Blasting and Painting Procedure
Blasting and Painting Procedure
Document Title
Prepare
Rev Description Date Review by
by
Aug 26,
0 New release
2014
1
2
TABLE OF CONTENS
Cover..................................................................................................... 1
.
Table of Contens...................................................................................... 2
1.0 Scope................................................................................................... 3
2.0 Reference Document................................................................................. 3
3.0 Material 3
Control........................................................................................
4.0 Inspection Equipment .............................................................................. 3
5.0 Blasting And Painting Equipment................................................................ 4
6.0 General................................................................................................... 4
7.0 Atsmopheric Conditions............................................................................. 4
8.0 Surface Preparation.................................................................................. 4
9.0 Mixxing and Thinning................................................................................ 6
10.0 Painting and Coating Application................................................................. 6
11.0 Driying and 8
Curing....................................................................................
12.0 Inspection And Testing.............................................................................. 8
13.0 Repair of Demaged Areas.......................................................................... 9
14.0 Safety..................................................................................................... 9
15.0 Quality Record And Inspection Report......................................................... 9
16.0 Revision 9
Note...........................................................................................
2
3
1.0 Scope
This construction procedure covers the control of materials and the procedure to be followed
in the course of surface preparation, painting/coating application, inspection and safety
requirements for aboveground piping for Field Surface Facilities Project of Water Steam
Cycle Project. Detailed specifications and/or equipment shop drawings shall be used in
conjunction with this procedure.
The following inspection equipment shall be kept available during blasting and painting
operations:
a. A temperature gauge and a hygrometer
b. Surface profile gauge
c. Wet film thickness gauge
d. Dry film thickness gauge (for DFT measuring25 µm to 5 mm)
3
4
e. Holiday detector
NOTE: Surface profile Gauge & Dry film Thickness must be able to gauge flat and round
surfaces.
2) All the equipment shall be ready and checked as being in good within working order
prior to and during blasting and coating operations and shall be kept in a sufficiently
clean condition to avoid surface and/or coating contamination.
6.0 General
1) Work shall be done by qualified personnel in a neat and workmanlike manner conforming
to all applicable OWNER specification. CONTRACTORS to carry out any type of
surface preparation and painting or coating qualification prior proceeding with actual
work.
2) All coating shall be done in accordance with manufacture’s recommendations. Where
specifications contained herein conflict with manufacturer’s recommendations the
conflict shall be referred to OWNER for written clarification prior to the commencement
of work.
3) The numbers of coating and the thickness of coating should be in accordance with
approved IFC drawing or Owner’s specification listed in chapter 2.
The applicator shall measure the ambient conditions at regular intervals prior to and during of
any type of power tooling or blasting painting/coating, and keep records of prevailing
temperature, humidity and dew point.
c at the time of coating.c above the dew point or above 507.2 No surface preparation or
application of material may take place when steel surface temperatures are less than 3
Surface preparation shall be in accordance with paint manufacturer’s instruction and project
specification, whether blast cleaning, power tool, hand tool or solvent cleaning.
4
5
1) General
a. Surface preparation shall be done in accordance with Steel Structures Painting
Council surface preparation specifications defined in Steel Structures Painting Manual
Volume 2
b. The blast cleaning abrasive (sand) shall be determined by the test methods in SSPC-
AB 1 (Mineral and Slag Abrasives) specification in order to comply with the SSPC-10
standard. Only abrasive approved by the OWNER will be acceptable for use as a blast
medium
c. The abrasive shall be dry and free from oil, grease, dust and other impurities. Re-
usable abrasive shall be clean and reasonably sharp, contain no rust or noticeably
worn abrasives.
d. Alternative surface preparation methods may be approved when dry blast cleaning is
unsafe or impractical.
e. Blast cleaning shall not be permitted where adjacent areas or equipment are not
sufficiently protected from contamination by abrasive dust or debris.
f. Blast cleaning shall not be permitted in areas close to painting operation to prevent
contamination of wet paint film by dust and grit
g. All organic substance such as oil, grease, and other contaminants shall be removed in
accordance with per specification prior to blasting operations.
h. All rough welds, burrs and sharp surface projections shall be ground smooth and all
weld spatter shall be removed prior to blasting operations.
i. The compressed air supply used for surface preparation must be of sufficient pressure
and volume to prepare the surface to the degree specified and shall be free of oil and
water.
j. During blasting, the rise face flanges must be protected at all time. This should be
done by covering the rise surface with a round plate that covers exactly the rise
surface diameter.
Power-tool cleaning shall be to a visual standard in accordance with ISO 8501-1 St3.
Power-tool cleaning shall be done using abrasive or wire-type power discs. Power-tool
cleaning shall extend a minimum of 25mm distance into adjoining coated surfaces.
Hand-tool cleaning is the least effective of the surface preparation methods, but it may be
used for touch-up/repair maintenance with certain surface-tolerance coating systems.
5
6
Solvent cleaning shall be done in accordance with SSPC-SP1 “Solvent Cleaning’ on the
surface examined for the presence of oil or grease.
All spray application of paint whether air, or airless spray, shall be in accordance with the
following :
a. The equipment used shall be suitable for the intended purpose, shall be capable of
properly atomizing the paint to applied, and shall be equipped with suitable pressure
regulators and gauges. The equipment shall be maintained in proper working
condition at all times.
b. Paint ingredients shall be kept uniformly mixed in the spray pots or containers during
paint application either by continuous mechanical agitation or by intermittent agitation
as frequently as is required.
c. Paint shall be applied in a uniform layer with a 50% overlap at the edges of the spray
pattern, and 20 to 25 cm away from the surface
d. Brush or daubers shall be painted for cracks, crevices, blind areas of all rivets and
bolts, and all other inaccessible areas.
e. Paint manufacturer’s instructions regarding pot life, drying/curing intervals between
successive coats and final curing periods before assembly or transport, shall be
followed
f. Each layer of paint shall be allowed to dry for a period of time within the limits
prescribed by the paint manufacturer, before the next layer is applied
g. No coating shall be applied to edges prepared for field welds or within 50mm of these
edges, except for a prefabrication or welding (shop) primer which shall be limited to a
maximum 25 microns.
3) Airless Spray Application
a. Airless or high pressure spray application of paint shall be in accordance with all of
the provision of Section 10.2.1 And in addition shall comply with following:
b. The air pressure to the paint pump shall be adjusted so that the paint pressure to the
gun is proper for optimum spraying effectiveness in accordance with paint
manufacture’s recommendation
c. The trigger of the gun should be pulled fully open during all spraying to insure proper
application of paint.
d. Airless paint spray equipment shall always be provided with an electric ground wire
in the high pressure line between the gun and the pumping equipment. Further, the
pumping equipment shall be suitably grounded to avoid the build-up of any
electrostatic charge on the gun. The manufacturer's instruction should to be followed
regarding the proper use of the equipment.
4) Brush Application
a. Brush application shall be done in areas which cannot be properly sprayed and for
touch up maintenance where spray application is not practical
b. Brush shall be of a type and size which permits proper application of paint. Round or
oval brushes are most suitable for irregular surfaces such as bolts, weld, pitted steel,
etc. Wide flat brushes shall be used for large flat areas.
c. Paint shall be worked into all corners and crevices.
d. Rugs and sags or other defects will not be permitted
5) Critical Internal Coating
a. For critical internal coating of tanks /and vessels, all crew supervisors, abrasive
blasters and paint coating applicators shall be fully conversant with all aspects of the
7
8
blasting and coating operations. All equipment i.e. lights, air extractor’s to conform to
safety requirements.
b. The method of application used shall be governed by the coating manufacturer’s
recommendation for the particular coating being applied. Method of application shall
also be considered by the immediate vicinity where work will be carried out
c. Warning notes shall be clearly paint specified on the external surface of all internally
coated vessels: “INTERNALLY COATED – DO NOT WELD – HANDLE WITH
CARE”.
6) Detailed Painting System
The detailed painting system shall conform to the Owner approved IFC drawings and
Painting Manual which CONTRACTORS should submitted prior proceeding the works.
7) Cheklist Detail
For the check list details refer to Blasting Painting/coating Inspection and Test Plan
It shall be the responsibility of contractor to conduct the test and inspection as follows in
accordance with paint manufacturer’s application instruction and project specification.
OWNER shall monitor all tests performed by Contractor.
The following tests shall be performed at start-up and at specified intervals.
b. Enveronment Check
Before commencing work on surface preparation and coating, the atmospheric
temperature and relative humidity shall be measured in order to determine the dew
point. Relative humidity readings shall be measured a maximum interval of 2-hour.
Following determination of the dew point, the steel surface temperature shall be
measured at regular 2-hour intervals. The steel surface temperature shall be 3ºC or
more above the dew point during surface preparation as well as during coating
c. Visual Finished Coating
The finished coating surfaces shall be of uniform color and free from pinholes, peeling,
sags, and runs. etc.
d. Film Thickness measurement
The dry film thickness of individual coats and of the total coating system shall be
checked at 5 random locations over areas representative of the work in progress.
There shall be a check of at least one area on each horizontal, vertical and curved
8
9
surface. For internal coating of tanks and vessels, a minimum of 10 random areas shall
be checked.
With the exception of areas such as welds, crevices, etc. the specified minimum dry
film thickness shall not be exceeded by more than 50%.
3 Dry film thickness shall be measured with a coating thickness gauge suitable for
given type of coating thickness range and substrate material (magnetic or
nonmagnetic).
CONTRACTORS shall insure that all the inspection, measuring and test equipment
has a valid calibration certificates.
14.0 Safety
1) Safety in blasting and painting operations are paramount. Both operators and supervisors
must be fully conversant with all safety requirements associated with blasting and
cleaning, scaffolding and access platforms, ventilation in enclosed areas, as per project
safety manual.
2) All spraying equipment shall be earthed, all high lines checked daily, operators shall wear
all approved safety equipment at all times when spraying operations are in progress, and
warning signs erected when blasting work is in progress.
3) Protection of working area environment please refer to HSE plan
Daily reports shall be assured on all painting activities and recorded on blasting / painting
inspection reports. These records shall be maintained and monitored by QC engineer who
together with OWNER shall sign on all inspection reports which are included in the inspection
and test procedures.
This procedure shall be revised if it is found to be inadequate for purposed work upon
completion of engineering/new construction practice/new site information or as requested by
OWNER.