Questions & Answers - Planning & Scheduling
Questions & Answers - Planning & Scheduling
PLANNING
OPTIONAL QUESTIONS
1
Section 1A – Planning Development
Subchapter 1.1 Input and Data
1.1.1 Contract Requirements
1. The traditional governmental contracting process in the United States is:
A. Design, build, and operate
B. Design, bid, build
C. EPC
D. Design, build
3. When a planner-scheduler is collecting information about the project during the initial planning
cycle, which information is of GREATEST value?
A. Contract specifications.
B. The contractor’s pre-bid site visit meeting minutes and notes.
C. The contract’s Changes clause.
D. A detailed scope of work statement
6. All project stakeholders provide input data and information during the initial planning process
to set the overall project duration?
A. Absolutely true.
B. Absolutely false.
C. Only by analyzing the contract can one determine if a change in duration is allowed.
D. Only the project owner-client may set the overall duration, and this is often driven by
marketing and business considerations. .
2
1.1.3 Constructability Methods
7 Which should not be a reason why superintendent and subcontractors are included during
planning phase?
A. They have more immediate “buy-in” to project plan.
B. Planning phase is a theoretical exercise and their input is not needed until the
execution phase.
C. Accuracy of a resultant plan is improved through “brainstorming.”
D. Management expectations regarding plan are transmitted to the team (alignment).
8. Constructability, in terms of schedule modeling, is best defined as:
10. True or False: During a constructability analysis, the availability of specified materials is
determined?
11. True or False: A constructability analysis is only performed during the initial planning stage
Of design?
3
Subchapter 1.2 Considerations and Constraints
1.2.1 Identification of Resources
12. During the planning process for a capital project, which is NOT a consideration?
A. Religious holidays.
B. Local country language.
C. Education and skill level of local craft labor.
D. None of the above.
13. Material resource considerations include all except:
A. Availability
B. Installation
C. Crew skills
D. Timing of delivery
14. Which of the following is NOT a constraining resource?
A. Labor availability
B. Scheduling software
C. Material delivery
D. Craft skill levels
15. True or False: On construction projects, labor and equipment are considered limitless
resources?
16. True or False: The physical constraints of a jobsite can impose a limit on the amount of
simultaneous equipment usage?
1.2.2 Value Engineering
17. Implemented VE provides the contractor with the following, except:
18. Among the six phases of the VE process are all except:
19. True or False: The VE process starts with the submittal of bid price?
20. True or False: The information phase of VE occurs during design development?
1.2.3 Stakeholder Considerations
21. Which of the following documents is probably of LEAST value when planning a contractor’s
baseline critical path schedule for construction of a high-rise building on a remote South
Pacific Resort Island for a private developer? The contract has been awarded.
A. Specifications – as found in the contract document.
B. The local government’s report on future resort projects on the island.
C. International Building Codes – as referenced in the contract document.
D. A project-specific geotechnical report.
22. Which of the following is NOT normally considered a project stakeholder?
A. Project supplier to a subcontractor.
B. Client or owner.
C. Project consultant or engineer.
D. Non-governmental organizations (NGOs)
E. Local news media
4
Section 1B Planning Product
23. When reporting progress and completion forecasts to the client’s management, a schedule that
is organized by the projects work breakdown structure (WBS) structure provides ___________.
A. A useful reporting tool that meets the client’s project team special needs.
B. An “early finish” constraint with a 20 day negative lag on the last activity.
C. A “late start” constraint on the first activity with a 20 day negative lag.
D. A “late finish” constraint on the last activity.
24. When gathering data to document activity progress and observed trends, the activity’s
reported percent complete ______________.
A. Is all that is necessary to forecast remaining duration for that activity?
B. Is used as part of the 6/10 rule to determine the remaining duration for that activity.
C. Must be analyzed in conjunction with all observed activity data (actual start dates,
trends, etc.) to estimate the remaining duration for the activity.
D. Provides sufficient information necessary to determine the activity’s earned value.
25. True or False: Contract deliverables are defined in the scope of work?
26. True or False: Drawings and specifications augment the written scope of work narrative?
29. True or False: WBS is a system by which work activities are organized and summarized into
like activities?
30. True or False: WBS may be organized as a result of capital costing requirements
5
1.3.6 Establish Organizational Breakdown Structure (OBS)
31. When reporting progress and completion forecasts to the client’s management, a schedule that
is organized on the project’s OBS provides ______.
A. A list of all equipment resources utilized on the project.
B. A baseline for change management reporting.
C. A useful reporting tool that meets the client’s project team special needs.
D. Identifies resource utilization, and identifies gaps, utilization variances, and areas of
management attention.
32. A CBS:
A. Should generally not include indirect costs.
B. Is not absolutely essential for effective management of a large project.
C. Allows ready comparison of actual versus planned costs.
D. All of the above.
35. The baseline plan is an end result of the planning process. What is not a basic step in the
planning process that results in the baseline plan?
A. Identification of the project goals and objectives.
B. Scope of work definition.
C. Phase identification and sequencing result in the baseline plan.
D. Identification of the schedule specification.
6
37. The baseline plan is a fixed document and should be changed only if the following occurs:
A. Contract modifications result due to significant changes in the work.
B. Change is allowed whenever one of the primary stakeholders thinks it appropriate.
C. Never
D. Once a year
43. Which of the following types of plans is not associated with risk and recovery?
A. Baseline contingency plan.
B. Budget contingency plan.
C. Recovery plan.
D. Schedule contingency plan.
7
44. Which one of the following is an important processing during planning for risk and recovery?
A. Detailed cost evaluation.
B. Planning for change.
C. Using only the contract.
D. Plan reevaluation for change.
45. Plan recovery is:
A. Always part of the planning process.
B. Sometimes part of the planning process.
C. Usually required during planning.
D. Always used during construction evaluation.
8
1. PLANNING
OPTIONAL QUESTIONS-ANSWERS
9
Section 1A – Planning Development
Subchapter 1.1 Input and Data
10
Section 1B Planning Product
31. D. Identifies resource utilization and identifies gaps, utilization variances, and areas for
Management attention.
11
1. PLANNING
THEORY QUESTIONS
12
Section 1A – Planning Development
Subchapter 1.1 Input and Data
13
Section 1B Planning Product
33. How are the scope of work and the WBS related?
34. How are the WBS and the project schedule related?
35. Describe the difference between a work package and a cost account
37 What is a CBS?
38. How is the CBS related to the WBS and OBS?
39. Can the CBS be broken down between direct and indirect costs?
14
47. Why are budgets often revised?
48. The budgetary process provides the basis for what?
15
1. PLANNING
THEORY QUESTIONS-ANSWERS
16
Section 1A – Planning Development
Subchapter 1.1 Input and Data
2. Milestones are interim completion dates that are either contract driven or contractor self-
imposed to measure progress or trigger subsequent work activities. Their achievement may earn
progress payments for the contractor.
17
Section 1B Planning Product
18
*1.3.8 Sequencing and Phase Relationships
40 Phases are a significant period of time or grouping of activities within the project. The logical,
chronological sequencing of the phases begins the process that builds phases into a schedule.
41. A phase relationship identifies how major work elements will be completed in a logical
manner.
42. Progress monitoring, analyzing, controlling and reporting.
52. Change and risk are inevitable on projects. There must be a plan developed to identify and
manage risk as well as a plan to mitigate negative impacts and exploit positive affects.
53. A risk plan defines how to identify and minimize the effect of risks, whereas a recovery plan
is an array of means or methods to eliminate or reduce undesirable impacts of changes.
54. Maybe and maybe not. Risk might derive, in part, from the possibility of undesirable changes,
but some changes might reduce risk and not increase it.
19
2. SCHEDULING
OPTIONAL QUESTIONS
20
Chapter 2.0 Scheduling
Section 2A. Schedule Development
Subchapter 2.1 Input and Data (from Planning)
2.1.1 Define Schedule Scope
1. If a plan estimates that 5,184 labor-hours will be expended on a series of related construction
activities, and the projected number of construction worker equivalents expected to perform that
activity is 12 personnel working a 12-hour day, what is the calculated overall duration for those
activities? Assume the work is performed sequentially.
A. 6 work weeks
B. 35 calendar days
C. 5 work weeks
D. 36 work days
2. The primary source of information that defines the scope of work that the planner-scheduler
relies upon to create a schedule model is what?
A. Contract specifications.
B. Contract provisions that define scope along with the contractor’s execution plan and
related assumptions.
C. Contract special conditions and specifications.
D. Pre-bid site visit and planning meetings.
21
Subchapter 2.2 Creating Schedule
3. What are three requirements that determine what type of schedule should be utilized on a
project?
A. Cost estimate, number of stakeholders, reporting requirements.
B. Project size, scope, complexity.
C. Project size, project variables, phases definition.
D. Risk and recovery plan, milestones, durations.
2.2.2 Activities
2.2.3 Durations
22
9. Durations may include the following:
A. Multiple elements of the scope of work.
B. Relationships
C. Risk plan
D. Scheduling specification
10. In combining multiple logically tied activities with the duration provides the basis for the
following:
A. Cost estimate model
B. Defines the schedule scope
C. A fragnet schedule duration
D. The baseline schedule
2.2.4 Relationships
11. In addition to relationships and lags, which of the following should not be considered when?
building a schedule?
A. Constraints
B. Calendars
C. Stakeholders
D. Durations
12. Constraints are factors that affect an activity’s start, finish and/or duration. Which of the
following is not an example of a constraint?
A. Calendar
B. Date restraint
C. Stakeholder
D. Weather
13. Which is not a characteristic of typical project calendars?
A. Multiple
B. Weather, environmental, seasonal
C. Workday
D. Based on the type of schedule used.
14. Project calendars are formulated:
A. For estimates
B. To reflect specific, long-running conditions or circumstances.
C. For relationships
D. For resource loading
15. Calendars along with durations provide the basis for an activity’s estimated:
A. Resources
B. Cost
C. Timeframe
D. Relationships
23
2.2.6 Cost / Resource Loading
2.2.7 Milestones
24
24. The schedule basis documentation narrative includes the following:
A. Baseline schedule development and schedule change management procedures.
B. Baseline schedule development and critical/near critical path activities.
C. Critical and near-critical path activities and cost estimate model.
D. Schedule change management procedures and cost and resource management
guidelines.
25. If the baseline schedule is revised and rebaselined, what should one do to the schedule basis
documentation?
A. Leave it as is.
B. Revise the document as necessary when the rebaseline has been approved.
C. Revise the document at the completion of the project.
D. Revise the document monthly.
25
31. From the following list of requirements that an owner might specify for a baseline submittal,
which one is most likely not a requirement?
A. Time for submittal after Notice-to-Proceed.
B. Time for submittal after construction is initiated.
C. Time as a requirement for completion of the work.
D. Time length for increments of long duration activities.
26
2.3.5 Acceleration
39. Which of the following is not a form of acceleration?
A. Crashing
B. Compression
C. Constructive baselining
D. Directive acceleration
2.3.6 Schedule Maintenance Feedback
40. Which is not a resultant of schedule maintenance feedback?
A. Recovery schedules
B. Schedule acceleration
C. Constructability review
D. Control level schedules
41. Stakeholder schedule maintenance feedback includes?
A. Documentation
B. Management
C. Project team
D. All of the above
42. Feedback to the scheduler is not received as?
A. Written responses to previous update reports.
B. Stakeholder meetings
C. Comments from the project team.
D. Contract request for change.
27
2.4.4 Schedule Forecasts
46. The following earned value concepts are included in schedule forecast development?
A. Actual costs
B. Estimate-to-complete (ETC)
C. Schedule variance (SV)
D. All of the above
47. Important factors in developing schedule forecasts do not include?
A. Historical information, along with staffing and manning levels.
B. Future productivity factors.
C. Negative float.
D. Baseline schedule.
48. Why is it important to perform “what-if” scenarios for significant pending change
orders?
A. Impact to schedule and cost.
B. Equipment and material delivery lead time implications.
C. Evaluation of available resources.
D. All of the above.
49. Which of the following is not an element of schedule forecasts?
A. Prediction of future work.
B. Planned sequence of activities.
C. Baseline schedules.
D. Labor and material utilization.
2.4.5 Constructability Review
50. All of the following conditions predicate a constructability review, except which one?
A. Schedule progress
B. Trends
C. Stakeholders
D. Forecasts
2.4.6 Progress Reports and Reviews
51. For what can a progress report be used?
A. Become the basis for historical data.
B. Used to estimate and schedule future work.
C. Convey information concerning the project progress.
D. All of the above.
52. True or False: The progress report includes the following?
A. Status of impacts and delays.
B. Descriptive analysis of progress since last reporting period.
C. Brief statements on short term and long term future work.
D. Various types of progress, trend, and variance graphs and charts.
53. Which is not a characteristic of progress reports?
A. Reliable
B. Fixed
C. Credible
D. Accurate
28
2.4.7 Recovery Schedules
54. What are some common types of recovery schedule techniques?
A. Acceleration, schedule compression, overtime, multiple shifts, or additional
resources.
B. Extending the schedule duration.
C. Reducing manpower or subcontracts.
D. Deceleration of critical activities in order to have non-critical path activities
reaches a par with critical path activities.
29
2. SCHEDULING
OPTIONAL QUESTIONS-ANSWERS
30
2.1.1 Define Schedule Scope
1. D. 36 workdays
2. B. Contract provisions that define scope along with the contractor’s execution plan and related
assumptions.
2.2.2 Activities
5. D. Is constrained in time.
6. B. The schedule
2.2.3 Durations
7. B. Work is always performed continuously from start to finish.
8. C. Activity ID
9. A. Multiple elements of the scope of work.
10. D. The baseline schedule.
2.2.4 Relationships
11. C. Stakeholders
12. C. Stakeholder
13. D. Based on the type of schedule used.
14 B. To reflect specific, long-running conditions or circumstances.
15. C. Timeframe
2.2.7 Milestones
31
2.2.9 Schedule Basis Documentation
2.3.5 Acceleration
39. C. Constructive baselining
32
2.4.4 Schedule Forecasts
46. D. All of the above.
47. A. Historical information, along with staffing and manning levels.
48. D. All of the above.
49. C. Baseline schedules.
33
2. SCHEDULING
THEORY QUESTIONS
34
Chapter 2.0 Scheduling
Section 2A. Schedule Development
Subchapter 2.1 Input and Data (from Planning)
2.1.1 Define Schedule Scope
1. What are three key elements in defining the schedule scope?
2. The basis for the schedule model should include identification of what components?
3. Why is it important to understand how the WBS and OBS are related?
10. Explain why planner-scheduler would choose a linear schedule instead of a network schedule.
11. Explain why different schedules can and should sometimes be used within one project.
2.2.2 Activities
2.2.3 Durations
15. Why is it important to understand the interconnectivity between an activity’s duration,
constraints, and calendar?
16. What is a key element in determining the duration of an activity?
2.2.4 Relationships
16. Name and describe the different types of schedule relationships that are used in scheduling
software tools based on the Precedence Diagram Method (PDM).
17. Describe the function of relationship lags.
18. What is a schedule relationship?
35
2.2.5 Constraints and Calendars
19. Why are multiple calendars used on a project?
2.2.7 Milestones
23. Name six examples of milestones.
24. What is a milestone?
25. True or False: Milestones can be tied to payments?
26. True or False: Milestones should be agreed by principal stakeholders?
36
47. When accelerating a schedule, what should be considered?
48. Why is it important to document and communicate actions, when implementing schedule
acceleration?
37
2. SCHEDULING
THEORY QUESTIONS-ANSWERS
38
2.1.1 Define Schedule Scope
1. The scope of work; computer applications and limitations; and ability to communicate the plan
into a workable schedule.
2. Deliverables, milestones, timing, phasing, sequencing requirements, resources and interface
points.
3. During schedule development the WBS and OBS define the overall work scope and the work
packages.
11. Different schedules should be used within one project based on the phase, system, timeframe,
and complexity of the project. Different schedules are used based on the need of the project
at the time or phase and the need to control that aspect of the project.
2.2.2 Activities
12. An activity is an individual element of work that is logically linked to other activities to form
the schedule. Its primary characteristics include an overall duration based upon the resources
applied to it (manpower, materials and equipment), a start and completion date that is tied to
a work calendar and has relationships to other activities (predecessor and successors).
13. The level of detail must be appropriate for managing the project with concern to duration,
complexity, methodology, cost and risk.
39
2.2.3 Durations
15. The relationship between an activity’s duration, calendar assignment, and constraints form the
basis for determining the overall timeframe required to complete an activity. One must
understand the how constraints and the activity’s calendar directly affect the activity’s
duration, based on the calendar and constraints imposed on either the start or finish of the
activity.
16. A key element in determining the duration of an activity is understanding the scope of the
activity.
2.2.4 Relationships
17. Relationship lags delay start-finish relationships. One should be careful in determining the lag
duration, since preparation time and the actual delay between activities should be considered.
18. A schedule relationship is a logic link between activities that becomes the fundamental tool in
building a schedule network.
2.2.7 Milestones
23. Start milestone.
Finish milestone.
Start no sooner than (constraint).
Start no later than (constraint).
Finish no sooner than (constraint).
Finish no later than (constraint).
24. A milestone is a key event (without duration) that serves to indicate that an interim project
requirement has been achieved. A milestone may be a contractual or functional requirement in
the schedule.
25. True.
26. True.
40
2.2.9 Schedule Basis Documentation
29. This documentation provides the assumptions, constraints and parameters that the
development of the baseline schedule is derived. It also provides the foundation for schedule
change or delay and impact identification.
30. The baseline schedule is the significant document used for identifying and analyzing schedule
change.
2.3.5 Acceleration
45. Directive is when it is directed versus a stakeholders inaction or action in advance of
direction.
46. Delay, increase in work scope, maintaining the current completion date, or expediting the
completion date is an example of acceleration.
47. Effect of multiple shifts, overlapping of activities, overtime, modifying work methods,
increasing or changing of resources, and cost among other elements.
48. Schedule acceleration is often a contractual issue, therefore it is important to communicate the
means, methods, and assumptions used in revising the execution plan.
41
2.3.6 Schedule Maintenance Feedback
49. Continual reassessment is important to the overall success. Feedback may also identify
failures in alignment with the execution plan.
53. Variance and trends can influence the end result of the project. Variances and trends provide
the basis for revisions to the baseline plan, corrective action, alternatives and
recommendations or potential change orders.
54. Earned value concepts assist in the analysis of variances and trends that lead to schedule
forecasts.
55. A. The schedule critical path activity is slipping and impacting completion for the entire
project.
B. The current variance is negative and may continue to grow, based on the difference
between the previous and current reports unless corrective action is taken.
42
2.4.4 Schedule Forecasts
59. Schedule forecasts are a result of actual performance and the analysis of variances
and trends.
60. Contract requirements while meeting the reporting needs of stakeholders.
43