1
1
1
Outline of Topics
➢ Geotechnical Instrumentation and
Monitoring
➢ Application to Deep Excavation
➢ Application to Ground Improvement
➢ Construction Vibration Control
➢ Pile Instrumentation
2
Overview of Geotechnical
Instrumentation
Two categories of instruments:
➢ Insitu Tests – for soil and rock properties
(this part covered by Prof Chew)
➢ Performance monitoring – to check that
design assumptions apply in the actual
ground conditions (this part covered by
Prof Tan)
3
Questions
➢ Why do we need to monitor performance?
➢ What must be capabilities of instruments?
➢ What must be capabilities of people?
➢ Where were we?
➢ Where are we now?
➢ What are future trends?
4
Geotechnical Instrumentation
Application to
Deep Excavations
5
• Excavation of soil is a common
activity in heavily built-up cities
➢excavation for basement
➢excavation for
underground road
and tunnel
6
Building founded
• Excavation caused stress on pile foundation
relief, results in:
1. Movement of soil
B
surrounding the d1 B'
F d2 F'
excavation
2 d
Illustration of an excavation
7
Before Excavation
8
Vv
Vh
9
Vv
= Vh
Immediate response
Vh = Vv
assume
i) the soil is saturated, and
ii) no water flow out from soil
mass – undrained condition
10
• Excavation caused stress
relief, results in:
1. Movement of soil
surrounding the Building founded on
excavation pile foundations
11
Observed settlements behind strutted excavation in Chicago
(after O’Rourke et al., 1976)
O’Rourke, T.D., Cording, E.J. & Boscardin, M. The ground movements related to braced excavation
and their influence on adjacent buildings. U.S. Department of Transportation, Report no. D0T-TST 76,
T-23, 1976 12
Observed settlements behind excavation (after Peck,
1969)
Peck. R.B. Deep excavations and tunnelling in soft ground. Prof. 7th Int. Conf. S.M.F.E.,
Mexico, State-of-the-art volume: 225 –290. 1969 13
Relationship between maximum ground settlements and
maximum lateral wall movement from case histories
(after Mana & Clough, 1981)
Mana A.I. and Clough G.W. Prediction of movements for braced cuts in clay. J. Geotech.
Engng, ASCE, (107), June: 759 – 777. 1981
14
Why is dHmax > dVmax ?
Settlements
A Wall deflection
dVmax = f(A)
So dVmax </= dHmax
15
Ground Deformation and Basal Stability
Diaphragm Walls
16
200mm settlement near to
an excavation
17
Pore Water Pressure (kPa) Pore Water Pressure (kPa) Pore Water Pressure (kPa)
200.0
205.0
210.0
215.0
220.0
130.0
140.0
150.0
160.0
170.0
180.0
75.0
80.0
85.0
90.0
95.0
100.0
Date of Monitoring
12-Jul-04 12-Jul-04 12-Jul-04
Piez o reading
Piez o reading
27-Dec-04
Theory hy dros tatic bas ed on WSP reading
Theory Hydraustatic Based on WSP Readings
27-Dec-04 27-Dec-04
Possible Under Drainage Problem
Pneumatic Piezometer
0m
Fill 0
2m
Theoretical Hydrostatic
-5
line based on water
table measurement
P1
Marine Clay -10
Depth
(m)
12-Jul-04 16-Aug-04
-15
7-Oct-04 22-Oct-04
18 m 4-Nov-04
Silty Sand
P2
21 m -20
P3
Tekong
Sand
25m -25
0 50 100 150 200 250
Pressure (kPa)
19
Crack up to 20mm width
at a house 200m away
from an excavation:
Possible cause – water
pumping
20
Crack up to 20mm width
at a house 150m away
from excavation:
Possible cause – water
pumping
21
Outline Of This Presentation
1. Introduction
2. Objectives of Instrumentation Monitoring
3. Type of Commonly Used Instruments for
Deep Excavation
4. Design of Instrumentation Scheme
5. Interpretation, Review Levels and Action
Plan
2
22
OBJECTIVES OF INSTRUMENTATION
MONITORING
1. Design Verification:
a. Instrument monitoring results can be used to verify design data
and design assumptions and to check that performance is as
predicted.
b. This include back analysis to fine-tune design parameters and
construction sequences during the progress of excavation, to
enable a better prediction for subsequent stages of excavation.
c. Usually, soil deformation data, such as inclinometer movement
and surface settlement data are used.
d. However, soil deformation is the “end results” of soil stress
changes. Hence, monitoring that indicates causes of
deformation, such as water table and pore pressure changes in
soils is essential.
23
2. Construction Control: The instruments will monitor the effects of
construction to the surrounding ground and properties.
a. To determine the magnitude of soil and nearby structures
deformation. Instruments are designed to capture small changes
which cannot be seen by naked eyes.
b. To estimate the influence zone of the construction impact
c. To establish the stabilization time of the ground after the
construction changes
24
4. Evidence for Damaged Dispute : Instrumentation results
to serve as record of construction impact for damage
assessment.