Quality Tool Box Meeting - Format

The document summarizes a quality toolbox talk meeting discussing coating application, defects, and repair for a construction project. It lists 8 topics that were covered, including proper mixing and application of coatings, safety precautions, and standards for defect-free application and repair. An attendance sheet is attached to record the 10 people present at the meeting to discuss raising quality of construction activities through simple process steps.

Uploaded by

Ram
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (4 votes)
3K views2 pages

Quality Tool Box Meeting - Format

The document summarizes a quality toolbox talk meeting discussing coating application, defects, and repair for a construction project. It lists 8 topics that were covered, including proper mixing and application of coatings, safety precautions, and standards for defect-free application and repair. An attendance sheet is attached to record the 10 people present at the meeting to discuss raising quality of construction activities through simple process steps.

Uploaded by

Ram
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Hh ALKIFAH CONTRACTING COMPANY (KCC)

MARJAN DEVELOPMENT PROGRAM TEMPORARY CONSTRUCTION FACILITIES


Contract No. 6600042840 Under B.I No.-10-09003-000

Quality Toolbox Talk Meeting


The objective of this Document is to give information on a system called Quality Tool Box Talk Meeting (QTBTM) that will
help raise the quality of construction activities in project smoothly and with simple steps.

Meeting No: KCC-MARJAN-QTTM-63


Date : 29 April, 2019
Time : 10:20 AM
Location / Area : Jubail MCCL Yard 2 / MARJAN

LIST OF ATTENDEES: (See Attached Attendance Sheet / Photo)


TITLE TOPIC DISCUSSED: Coating Application , Defects and Repairing.
Check list (SAIC) and SATIP for the specific activity.
Item ACTION BY:
Topic Item
No. (If Required etc.)
Prior to application, all coating shall be thoroughly mixed until it is
1 homogeneous. For quantities over 5L, a power stirrer shall be used.( SAES-H- Applicators, Crew Supervisor
001-9.2.2)
Applicators, Crew Supervisor
2 Coatings, which have gelled, shall not be used. ( SAES-H-001-9.2.1)

Solvents shall not be flushed into containers that are hotter than 50°C. Applicators, Crew Supervisor
3
(SAES-H-001 -5.4.5.10)
Coatings shall be mixed in an open area or in an adequately ventilated area. Applicators, Crew Supervisor
Use eye protection (goggles), respirators, protective gloves and other safety
4 equipment. (SAES-H-001-5.4.4.1)

Applicators, Crew Supervisor


Solvents and coatings shall not be applied to surfaces warmer than 50°C if
5
practical alternatives exist. (SAES-H-001-5.1.3)

Neither compressor air nor equipment cleaning solvents shall be used by Applicators, Crew Supervisor
6
personnel for personal cleaning or personal cooling. (SAES-H-001-5.3.5)
Generally free of application related defects such as runs, sags, drips, dry Applicators, Crew Supervisor
7
spray or foreign matter. (SAES-H-001-9.3.5-b)
For areas less than 0.1 m², grind to a rough metal surface using at least an 80 Applicators, Crew Supervisor
8 grit disc sander. Alternatively spot blast or power tool cleaning to bare steel.
Feather edge of coating at least 25 mm beyond bare metal. (SAES-H-001-9.6.3)

Controlled Form No: QTTM-001 Rev.00 NOV 20, 2018 Distributions: QC/Engineer/Foreman-Attendee File Original: Quality DC
Prepared By: NRL
ALKIFAH CONTRACTING COMPANY (KCC)
MARJAN DEVELOPMENT PROGRAM TEMPORARY CONSTRUCTION FACILITIES
Contract No. 6600042840 Under B.I No.-10-09003-000

Quality Toolbox Talk Meeting


ATTENDANCE SHEET NO: KCC-MARJAN-QTTM-

Date Conducted: 17 April, 2019

Sr. No Name Position Company Email/Phone No. Signature

10

Conducted/Prepared By: Monitored/Observed By: Reviewed/Noted By:

QC Inspector QC SUPERVISOR QC Manager


KCC KCC KCC

Adjourned Date/Time:
Next Quality Toolbox Talk Meeting:

Controlled Form No: QTTM-001 Rev.00 NOV 20, 2018 Distributions: QC/Engineer/Foreman-Attendee File Original: Quality DC