FP - Method of Statement - Al Pheniq
FP - Method of Statement - Al Pheniq
FP - Method of Statement - Al Pheniq
TABLE OF CONTENTS
1. REVISION RECORD .......................................................................................................................................... 3
2. SCOPE ............................................................................................................................................................... 4
3. PURPOSE .......................................................................................................................................................... 4
4. REFERENCES ................................................................................................................................................... 4
4.1. Contract documents .................................................................................................................................... 4
4.2. Contractors Submittal...................................................................................Error! Bookmark not defined.
5. DEFINITIONS / ABBREVIATIONS .................................................................................................................... 4
5.1. Definition ....................................................................................................................................................... 4
5.2. Abbreviations ............................................................................................................................................... 5
6. QUALITY CONTROL ......................................................................................................................................... 5
7. EQUIPMENTS/ TOOLS / MANPOWER/MATERIALS ....................................................................................... 5
7.1. Materials used .............................................................................................................................................. 5
7.2. Tools & equipment ....................................................................................................................................... 5
8. FIRE FIGHTING SYSTEM DESCRIPTION ........................................................................................................ 6
9. WORK SEQUENCE AND METHODOLOGY ..................................................................................................... 6
9.1. Storage and handling................................................................................................................................... 6
9.2. General Piping Installation Guidelines ....................................................................................................... 6
9.3. Installation of pipes...................................................................................................................................... 6
9.4. Installation of Fire Hose Reel / Fire Hose Cabinets................................................................................... 7
9.5. Threaded Joints............................................................................................................................................ 7
9.6. Offsets and Fittings...................................................................................................................................... 7
9.7. Painting ......................................................................................................................................................... 8
9.8. Flushing: Cleaning of Piping and Equipment ............................................................................................ 8
10. HEALTH AND SAFETY ................................................................................................................................. 9
TECHNICAL DEPARTMENT
Doc. No. ALP/QR/119-MOS
UNION CEMENT COMPANY
METHOD STATEMENT Issue Date 27 July 2014
Method statement for installation and inspection of fire fighting Rev. Date NA
AL PHENIQ system. Pages 3 of 9
1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All
previous revisions are hereby superseded and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions
Signature field
Revision
Revision
Number 0
Date
Prepared by Checked by
Reviewed
By Project
Engineer
Approved
By Projects
Manager
TECHNICAL DEPARTMENT
Doc. No. ALP/QR/119-MOS
UNION CEMENT COMPANY
METHOD STATEMENT Issue Date 27 July 2014
Method statement for installation and inspection of fire fighting Rev. Date NA
AL PHENIQ system. Pages 4 of 9
2. SCOPE
This procedure covers installation and inspection of Fire Fighting System
3. PURPOSE
The purpose of this procedure is to define the method of installation and inspection of Fire Fighting System
4. REFERENCES
4.1. Documents
1. Project Specification:-
2. Tender Drawings :-
3. Material approvals
Sr. No. Description Material Sub. No. Rev No. Date Remarks
1
2
3
4. Shop Drawings
Sr. No. Description Shop Drawings Rev No. Date Remarks
1
2
3
5. DEFINITIONS / ABBREVIATIONS
5.1. Definition
1. Project -Union Cement Company, Fire Protection System
2. Client -Union Cement Company (P.S.C)
3. Consultant -Emco Engineering Consultant
4. Contractor -
5. Supplier -As per Vendors List
TECHNICAL DEPARTMENT
Doc. No. ALP/QR/119-MOS
UNION CEMENT COMPANY
METHOD STATEMENT Issue Date 27 July 2014
Method statement for installation and inspection of fire fighting Rev. Date NA
AL PHENIQ system. Pages 5 of 9
5.2. Abbreviations
1. ICL - Inspection Check List
2. IR - Inspection Request
3. ITL -Independent Testing Laboratory
4. ITP - Inspection and Test Plan
5. ITR -Inspection & Test Requests
6. MAT - Material Submittal
7. MEP - Mechanical Electrical Plumbing
8. MET - Method Statement
9. MIR - Material Inspection Request
10. MSDS - Material Safety Data Sheet
11. PPE -Personal Protective Equipment
12. PQP -Project Quality Plan
13. PTW -Permit To Work ( Working at Height or enclosed spaces)
14. RA -Hazard Identification and Risk Assessment
15. RFIA - Request for Inspection and Approval
16. SPD - Shop Drawing
17. TBM - Temporary Bench Mark
6. QUALITY CONTROL
1. Quality of installation and materials at site will be ensured by our project team consisting of a Project
Manager, Project Engineers, the site Foremen. All will be according to the Specification, NFPA
standards and /or local civil Defence authority requirements.
4. All piping must be rigidly supported by a combination network comprised of pipe hangers and rigid
support brackets. Pipe hangers are used to support the “dead load” of the pipe system. Pipe hangers
will be spaced according to the relevant NFPA standard / Specification clause and Hanger rod sizes and
numbers will comply with the requirement of the respective NFPA standard / Specification clause or
Manufacture’s recommendations.
any pipe for maintenance or removal without disturbance to the remaining pipe work and other
services.
4. Pipes will not be solidly built into walls or plaster. Pipe joints will not be positioned within the
thickness of walls, floors or in any other inaccessible position. Pipes passing through walls and floors
will be sleeved;
5. Couplers, unions and fittings will be screwed up to the reduced depth of the thread, such that no more
three-turns are showing when pulled up tight.
6. All pipes, valves and fittings and connected equipment will be thoroughly cleaned of rust, sand and
dust, scale and other foreign matter before erection and before any initial fill water for hydraulic
testing.
7. Prior to hydraulic testing, all pipe work systems including valves, strainers and fittings will be washed
thoroughly. Any washing of the piping systems will be carefully carried out where there are isolation
valves or equipment are employing.
8. Any stoppage due to foreign matter or air lock which is found to impede the flow of fluid will be
removed, either before or after the systems are in operation.
9. Fittings will be of the eccentric pattern to ensure proper drainage and the elimination of air pockets
wherever necessary. Increases or decreases in pipe diameters required to suit fittings, tee-offs and
equipment connections will be formed using taper pieces, flanged as
10. Required with taper reduction located about axis of the pipe to facilitate proper flow and to allow
proper venting and draining of the pipes. The angle of the taper of such fabricated taper pieces will not
be greater than twenty (20 ▫) degree.
9.7. Painting
1. All pipes will be cleaned inside and outside for removal of dust and debris before painting.
2. One coat of Approved Red-oxide Primer will be applied of 35 Microns film thickness
3. After drying, one coat of Approved Enamel Paint will be applied of 35 Microns film thickness before
installation of pipe.
4. Finally one coat of Approved Enamel Paint of 35 Microns will be applied after hydraulic test and in the
final stages.