Civil Engineer Notes
Civil Engineer Notes
Civil Engineer Notes
Acre Canals Acre Marla Canals Marla Acre sqft Canals sqft Marla Water volume 100 gallon
sqft liter
1 8 1 160 1 20 43560 5445 272.25 2831 748
Kilogram Pound lbs Hot weather Cold weather Rft in mtr Sqft in mtr Mm in micron
1 2.204 32cg 4 cg Rft/3.28 Sqft/10.75 1mm=1000mi
c
Convert To,
Mpa to psi= 38*145=5500 mpa
Psi to mpa= 5500/145=38 mpa
TYPES OF RATIO
Class A: 1:1:2
Class B: 1:11/2:3
Class C: 1:2:4
Class D: 1:3:6
Class E: 1:4:8
According to Indian standard specification,
M10 1:3:6
M15 1:2:4
M20 1:1/2:3
M25 1:1:2 OR 1:4:8
QUANTITY BRICK OF WALL
For 9 inch: 100*1350/100=1300 Bricks
For 4 inch: 100*650/100=650 Bricks
For 13 inch: 100*1950/100=1950 Bricks
Ratio of plaster
Internal & external: int 1:4 to 1:6 ext 1:5 to1:6
SAND QUANTITY IN BRICK MASONRY Required 177 Cft
So,
100x30/100=53.1cft
Then,
Ratio 1:4
Sum of ratio: 1+4=5
Quantity of cement:
1/5x53.1cft =10.62 Cft
Or
10.62/1.25=8.496 bags
Quantity of sand:
4/5x53.1cft =42.48 Cft
QUANTITY IN PLASTER
Required 177 sqft, example ¾” thick plaster
So,
177x3/4x1/12=11.0625cft
11.0625x Dry volume 1.27=14.049cft
Then,
Ratio 1:3
Sum of ratio: 1+3=4
Quantity of cement:
1/4x14.049=3.51 Cft or 3.51/1.25=2.8098 bags
Quantity of sand:
3/4x14.049=10.53 Cft
4
Class : Liter
A : 25
B : 27
C : 30
D : 34
E : 34
Quantity of Concrete
Required 177 Cft, example Ratio 1:2:4
So,
177xDry volume 1.54 x=272.58cft
Then,
Ratio 1:2:4
Sum of ratio: 1+2+4=7
Quantity of cement:
1/7x272.58=38.94 Cft or 38.94/1.25=31.152 bags
Quantity of sand:
2/7x14.049=77.88 Cft
Quantity of Crush:
4/7x14.049=155.76 Cft
Short formula
For class C concrete
For example
10*10*.5=50*.22 cement
10*10*.5=50*.44 sand
10*10*.5=50*.88 crushes
Quantity of RBC Concrete
Required 177 Cft, example Ratio 1:2:4
So,
177x29/100 =51.33 Cft
51.33x1.54=79.048 Cft
Then,
5
Ratio 1:2:4
Sum of ratio: 1+2+4=7
Quantity of cement:
1/7x272.58=79.048 Cft or 38.94/1.25=31.152 bags
Quantity of sand:
2/7x79.048 =79.048 Cft
Quantity of Crush:
4/7x79.048 =79.048 Cft
PARTS OF FLOOR
Sub Base: Take a Stone Ballast
Base: Take a Concrete
Topping: Take a Terrazzo Etc
What is the culvert-If any bright length less than 6 meter, so that’s called culvert,
Deck:-on the bright where going the traffic that’s called deck,
Wheel guard:- on the bridge edge casting concrete pad that’s called WG
Parapet:- on the Bridge edge concrete wall that’s called PW
Spread foundation, where land is hardness, so there we can use the spread foundation,
6
Raft foundation: when the land bearing capacity low, so there we will use the raft
foundation
Pile foundation: Pile foundations consist of piles that are nbgf into the soil till a layer of
stable soil is reached. Pile foundations transfer building load to the bearing ground with
greater bearing capacity. Pile foundations are useful in regions with unstable upper soil that
may erode, or for large buildings.
Surface water:-when the water store on the natural land that’s called sw.
Sub surface water: - when the water store on land and after down in the land that’s called
SSW,
Used of proofing chemical in Dpc: empermo or pudlo
Bitumen mastic: - sand and hot bitumen that’s called BM.
Bitumen membrane:-4mm elastomeric bitumen membrane
Hot laid bitumen/coil tar epoxy primer: - on the dpc take a 1.75 kg per mtr square,
Component of floor:
1. Sub base
2. Base
3. Toping
2. Specification
3. Rates
1. Stretcher bond: in this type of bond all the bricks are laid as stretchers on the faces
this is use only 11 cm wall
2. Header bond: in this type of bond all the bricks are laid as header on the faces of wall
it is suitable for one brick wall only,
3. English bond, this type of bond alternate courses of header and stretcher,
4. Flemish bond: in this type of bond each courses layer one brick header face and
alternate one stretcher face.
5. Dutch bond
6. Raking bond
8
7.
American band
Kinds of cement
1. Ordinary port land cement initial time 30 min and final time 10hrs
3. Quick setting cement, initial time just 5 min and final setting time 30 min, and use for
running water , store tank,
4. High alumina cement initial time 3 min and use for cold weather and also sea places,
Cement ingredients
Lime, silica, alumina, Iron oxide, magnesium oxide, sulphur trioxide, alkalis,
1. Pre-tension rcc;-before pouring concrete tension the steel bar, that called Pre tension
2. Post stressed rcc, after concrete tension the steel bar that’s called post stressed
Slum test:-
ASTM C143 Slum con height 300mm top width 100mm and bottom 200
1. For beam or slab, from 100+-25
Sticking damp material: on the concrete take the Ginny bags(boric)after start the
curing on Ginny bags etc
where shortage the water also cold weather their use the (CC) calcium chloride how’s
use mix the water cement ratio
Steam curing, the use for precast concrete, & temperature 65C
Concreting in hot weather: first of all use the cold water cold sand cold aggregated ,and can
use Maia nitrogen or carbonic acid gas,+ICE
Concreting in cold weather, use the hot water, sand, aggregate and heater, also can use
potassium carbonate or calcium nitrite and sodium nitrite and also air entraining agents.
Literarily ties
1. Civil engineering that deals with the design, construction, and maintenance of the physical
and naturally built environment, including works like roads, bridges, canals, dams, and
buildings.
Types of foundation
1. Shallow foundation 2.deep foundation
1. Shallow foundation
.Raft foundation
Spread foundation
Step foundation
Mat foundation
Grillage foundation
Isolated footing
2. Deep foundation
Pile foundation: a pile is a ling vertical load transferring member composed of either timber
steel or concrete in pile foundation a number of piles are driven in the base of the structure
the pile foundation is generally use when the soil is compressible water logging and made up
type, it is most suitable for bridges,
PIER FOUNDAITON
WELL FOUNDATION
Classification of piles
Bearing piles
Friction piles
Compaction piles
Batter piles
What is shoring?
That’s mean. Supporting to unsafe structure that’s called shoring.
Thread,
The horizontal upper part of a step on which foot is placed in ascending o descending a
stairway, is called tread,
Riser,
A vertical portion of a step providing a support to the tread is called riser
Concrete technology,
Workability,
The concrete should have good workability & depends on quantity of water and percentage of
fine materials.
Segregation,
Separation of coarse aggregate from concrete. That’s called segregates
Bleeding,
Separation of water from concrete that’s called Bleeding,
Durability
The hardened concrete must be durable to resist the effects of rain frost action etc,
Shrinkage:
The hardened concrete should exhibit minimum shrinkage,
11
Creep,
The hardened concrete should be subjected to minimum creep,
Sec: Saudi electric company
Tes: transmission engineering standard
Tcs : transmission construction standard
Concrete under foundation: type 5 Sulfate resistant Cement and also use the micro silica
Concrete super structure type 1 opc
Fddt Test: field density dry test for compaction soil and that 2 method. .
Nuclear ASTM D 2922
Sand con ASTM D 1556
SCOPE
This Transmission Material Standard Specification (TMSS) specifies the minimum
Requirements for mix design, mixing, delivery and testing of Normal Weight Ready-Mixed
Portland Cement Concrete for in-situ or Precast intended to be used in the Transmission
System of Saudi Electricity Company (SEC), Saudi Arabia.
96.2*2.10%*mc 107%
1. Repairing
14
2. Primer coat
3. Epoxy
1. Repairing
15
2. Primer coat
16
3. Paint coat
International standard
ASTM D 421 DRY SOIL SAMPLES
Abrasion test…sieve analysis…cbr test.. Procter test…plastic limit…sand equaland
2
27
28
Read till
43
44
45
46
47
48
49
50
51
52
Read till
53
1. What is QA/QC?
3. What is schedule Q?
Ans: Schedule Q is an attachment to the contract, which is provision of Quality Assurance
and Control, Inspection and Test Plan
Ans: Request for Inspection (RFI). RFI shall be raised only when the status of the preliminary
inspection is satisfactory, and the work (items) are Hold or Witness points.
Ans: ITP means Inspection and Test Plan, details of work scope and required types of
inspection.
Surveillance (S) inspector has right to conduct random inspection if works.
Hold Points client inspection must require through RFI and cannot be proceed until
inspection is done by client.
Witness Point (W) is the level of inspection that inspection activity can be proceeded
without client inspection or if client is not available as per RFI timing.
1. Concrete surfaces in contact with the cementitious grout shall be saturated with clear
water for a minimum of 24hours.
2. The type of bolts is used for structural steel connectors is A325.
61
3. 4hrs is a hydro test carried out on an uncovered oily water sewer line.
4. 24hrs is a hydro test carried out on a covered oily water sewer line.
150mm minimum thickness of sand bedding for a pipe in a trench.
Silica fume
Acquire more strength and for durability for concrete
68
69
70
71
72
73
74
75
76
77
78
79
80
81
4- What is PQP and which Saudi Aramco Standard to be followed for PQP
SAEP 1154
5- What is the Management Responsibilities as per Schedule Q
Ans in according with ISO 9001 contractor top management will review the
project specification every six months to insure the QS is suitable for project.
11- What is the Saudi Aramco Procurement Procedure as per Schedule Q >
Required quality documents in the procurement of equipment and material to
use or installed during construction as per the contract
12- What are the Level of Inspection and which Saudi Aramco procedure to
be followed
Ans SAER 1972
13- What is SA 175 Form and when it will be used
Ans Special inspection form for inspection
audits complete and status of open corrective action for NC Reports &
quality personnel list and request for engineering waivers
15- What are the reports included in Weeks Quality Reports > density test
report with omc and completed earth work report.
16- How to control the NCRs in Construction Projects> proper maintain the
quality work and day by day instruction to site team related quality also by
pro-active.
17- Who will responsible to review and record the special SA175 form
Contractor
18- How to control and monitoring Measuring Devices insure & monitor the
calibration certificates by monthly wise and calibration not more than 12
months
What are the steps for measurement, improvement of Contractor QMS
Customer satisfaction
▪ Internal and external audits
▪ Internal and external Non-conformities
▪ Repeat violations
▪ Process performance measures
▪ Data analysis
▪ Management reviews
▪ Preventive action
▪ Corrective action
19- What are the requirements of SA1972
Ans documents copy of PO company standard and inspection requirement
ITP agenda for each pre inspection
20- What are the Quality activities during pre- commissioning stage
Comply with the Pre-commissioning quality requirements of approved Quality Plan
and Schedule “B”.to complete pre-commissioning activities and document and
correct any of non-conformances shall be submitted to the Company Representative
What is Quality Objectives> proper main the quality and insure documents
quality related. Monitor the calibration certificates day by day material
inspection .focus on testing etc
21- What is the process and requirements for contractor supplied materials :
approved submittal for material delivery notes/manufacture testing report …
22- What are requirements of Quality Dossier ITP/WP/RFI/QR/NCR/PRO-
ACTIVE
84
28- What is standards for Approval procedure for ready mixed concrete mix
design?? SAEP 1152
85
86
87
88
89
90
91