FP - Method of Statement - Al Pheniq

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 9

TECHNICAL DEPARTMENT

Doc. No. ALP/QR/119-MOS


UNION CEMENT COMPANY
METHOD STATEMENT Issue Date 27 July 2014
Method statement for installation and inspection of fire fighting Rev. Date NA
AL PHENIQ system. Pages 1 of 9

METHOD STATEMENT FOR INSTALLATION AND


INSPECTION OF FIRE FIGHTING SYSTEM

FIRE FIGHTING SYSTEM FOR UNION CEMENT COMPANY


PROJECT :
RAS AL KHAIMAH

CLIENT : UNION CEMENT COMPANY

LEAD CONSULTANT : EMCO ENGINEERING CONSULTANT


TECHNICAL DEPARTMENT
Doc. No. ALP/QR/119-MOS
UNION CEMENT COMPANY
METHOD STATEMENT Issue Date 27 July 2014
Method statement for installation and inspection of fire fighting Rev. Date NA
AL PHENIQ system. Pages 2 of 9

TABLE OF CONTENTS
1. REVISION RECORD .......................................................................................................................................... 3
2. SCOPE ............................................................................................................................................................... 4
3. PURPOSE .......................................................................................................................................................... 4
4. REFERENCES ................................................................................................................................................... 4
4.1. Contract documents .................................................................................................................................... 4
4.2. Contractors Submittal...................................................................................Error! Bookmark not defined.
5. DEFINITIONS / ABBREVIATIONS .................................................................................................................... 4
5.1. Definition ....................................................................................................................................................... 4
5.2. Abbreviations ............................................................................................................................................... 5
6. QUALITY CONTROL ......................................................................................................................................... 5
7. EQUIPMENTS/ TOOLS / MANPOWER/MATERIALS ....................................................................................... 5
7.1. Materials used .............................................................................................................................................. 5
7.2. Tools & equipment ....................................................................................................................................... 5
8. FIRE FIGHTING SYSTEM DESCRIPTION ........................................................................................................ 6
9. WORK SEQUENCE AND METHODOLOGY ..................................................................................................... 6
9.1. Storage and handling................................................................................................................................... 6
9.2. General Piping Installation Guidelines ....................................................................................................... 6
9.3. Installation of pipes...................................................................................................................................... 6
9.4. Installation of Fire Hose Reel / Fire Hose Cabinets................................................................................... 7
9.5. Threaded Joints............................................................................................................................................ 7
9.6. Offsets and Fittings...................................................................................................................................... 7
9.7. Painting ......................................................................................................................................................... 8
9.8. Flushing: Cleaning of Piping and Equipment ............................................................................................ 8
10. HEALTH AND SAFETY ................................................................................................................................. 9
TECHNICAL DEPARTMENT
Doc. No. ALP/QR/119-MOS
UNION CEMENT COMPANY
METHOD STATEMENT Issue Date 27 July 2014
Method statement for installation and inspection of fire fighting Rev. Date NA
AL PHENIQ system. Pages 3 of 9

1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All
previous revisions are hereby superseded and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions

0 27-Jul-14 First issue

Signature field
Revision
Revision
Number 0
Date
Prepared by Checked by

Reviewed
By Project
Engineer

Approved
By Projects
Manager
TECHNICAL DEPARTMENT
Doc. No. ALP/QR/119-MOS
UNION CEMENT COMPANY
METHOD STATEMENT Issue Date 27 July 2014
Method statement for installation and inspection of fire fighting Rev. Date NA
AL PHENIQ system. Pages 4 of 9

2. SCOPE
This procedure covers installation and inspection of Fire Fighting System

3. PURPOSE
The purpose of this procedure is to define the method of installation and inspection of Fire Fighting System

4. REFERENCES
4.1. Documents
1. Project Specification:-
2. Tender Drawings :-
3. Material approvals
Sr. No. Description Material Sub. No. Rev No. Date Remarks
1
2
3

4. Shop Drawings
Sr. No. Description Shop Drawings Rev No. Date Remarks
1
2
3

5. Related method Statements


Sr. No. Description MET no. Rev No. Date Remarks
1
2
3

5. DEFINITIONS / ABBREVIATIONS
5.1. Definition
1. Project -Union Cement Company, Fire Protection System
2. Client -Union Cement Company (P.S.C)
3. Consultant -Emco Engineering Consultant
4. Contractor -
5. Supplier -As per Vendors List
TECHNICAL DEPARTMENT
Doc. No. ALP/QR/119-MOS
UNION CEMENT COMPANY
METHOD STATEMENT Issue Date 27 July 2014
Method statement for installation and inspection of fire fighting Rev. Date NA
AL PHENIQ system. Pages 5 of 9

5.2. Abbreviations
1. ICL - Inspection Check List
2. IR - Inspection Request
3. ITL -Independent Testing Laboratory
4. ITP - Inspection and Test Plan
5. ITR -Inspection & Test Requests
6. MAT - Material Submittal
7. MEP - Mechanical Electrical Plumbing
8. MET - Method Statement
9. MIR - Material Inspection Request
10. MSDS - Material Safety Data Sheet
11. PPE -Personal Protective Equipment
12. PQP -Project Quality Plan
13. PTW -Permit To Work ( Working at Height or enclosed spaces)
14. RA -Hazard Identification and Risk Assessment
15. RFIA - Request for Inspection and Approval
16. SPD - Shop Drawing
17. TBM - Temporary Bench Mark

6. QUALITY CONTROL
1. Quality of installation and materials at site will be ensured by our project team consisting of a Project
Manager, Project Engineers, the site Foremen. All will be according to the Specification, NFPA
standards and /or local civil Defence authority requirements.

7. EQUIPMENTS/ TOOLS / MANPOWER/MATERIALS


7.1. Materials used
1. All materials to be used are as per the approved material submittals.

7.2. Tools & equipment


The following Tools and Equipment will be used for Fire Fighting System Installation:
1. Grooving Machine
2. Threading Machine
3. Welding Machine
4. Drill Machines
5. 14” Grinding Machine
6. Pipe Cutter
7. Pressure Machine (Elec/ Manual)
8. HDPE Welding Machine
9. Smoke & Heat Tester
10. Aluminium Ladder
TECHNICAL DEPARTMENT
Doc. No. ALP/QR/119-MOS
UNION CEMENT COMPANY
METHOD STATEMENT Issue Date 27 July 2014
Method statement for installation and inspection of fire fighting Rev. Date NA
AL PHENIQ system. Pages 6 of 9

8. FIRE FIGHTING SYSTEM DESCRIPTION


1. Fire Hose Reel
1. Automatic Wet System
2. It is a system that is attached to a water supply capable of supplying the system demand at all fires
and that requires no action other than opening a hose valve to provide water at hose connection.
2. System Components
3. Network of pipes
4. Fire hose & fire hose reel cabinets
5. Landing Valves
6. Pressure reducing valves
7. Air release valve
3. 1”Fire Hose Reel & 2 1/2” Fire Hose System
8. As per approved shop drawings.
4. Minimum pressure of stand pipe
9. The fire water demand shall be calculated based on the flow rates of landing valves and fire hose reels
or racks installed in the wet riser system. The minimum flow rate at the hydraulically remotes 65mm
dia landing valve in a wet riser shall be not less than 250 GPM at the residual pressure of 7 bar
10. The minimum flow rate at hydraulically remotest 25 mm dia hose reel in a fire fighting system shall be
6.5 GPM at the residual pressure of 4.5 bar and for the hydraulically remotest 40 mm dia hose valve in
a fire fighting system shall be 100 GMP at the residual pressure of 4.5 bar.

9. WORK SEQUENCE AND METHODOLOGY


9.1. Storage and handling
1. The pipes will be stacked in the site store on a flat surface at a height not exceeding 1.7m from the
bottom layer. Fittings will be separately packed and stored as per the sizes required for the project. All
open ends of pipes will be covered to protect from foreign matter, dirt/debris.

9.2. General Piping Installation Guidelines


1. Pipe work shall be installed in accordance with the piping general arrangements and their supporting
drawings, specifications and schedules.
2. Installation of pipe work shall be carried out under conditions satisfactory to the contractor.
3. All work performed and completed must meet the approval of the contractor.
4. Scheduling of work to carry out the installation of pipe work shall be agreed and to the satisfaction of
the contractor and shall be co-coordinated with the work schedules of other trades and disciplines
involved in the overall construction.

9.3. Installation of pipes


1. Run all piping as direct as possible, avoiding unnecessary offsets and conceal piping in finished rooms.
2. 2” and below sizes of pipes are made threaded, 2 ½” and above sizes are normally grooved type.
Groove can be made Cut groove or Roll groove. We will make Roll Grooves utilizing manufacturers
Roll Grooving Tools
3. Make tee connections with standard tee fittings for full size branches.
TECHNICAL DEPARTMENT
Doc. No. ALP/QR/119-MOS
UNION CEMENT COMPANY
METHOD STATEMENT Issue Date 27 July 2014
Method statement for installation and inspection of fire fighting Rev. Date NA
AL PHENIQ system. Pages 7 of 9

4. All piping must be rigidly supported by a combination network comprised of pipe hangers and rigid
support brackets. Pipe hangers are used to support the “dead load” of the pipe system. Pipe hangers
will be spaced according to the relevant NFPA standard / Specification clause and Hanger rod sizes and
numbers will comply with the requirement of the respective NFPA standard / Specification clause or
Manufacture’s recommendations.

9.4. Installation of Fire Hose Reel / Fire Hose Cabinets


1. Check cabinets are approved size and dimension. Inspect for signs of damage.
2. Locate exact location of these Cabinets as per approved shop drawings and with careful measure of
elevation.
3. Fix cabinet using recommended Rawl (anchor bolts) bolts. Proceed with installation of accessories, lock
shield valve, landing valves, etc. taking in consideration of approval for these devices.
a. Installation of Breaching Inlet
4. Locate Breaching inlet cabinet and its accessories as shown on the shop drawing near the main
entrance of the building for Civil defence inject water in to the system in case of emergency.

9.5. Threaded Joints


1. Threaded piping will be made with Teflon tape or with a suitable pipe sealing compound (jute and
mastic combination) applied on male threads only. Ends of pipe will be reamed out before being made
up into fittings.
2. Joints in threaded steel pipe will conform to the American National taper pipe thread, ANSI B1. 20.1 Or
British Standard BS 21. All burrs will be removed, pipe ends will be reamed or filed out size of bore,
and all chips will be removed.
a. Pipe Fabrications and Installation
3. Make piping layout and installation in the most advantageous manner possible with respect to
headroom, valve access, opening and equipment clearance, and clearance for other work, particular
attention will be given to piping in the vicinity of equipment. Preserve the equipment parts for
maintenance.
4. Cut all pipes accurately to measurement determined at the site. After cutting the pipe, ream it and
remove all burrs.
5. Install piping neatly, free from unnecessary traps and pockets. Work into place without springing or
forcing. Use fittings to make all changes in direction. Make all connections to equipment using flanged
joints or unions. Make reducing connections with reducing fittings only.
6. Remove dirt, scale and other foreign matter from inside piping before tying in sections, fitting, valves
or equipment.

9.6. Offsets and Fittings


1. Carefully investigate the structural and finish conditions affecting the work and take such steps as may
be required to meet such conditions.
2. Install all piping close to walls, ceilings and columns so piping will occupy the minimum space. Proper
space will be provided for covering and removal of pipe, special clearance, and for offsets and fittings.
3. Pipe work will be installed not closer than 200 mm to electrical conduits, lighting, and power cables.
Pipes will be spaced in ducts, ceilings, voids and plant areas, such as adequate access is permitted to
TECHNICAL DEPARTMENT
Doc. No. ALP/QR/119-MOS
UNION CEMENT COMPANY
METHOD STATEMENT Issue Date 27 July 2014
Method statement for installation and inspection of fire fighting Rev. Date NA
AL PHENIQ system. Pages 8 of 9

any pipe for maintenance or removal without disturbance to the remaining pipe work and other
services.
4. Pipes will not be solidly built into walls or plaster. Pipe joints will not be positioned within the
thickness of walls, floors or in any other inaccessible position. Pipes passing through walls and floors
will be sleeved;
5. Couplers, unions and fittings will be screwed up to the reduced depth of the thread, such that no more
three-turns are showing when pulled up tight.
6. All pipes, valves and fittings and connected equipment will be thoroughly cleaned of rust, sand and
dust, scale and other foreign matter before erection and before any initial fill water for hydraulic
testing.
7. Prior to hydraulic testing, all pipe work systems including valves, strainers and fittings will be washed
thoroughly. Any washing of the piping systems will be carefully carried out where there are isolation
valves or equipment are employing.
8. Any stoppage due to foreign matter or air lock which is found to impede the flow of fluid will be
removed, either before or after the systems are in operation.
9. Fittings will be of the eccentric pattern to ensure proper drainage and the elimination of air pockets
wherever necessary. Increases or decreases in pipe diameters required to suit fittings, tee-offs and
equipment connections will be formed using taper pieces, flanged as
10. Required with taper reduction located about axis of the pipe to facilitate proper flow and to allow
proper venting and draining of the pipes. The angle of the taper of such fabricated taper pieces will not
be greater than twenty (20 ▫) degree.

9.7. Painting
1. All pipes will be cleaned inside and outside for removal of dust and debris before painting.
2. One coat of Approved Red-oxide Primer will be applied of 35 Microns film thickness
3. After drying, one coat of Approved Enamel Paint will be applied of 35 Microns film thickness before
installation of pipe.
4. Finally one coat of Approved Enamel Paint of 35 Microns will be applied after hydraulic test and in the
final stages.

9.8. Flushing: Cleaning of Piping and Equipment


1. After piping is erected, all piping systems including main header line and branch line will be cleaned to
remove all mill, welding scale, oil, corrosion, and other construction debris.
2. System will be flush cleaned and filled ready for service immediately after cleaning.
3. Do not operate pumps or equipment until debris has been removed from the respective system has
been flushed out.
4. Flushing of the system can be done from a pumping source with minimum flow rate to provide a
velocity of 3 m/ sec.
5. Flush the piping system until all debris is removed and clean water comes out.
6. Automatic devices which can become clogged during the cleaning process will be disconnected and
will not be connected permanently until the cleaning process is complete.
TECHNICAL DEPARTMENT
Doc. No. ALP/QR/119-MOS
UNION CEMENT COMPANY
METHOD STATEMENT Issue Date 27 July 2014
Method statement for installation and inspection of fire fighting Rev. Date NA
AL PHENIQ system. Pages 9 of 9

10. HEALTH AND SAFETY


1. Work shall strictly follow as per the Client’s / Consultant’s Health & Safety recommendations for
handling and use of the materials. Ensure all involved personnel shall be aware of the same.

You might also like