INSP-F01 WICS Form (Rev.10 - Oct2015)
INSP-F01 WICS Form (Rev.10 - Oct2015)
WICS/CS/2019/001
INSPECTION SECTION, TSD, PC FKSB 06.01.03 L3 QP-TSD-INSP-003 Appendix 3 NO.
√ WPS/PQR or WPS Summary Sheet √ Weld map √ Mill Certificate or PMI Report (for
To welding 1 joint between the WNRF Flange & pipe 2' sch 80 carbon steel using the Low-Temp CS, SS, LAS, Ni-based,
GTAW welding process. Weld summary sheet WQT / welder list etc)
√ Planned √ Permanent SAP WO#: EMOC#: Pressure Test Certificate Isometric / GA dwg Others :
Emergent Temporary IRS#: NSR#: √ Inspection Test Plan (ITP) Insp. Report (IRS)
Eqpt Tag OR Piping Line ID Piping Class Fluid / Medium Design Pressure A8 JOINT SUMMARY (TYPE & QUANTITY)
Shop Field Total Joints
Tag No: 4200-P-0001 A/B/C/D/E
ASTM A106 WATER NA
√ Butt Weld (BW) : 1 + NA = 1
Dwg No: Q1617-FE-713-A Rev.01
Fillet / Socket Weld (FW) : NA + NA = NA
A9 WELDING DATA
Part / component
WNRF Flange 1500# Pipe Manufacturer KOBE WIRE THAILAND
(e.g. pipe,tube,shell, flange)
Material Spec. / Grade &
ASTM A105 SA106 Gr.B Trade Name TGS 50
UNS No. (for High Alloy)
P. No 1 1 F - No. 6
BEFORE WELDING
√ Carbon Steel Stainless Steel √ Carbon Steel Stainless Steel AWS Class. /
Material Group
Group
ER 70S-G
Low Alloy High Alloy Low Alloy High Alloy
If Pipe (NPS & Sch.)
2"SCH 80 1500# 2"SCH 80 SFA No. 5.18
THICKNESS
1 100% VI @ all bevel joints (BW & FW) and weld cap Rejected:
7
NOTE : To add % as per Piping Class requirement; Abbreviation: VI (Visual Inspection), MPI (magnetic particle inspection); DPT (dye
penetrant testing), RT (radiography testing); PWHT (post weld heat treatment); HT (hydrostatic test); HdT (Hardness Test)
MOHD AS SHAHIDDIN
Maintenance / PECS Engineer 20/9/2019
JAFRI
Review & Verify
A13 NDT REPORT & RESULTS (to be filled-up by Maintenance / PECS) B2 (by Insp)
Acc. Criteria
Item (e.g. NDT, Date of Result (√) Signed by
Report No. Code (√) Sign. & Date Remarks
PWHT etc) Report QC / Supervisor
B31.3 ASME VIII Acc. Rej.
1
AFTER WELDING
B3 COMPLETION / CLOSE-OUT
I hereby certify that the welding work is satisfactory and all necessary tests (NDT) has been carried out and accepted as per specifications.
To welding 1 piece Orifite Plate stainless steel SS316 to Pipe 2"sch 80 ASTM A105 using √ WPS/PQR or WPS Summary Sheet √ Weld map Mill Certificate or PMI Report (for
Low-Temp CS, SS, LAS, Ni-based,
GTAW welding process Weld summary sheet WQT / welder list etc)
√ Planned √ Permanent SAP WO#: EMOC#: Pressure Test Certificate √ Isometric / GA dwg Others :
Emergent Temporary IRS#: NSR#: √ Inspection Test Plan (ITP) Insp. Report (IRS)
Eqpt Tag OR Piping Line ID Piping Class Fluid / Medium Design Pressure A8 JOINT SUMMARY (TYPE & QUANTITY)
Shop Field Total Joints
Tag No: 4200-P-0001 A/B/C/D/E
N/A WATER NA
Butt Weld (BW) : NA + NA = NA
Dwg No: Q1617-FE-713-A Rev.01
√ Fillet / Socket Weld (FW) : 2 + NA = 2
A9 WELDING DATA
Part / component
Plate Pipe Manufacturer NA NA
(e.g. pipe,tube,shell, flange)
Material Spec. / Grade &
SS 316 A106 Gr.B Trade Name TG-S309L NA
UNS No. (for High Alloy)
P. No 1 1 F - No. 6 NA
BEFORE WELDING
Carbon Steel √ Stainless Steel √ Carbon Steel Stainless Steel AWS Class. /
Material Group Group
SFA5.9 NA
Low Alloy High Alloy Low Alloy High Alloy
If Pipe (NPS & Sch.)
6mm 2"SCH 80 SFA No. 5.9 NA
THICKNESS
1 100% VI @ all bevel joints (BW & FW) and weld cap Rejected:
NOTE : To add % as per Piping Class requirement; Abbreviation: VI (Visual Inspection), MPI (magnetic particle inspection); DPT (dye
penetrant testing), RT (radiography testing); PWHT (post weld heat treatment); HT (hydrostatic test); HdT (Hardness Test)
1
AFTER WELDING
B3 COMPLETION / CLOSE-OUT
I hereby certify that the welding work is satisfactory and all necessary tests (NDT) has been carried out and accepted as per specifications.