academic Building Energy Use Intensity full-building energy
(kBtu/GSF/year electric) Total: 29.3 model to track
progress towards
achieving LEED
Plug load 8.6 Platinum status
4: LED lighting was
Lights 5.3
used throughout
Fans 2.9 the Center
Pumps 2.2 5: The rooftop
canopy is made up
round source
G of 1,465 PV panels
plant – heating 5.7
round source
G
plant – cooling 4.4
ooling tower
C
fan/pumps 0.2
3. 4.
the building for cooling. The solar photovoltaic canopy supports 1,465 PV panels. Arup transparency (40%) and opaqueness (60%)
(PV) roof canopy provides the building’s worked with the client and solar project to decrease energy demand. The system,
primary power on-site. The building was also developer Distributed Sun to review developed in conjunction with the internal
designed in accordance with the LEED NC preliminary energy analysis and panel layout. efficient LED lighting scheme, ensures
2009 rating system, and has achieved the adequate daylighting and maximises views
highest LEED Platinum certification. The panels are laid flat, rather than placed in across the East River towards Manhattan for
the more traditional tilted style. For this the building’s occupants. It reduces solar
Arup tracked progress towards these goals project, where area is limited, it is a more heat gain within the building and maximises
by producing a full-building energy model cost effective and energy-efficient system. insulation. Exterior shading systems were
based on an electric energy consumption More panels can be fitted on the canopy, and located on the eastern façade to help balance
rate of 30 kBtu/GSF/year, providing an with flat panels there is no additional daylight harvesting against cooling
improvement of 35.5% against ASHRAE supporting structure required, nor is there demands, and to minimise the mechanical
Appendix G energy baseline levels. any shading of adjacent panels as would be systems required along that perimeter.
the case with a sloping strategy.
All-electric building The metal panel cladding on the east and
New York City has the stated goal of Building façade west façades includes a series of small discs
reducing greenhouse gas emissions to 80% The façade plays an important part in the set at different angles, which form a
of the 1990 baseline by 2050. Much of these building’s passive energy design. It balances pixelated pattern. The eastern façade image
carbon emission reductions will stem from
power plants as coal and oil are phased out
of electricity generation in New York State
and replaced by solar and wind sources.
PV canopy
The PV array on the Bloomberg Center’s
canopy provides on-site renewable energy
generation, as well as shading that reduces
the building’s cooling load in summertime.
A campus-wide array of solar panels was
developed, with PV panels placed both on the
Bloomberg Center and the adjacent Tata
Innovation Center. The 40,000ft2 (3,750m²)
5.
44
6: The building’s façade balances
transparency and opaqueness to further
minimise energy demand
7: The east and west façade faces are formed of
small discs set at different angles, which together
create an overall image
8: Michael Riedel’s
sprinklers), satisfied code requirements and black and white
met both the architectural and artistic inkjet print graphic
requirements for the space. decorates the café
ceiling and tables
Structural design 9 & 10: The feature
The building has a single-level basement staircase is located
under part of its footprint and is founded on above the campus
footings bearing on rock (with rock anchors) plaza and forms
and mini-piles socketed into rock. These act the apex of the
against uplift from groundwater – a key building’s canopy
requirement, as in the event of flooding the support. Its central
resulting hydrostatic uplift pressure on the spine truss provides
structural support to
basement would exceed the building’s
the canopy
permanent weight.
11: 3D model
showing the
structural frame.
The steel columns
extend above roof
level to support the
PV canopy and
incorporate thermal
breaks to reduce
cold bridging
11.
46
9. 10.
structure. This system is part of the system and is connected to the transverse damage and further highlighted the
primary structural system providing and central spine trusses. A vertical truss resilience required by the campus.
gravity support to the stair edges and on the south end laterally connects the
façade. Similar to an outrigger system diagrid system and central column to To mitigate potential damage to equipment
used in high-rise construction, the the main building. during a flood event, the main electrical
exterior diagrid system also helps to switchroom and emergency and life
brace the overall stair structure laterally Resilience safety power systems are located at roof
and transfer the lateral forces back into Roosevelt Island is in a vulnerable location level, along with the generator, while
the main building structure. for flooding, so resilience against flood the basement footprint and plant equipment
conditions and rising sea levels was a are minimised.
Additional concealed trusses include critical design component. In October 2012,
transverse trusses perpendicular to the only a few months after the design process The number of electrical panels installed
central spine truss, and an edge truss that began, New York City was hit by Hurricane in the basement was kept to a minimum.
vertically supports the perimeter diagrid Sandy. The flooding caused $70bn in Ground fault circuit interrupters were also
put in place so that in the event of a flood, or
if water infiltrates those circuits, they can be
Authors Chad Fusco, John Hand, Spencer Harris,
isolated without damaging the connected
Fiona Cousins was the Project Director. She is Andrew Heiser, Peter Ibragimov, David Jones, circuits or panels. Similarly, motors and
an Arup Fellow based in the New York office. Deepak Kandra, Igor Kitagorsky, Marina Kremer, critical mechanical equipment were kept
Ken Garmson, Leonie Van Ginkel, Alex above the flood line.
Carl Mister was the lead electrical engineer. He Gorenstein, Tyler Gorton, Tom Grimard, Anne
is an Associate Principal in the New York office. Guthrie, Matthew Lacey, Gary Lam, Dennis Continued work on campus
Lowenwirth, Filip Magda, Andrew Marchesin, Arup has continued its work on Cornell
Tom Rice was the Project Manager and lead Will Mason, Claudia Mazzocchetti, David Tech’s Roosevelt Island campus with
structural engineer. He is an Associate Principal McNell, Anjali Mehrotra, Ashraf Metwally, Carl involvement in two further projects.
in the New York office. Mister, Sarah Moore, Elvis Nunez, Allan Olson,
Working with Weiss/Manfredi Architecture,
James Olson, Christian Paunon, Filip Popovic,
Project credits Eugene Prokofiev, Dylan Quan, Alvaro
Arup provided security, IT and AV
Client Cornell Tech Quinonez, Tom Rice, Ron Ronacher, Chris Rush, consulting services for the interior fit out of
Architect Morphosis Roberto Saldarriaga, Kirsten Salmins, Yet Sang, four floors within the Tata Innovation
Main Contractor Barr & Barr Adriana Sangeorzan, Katelyn Sapio, Joe Center. This building consists of classrooms,
Cost Estimator Dharam Consulting Saverino, John Scavelli, Jeff Schwane, Markus general and robotics laboratories, huddle
Geotechnical Engineer Mueser Rutledge Schulte, Juanma Serrano, Anatoliy Shleyger, rooms, studio and open office space, and
Acoustics, Façade, Fire Protection, Lighting Christopher Simon, Joe Solway, Daniel several large collaborative spaces.
MEP, Structural and Sustainability Engineer, Wilcoxon, David Wilts, Therese Worley.
IT/AV/Security, Smart Building Arup: Currently under construction, Arup is
Jonah Allaben, Chelsea Bajek, Daniel Brodkin, Image credits
also providing (in collaboration with
Beverly Brooks, Cillian Brown, Thomas 1, 6, 9: Iwan Bann
Bukovac, Aaron Burger, Foram Chaliawala, Dan 2: Cornell Tech
Snøhetta) acoustic, AV, IT and
Clifford, Fiona Cousins, Casey Curbow, Daniel 3, 5, 7, 10: Arup security consulting services on the Verizon
Dichiro, Zohaib Dar, David Easter, Ming Feng, 4, 8: Matthew Carbone Executive Education Center, a 40,000ft2
Adrian Finn, Vincent Fiorenza, Adam Foxwell, venue for executive programmes, academic
conferences and workshops.
3 4
5 6
1. Harbour Area Treatment Scheme, Hong Kong: Arup; 2. V&A Grain Silo Complex, Cape Town, South Africa: Arup/Tessa Brunette; 3. Francis Crick Institute, London,
UK: Paul Carstairs; 4. 3D Housing 05, Milan, Italy: Arup; 5. Singapore Downtown Line: Arup; 6. Bloomberg Center at Cornell Tech, New York, USA: Iwan Bann.
Front cover and inside cover images: V&A Grain Silo Complex, Cape Town, South Africa: Arup/Tessa Brunette.
Published by Arup
13 Fitzroy Street
London W1T 4BQ, UK.
Tel: +44 (0)20 7636 1531
All articles ©Arup 2018
www.arup.com