Method Statement For Road Work
Method Statement For Road Work
Method Statement For Road Work
METHOD STATEMENT
ROAD WORKS
THIS DOCUMENT IS INTENDED FOR USE BY (NAME) AND ITS NOMINATED CONSULTANTS,
CONTRACTORS, MANUFACTURERS AND SUPPLIERS
ORIGINATOR:
HUADONG ENGINEERING CORPORATION
Page 1 of 6
DOC. No. XXXX-Q-HS-MS-002 PROJECT NO. XXXX REV.00 DATE: 11-DEC-2016
REVISION RECORD
TABLE OF CONTENTS
DOCUMENT TITLE
2. SCOPE------------------------------------------------------------------- 4
3. REFERENCES------------------------------------------------------------ 4
4. DEFINITIONS---------------------------------------------------------- 4
5. RESPONSIBILITIES---------------------------------------------------- 4
6. PROCEDURE------------------------------------------------------------ 5
8. HSE INSTRUCTIONS---------------------------------------------------- 6
9. RELATED DOCUMENTS----------------------------------------------- 6
1. OBJECTIVE
DOCUMENT TITLE
2. SCOPE
3. REFERENCES
4. DEFINITIONS
5. RESPONSIBILITIES
DOCUMENT TITLE
Quality Inspection Plan (QIP) specific to project requirements shall be made and inspection
activities shall be recorded either on the formats as given under “Related Documents” or those
supplied by customer. Inspection with protocol of (Witness) will be sign by OE/Client and
with protocol of (Reviews and Surveillance) will be sign by EPC.
The road will be constructed into two phases.
PHASE “I”
Mark the centre line of Road and note down the NSL both sides of centre line.
Cutting & Filling will be done, where required to maintain the slops.
PHASE II
Perform the quality tests of each material by the third party (Lab) and get its
approval by customer/consultants.
After erection of WTG’s tower a layer of approved road material will be placed for
road as per drawing width & thickness.
Compact the material with specified equipment up to required percentage of
compaction as given drawings & required test will be carried out.
For documentation QIP for road work will be followed.
DOCUMENT TITLE
8. HSE INSTRUCTIONS
8.1 A competent civil person will supervise filling operation.
8.2 Workers will use Personal Protective Equipment.
8.3 All excavations shall be filled and consolidated and the surface shall be left in good
condition as soon as practicable.
8.4 The fall path area will be cleared of items, which may cause injury during falling.
8.5 To avoid fall of the persons, the area to be filled will be flagged off and lighted
barricades installed to inform others if the area is left open overnight.
8.6 Back mirror along the guider must be used if filling is done by dumper etc.
8.7 The area will be assured free of workers and/or tools etc. before filling.
8.8 No trash, shopping bags, papers, cans, bottles or any other litter should be left in the
open.
8.9 Preserve your natural environment.
9. RELATED DOCUMENTS
9.1 IFC Drawings/ Specifications
9.2 QIP (Quality Inspection Plan)
DOCUMENT TITLE